Discusses Status of Det Matl Condition Improvements.Util Final Resolution of Issue Will Be Transmitted to NRC by 970805
ML20141C426
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 06/19/1997
From: Kraft E
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
ESK-97-117, GL-96-03, GL-96-3, NUDOCS 9706250175
Download: ML20141C426 (2)


Text

.. . . . ..

Commonwealth FAle.on Compan)

,g , Quad Cities Generating Station
  1. 227 to 206th Avenue North Cordova. II. 612 62 97 iu
Tri .w>w22 i t i

l ESK-97-117 June 19,1997 U. S. Nuclear Regulatory Commission Washington, D. C. 20555 i

Attention: Document Control Desk

Subject:

Quad Cities Nuclear Power Station Units 1 and 2 Status of Diagnostic Evaluation Team (DET)

Materiel Condition Improvements Docket Nos. 50-254 and 50-265

Reference:

(a) J. O' Conner to J. Taylor letter concerning DET Response dated December 30,1993 (b) E. S. Krafl, Jr. to USNRC letter (ESK-96-197) concerning Status of DET Improvements dated October 30,1996 In reference (b), I stated that Quad Cities Station would complete the replacement of the signal cables (triple shielded cables) for the Unit 2 Source Range Monitors (SRMs) and Intermediate Range Monitors (IRMs) during Q2R14. Prior to the outage, a management review determined that other priority work needed to be accomplished in the vicinity of this cable replacement. This work included the permanent repair to eliminate the l furmanite clamp on the 2A Reactor Recirculation Pump flange (DET commitment).

l Also accomplished was insulation removal in the drywell in response to Generic Letter /

' 96-03.  !

O It was also determined that the modification would require the installation ofextensive conduit runs. This resulted in a significant increase, over what had been previously assumed, in both the scope and cost of the modification, and in the radiation dose g\

estimate. Therefore, the signal and drive cable replacement was removed from the outage scope. An evaluation will be completed to determine future plans concerning this l modification. Our final resolution of this issue will be transmitted to you by August 5, l 1997.

l 9706250175 970619 fo"

^o cx 03 02j qqiggy;jgqi t

i A 1:nicom Compan)

a - a 1 i

U. S. NRC ESK-97-117 2 June 19,1997 Ifyou have any questions concerning this letter, please contact Charles Peterson, Regulatory Affairs Manager, at (309) 654-2241, extension 3609.

Respectfully, l

h , b ,, -

E. S. Kraft, J Site Vice Preside l

Quad Cities Station i

cc: A. B. Beach, Regional Administrator, Region III R. M. Pulsifer, Project Manager, NRR C. G. Miller, Senior Resident Inspector, Quad Cities W. D. cech, MidAmerican Energy Company l . D. C. Tubbs, MidAmerican Energy Company l F. A. Spangenberg, Regulatory Affairs Manager, Dresden INPO Records Center Office of Nuclear Facility Safety, IDNS DCD License (both electronic and hard copies) '