Forwards Insp Rept 50-346/96-05 on 960611-0814.Two Violations of NRC Requirements Were Identified Concerning Issues Initially Reviewed During Previous Insp
ML20134M772
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 11/19/1996
From: Caldwell J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Jeffery Wood
CENTERIOR ENERGY
Shared Package
ML20134M775 List:
References
EA-96-303, NUDOCS 9611260036
Download: ML20134M772 (3)


See also: IR 05000346/1996005

Text

. . . ~ . . _ _ . . _ _ _ _ _ _ . _ . _._. _ _ _.-._._ .. _ . _ _ _ _ _ . _

.

l

i.

i

//

Nhh ~0

l

November 19, 1996

l

i

i ,

!

l

EA No.96-303

Mr. John K. Wood

Vice President - Nuclear

Davis-Besse Nuclear Power Station I

i

Centerior Service Company

5501 North State Route 2

,

Oak Harbor, OH 43449

i

SUBJECT: .NRC INTEGRATED INSPECTION REPORT 50-346/96005 (DRP); NOTICE OF

VIOLATION

,

Dear Mr. Wood: .

!

'

On August 14,1996, the NRC completed an inspection at your Davis-Besse site. 'The .

enclosed report presents the results of that inspection.  ;

i

l In general, we noted that plant activities continued to be performed in a controlled,. I

j professional manner, utilizing a safety conscious approach. However, two violations of

!

NRC requirements were identified concerning issues initially reviewed during previous

. inspections.

l The first of these involved failure of personnel to understand and adhere to a procedure

l. designed to prevent unauthorized heavy loads from being transported over the open

reactor with fuelin the vessel. Ultimately, that failure coupled with weak

communications, resulted in a 9-ton load actually being lifted over the open reactor vessel.

The second violation involved station personnel failing to perform a timely safety

evaluation for the draining and abandonment of the Primary Water Storage Tank prior to

that activity occurring.

These violations are cited in the enclosed Notice of Violation, and the circumstances

surrounding the violations are described in detailin the enclosed report. Please note that

j you are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your response. The NRC will use your response, in part,

to determine whether further enforcement action is necessary to ensure compliance with

regulatory requirements.

I

200010

i  %

3

9611260036 961119

PDR ADOCK 05000346

G ppg g

-. - ._

, .- -- . _ . . -. .-- - _ - . -

l

.

J. K. Wood -2-

We are also concerned with the fact that training provided for control room operators in

l support of a recent technical specification change was ineffective. This change required

l that the volumes and boron conentrations for both boric acid addition tanks be considered

l in the aggreate to verify complicence with the technical specifications. When question

about an apparent discrepancy in the concentrations control room operators were unable

l to verify compliance (a reactor engineer did subsequently verify compliance).

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter

and its enclosures will be placed in the NRC Public Document Room (PDR).

Sincerely,

/s/ John A. Grobe

James L. Caldwell, Acting Director

Division of Reactor Projects

Docket No.: 50-346; 72-14

Enclosures: Notice of Violation

Inspection Report 50-346/96005 (DRP)

  1. See previous concurrence

Document name R:\ Davis \Dav96005.DRP

To receive a copy of this document, indicate in the box "C" = Copy without attach /enct

"E" = Copy with attach /enci "N" = No copy

0FFICE DRP DRS DRS EIC

NAME Tongue /sn & Creed M Kozak M Burgess iM

DATE 9/ /96 9/ /96 9/ /96 9/ /96

0FFICE DRP M DRP i

NAME LariksburMb Caldwelldk

DATE //p/ /7/96 //#/ d/96 /

OFFICIAL RECORD COPY

.. _ _ _ _ _ _ _ _ _ _. . . . . _ _ . . , _ _ _ _ _ . _ _ _

J. K. Wood -2-

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of

this letter and its enclosures will be placed in the NRC Public Document Room

(PDR).

Sincerely,

!

!

' James L. Caldwell, Acting Director

Division of Reactor Projects

Docket Nos.: 50-346

l

l Enclosures: Notice of Violation

Inspection Report 50-346/96005

cc w/ encl: J. P. Stetz, Senior Vice President - Nuclear

J. H. Lash, Plant Manager

.

J. L. Freels, Manager

l Regulatory Affairs

State Liaison Officer, State

of Ohio

Robert E. Owen, Ohio

l Department of Health

'

C. A. Glazer, State of Ohio,

Public Utilities Commission

Docket File w/ encl DRP w/ encl

PUBLIC IE-01 w/ encl RIII PRR w/ enc 1

OC/LFDCB w/ enc 1 CAA1 w/enci (e-mail)

SRI Davis-Besse w/ encl W. L. Axelson w/ enc 1

Project Manager, NRR w/ encl A. B. Beach, w/ enc 1

B. L. Burgess, w/ encl

Document name R:\ Davis \Dav96005.DRP

i To receive a copy of this document, indicate in the box "C" = copy without

! attach /enci "E" = copy with attach /enci "N" = No copy

0FFICE DRP 8. DRS _ 2 b DRS N EIC . /, b

NAME Tongue /snN# CreedY Kozak h Burg

l

i DATE 9/fD/96 9/N/96 9/ O /96 9/d/96

0FFICE DRP DRP

<

NAME Lanksbury Caldwell/Grobe

'

DATE 9/ /96 9/ /96

0FFICIAL RECORD COPY