ML20137U602

From kanterella
Jump to navigation Jump to search
Insp Repts 50-348/97-04 & 50-364/97-04 on 970125-0314. Violations Noted.Major Areas Inspected:Detailed Esfs Review & Walkdown of Units 1 & 2 PRF Sys,Including Associated Surveillance Test & Sys Design Requirements
ML20137U602
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 04/02/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20137U594 List:
References
50-348-97-04, 50-348-97-4, 50-364-97-04, 50-364-97-4, NUDOCS 9704170045
Download: ML20137U602 (15)


See also: IR 05000348/1997004

Text

,

. . .

.

U.S. NUCLEAR REGULATORY COMMISSION (NRC)

REGION II

Docket Nos: 50-348 and 50-364

License Nos: NPF-2 and NPF-8

.

'

Report No: 50-348/97-04 and 50-364/97-04

.

Licensee: Southern Nuclear Operating Company. Inc

Facility: Farley Nuclear Plant (FNP). Units 1 and 2

Location: 7388 North State Highway 95

Columbia.'AL 36319

l

Dates: January 25 - March 14. 1997 j

Inspectors: T. Ross. Senior Resident Inspector

J. Bartley, Resident Inspector

R. Caldwell. Resident Inspector (In training)

Approved by: P. Skinner. Chief. Projects Branch 2

Division of Reactor Projects

Enclosure

~

9704170045 970402

FDR ADOCK 05000348

(D PDR 2

. . , -

- . _ - - . -

._ . _ _ _ _ _ _ _ . _ _ . - _ . ~ . . _ _ _ _ _ _ . . - _ _ . _ _ _ _ . _ . _

. . .

.

.

'

EXECUTIVE SUMMARY

I

Farley Nuclear Power Plant. Units 1 And 2 I

NRC Inspection Report 50-348/97-04. 50-364/97-04

This special inspection documents the results of a detailed Engineered

Safeguards Feature system review and walkdown of the Unit 1 and Unit 2

Penetration Room Filtration (PRF) systems, including associated surveillance

1

test and system design requirements.

Ooerations

l

4

e The PRF system was physically well maintained. However, procedural

4

guidance for normal operation, surveillance testing, and emergency

l conditions was inadequate. Licensee corrective actions to date have

been thorough and prompt. The most serious procedural deficiency was

, the lack of guidance for ensuring system operation prior to and during

'

post loss of coolant accident' (LOCA) cold leg recirculation in a manner

consistent with the Updated Final Safety Analysis Report (UFSAR) design

and safety function descriptions. Based on the combination of

inadequate PRF procedural guidance and excessive penetration room

i boundary (PRB) in-leakage. the Unit 1 and 2 PRF systems may not have

l been able or available to perform their intended safety function under -

l

all required accident conditions (Sections 02.1 M2.1).

e Fuel movement was performed in the Unit 2 spent fuel pool (SFP) with

both trains of the PRF system inoperable. This was a condition

prohibited by Technical Specification (TS) 3.9.13 (Section 08.1).

k M.intenance

a

.

e The inspectors and licensee identified many discrepancies in the data

i recorded during PRF surveillance testing. Unclear test procedure

! guidance contributed significantly to the many documented errors. One

i surveillance test conducted on December 1.1992. resulted in failing to

i meet TS system flow acceptance criteria (Section M1.1).

1

e The PRB has degraded to such an extent that in-leakage was many times

greater than assumed in the UFSAR. Excessive in-leakage 3revented the

PRF system from operating per the design descriation in tie UFSAR. This

condition has existed for many years and could lave been recognized by

the licensee with the evidence available from routine surveillance

testing (Section M2.1).

e The PRF system surveillance test procedures contained numerous

deficiencies and failed to provide adequate guidance for testing the PRF

system (Section M2.1 and M3.1)

-

e The licensee failed to fully implement the Unit 1 and 2 TS surveillance

requirements (SR) for airflow capacity tests, visual inspections, and

heater testing for the PRF system. Control Room Emergency Filtration

System, and Containment Purge exhaust filter (Section M3.2).

l Enclosure

i

-- - - . _ _ . . _ _

.-.

a

. .

.

Reoort Details

I. Ooerations- i

!

