HL-5314, Monthly Operating Repts for Jan 1997 for Ei Hatch Nuclear Plant

From kanterella
(Redirected from ML20134L805)
Jump to navigation Jump to search
Monthly Operating Repts for Jan 1997 for Ei Hatch Nuclear Plant
ML20134L805
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 01/31/1997
From: Shannon Rogers, Woodard J
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
HL-5314, NUDOCS 9702190294
Download: ML20134L805 (11)


Text

. .. . . - . .- - --..

. - - - - - - - - - - . ~ - . -

- - - - - - ~ ~ ~ ~

-Georgia Power Company.

+

333 Piedmont Avenue

.

  • Atlanta, Georgia 30308 Telephone 404 526-3195 0
  • Maihng Address j

4- 40 inverness Center Parkway Post Office Box 1295 Birmingham, Alabama 35201

j ' Telephone 205 868-5086 J. D. Woodard the sauthem electrc system Senior Vice President February 7, 1997

$ Docket Nos. 50-321 l 50-366 HL-5314 l

l U. S. Nuclear Regulatory Commission j ATTN: Document ControlDesk Washington, D. C. 20555 Edwin I. Hatch Nuclear Plant Monthly Operatine Report,s Gentlemen:

Enclosed are the January 1997 Monthly Operating Reports for Edwin I. Hatch Nielear Plant Unit 1, Docket No. 50-321, and Unit 2, Docket No. 50-366. These reports are submitted in accordance with Technical Specifications requirements.

Sincerely, foA J. D. Woodar CLT/eb

Enclosures:

l

1. January Monthly Operating Repon for Plant Hatch Urit I  ;
2. January Monthly Operating Report for Plant Hatch Unit 2 cc: Georeia Power Comnany l Mr. H. L. Sumner, Nuclear Plant General Manager l

< NORMS

\

U. S. Nuclear Remilatorv Commission. Washineton D. C.

l Mr. K. Jabbour, Licensing Project Manager - Hatch U. S. Nuclear Rendatory Commission. Region 11 i Mr. L. A. Reyes, Regional Administrator Mr. B. L. Holbrook, Senior Resident Inspector - Hatch Utility Data Institute. Inc.

Mr. Fred Yost, Director - Research Services 9702190294 970131 7 PDR ADOCK 05000321-R P DR...-

=====ar. --,wrc._ w --,r------ -

.---w- - - --- -

m - - , - - - e

._-._s Enclosure 1 t Mant Hatch Unit 1

, Month'y Operating Report j inuary 1997 Table if Contents i P3.gc Narrative Report El-1 ,

' i Operating Data Report El-2 Average Daily Power Level El-3 l

Unit Shutdowns and Power Reductions El-4 i

l I

l l

PLANT E.1. HATCH - UNIT ONE DOCKET NO.: 50-321 NARRATIVE REPORT DATE: FEBRUARY 4,1997 COMPLETED BY: S. B. ROGERS TELEPHONE: (912) 367-7781 x2878 JANUARY 1 0000 Shift continued to rnaintain rated thermal power.

JANUARY 25 1240 Shift began reducing load to approximately 820 GMWe to perform Control Rod Drive Exercises on selected control rod drives.

JANUARY 25 1255 Shift began ascension to rated thermal power.

JANUARY 25 1313 The unit attained rated thermal power.

JANUARY 28 1530 At management direction, Shift began reducing load for a urst shutdown due to an increasing trend on unidentified drywellleakage.

JANUARY 29 0121 Shift manually tripped the Main Turbine.

JANUARY 29 0849 Shift manually scrammed the reactor.

JANUARY 31 2400 Personnel continued activities associated with the drywell leak repair outage.

E1-1

  • i OPERATING DATA REPORT DOCKET NO.: 50-321 DATE: FEBRUARY 4,1997 COMPLETED BY: S. B. ROGERS TELEPHONE: (912) 367-7781 x2878 OPERATING STATUS
1. UNIT NAME: E.1. HATCH - UNIT ONE
2. REPORT PERIOD: JANUARY 1997
3. LICENSED THERMAL P0WER (MWt): 2558 l
4. NAMEPLATE RATING (GROSS MWe): 850
5. DESIGN ELECTRICAL RATING (NET MWe): 822.1
6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe): 835
7. MAXIMUM DEPENDABLE CAPACITY (NET MWe): 800
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

Maximum Dependable Capacities for 1997 are 835 MWe (Gross) and 800 MWe (Net).

The values were determined from 1996 operational data.

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe): NO RESTRICTIONS
10. REASONS FOR RESTRICTION,IF ANY: N/A THIS MONTH YEAR-TO-DATE CUMULATIVE
11. HOURS IN REPORTING PERIOD: 744.0 744.0 184847
12. NUMBER OF HOURS REACTOR WAS CRITICAL: 680.8 680.8 142913.6
13. REACTOR RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
14. HOURS GENERATOR ON LINE: 673.4 673.4 137600.8
15. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWHt): 1710048 1710048 312024724
17. GROSS ELECTRICAL ENERGY GENERATED (MWHe): 561214 561214 100423936
18. NET ELECTRICAL ENERGY GENERATED (MWHe): 537776 537776 95621186
19. UNIT SERVICE FACTOR: 90.4 % 90.4 % 74.4 %
20. UNIT AVAILAfilLITY FACTOR: 90.4 % 90.4 % 74.4 %
21. UNIT CAPACI P/ FACTOR (USING MDC NET): 90.4 % 90.4 % 68.8%
22. UNIT CAPACITY FACTOR (USING DER NET): 87.9% 87.9 % 66.4 %
23. UNIT FORCED OUTAGE RATE: 0.0% 0.0% 10 2%
24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH): N/A
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

Generator was tied to the grid February 3,1997.

