ND-22-0493, Notification of Completion of All ITAAC

From kanterella
(Redirected from ND-22-0493)
Jump to navigation Jump to search

Notification of Completion of All ITAAC
ML22210A090
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 07/29/2022
From: Coleman J
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ND-22-0493
Download: ML22210A090 (3)


Text

>,. Southern Nuclear Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel JUL 2 9 2022 Docket No.: 52-025 ND-22-0493 10 CFR 52.99(c)(4)

U.S. Nuclear Regulatory Commission Document Control Desk Washington , DC 20555-0001 Andrea D. Veil Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington , DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 Notification of Completion of All ITAAC Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(4), and in accordance with Vogtle Electric Generating Plant (VEGP)

Unit 3 Combined License (COL) NPF-91 condition 2.D.(2)(d), Southern Nuclear Operating Company (SNC) hereby notifies the NRC that all of the inspections, tests, analyses and acceptance criteria (ITAAC) in VEGP Unit 3 COL Appendix C have been successfully completed and are being maintained.

ITAAC Closure Notifications have been submitted to the NRC for each ITAAC in VEGP Unit 3 COL Appendix C in accordance with 10 CFR 52.99(c)(1 ). All of the ITAAC Closure Notifications are substantiated by ITAAC Completion packages, which include the documentation (tests, reports, completed procedures , completed analyses, etc.) that support the ITAAC determination bases. The ITAAC completion packages are available for NRC inspection at the plant site .

SNC is not aware of any condition that warrants submittal of an ITAAC Post-Closure Notification (IPCN) under 10 CFR 52.99(c)(2) for which an IPCN has not been submitted and hereby affirms the completion of all lTAAC prescribed in the combined license for VEGP Unit 3. On this basis , SNC requests that NRC staff make a finding that the acceptance criteria in the combined license are met (10 CFR 52.103(g)).

If there are any questions, please contact Kelli Roberts at 706-848-6991.

Respectfully submitted ,

~ 0,~

Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 JMC/CEM/sfr

U.S. Nuclear Regulatory Commission ND-22-0493 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. D. Pitts Mr. J.B. Williams Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C . E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms. A. C . Chamberlain Mr. J.C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Regulatory Commission Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J . Even Mr. B. J. Kemke r Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C . Santos Mr. B. Davis Mr. J . Vasquez Mr. J. Eargle Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall

U.S . Nuclear Regulatory Commission ND-22-0493 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. S. Harper Ms. S.L. Zwack Other Mr. S. W. Kline , Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr. , Ph .D. , GOS Associates, Inc.

Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey , Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton , Balch Bingham