02 Operational Status of Facilities and Equipment

i

02.1 Enaineered Safeauards Feature System Walkdown l

a. Insoection Scoce (IP 71707)

Ins)ectors used Inspection Procedure (IP) 71707 to perform a detailed

wal(down of the accessible portions of the Unit 1 and Unit 2 Penetration

Room Filtration (PRF) system. The inspectors also performed a detailed

review of the current licensing basis for PRF and compared it to the

existing plant configuration and procedural guidance including

Emergency Response Procedures (ERPs). System Operating Procedures

(SOPS). Annunciator Response Procedures (ARPs), and Surveillance Test

Procedures (STPs). Refer to paragraphs M1.1. M2.1, M3.1. and M3.2 for

inspection findings regarding PRF system surveillance testing and

discrepancies between the as-built versus Updated Final Safety Analysis '

. Report (UFSAR) design description.

b. Observations and Findinas

The UFSAR identifies that the PRF system is a dual purpose system

designed to: 1) process air from the fuel handling area during a fuel

handling accident and 2) establish a negative pressure within the

penetration room boundary (PRB) and provide a filtered release path for

airborne radioactivity during a loss of coolant accident (LOCA). The i

PRF system is normally aligned to exhaust air from the spent fuel 2001

'

(SFP) and is designed to automatically start upon receipt of a hig,

radiation signal or low SFP ventilation system exhaust flow. In the <

event of a LOCA. the PRF system is designed to automatically start on a

containment phase B signal (i.e., high-high-high containment pressure

setpoint of 27 psig) and must be manually realigned to allow cleanu) of

radioactive containment leakage and emergency core cooling system (ECCS)

component leakage into the PRB.

As described in the UFSAR. each PRF train is composed of: 1) a filter

bank containing a prefilter. High Efficiency Particulate Air (HEPA)

filter, and charcoal adsorber section. 2) two fans, a 4500 cubic feet

per minute (cfm) recirculation fan and a 500 cfm exhaust fan, which take

a suction on the outlet end of the filter Dank. and 3) the associated

ducting and dampers to contr01 the flow path of the system. The exhaust

fan has only one discharge path, which is out the plant vent stack. The

recirculation fan has two discharge paths. one out the plant vent stack

(exhaust) and the other back into the PRB (recirculation). On a phase B

actuation, both fans are designed to start in the exhaust mode to

rapidly draw a negative pressure in the PRB. When the Residual Heat

Removal (RHR) system heat exchanger room reaches approximately -2 inches

of water pressure, the recirculation fan recirculation valve is designed

to automatically modulate open until pressure in the PRB reaches

Enclosure

__ _ __

. - . _ _ _ _ ._ _ _ _ _ _ _ _ _ _ _ _ _ .._ ._ ._

b

'

  • e

.

l

l

,

2 i

,

l approximately -1.7 inches of water. In this alignment, the  !

4

recirculation path provides for cleanup of the PRB and reduces the '

exhaust flow out the plant vent stack, thus reducing the amount of I

radioactivity released to the environment and providing for filtration  :

of the PRB atmosphere for increased cleanup. )
1

[ UFSAR Section 6.2.3.2.2 describes two manual operator actions necessary

2

to o)erate the PRF system in the post-LOCA mode. The operator has to: 1

1) slut the SFP area suction dampers to the PRF system, and 2) shut the )

recirculation fan exhaust damper, when the recirculation valve receives  !

'

!

an o)en signal .cr the PRB low pressure annunciator is received. to place

{ the 3RF system in the recirculation mode. The UFSAR also identifies

that the safety function of the PRF system is to: 1) keep the SFP area

);

'

at a negative pressure for fuel handling accidents, and 2) maintain the i

PRB at a negative pressure to ensure that containment and ECCS component

'

leakage during post-LOCA reactor coolant recirculation is filtered prior

to release.

The inspectors reviewed applicable ERPs. SOPS, ARPs, and STPs to verify

,

that operator actions were properly specified and that the PRF system

-

was tested in a manner to ensure that it would operate as stated in the

.

UFSAR. On January 28. 1997, the inspectors determined that shutting the

?

'

suction dampers from the SFP area to the PRF system was identified in

plant operating and test procedures. However, shutting the PRF

recirculation fan exhaust damper, to shift into the recirculation mode,

was not identified in any ERP or SOP. Existing ERP guidance only

'

directed operations to verify that both trains of the PRF system

started, and then place one train in standby. UFSAR Section 6.2.3.2.2

states. "When either a two out of three differential pressure signal of

l -2 in, or a recirculation line valve open signal is annunciated in the

'

control room, the operator closes the valve at the discharge of the

recirculation fan;" and "the analysis of the combined system (fans vs.

'

in-leakage) indicates a setpoint of -2 in. wg pressure to be used for

i switching to recirculation operation." Also, Alabama Power Company

,

'

Drawing D-205013. HVAC: Process Flow Diagram Penetration Filtration

System. Revision 6, specifically identifies Post LOCA Recirc Mode and

i Post LOCA Exhaust Mode as PRF system configurations which correspond

with the system operation described in the UFSAR. However, instructions

for PRF system operation in the recirculation mode, exhaust mode, or

combined mode of operation, were not contained in alant procedures.