26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): N/A E1-2

. _ - - . - - -- . . ._. . .. - _ _ _ - . . _ - . . - - - . = . _ _ - ~ .

l r

PLANT E.1. HATCH - UNIT ONE DOCKET NO.: 50-321 4

DATE: FEBRUARY 4,1997  !

j

' AVERAGE DAILY POWER LEVEL COMPLETED BY: S. B. ROGERS  !

TELEPHONE: (912) 367-7781 x2878 l JANUARY 1997 DAY NetMWe i

s

~

1 . ... . . . . . . . . ... 805  !

2.................. 804  !

3 . ... . . . . . . . 804 l 4...... . .. 803  !

5... . . . . 803 i 1

6............. .... .. 808

7. . . . . . . . . . . . . . 809 i
8. .. . . . . 810 9- . . . . . . 808
10. . .. 810 11... . . . . . . 811 12.. . . . . . .. . 812  ;
13. . . . . . ... .. 811 .

14 . .. . . . .. 810

15. . . . . . . . . . . . 807 16........ . . . . 808  ;

17 . . . . . .. . . . . . 812

18. . 812 19 .. . . . . 811  ;

20 .. .. . . . . . . . . . 810  :

21.... ... 809  ;

22.. .. . . . . . 807 l 23.. .. . . . . . . 805  ;

24 .. . . . . . . . . . . . . . 804 ,

25. . . . . . . . . . .. 807 26.... . . .. . . . . 810 27 .. .. . . 807  !

28 . .. .. .. . . . . . . . . 631 1 29 . . . .. 0

30. . . . .. 0 31 . . . . . . . 0 l

i

)

E1-3

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-321 DATE: FEBRUARY 4,1997 UNIT NAME: E.1. HATCH - UNIT ONE COMPLETED BY: S. B. ROGERS TELEPHONE: (912) 367-7781 x2878 1

3 REPORT MONTH: JANUARY 1997 1 l

R M S E E Y T A T LICENSEE SC Y S H EVENT TO COMPONENT CAUSE & CORRECTIVE 3 P DURATION O O REPORT ED CODE ACTION TO {

NO. DATE E (HOURS) N D NUMBER ME (SUBCODE) PREVENT RECURRENCE

97-001 970128 S 0.0 B 5 97-001 CF PIPEXX Shift began reducing load for a unit (A) shutdown due to an increasing
trend on unidentified drywell leakage.

i 97-002 970129 S 70.6 B 1,2 97-001 CF PIPEXX Shift manually tripped the Main (A) Turbine and inserted a manual scram.

Sources of leakage have been identified and repair activities are continuing.

TYPE: REASON: METHOD: EVENTS REPORTED INVOLVE A GREATER THAN 20%

F-FORCED A-EQUIPMENT FAILURE (EXPLAIN) 1-MANUAL REDUCTION IN AVERAGE j S-SCHEDULED B-MAINTENANCE OR TF.ST 2-MANUAL SCRAM DAILY POWER LEVEL FOR I C-REFUELING 3-AUTOMATIC SCRAM THE PRECEDING 24 HOURS.

D-REGULATORY RESTRICTION 4-CONTINUATIONS E-OPERATOR TRAINING & LICENSE 5-LOAD REDUCTION l F-ADMINISTRATIVE 9-OTHER (EXPLAIN)  !

G-OPERATIONAL ERROR (EXPLA;N) l H-OTl!ER (EXPLAIN)

E1-4

1 i

l Enclosure 2 i

Plant Hatch Unit 2  !

Monthly Operating Report  !

January 1997 l Table of Contents l

f b  !

t i

l Narrative Report E2-1 i t i

?

Operating Data Report E2-2  !

Average Daily Power Level E2-3 Unit Shutdowns and Power Reductions E2-4 ,

1 i

J l

q r

i i

I l

I i

i

PLANT E.1. HATCH - UNIT TWO DOCKET NO.: 50-366 DATE: FEBRUARY 4,1997 NARRATIVE REPORT COMPLETED BY: S. B. ROGERS l TELEPHONE: (912) 367-7781 x2878 ,

i l

0000 l JANUARY 1 Shift continued to maintain rated thermal power. i JANUARY 5 1640 Shift began reducing load to approximately 800 GMWe when the unit experienced a par 1ialloss of feedwater heating upon inadvertent isolation of extraction steam to the 6th Stage "A" Feedwater Heater, 1 JANUARY 5 1703 The 6th Stage "A" Feedwater Heater was retumed to service. Investigation revealed that the partial loss of feedwater heating was caused by a ,

blown fase which resulted in the closure of the 6th Stage "A" Feedwater Heater Extraction Steam isolation Valve. ,

JANUARY 5 1740 Shift began ascension to rated thermal power. i l

JANUARY 5 1817 The unit attained rated thermal power.  ;

l JANUARY 23 0800 Shift began reducing load to approximately 450 GMWe to remove  !

