ND-22-0431, Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule, and the Unit 3 and 4 Completion Schedule for Inspections, Tests, and Analyses (ITA)

From kanterella
Jump to navigation Jump to search
Combined License (COL) Operational Programs and Other License Conditions Implementation Schedule, and the Unit 3 and 4 Completion Schedule for Inspections, Tests, and Analyses (ITA)
ML22164A983
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 06/13/2022
From: Coleman J
Southern Nuclear Operating Co
To: Andrea Veil
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML22164A982 List:
References
ND-22-0431
Download: ML22164A983 (4)


Text

i. Southern Nuclear Jamie M. Coleman Regulatory Affairs Director 7825 River Road Waynesboro. Georgia 30830 Vogtle 3 & 4 706 848 6926 te l June 13, 2022 ND-22-0431 10 CFR 52.99(a) 10 CFR 52 .103(a)

Docket Nos.: 52-025 52-026 U.S. Nuclear Regulatory Commission ATTN : Document Control Desk Washington , DC 20555-0001 Ms. Andrea Veil Director, Office of Nuclear Reactor Regulation U.S . Nuclear Regulatory Commission Washington , DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant (VEGP) - Units 3 and 4 Combined License (COL} Operational Programs and Other License Conditions Implementation Schedule, and the Unit 3 and 4 Completion Schedule for Inspections, Tests, and Analyses (ITA)

  • Ladies and Gentlemen :

The U.S. Nuclear Regulatory Commission (NRG) issued Combined Licenses (COLs) NPF-91 and NPF-92 to Southern Nuclear Operating Company (SNC) pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 52.97 , "Issuance of combined licenses," on February 10, 2012.

Two license conditions require SNC to submit, no later than twelve months after issuance of the COL, the following :

  • A schedule for implementation of the operational programs listed in the Final Safety Analysis Report Table 13.4-201, including the associated estimated date for initial loading of fuel (COL section 2. D.(11 ))
  • A schedule for implementation of the license conditions listed in COL section 2.D.(12)(f)1-9 In accordance with the license conditions, the schedules shall be updated every six months until twelve months before scheduled fuel loading , and every month thereafter until each license condition has been fully implemented.

U. S. Nuclear Regulatory Commission ND-22-0431 Page 2 of 4 SNC is also required to submit, with similar frequency, its schedule for completing the Inspections, Tests, or Analyses (ITA) for the Nuclear Regulatory Commission approved Inspections , Tests, Analyses , and Acceptance Criteria (ITAAC) per 10 CFR 52.99(a) . SNC intends to submit the Unit 3 and Unit 4 updates to the ITAAC schedule every 30 days until the final notification is provided to the NRC under 10 CFR 52 .99(c)(1) .

On January 13, 2020 and November 11 , 2021 , SNC submitted the scheduled dates for initial loading of fuel at VEGP Units 3 and 4 , Agencywide Documents Access and Management System (ADAMS)

Accession Numbers ML20013F991 and ML21315A011, respectively . These submittals stated updates to the scheduled dates for initial loading of fuel would be made every 30 days in accordance w ith 10 CFR 52.103(a) . The scheduled dates for initial loading of fuel at VEGP Units 3 and 4 are provided in . contains the Unit 3 and 4 COL Operational Programs and Other License Conditions Implementation Schedule and the scheduled date for initial loading of fuel at VEGP Unit 3 and Unit 4 . contains the Unit 3 Preoperational Test Procedure Completion Schedule. Enclosure 3 contains the Unit 3 Inspections, Tests, and Analyses Completion Schedule. Enclosure 4 contains the Unit 4 Inspections, Tests , and Analyses Completion Schedule. As is typical with a construction project, the schedule information is dynamic in nature.

The schedule information provided in the enclosures is considered confidential commercial information and exempt from mandatory public disclosure pursuant to the provisions of 10 CFR 2 .390(a)(4) and 10 CFR 9.17(a)(4) . Following the approach described in SECY-06-0114 , no additional withholding determination is needed as the schedule information was demonstrated to be confidential commercial information based on the schedule updates provided to the NRC on February 8, 2019 , ADAMS Accession Number ML19039A264, and on October 6, 2017 , ADAMS Accession Number ML17279A661 .

Accordingly, the enclosures to this letter should be withheld from public disclosure.

This letter contains no regulatory commitments.

Should you have questions regarding the enclosed information , please contact Steve Leighty at (706) 848-6790 .

Respectfully submitted ,

~(9&~

Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 Southern Nuclear Operating Company JMC/KJD/sfr

U.S. Nuclear Regulatory Commission ND-22-0431 Page 3 of 4

Enclosures:

1. COL Operational Programs and Other License Conditions Implementation Schedule {Withhold from Public Disclosure}
2. Preoperational Test Procedure Completion Schedule {Withhold from Public Disclosure}
3. Unit 3 ITAAC Closure Schedule {Withhold from Public Disclosure}
4. Unit 4 ITAAC Closure Schedule {Withhold from Public Disclosure}

Southern Nuclear Operating Company/ Georgia Power Company Mr. S. E. Kuczynski (w/o enclosures)

Mr. P. P. Sena Ill (w/o enclosures)

Mr. H. Nieh (w/o enclosures)

Mr. G. Chick Mr. J. B. Williams Mr. S. Stimac Mr. P. Martino Mr. B. H. Whitley Mrs. J. M. Coleman Mr. A. S. Parton Ms. K. A. Roberts Mr. S. C. Leighty Mr. C. T. Defnall Ms. A. C. Chamberlain Mr. J. C. Haswell Mr. A. Nix Mr. T. M. Drouin Document Services RTYPE : VND .LI .L00 File AR.01 .02.06 Nuclear Regulatory Commission Mr. M. King (w/o enclosures)

Mr. G. Bowman (w/o enclosures)

Ms. M. Bailey (w/o enclosures)

Ms. A. Veil (w/o enclosures)

Mr. C. Patel Mr. G.J. Khouri Mr. C. J. Even Mr. B. J. Kemker Mr. J. Eargle Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Ms. K. Mccurry

U. S . Nuclear Regulatory Commission ND-22-0431 Page 4 of 4 Mr. B. Davis Mr. B. Gleaves Mr. J. Parent Mr. B. Griman Mr. V. Hall Mr. P. O'Bryan State of Georgia Mr. R. Dunn (w/o enclosures)

Oglethorpe Power Corporation Mr. M. W. Price (w/o enclosures)

Mr. B. Brinkman (w/o enclosures)

Mr. E. Rasmussen (w/o enclosures)

Municipal Electric Authority of Georgia Mr. J. E. Fuller (w/o enclosures)

Mr. S. M. Jackson (w/o enclosures)

Dalton Utilities Mr. T. Bundros (w/o enclosures)

Westinghouse Electric Company, LLC Mr. L. Oriani (w/o enclosures)

Mr. T. Rubenstein (w/o enclosures)

Mr. M. Corletti Mr. D. Hawkins Ms. S. Zwack Other Mr. S. W. Kline, Bechtel Power Corporation Mr. S . Blanton , Balch Bingham Ms. L. A. Matis , Tetra Tech NUS , Inc. (w/o enclosures)

Mr. W . R. Jacobs, Jr., Ph .D., GOS Associates , Inc. (w/o enclosures)

Mr. S. Roetger, Georgia Public Service Commission (w/o enclosures)

Mr. R.L. Trokey , Georgia Public Service Commission (w/o enclosures)

Mr. K. C. Greene, Troutman Sanders (w/o enclosures)