Further review by the inspectors discovered that tais UFSAR discrepancy

was identified by the licensee's UFSAR reverification program on

September 30, 1996. However, no corrective actions had been taken.

The inspector discussed the post-LOCA PRF system operation with several

licensed reactor operators and senior reactor operators. These

personnel were not aware of the post-LOCA PRF system recirculation mode

nor with the design basis requirement to shut the PRF system

recirculation fan exhaust valve. Feiling to shift the PRF system into

the post-LOCA recirculation mode as described in the UFSAR would cause

Enclosure

_ _ . _ _. , .

. _ . . . _ . . _ _.___ _ . _. _ _ _-_ __ - _ _ .

.

. .

.

.

3

. higher than designed exhaust flow and lower than designed recirculation

4 cleanup of the PRB. Although the higher exhaust flows could increase

1- the rate of radioactive release, the quantity of release would be within

l' the bounds of the UFSAR evaluation that concluded such releases would be

'

less than 10 CFR 100 limits. The lower than designed recirculation flow

would reduce the effectiveness of the recirculation cleanup and could

result in higher dose rates and exposures in the PRB during a:cident

recovery activities. Failure to operate the PRF system in the

4

"

recirculation mode would adversely affect licensee ability to maintain

doses "as low as reasonably achievable."

UFSAR Sections 6.2.3 and 15.4.1.10 describe that the safety function of

i

"

the PRF system is to maintain the PRB at a negative pressure to ensure

- that ECCS equipment leakage during the post-LOCA reactor coolant

-

recirculation phase is filtered prior to release. UFSAR

i Section 6.2.3.2.2 stated. "In the event of a LOCA. the penetration room

)

'

filtration system will be manually realigned to operate in the LOCA mode

orior to the end of in.iection [ underline added] and will operate

i#

automatically." However, the PRF system is only designed to start

automatically on a phase B containment isolation signal. as a

4 consequence of a very large break LOCA. For the broad range of smaller

LOCA break sizes that do not reach the phase B setpoint. the PRF system
. is not designed to automatically start. The inspectors reviewed

FNP-1/2-ESP-1.3. Transfer to Cold Leg Recirculation. Rev u 'n 11. and

other applicable ERPs. and found that they did not provide any

i instructions for starting the PRF system. Since plant ERPs did not

direct starting the PRF system arior to initiation of )ost-LOCA cold leg

recirculation (i.e. , prior to tie end of injection), t1e PRF system

'

would only perform its intended safety function for those LOCAs that

, result in containment pressure over 27 psig. There was no indication

. . that the PRF system would ever be started during LOCAs involving small

or medium sized breaks. The inspectors also noted that plant ERPs did

not direct the operators to periodically monitor PRF system operation to

ensure that it was operating properly. Interviews of operators

determined that they were not aware that the PRF system was required to

be running prior to initiating cold leg recirculation.

The inspectors reviewed FNP-1/2-ESP-1.1. SI Termination. Revision ll,

and FNP-1/2-ESP-1.2. Post LOCA Cooldown and Depressurization.

Revision 12. FNP-1/2-ESP-1.1. step 3. and FNP-1/2-ESP-1.2. step 4.

direct the operators to secure one train of the PRF system and place it

in standby. However, the procedures did not )rovide operator

instructions for monitoring the PRB to atmosplere differential pressure

(dP) to ensure that the remaining PRF train was performing properly.

The PRB to atmosphere differential pressure is not indicated in the main

control room at-the-controls area nor does an annunciator alarm to

indicate loss of PRB negative pressure. The inspectors concluded that

the ESPs did not provide adequate operator guidance for placing one

train of the PRF system in standby during post-LOCA operation. This

lack of guidance could have resulted in operators securing one train of

Enclosure

. _ _ _ . __ _._ -

- _ _ _ _ _ _ _ _ . _ . _ _ . _ _ .

. .

i

, ,

'

j 4

the PRF system, with the other train being unable to maintain a negative

pressure due to excessive PRB in-leakage. ,

in The inspectors reviewed FNP-1/2-SOP-60.0, Penetration Room Filtration

System. Revision 11. and determined that it did not contain guidance for

aligning the PRF system to the recirculation mode nor how to operate and

,

monitor system performance after one train was secured as directed in  :

1 the ERPs.

Plant procedural deficiencies regarding PRF system operation, testing i

l. (see Sections M2.1 and M3.1). and emergency response are examples of ,

l Escalated Enforcement Item (EEI) 50-348. 364/97-04-01. Inadequate l

'

Procedural Guidance for PRF System Operation and Testing - Multiple

Examples.

