Advises of Planned Insp Effort Resulting from Plant,Units 2 & 3.Details of Insp Plan for Next 8 Months Encl
ML20148B771
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 05/05/1997
From: Gwynn T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Ray H
SOUTHERN CALIFORNIA EDISON CO.
References
NUDOCS 9705130344
Download: ML20148B771 (7)


Text

.

t h""%g UNITED ST ATES

. f \ NUCLEAR REGULATORY COMMISSION

$ REGtON IV

  • 611 R YAN PL AZA DRIVE, SUITE 400 4 ",

't 9 # AR LINGToN, TE XAS 76011,8064 MAY - 5 .E Harold B. Ray, Executive Vice President Southern California Edison Co.

San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, California 92674-0128

SUBJECT:

SEMIANNUAL PLANT PERFORMANCE REVIEW (SPPR) - SAN ONOFRE UNITS 2 AND 3 i

Dear Mr. Ray:

On March 25,1997, the NRC staff completed the SPPR of San Onofre Units 2 and 3. The staff conducts these reviews for all operating nuclear power plants to develop an integrated understanding of safety performance. The results are used by NRC management to facilitate planning and allocation of inspection resources. The SPPR for l

San Onofre Units 2 and 3 involved the participation of all technical divisions in evaluating ;

j inspection results and safety performance information for the period from October 1,1996, I l _through March 1997. SPPRs provide NRC management with a current summary of l i licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee l

, Performance and Senior Management Meeting reviews.

This letter advises you of our planned inspection effort resulting from the San Onofre Units 2 and 3 SPPR review. It is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. The enclosure details our inspection plan for the next 8 months.

The rationale or basis for each inspection outside the core inspection program is provided so that you are aware of the reason for emphasis in these program areas. Resident inspections are not listed due to their ongoing and continuous nature.

?

4 We willinform you of any changes to the inspection plan. If you have any questions, please contact Mr. Dennis Kirsch at (510)-975-0290.

4

! Sincerel 1

~

- /"

u homas P. Gwynn, ire or Division of Reactor cts Docket Nos.: 50-361 50-362 License Nos.: NPF-10 NPF-15 L

l \

9705130344 970505 * * * * ' '

Southern California Edison Company .

Enclosure:

Inspection Plan cc w/ enclosure:

Chairman, Board of Supervisors County of San Diego 1600 Pacific Highway, Room 335 San Diego, California 92101 Alan R. Watts, Esq.

Woodruff, Spradlin & Smart l 701 S. Parker St. Suite 7000 1 Orange, California 92868-4720 Sherwin Harria, Resource Project Manager Public Utilities Department City of Riverside 3900 Main Street Riverside, California 92522 R. W. Krieger, Vice President Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, California 92674-0128 Dr. Harvey Collins, Chief Division of Drinking Water and Environmental Management California Department of Health Services P.O. Box 942732 Sacramento, California 94234-7320 Terry Winter, Manager Power Operations San Diego Gas & Electric Company P.O. Box 1831 San Diego, California 92112 Mr. Steve Hsu Radiological Health Branch State Department of Health Services P.O. Box 942732 Sacramento, California 94234

Southern California Edison Company Mayor City of San Clemente 100 Avenida Presidio San Clemente, California 92672 Mr. Truman Burns \Mr. Robert Kinosian California Public Utilities Commission l 505 Van Ness, Rm. 4102 San Francisco, California 94102 l

l l

i

D

)

, o h

Southern California Edison Company MAY - o_ .

bec to DCD lE01 bec distrib. by RIV:

Regional Administrator Resident Inspector DRP Director DRS-PSB Branch Chief (DRP/F, WCFO) MIS System Senior Project inspector (DRP/F, WCFO) RIV File Branch Chief (DRP/TSS) M. Hammond (PAO, WCFO)

WCFO File

R. V. Azua, DRP DOCUMENT NAME

To receive copy of document, indicate in box: "C" = Copy withoupnclosures "E" = Copy with enclosures "N" = No copy l

RIV:Pl:DRP/F E C:DRP/F E D:DRSg l D:DRP G l l DGAcker;cm DFKirsch ATHdQ(ll TPG,wynn (W 04/10/97 04/10/97 0@/ \ /97 Off/( /97 " V OFFICIA1 RECORD COPY

\

Southern California Edison Company MAY - 5 m,,.t o bec to DCD IE01 bec distrib. by RIV:

Regional Administrator Resident inspector DRP Director DRS-PSB Branch Chief (DRP/F, WCFO) MIS System Senior Project inspector (DRP/F, WCFO) RIV File Branch Chief (DRP/TSS) M. Hammond (PAO, WCFO)

WCFO File R. V. Azua, DRP DOCUMENT NAME:

To receive copy of document, Indicate in box: "C" = Copy wthoupnclosures "E" = Copy with enclosures "N" = No copy RIV:Pl:DRP/F E C:DRP/F E D:DRSg l D:DRP l V, j DGAcker;cm DFKirsch ATH6@ll TPG,wynn (W 04/10/97 04/10/97 OQ/ \ /97 Og/( /97 " V OFFICIAL R$ CORD COPY

SAN ONOFRE NUCLEAR GENERATING STATION INSPECTION PLAN IP -Inspection Procedure Tl - Temporary Instruction Core Inspection - Minimum NRC Inspection Program (mandatory all plants)

TITLE / NUMBER OF PLANNED TYPE OF INSPECTION ,

PROGRAM AREt INSPECTORS INSPECTION DATES INSPECTION COMMENTS IP 73753 Inservice Inspection 3 04/21-25/97 Core Inspection and Regional Initiatives -

IP 55050 Nuclear Welding Initiatives are a followup from a previous  ;

IP 62001 Boric Acid Corrosion Prevention maintenance reliability team inspection l Program Tl133 Solid Radioactive Waste 2 04/21-25/97 Safety issue and Core Inspection IP 86750 Management and j Transportation of Radioactive Materials j iP 50002 Steam Generator Followup 2 05/12-16/97* Regional Initiative to review results of inspection of Unit 2 tubes which included an l unexpected number of tubes that required plugging. *(Schedule may change.)  !

Tl130 Implementation of improved 3 06/02-06/97 Safety issue l Technical Specification l IP 81700 Physical Security Program for 2 06/09-13/97 Core Inspection Power Reactors IP 83750 Occupational Radiation 1 06/09-13/97 Core Inspection l Exposure l

IP 71001 Licensed Operator 3 09/15-19/97 Core Inspection Requalification Program Evaluation IP 82301 Evaluation of Emergency 5 10/27-31/97 Core inspection Preparedness Exercise IP 62706 Maintenance Rule Audit 7 12/01-05/97 Regional Team Baseline (required by NRR program office)

- _ _ _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ _ _ - - - _ _ _ _