Advises That Operator & Senior Operator Licensing Written & Orals Exams Scheduled for 860203-10.Encl Listed Ref Matl Requested by 851203.License Applications Required 60 Days Prior to Exam
ML20138Q941
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 11/13/1985
From: Reyes L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
References
NUDOCS 8511180344
Download: ML20138Q941 (6)


Text

I NOV 1 3 1335 Docket No. 50-456 Commonwealth Edison Company ATTN: Mr. Cordell Reed Vice President post Office Box 767 L51cago, IL 60690

Dear Mr. Reed:

SUBJECT:

OPERATOR AND SENIOR OPERATOR LICENSING EXAMINATIONS In a telephone conversation between Mr.W. McGee, Training Supervisor, and Mr. T. Burdick, examiner, arrangen'ents were made for the administration of examinations at the Braidwood Station.

The written and oral examinations are scheduled for the week of February 3 and February 10, 1986.

In order for us to n.eet this schedule, it will be necessary for the facility to furnish the approved reference material listed in Enclosure 1 " Reference Material Requirements for Operator / Senior Operator Licensing Examinations" by Decerrber 3,1985. Any delay in receiving this material will result in a delay in administering the examinations. Our examinations are scheduled far in advance with considerable planning to best utilize cur limited examiner man-power and to ncet the examination dates requested by the various facilities.

Therefore, missing the Decerrber 10, 1985 deadline, even by a few days, will likely result in a long delay since it may not be possible to reschedule examinations at other facilities. Hr. McGee has been advised of our reference material requirements, the nonber of reference n;aterial sets that are required, and the examiners' naces and addresses where each set is to be mailed.

The facility nianagement is responsible for providing adequate space and facilities in order to properly conduct the written examinations.

Enclosure 2, " Administration of Operator / Senior Operator Licensing Written Examinations," describes our requiren;ents for conducting these exaniinctions.

Mr. McGee has also been infomed of these requirements.

All operator and senior license applications should normally be subnitted at least 60 days prior to the first examination dates so that we will be able to review the training and experience of the candidates, process the tredical certifications, and prepare final examiner assigroents af ter candidate eligibility has been determined. If the applications are not received at least 30 days prior to the c> amination dates it is likely that a postponement will be necessary.

OD11100344 051113 PDH ADOCK 05000456 I V PDH l s i

W

Comonwealth Edison Company 2 NOV 13 1985 This request for infonnation was approved by the Office of Management and Budget under Clearance Number 3150-0101, which expires June 30, 1986.

Conenents on burden and duplication may be directed to the Office of Management and Budget. Reports Managenent Room 3208, New Executive Office Building, l Washington, D.C. 20503.

l Thank you for your consideration in this matter. If you have any questions

! regarding the examination procedures and requirements, please contact Mr. J. I. McMillen at 312-790-5559.

i Sincerely, l

f S$$NAL'$1 5 E h b U Luis A. Reyes, Chief Operations Branch

Enclosures:

1. Reference Material Requirements for Operator /Seninr Operator Licensing Examination
2. Administration of Operator Licensing Written Examinations 51.0. At.t,a,che,d,,0,1s_tribution

Ccnnonwealth Edison Conpany 3 ROV is mL Distribution cc w/ enclosures:

D. L. Farrar, Director of Nuclear Licensing M. Wallace, Project Manager D. Shamblin, Construction Superintendent J. F. Gudac, Plant Manager C. W. Schroeder, Licensing and Compliance Superintendent DCS/RSB (RIDS)

Licensing Fee Managen.cnt Branch Resident Inspector, RIII Braidwood Resident Inspector, RIII Byron Phyllis Dunton, Attorney General's Office, Environmental Control Division D. W. Cassel, Jr., Esq.

J. W. McCaffrey, Chief, Public Utilities Division H. S. Taylor, Quality Assurance Division E. Chan, ELD J. Stevens, NRR The lionorable Herbert Grossman, ASLB The Honorable A. Dixon Callihan, ASLB The lionorable Richard F. Cole, ASLB W. McGee, Plant Training Manager cc w/o enclosures:

J. Stevens, Project Manager, NRR B. Boger, Branch Chief, OLB Hl.l l R I

/J- (Hil{$

cli /T burd ick /niab l' pi len j yes' 11/07/05 .; 5

p

)(  !

t

o .

)

i ENCLOSURE _1 Reference Material Requirements for Operator / Senior Operator Licensing Examinations Note: Regujred_Ma_terja,1_jf_jn_djcate,d_by a an "X" opp _osj_t,e the item.

_X_ 1. ProcedureIndex(alphabeticalbysubject)

All administrative Procedures (as applicable to reactor operation I

_X_ 2.

or safety

_X_ 3 . All Integrated Plant Procedures (Nomal or General Operating g Procedures)

_X_ 4. Emergency Procedures (Emergency Instructions, Abnormal or Special Procedures)

~-

X 5. Standing Orders (Important orders which are safety related and rray supersede the regular procedures) l _X_ 6. Fuel Handling and Core Loading Procedures, (Initial Core Loading Procedure,whenappropriate)

_X_ 7. AnnunciatorProcedures(alarmprocedures,includingsetpoints)

_X_, 8. RadiationProtectionManual(RadiationControlManualorProcedures)

_X_ 9. Emergency Plan Implementing Procedures

_X _ 10. Technical Specifications -

-~

X 11. LessonPlans(TrainingManuals,PlantOrientationManual, System Descriptions, Reactor Theory, Thermodynamics, etc.)

_X_ 12. System Operating Procedures X 13. Piping and Instrumentation Diagrams, electrical single line diagrams, or flow diagrams

_X_ 14. Technical Data Book, and/or plant curve infomation as used by operators

_X _ 15. Questions and Answers that icensee has prepared (Voluntary by Licenset-)

~~

X 16. Malfunction and initial Cordition Material for Simulator (if applicable)

_X_ 17. Other Surveillance, incident reports

l i

i i

! All of the above reference material should be approved, final issues, and i

shculd be so n.arked. Uncontrolled, preliminery, or other such issues will not be acceptable except for cold license examinaticns. All procedures and

! reference material should be bound or in the form as used by the control room 1

operators, with appropriate indexes or tables of contents so that they can be l

used efficiently.

l l If a cold-license plant has not finalized some of the material, the chief I examiner is responsible for ensuring that the most complete, up-to-date material is available and that agreement has been reached with the licensee l for limiting changes before the administration of the examination, l

l l

2

.o ENCLOSURE 2 Administration of Reactor / Senior Reactor Operator Licensing Written Examinations Operator Licensing Branch requirements are:

1. A single room shall be provided for completing the written examination.

The location of this room and supporting restroom facilities shall be such as to prevent contact with all other facility and/or contractor personnel during the duration of the written examination. If necessary, the facility should make arrangements for the use of a suitable room at a local school, motel, or other building. Obtaining this room is the responsibility of the licensee.

2. Minimum spacing is required to ensure exam integrity as determined by the chief examiner. Minimum spacing should be one candidate per table, with 3 foot spacing between tables. No wall charts, models, and/or other training materials shall be present in the examination room.
3. Suitable arrangements are to be made by the facility if the candidates are to have lunch, coffee, etc. These arrangeoents shall comply with Item 1 above. These arrangen.ents will be reviewed by the examiner and/or proctor. .
4. A copy of the written examination and answer key shall be given to the utility training department after the last candidate has turned in his completed examination. The utility will then have until the end of the exam week to provide coments and supporting documentation to suggest changes or corrections to the examination and answer key. The utility may provide these coments in writing to the Chief Examiner before he leaves the site or forward them to the Operator Licensing Section Chief in the appropriate regional office.
5. The licensee will provide pads of 8-1/2 x 11" lined paper in unopened packages for each candidate's use in completing the examination. The .

examiner will distribute these pads to the candidates. All reference material needed to complete the examination will be furnished by the examiner.' Candidates can bring pens, pencils, calculators or slide rules into the examination room and no other equipment or reference material is allowed.

6. Only black ink or dark pencils should be used for writing answers to '

questions.

l

!