!-

4- The inspectors identified each of above discrepancies to plant

! management as they were identified. Several meetings were held with

! licensee personnel between January 29 and February 14 to discuss these

and other findings described in this report. On January 31., the

licensee informed the inspector that the plant was within the design

basis because: 1) the offsite dose calculations for the design basis

accident did not depend on the PRF system exhaust flow rate, and 2) PRF

was able to achieve a negative pressure in the PRB with the current I

plant 3rocedural guidance. The licensee also stated that it considered I

the PR system to be operable because FNP-1/2-STP-20.0. Penetration Room 4

Filtration System Train A(B) Quarterly Operability and Valve Inservice ,

Test Revision 23. 'had demonstrated the system's capability to maintain l

.a negative pressure in the PRB (albeit in the exhaust mode only, and

only while running one train at a time). ,

,

!

On February 5. the licensee provided the inspectors a copy of the PRF

system operability determination. That afternoon. the Plant Operations

Review Committee reviewed and approved a safety evaluation to change the

UFSAR. This change allowed operators the flexibility to align the PRF

system in either the recirculation or exhaust mode of operation. The

inspectors reviewed these documents and considered them to be adquate.

However, the inspectors disagreed with the specific statecent in the

safety evaluation that described the operator action to shut the

recirculation fan exhaust damper as an " inconsistency between FSAR

sections." The licensee also revised all ap)licable ERPs and S0P to

incorporate adequate instructions to ensure 3RF system operation during

all LOCAs.

Licensee corrective actions to address the procedural deficiencies were ,

prompt and thorough. All- procedure deficiencies were corrected by  !'

temporary change notices and/or procedure revisions The inspectors

reviewed these procedure corrections and determined that they adequately

, addressed the deficiencies. Most changes were implemented within seven

days of identification, The procedure changes for the ERP deficiencies

4

Enclosure '

. _ _ _ . _ . . - _ . _ _ . _ _ . _ _ _ . _ _ _ _ _ _ _ _ _ _

'

. .

}

j' .

L

J-

l 5

i

! were implemented two days after the inspectors identified the deficiency

to the licensee.

The system components were in good condition and installed as described-

4

in the UFSAR. The PRF system room was clean and well-maintained. J

c. Conclusions

-

4

The system was physically well maintained. However, procedural guidance

! for normal operation. surveillance testing, and emergency conditions was

l- inadequate. Licensee corrective actions to date have been thorough and

prompt. A lack of procedural guidance for ensuring system operation

prior to and during )ost-LOCA cold leg recirculation in a manner

consistent with the JFSAR design and safety function descriptions was  :

, identified. The inspectors determined that, based on the combination of

i inadequate PRF system procedural guidance and excessive PRB in-leakage

j (Section M3.2), the Unit 1 and Unit 2 PRF systems may not have been able

-

or available to perform their intended safety function under all

p required accident conditions.

, ,

f 08 Miscellaneous Operations Issues (IP 92901)

$ 08.1 .(Closed) URI' 50-364/96-13-01. PRF Ooerability Reauirements for SFP.

,

} This issue concerned the failure to meet the TS operability requirements

L for the PRF system on October 31. 1996, while moving fuel in the Unit 2

SFP area. Both the onshift o)erating crew and inspectors independently

L concluded that two' trains of 3RF were inoperable during fuel movement in

l the Unit 2 SFP. Plant management disagreed with this conclusion and

, subsequently documented its position in a letter to the NRC dated i

i November-27. 1996, requesting a formal TS interpretation. On March 6.- ,

. 1997, the NRC issued a reply to Southern Nuclear Operating Company. Inc. j

L (SNC), supporting the operators' and inspectors' original conclusions.

i Consequently. on October 31, 1996. fuel movement had been performed in

j the Unit 2 SFP while both trains of the PRF system were inoperable.

This was a condition prohibited by TS 3.9.13 and should have been l

terminated as soon as possible and reported pursuant to 10 CFR 50.73.

The licensee's failure to conform wit 1 their TS and required reporting

requirements is identified as EEI 50-364/97-04-02. Moving Fuel in a

Condition Prohibited by TS. URI 50-364/96-13-01 is closed based on

identifying this item as an apparent violation.

Enclosure

. . - . -

. .

6

II. Maintenance

M1 Conduct of Maintenance

M1.1 Penetration Room Filtration (PRF) System Performance Test

a. Insoection Scoce (IP 37551)

The inspectors reviewed past test data packages of FNP-1/2-STP-124.0,

Penetration Room Filtration Performance Test, performed in 1995 and the

' test results dating back to 1992.

b. Observations and Findinas

On January 28, 1997, the inspectors reviewed seven data packages which

documented the performance of FNP-1/2-STP-124.0 in 1995 on both units.

