Text

i Northern States Power Company Prairie Island Nuclear Generating Plant 1717 Wakonade Dr. East Welch, Minnesota $5089 June 30,1997 Generic Letter 92-08 U S Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos.50-282 License Nos. DPR-42 50-306 DPR-60 Completion of All Activities Related to Generic Letter 9"-08 on Thermo-Lag issues (TAC Nos. M85592 and 'f.d5593)

We have completed the activities necessary to resolve the concerns discussed in Generic Letter 92-08, "Thermo-Lag 330-1 Fire Barriers". In our letter to you, dated December 31,1996, we discussed " . . . several small projects which also need to be completed prior to complete close-out of the inues addressed by Generic Letter 92-08.

None of these projects involve removal of Tbermo-Lag from required safe-shutdown raceways. These projects will be completed t,y the end of June 1997." We have not completed all aspects of these small projects, they will be completed in their entirety by the end of October 1997. However, we have reviewed the work remaining and have concluded that all of the work associated with Generic Letter 92-08 and the ensuing correspondence between us has been completed. Thus, our commitments regarding Generic Letter 92-08 have been completed, in this letter we have made no new Nuclear Regulatory Commission commitments.

Please contact Jack Leveille (612-388-1121, Ext. 4662) if you have any questions related to this letter.

Joel P Sorensen 9 Plant Manager Prairie Island Nuclear Generating Plant l 7

c: (see next page) lilEIElEllIlHlllHill 9707080250 970630 PDR ADOCK 0500o282 P PDR

.. I c

1 USN,RQ NORTHERN STATES POWER COMPANY June 30,1997 l Page 2 c: Regional Administrator - Region Ill, NRC l Senior Resident inspector, NRC NRR Project Manager, NRC '

J E Silberg

Attachment:

Affidavit i

i f

! l l

l l

l l

l l

l l

l l

t i

920s-13.poc

. '", i l

1 l

UNITED STATES NUCLEAR REGULATORY COMMISSION NORTHERN STATES POWER COMPANY PRAIRIE ISLAND NUCLEAR GENERATING PLANT DOCKET NO. 50-282 ,

50-306 l GENERIC LETTER 92-08, THERMO-! AG 330-1 FIRE BARRIERS l Northem States Power Company, a Minnesota corporation, with this letter is submitting information requested by NRC Generic Letter 92-08, pursuant to 10 CFR 50.54(f).

1 I

This letter contains no restricted or other defense information.

1 NORTHERN STATES POVER COMPANY j BY i

[ Joel P Sorerfsen '

Plant Manager Prairie Island Nuclear Generating Plant l

l On this2>0 day of 3h h E- NOl before me a notary public in and for said County, personally appeared Joel P Sorensen, Plant Manager, Prairie Island Nuclear Generating Plant; and being first duly sworn acknowledged that he is authorized to execute this document on behalf of Northem States Power Company, that he knows the contents thereof, and that to the best of his knowledge, information, and belief the statements made in it are true and that it is not interposed for delay.