pre-application Public Meeting 3/15/22 Slides - Applicant
ML22068A122
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 03/15/2022
From:
Xcel Energy
To:
Office of Nuclear Material Safety and Safeguards
Tran T, NMSS/REFS/ELRB
References
Download: ML22068A122 (15)


Text

MONTICELLO NUCLEAR GENERATING PLANT SUBSEQUENT LICENSE RENEWAL APPLICATION March 15, 2022 1

Environmental Report & SAMA Pre-Application Meeting 2

AGENDA

1. Opening Remarks NRC XCEL Energy

2. Background

3. Discussion Items
4. Lessons Learned
5. Closing Remarks XCEL NRC

OPENING REMARKS 1.NRC 2.XCEL Energy MNGP SLR ER Project Team Scott McCall, Director of Nuclear Fleet Operations Paul Young, Manager Site Routine Projects Max Smith, Senior Project Manager Steve Sollom, PE, Environmental Lead Tom Slavonic, ER Project Manager (ENERCON)

Rachel Turney-Work, ER Technical Lead (ENERCON)

=

Background===

  • One General Electric BWR Monticello Nuclear Generating Plant
  • 2004 Mwt OLs 40 Yrs 60 Yrs 80 Yrs
  • Net Capacity: 640 Mwe Unit 1 1970 2010 2030 2050
  • Capital improvements include uprate &

efficiencies since initial LR

  • No refurbishment anticipated for subsequent period of extended operation (SPEO) 5

Plant Aerial

  • MNGP is owned by Xcel Energy, the licensee and applicant, and operated by Northern States Power Company.
  • The property (approx. 2000 acres) straddles the river and is located in Wright and Sherburne Counties, MN.
  • The MNGP EAB falls within the site boundary.

6

Vicinity (6-mile) Map 7

Region (50-mile) Map 8

Discussion Items

  • Methodology
  • Regulatory
  • Permits / Authorizations
  • Coastal Zone Management Act (CZMA)
  • Clean Water Act (CWA) 401 Certification
  • CWA 316(a) and 316(b)
  • Consultations & Public Communications
  • Consultations with agencies and Native American Tribes will occur and all received responses will be included in the SLRA ER.

9

Discussion Items, Contd.

  • MNGP does not use High Burnup Fuel
  • Groundwater Use
  • Severe Accident Mitigation Alternatives (SAMA) Analysis Status
  • Independent Spent Fuel Storage Installation
  • Alternatives Analysis 10

Discussion Items: Ecology & Cultural Resources Critical Habitat

  • No designated critical habitat is listed for Sherburne or Wright counties.

Essential Fish Habitat

  • No essential fish habitat (EFH) is located within the vicinity of MNGP, nor were any EFH areas protected from fishing.

Habitat Areas of Particular Concern

  • No habitat areas of particular concern (HAPC) located within the six-mile vicinity of MNGP.

Threatened and Endangered Species

  • Three Federally listed threatened, endangered or candidate species are listed within Sherburne and Wright Counties.
  • Twenty-two state listed species are located within Sherburne and Wright counties.

Cultural Resources

  • The MOSAP and SHPO databases list no cultural resources within the MNGP site.

11

Lessons Learned SLR Review

  • Incorporate lessons learned from previously submitted ER & SAMA analyses into the MNGP ER and basis documents SAMA Evaluations Agency Consultations Alternatives
  • Review and incorporate applicable information into MNGP ER based on previously submitted SLR ER RAIs (e.g., PSL, PBN, PTN, SPS, ONS, PBAPS)
  • Allocate sufficient time to test IT resources (e.g., access to e-Portal and Microsoft Teams) and offer to walk through the organization presented on the e-Portal prior to environmental audit.

12

Discussion Regarding the Recent Orders

  • February 24, 2022 NRC Memorandum and Orders and SECY-21-0066
  • Xcel Initial Thoughts on Strategy 13

Closing Remarks XCEL NRC 14