-

The inspectors identified discrepancies in the data entries for the

tests and asked the licensee to verify the data and test results for

prior tests. The licensee performed an evaluation of Unit 1 and Unit 2

test data for FNP-1/2-STP-124.0 starting in 1992. Licensee engineers  !

identified four data transposition errors and one calculational error in  !

'the 1992 tests. The calculational error was corrected and flow was  ;

still within the Technical Specification (TS) acceptance criteria. Data- 1

transposition errors resulted in the wrong duct size being used to

determine flow through the 14-inch recirculation exhaust line. After

correcting the data and recalculating, the licensee determined that the  ;

system flow rate for the Unit 2 A train PRF system, as measured on

December 1, 1992, was 5615 cubic feet per minute (cfm). This flow rate

was outside the TS Surveillance Requirement (SR) 4.7.8.b.3 acceptance I

criteria of 5000 1 10%. However, the next 18-month performance of  !

FNP-1/2-STP-124.0 for the 2A PRF system on May 18, 1994 did meet the TS  ;

acceptance criteria. No modifications or attempts to change system ,

performance were made during the intervening period. The licerisee's

failure to meet TS acceptance criteria is identified as EEI

50-364/97-04-03, Failure to Meet TS SR 4.7.8.b.3 Acceptance Criteria.

c. Conclusions

The inspectors and licensee identified many discreaancies in the data

recorded during PRF system surveillance testing. Jnclear test procedure

guidance contributed significantly to the many documented errors. An

apparent violation was identified in one surveillance test conducted on

December 1, 1992, which resulted in failing to meet TS system flow  ;

acceptance criteria.

<

Enclo:;ure i

.

. .

.

7

M2 Maintenance and Material Condition of Facilities and Equipment

M2.1 Penetration Room In-leakaae

a. Insoection Scooe (IP 61726)

The inspectors reviewed past test data packages of FNP-1/2-STP-124.0,  !

Penetration Room Filtration Performance Test, aerformed in 1995 and the '

test results dating back to 1992. Data from t1e tests were compared

with design assumptions identified in the Updated Final Safety Analysis

Report (UFSAR). The inspector also reviewed the guidance contained in

FNP-1/2-STP-20.0, Penetration Room Filtration System Train A(B)

Quarterly Operability and Valve Inservice Test. PRF system testing

conducted on February 6. 1997 was observed by the inspectors.

b. Observations and Findinas j

' UFSAR section 6.2.3.1.2 describes the criteria used to determine PRF  !

design flow rates, and states. "The exhaust flow rate is equivalent to

the penetration room boundary in-leakage: 1.e. , the sum of all possible

in-leakages when a pressure of -1.5 in. wg is maintained within the  ;

penetration room boundary." It also states. " Minimizing the penetration '

room in-leakage increases the system effectiveness," and "...for

estimating the exhaust fan capacity, it has been conservatively assumed

that, with a -1.5 inches wg pressure, the in-leakage is 100 percent of

the penetration room volume per day. This in-leakage is equivalent to

250 scfm.

The previous FNP-1/2-STP-124.0 test results from 1995, indicated that

the penetration room boundary (PRB) in-leakage was much greater than

that assumed by the UFSAR. The data reviewed by the inspectors

indicated approximately 3700 cfm in-leakage on Unit 1, and 3000 cfm on

Unit 2, while at slightly less than -1.5 inches of water pressure. This  ;

condition has been evident in surveillance test data since at least i

1992. A surveillance test procedure (STP) observed on January 25, 1997,

(refer to Inspection Report (IR) 50-348, 364/97-01) indicated that the

Unit 1 PRB in-leakage was greater than 4000 cfm. far in excess of the .

250.cfm allowed in the UFSAR.  !

The excessive in-leakage of the Unit 1 and Unit 2 PRBs was reconfirmed

when the licensee performed FNP-1/2-STP-124.0 on the Unit 1 Train A PRF

on February 6, 1997. This test demonstrated that Train A could only

attain -0.9 inches of water in the Unit 1 PRB with both fans running in

the exhaust mode (indicating in-leakage of at least 4500 cfm). Three

minutes after shifting Train A to the recirculation mode, the Unit 1 PRB

returned to atmospheric pressure. Concurrently on Unit 2 the licensee

performed FNP-1/2-STP-20.0. Penetration Room Filtration System Train

A(B) Operability Test, on the B train PRF. The inspector observed that

while the 2B PRF system was in the recirculation mode, the Unit 2 PRB

pressure was atmospheric. This indicated that Unit 2 PRB in-leakage was

Enclosure

. . . . .-

.

. .

.

