Forwards Rev 3 to Project Procedure PP-07, Discrepancy Repts, Incorporating Changes Requested by NRC to Reflect Added Requirement for Conducting Preliminary Assessment of Potential Significance of Discrepancies
ML20141H596
Person / Time
Site: Millstone Dominion icon.png
Issue date: 07/29/1997
From: Curry D
AFFILIATION NOT ASSIGNED
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20141H601 List:
References
NUM2-PPNR-0358, NUM2-PPNR-358, NUDOCS 9707310189
Download: ML20141H596 (1)


Text

_ _. _ -m_

PARSONS

/

Parsons Power Group inc.

  • 2675 MorDantown Road a Reading, Pennsylvania 19607 * (610) 855 2000 Fax: (C10) 855-2001 July 29,1997 Docket No. 50-336 l Parsons NUM2-PPNR-0358-L U.S. Nuclear Regulatory Commission Attention: Document Control Desk i Washington, D.C. 20555 l l

Millstone Nuclear Power Station Unit No. 2 Independent Cctrective Action Verification Program (ICAVP) l Gentlemen:

This letter transmits Revision 3 of Project Procedure PP-07, " Discrepancy Reports". Rese revisions incorporate the changes requested by your letter dated July 24th to reflect the added requirement for i

! conducting a preliminary assessment of the potential significance of discrepancies.  ;

Revision 3 replaces in its entirety Revision 2 of the Project Procedure PP-07.

Please call me at (610) 855-2366 if you have any questions.

Sincerely,

' (/y

- ~

, i (A

/0 Daniel L. Curry Parsons ICAVP Project Director DLC:djv Attachments:

cc: E. Imbro (2) - USNRC H. Eichenholz - USNRC R. Laudenat - NNECo J. Fougere - NNECo f Rep. Teriy Concannon - NEAC CO /