Discusses Review & Evaluation of 960605 Request for Relief from Requirements of Section XI of ASME Boiler & Pressure Vessel code,1980 Edition Through Winter 1981 Addenda. Safety Evaluation Encl
ML20135D102
Person / Time
Site: Clinton Constellation icon.png
Issue date: 12/04/1996
From: Marcus G
NRC (Affiliation Not Assigned)
To: Telthorst P
ILLINOIS POWER CO.
Shared Package
ML20135D106 List:
References
TAC-M95671, NUDOCS 9612090246
Download: ML20135D102 (5)


Text

_ _ . _ _ _ . _ _ _

y

  • i

[p2tt; kl UNITED STATES I

. g j

NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. Saaam "1

  • % *****/ December 4, 1996 l i

Mr. Paul J. Telthorst l Director - Licensing

Clinton Power Station l P. O. Box 678  ;

l Mail Code V920 i l

Clinton, IL 61727 i

SUBJECT:

EVALUATION OF ASME SECTION XI RELIEF REQUESTS REGARDING PERFORMANCE 0F NON-DESTRUCTIVE EXAMIN/iTIONS FOR THE FIRST 120-MONTH INSERVICE l INSPECTION INTERVAL - CLINTON POWER STATION, UNIT 1 (TAC NO. M95671) l

Dear Mr. Telthorst:

By letter dated June 5, 1996 (U-602566), and supplemented by letter dated September 20, 1996 (U-602638), Illinois Power submitted nine requests for

! relief from the requirements of Section XI of the American Society of l Mechanical Engineers (ASNE) Boiler and Pressure Vessel Code, 1980 Edition

! through Winter 1981 Addenda. These relief requests are associated with the performance of non-destructive examination of welds and components for the l l first 120-month inservice inspection interval for the Clinton Power Station.

The staff, with technical assistance from its contractor, the Idaho National Engineering Laboratory (INEL), has reviewed and evaluated the information provided. As discussed in the enclosed safety evalution, we have determined 1 that Relief Requests Nos. 4005, 4011, 4012 and 4013 are granted pursuant to 10

, CFR 50.55a(g)(6)(1); those welds that have been previously examined and I

included in Relief Request No. 4006 are granted pursuant to 10 CFR 50.55a(g)(6)(1); Relief Requests Nos. 4007 and 4008 are granted pursuant to 10 CFR 50.55a(3)(ii) as compliance with the code would result in hardship or unusual difficulty without a compensatory increase in the level of quality and safety; and Relief Request No. 4009 is granted pursuant to 10 CFR 50.55a(g)(4)(iv), provided that all related requirements are met. Relief Request No. 4010 and those welds of Relief Request No. 4006 that have not been previously examined are denied.

For the reliefs granted pursuant to 10 CFR 50.55a(g)(6)(1), we have determined that the requirements of the code are impractical and granting relief is authorized by law and will not endanger life or property or the common defense f and security. We have also concluded that granting the relief is otherwise in the public interest considering the burden that could result if the i

9612090246 961204 PDR ADOCK 05000461 G PDR

P. Telthorst requirements were imposed on the facility. The staff's evaluation and conclusions are contained in Enclosure 1. Enclosure 2 is the INEL Technical Letter Report.

Sincerely, jy w Gail H. Marcus, Director Project Directorate III-3 Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation Docket No. 50-461

Enclosures:

As stated cc w/encls: See next page

P. Telthorst requirements were imposed on the facility. The staff's evaluation and conclusions are contained in Enclosure 1. Enclosure 2 is the INEL Technical Letter Report.

Sincerely, Original signed by:

Gail H. Marcus, Director Project Directorate III-3 Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation Docket No. 50-461

Enclosures:

As stated cc w/encls: See next page Distribution:

PDIll-3 r/f JRoe Docket EAdensam (E)

PUBLIC GHill (2)

ACRS BMcCabe OGC JCaldwell, RIII DOCUMENT NAME: GO.CLINTON\CLI95671.LTR To receive e copy of this dos ,sent. Indicate in the boa: "C" = Copy without enclosures

  • E" = Copy with enclosures *N" = No copy 0FFICE LA:PDIII-3 l (b PM:PDIII-3l_G BC:ECGB l OGC l D:PDIII-3 _ l NAME DFoster-Curseen, DPickett W b GBagchi* MYoung** GMarcus 6:dffl DATE 12/4/96 MP 12/ 4/96 10/9/96 11/ /96 12/4/96 0FFICIAL RECORD COPY
  • See GBagchi to GMarcus Memorandum dated 10/9/96
    • See previous concurrence (D\

T i

s 0900% \

I P. Telthorst requirements were imposed on the facility. The staff's evaluation and conclusions are contained in Enclosure 1. Enclosure 2 is the INEL Technical Letter Report.

Sincerely, Original signed by:

Gail H. Marcus, Director Project Directorate III-3 Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation Docket No. 50-461

Enclosures:

As stated cc w/encls: See next page Distribution:

PDIII-3 r/f JRoe Docket EAdensam (E)

PUBLIC GHill (2)

ACRS BMcCabe OGC JCaldwell, RIII F

DOCUMENT NAME: G:\CLINTON\CLI95671.LTR Ta rooohe e copy of shie '- r: r, indioste in the bos: "C" = Copy without enclosures *E" = Copy with enclosures "N" = No copy 0FFICE LA:PDIII-3 l 0, PM:PDIII-3 ,6 BC:ECGB l OGC l 0: PDIII-3 _ l NAME DFoster-Cursten, ,DPicketfS7J L GBagchi* MYoung** GMarcus 6sHil DATE 12/A/ /96 thl >' 12/ 4/96 10/9/96 l11/ /96 12/4/96 0FFICIAL RECORD COPY

$52e GBagchi to GMarcus Memorandum dated 10/9/96

    • See previous concurrence

Mr. Paul J. Telthorst Clinton Power Station Illinois Power Company Unit No. 1 CC:

Mr. Wilfred Connell Vice President Illinois Departh.?nt Clinton Power Station of Nuclear Safety Post Office Box 678 Office of Nuclear Facility Safety Clinton, Illinois 61727 1035 Outer Park Drive Springfield, Illinois 62704 Mr. Daniel P. Thompson Manager Nuclear Station Engineering Department Clinton Power Station Post Office Box 678 Clinton, Illinois 617727 Resident Inspector U.S. Nuclear Regulatory Commission RRf3, Box 229 A Clinton, Illinois 61727 Mr. R. T. Hill Licensing Services Manager General Electric Company 175 Curtner Avenue, M/C 481 San Jose, California 95125 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, Illinois 60532-4351 Chairman of DeWitt County c/o County Clerk's Office DeWitt County Courthouse Clinton, Illinois 61727 Mr. J. W. Blattner Project Manager Sargent & Lundy Engineers 55 East Monroe Street Chicago, Illinais 60603