8

greater than the capacity of the exhaust fan (which has a minimum design

capacity of 500 cfm). UFSAR section 6.2.3.3.2. states, "The 3enetration

rooms are maintained at a pressure of -0.5 to -1.5 in. wg wit 1 only the

exhaust fan operating. If the recirculation fan were to remain in

operation in the exhaust mode, the pressure in the penetration rooms

could be maintained at 3.0 in. wg." These tests indicated that the

Unit 1 and Unit 2 PRBs did not meet the UFSAR design descriptions. This

is identified as eel 60-348. 364/97-04-04 PRB In-leakage in Excess of

UFSAR Design. i

The inspectors reviewed the licensee's STPs to determine if any testing

was performed to specifically identify PRB degradation.

FNP-1/2-STP-20.0 contained a " Note" describing indications of proper

'

system operation (with PRB doors closed), acceptance criteria (i .e. .

recirculation valve open at -2.2 inches of water. -3 inches of water at

the PRB with both fans in the exhaust mode), and requirements for

corrective action if the expected system operation was not observed.

However, the )rocedure did not direct the operator to observe nor record

PRB-to-atmosplere differential pressure (dP) when the system was

configured in the modes identified by the note. Also there was no

evidence (e.g. , deficiency report) that operators recognized the

degraded PRB conditions during prior tests. This lack of guidance for

PRF testing is identified as an example of EEI 50-348, 364/97-04-01.

Inadequate Procedural Guidance for PRF System Operation and Testing -

Multiple Examples.

c. Conclusions

The PRB had degraded to such an extent that in-leakage was many times

greater than the design described in the UFSAR. The excessive in-

leakage prevented the PRF system from operating as described in the

UFSAR and was not recognized by the licensee staff even during the

conduct of FNP-1/2-STP-20.0, due to inadequate procedure guidance and

training.

M3 Maintenance Procedures and Documentation

M3.1 Unit 1 Penetration Room Filtration Performance Test (IP 61726)

The inspector observed the performance of FNP-1-STP-124.0. on the

Unit 1. Train A PRF system. Details of this observation were documented

in IR 50-348, 364/97-01. As a result of this observation the inspector

identified the following procedural deficiencies in FNP-1/2-STP-124.0.

e Several steps were no longer applicable due to updated equipment.

e The procedure did not specify the technique for obtaining the air

velocities. On one of the ducts, the test personnel performed

both horizontal and vertical traverses because the readings for

the horizontal traverse put the air flow below the acceptance

Enclosure

. _ _ _ . - . _ . -.-. _ _ _ _ . _ _ __ _ _._.._. .. .___m.. . _

. , .

,

g :

!

.

) 9

L criteria. Only a vertical traverse was performed on the other

duct.

{

e The precedure did not identify from which ducts to take air

j velocity measurements. There are three ducts per train but the

STP provides data columns for only two ducts.

J

! e The note prior to step.7.7 incorrectly specifies that the

individual velocity readings be within 20% of the average

velocity.

$ e TS 4.7.8.b.3 states that cystem flow rates be tested in accordance

j with Section 8 of ANSI N510-1980. However STP-124.0, which-

F implements this TS required test, did not perform system

i resistance flow tests as identified in Section 8 of ANSI N510-

L 1980.

i

e The inspector also determined that, while FNP-1/2-STP-124.0.

<

step 7.5, directed operations to start the PRF train to be tested

and align it in the recirculation mode, neither the STP-nor the

system operating procedure (SOP) contained guidance for-

} configuring the system for the recirculation mode.- The inspector

i noted that the system was not aligned in the recirculation mode as

described by the UFSAR for the performance of this test.

, The inspectors concluded that the above identified deficiencies are

! examples of inadequate guidance for testing the PRF system. This is an

i example of EEI 50-348, 364/97-04-01. Inadequate Procedural Guidance for

i

PRF System Operation and Testing - Multiple Examples. These ,

deficiencies were discussed with Engineering Su) port (ES) management 1

4

during various meetings between January 27 and rebruary 14. ES l

management was responsive to the inspectors' findings.

FNP-1/2-STP-124.0 was subsequently revised and reperformed. ]

1

M3.2 Surveillance Testino of Safety-Related Ventilation Systems Per American

i National Standards Institute. Inc. (ANSI)'N510 ,

j a. Insoection Scoce (IP 61726)-

4

) The inspectors compared the PRF system STPs to the TS surveillance

! requirements including ANSI N510-1980: reviewed previously completed

STPs
and reviewed original acceptance tests.

.

l b .' Observations and Findinas

TS SR 3.7.8.b describes the 18-month testing requirements for the High

Efficiency Particulate Air (HEPA) filter and charcoal filter efficiency,  !

i and system flow. TS SR 3.7.8.b.3 requires " verifying system flow rate '

of 5000 cfm 10% during system operation when tested in accordance with l

! Section 8 of ANSI N510-1980." The inspector reviewed Section 8 of j

j Enclosure ,

4

.

J

l

_ , - . . - ~ .. - .- . -- -

a , i

s. -

1

10 l

ANSI N510-1980 to verify that the observed tests met the ANSI l

specifications. On January 28, 1997, the inspector reviewed

FNP-1/2-STP-124.0 and determined that it did not incorporate the " dirty

filter" tests specified in steps 8.3.1.6 and 8.3.1.7 of ANSI N510-1980.

Section 8.3.1 Airflow Capacity Test. The inspector asked the licensee

to address why the " dirty filter" testing of section 8 was not being

performed. The licensee stated that the " dirty filter" tests are only

required for acceptance tests and are not required for periodic

surveillance. The insaectors disagreed with this interpretation. The

ins)ectors requested tlat the licensee provide the acceptance test

paccages for the PRF system documenting the conduct of the " dirty

filter" tests. The licensee provided the PRF system acce)tance test

package for Unit 2 but was unable to locate any Unit 1 PR system

acceptance package indicating that " dirty filter" testing was

performed. Also, the Unit 2 package did not clearly demonstrate that l

the " dirty filter" tests were performed per ANSI N510-1980. The '

inspectors verified that the " dirty filter" testing was not performed by

any periodic STP. This failure to perform TS SR 3.7.8.b.3 Jer '

ANSI N510-1980 is identified as EEI 50-348, 364/97-04-05, railure to

Perform TS Surveillance Requirements for Safety-Related Ventilation

Systems - Multi)le Examples. The licensee commenced " dirty filter" .

testing of the Jnit 1 and Unit 2 PRF systems on February 19 in  !

accordance with ANSI N510-1980, and successfully completed this testing

by February 21. 1997.

In addition to system flow testing to demonstrate PRF operability.

TS SR 4.7.8.b.1.a requires a visual inspection of PRF filters every 18

months, in accordance with Section 5 of ANSI N510-1980, and TS

SR 4.7.8.d.3 requires PRF heater testing, in accordance with Section 14

of ANSI N510-1980 every 18 months. Testing to ANSI N510-1980

requirements every 18 months also applies to other safety-related

ventilation systems. To demonstrate operability of the Control Room

Emergency Filtration System (CREFS). TS SR 4.7.7.1 requires visual

filter inspections, in accordance with Section 5: system flow

verifications, in accordance with Section 8: and pressurization system

heater testing. in accordance with Section 14. TS SR 4.9.14 requires

visual inspection of the Containment Purge exhaust filter, in accordance

with Section 5.

On February 23, 1997, after considerable review effort, the licensee

concluded that its surveillance test program did not include numerous

portions of ANSI N510-1980. Sections 5, 8, and 14. Testing and

,

inspection in accordance with these sections of ANSI N510 were required

! by TS SR 4,7.8 (PRF system). TS 4.9.14 (Containment Purge exhaust) and

TS SR 4.7.7.1 CREFS. This issue is identified as an example of

i EEI 50-348, 364/97-04-05. Failure to Perform TS Surveillance

Requirements for Safety-Related Ventilation Systems - Multiple Examples.

]

On February 26, 1997, at 12:27 PM CST. the licensee declared that it had

entered into TS 3.0.3 for' Units 1 and 2. for failing to comply with the

Enclosure

l

l

. . -- . - - - . . - - - - - -~. -~ - . . - . . .

. .

_

3-

l 11

TS SRs of the PRF system (TS 4.7.8), Containment Purge (TS 4.9.14) and

CREFS (TS 4.7.7.1). After entry into TS 3.0.3. the licensee requested .

that the NRC issue a notice of enforcement discretion (NOED), which was

subsequently granted by the NRC. After receiving verbal notification of '

the NOED, the licensee exited TS 3.0.3 at 1:51 PM CST the same day. The

licensee submitted its formal request for an NOED by letter dated

February 27. By letter dated February 28, the NRC issued the NOED.

c. Conclusions

The licensee failed to fully implement the Unit 1 and Unit 2 TS SRs for

airflow capacity tests, visual inspections, and heater testing for the -

PRF system, CREFS, and Containment Purge exhaust filter.

V. Manaaement Meetinas and Other Areas  !

l

X1 Review of Updated Final Safety Analysis Report (UFSAR) Commitments

]

A recent discovery of a licensee o)erating its facility in a manner

contrary to the UFSAR description lighlighted the need for a special 1

focused review that compares plant practices, procedures and/or l

parameters to the UFSAR descriptions. While performing the inspections ]

discussed in this re) ort, the inspectors reviewed the applicable  ;

portions of the UFSAR that related to the areas inspected. Several J

significant inconsistencies were identified between the wording in the

UFSAR and actual plant practices, procedures and/or parameters. These

inconsistencies principally involved the PRF system as described in

UFSAR Section 6.2.3, and are discussed in detail in the previous

inspection report paragraphs.

X2 Exit Meeting Summary

The resident inspectors presented the ins)ection results to members of

licensee management on March 13, 1997. T1e licensee acknowledged the

findings presented.

The resident inspectors asked the licensee whether any materials

examined during the inspection should be considered proprietary. No

proprietary information was dentified.

PARTIAL LIST OF PERSONS CONTACTED

Licensee

M. Aj1 uni SNC (Corporate) Licensing Manager - Farley Project

R. Coleman, Maintenance Manager

D. Grissette. Operations Manager

R. Hill, General Manager - FNP

Enclosure

!

j

_ . _ _ _ _ _ . _ _ . _ _ _ . . _ _ _ . _ . _ _ _ _ _ _ _ . _ _ . _ _ . _ . _

,

'

. . .

.

I

'

12

0. Jones. SNC (Corporate) Engineering Manager - Farley Project [

R. Martin, Superintendent Operations Support  :

C. Nesbit Assistant General Manager - Support t

R. Rogers, Engineering Support Supervisor - Engineering Support

J. Sims. SNC (Corporate) Project Engineer

L. Stinson, Assistant General Manager - Plant Operations

.J. Thomas, Engineering Support Nanager  :

NRC  ;

J. Zimmerman. Project Manager - Farley Nuclear Plant

INSPECTION PROCEDURES USED

IP 37551: Onsite Engineering

IP 61726: Surveillance Observations

IP 71707: Plant Operations

IP 92901: Followup - Operations

ITEMS OPENED, CLOSED, AND DISCUSSED -

Opened

lyng Item Number Status Descriotion and Reference i

!

EEI 50-348, 364/97-04-01 Open Inadequate Procedural Guidance for PRF

System Operation and Testing - Multiple

Examples (Sections 02.1, M2.1, and M3.1).  ;

EEI 50-364/97-04-02 Open Moving Fuel'in a Condition Prohibited by

TS (Section 08.1).

EEI 50-364/97-04-03 Open Failure to Meet TS SR 4.7.8.b.3 Acceptance

Criteria (Section M1.1).

EEI 50-348, 364/97-04-04 Open PRB In-leakage in Excess of UFSAR Design

(Section M2.1).

-EEI 50-348, 364/97-04-05 Open Failure to Perform TS Surveillance

Requirements for Safety-Related

Ventilation Systems - Multiple Examples

(Section M3.2).  :

Enclosure

.;

, _ _ _ . . .. .- . _ . _ . _ _ _ . _ _ _ _ _ . _ . _ _ . _ . _ . _ _ _ _ . - _.

,

. . .

,

,

l- 13

i

'

Closed

i

j Iygg Item Number Status Descriotion and Reference

!-

URI 50-364/96-13-01 Closed PRF Operability Requirements for SFP

(Section 08.1).

!

i

j. LIST.OF ACRONYMS USED

.

! ANSI American National Standards Institute, Inc.

l ARP Annunciator Res)onse Procedure

cfm Cubic Feet-per iinute

CFR Code of Federal Regulations

CREFS Control Room Emergency Filtration System

!' dP Differential Pressure

ECCS Emergency Core Cooling System

! EEI Escalated Enforcement. Item

! ERP Emergency Response Procedure

1 ES Engineering Sup) ort

FNP Farley Nuclear )lant

j HEPA High Efficiency Particulate Air

! HVAC Heating. Ventilation, and Air Ccnditioning

! IP Inspection Procedure

Inspection Report

'

IR

LC0 Limiting Condition of Operation

1

'

LOCA Loss of Coolant Accident

NOED Notice of Enforcement Discretion

! NRC- U.S. Nuclear Regulatory Commission

3 PRB Penetration Room Boundary

i PRF Penetration Room Filtration

l 3sig )ounds per square inch gauge

t lHR Residual Heat Removal

P scfm standard cubic feet per minute

! SFP Spent Fuel Pool

i SI Safety Injection

SNC Southern Nuclear Operating Company, Inc.

i S0P System Operating Procedure

! SR Surveillance Requirement

STP Surveillance Test Procedure

j TS Technical Specifications

Updated Final Safety Analysis Report

'

UFSAR

URI Unresolved Item

wg Water Gauge

>

'

Enclosure

_ _ _ . _ -. _ - . _ - _ . - _ __ _. .