"A" Reactor Feedwater Pump from service to replace the lube oil filters.

Shift performed a Rod Pattem Adjustment, Turbine Control Valve Testing, and inspection and replacement of selected servo-strainers in the Turbine Electro-Hydraulic Control (EHC) System while at reduced load. i JANUARY 23 1739 Shift began ascension to rated thermal power.

JANUARY 24 1325 The unit attained rated thermal power.

. JANUARY 31 2400 Shift continued to maintain rated thermal power.

l E2-1

8 OPEPATING DATA REPORT DOCKET NO.: 50-366 DATE: FEBRUARY 4,1997 COMPLETED BY: C. B. ROGERS TELEPHONE: (912) 367-7781 x2878 i OPERATING STATUS 1

1. UNIT NAMEi E. l. HATCH - UNIT TWO
2. REPORT PERIOD: JANUARY 1997
3. LICENSED THERMAL POWER (MWt): 2558 l 4. NAMEPLATE RATING (GROSS MWe): 850
5. DESIGN ELECTRICAL RATING (NET MWe): 784
6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe): 853 j 7. MAXIMUM DEPENDABLE CAPACITY (NET MWe): 818

. 8. IF CHANGES OCCUR IN CAPACITY RATINGS

, (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

Maximum Dependable Capacities for 1997 are 853 MWe (Gross) and 818 MWe (Net).

!' The values were determined from 1996 operational data.

4

9. POWER LEVEL TO WHICH RESTRICTED,IF ANY (NET MWe): NO RESTRICTIONS
10. REASONS FOR RESTRICTION,IF ANY: N/A THIS MONTH YEAR-TO-DATE CUMULATIVE

, 11. HOURS IN REPORTING PERIOD: 744.0 744.0 152473

12. NUMBER OF HOURS REACTOR WAS CRITICAL: 744.0 744.0 119902.7 1
13. REACTOR RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
14. HOURS GENERATOR ON LINE: 744.0 744.0 116034.7
15. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0 4
16. GROSS THERMAL ENERGY GENERATED (MWHt): 1887329 1887329 260114063 i 17. GROSS ELECTRICAL ENERGY GENERATED (MWHe): 634497 634497 85389960
18. NET ELECTRICAL ENERGY GENERATED (MWHe): 608372 608372 81387534
19. UNIT SERVICE FACTOR: 100.0% 100.0 % 76.1 %
20. UNIT AVAILABILITY FACTOR: 100.0 % 100.0% 76.1 %
21. UNIT CAPACITY FACTOR (USING MDC NET): 100.0% 100.0 % 69.4%
22. UNIT CAPACITY FACTOR (USING DER NET): 104.3 % 104.3 % 68.1 %

l SHUTDOWNS SCHEDUL O ER THE NEXT 6 MONTHS (TYPE ATE, AND DURATidN OF EACH):

34 Day Refueling Outage tentatively scheduled for Marcic 15,1997,

25. lF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): N/A i

E2-2

]

PLANT E.1. HATCH - UNIT TWO DOCKET NO.: 50-366 DATE: FEBRUARY 4,1997 AVERAGE DAILY POWER LEVEL COMPLETED BY: S. B. ROGERS TELEPHONE: (912) 367-7781 x2878 JANUARY 1997 RM NeWWit 1 . . . . . 821 2 .. . 822 3............... . 821

4. .. . . 821 5 .. . . . ... 818 6.. . . 824 7 .. .. .. 825 8 ... .. . . 826
9. . . 823
10. . .. . 826 11 . . . 828
12. .. . 828
13. . . . . . . 828
14. .. . . . . . 826 15 .. . . . . . . . . . . 825 16 . . . . . . . . . . .. 824 17 . . . . . . . . . . . . . . . . 827
18. .. . . . 828
19. 827 20 .. . . . . .. . .. 826 21 . . . . . . . . 825
22. . . . . . . . . . . . 824 23.. . .. . . .. 636 24 .. . . .. 804 25........ . . . . . . . . 822 26 .. . . . ... . . . . 825
27. . . . . . .. . .. .. 824
28. . . . . . ..... . 821 29.. .. . . . . . 824 30 . . .. 826 31 . . 825 E2-3

- - . -~ - . _ - -. - . . . - ... - . .- . , ,-

l UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-366 DATE: FEBRUARY 4,1997 ,

l UNIT NAME: E.1. HATCH - UNIT TWO COMPLETED BY: S. B. ROGERS '

TELEPHONE: (912) 367-7781 x2878 REPORT MONTH: JANUARY 1997 l

4  :

1 R M S '

E E Y T A T LICENSEE SC i Y S H EVENT TO COMPONENT CAUSE & CORRECTIVE i P DURATION O O REPORT ED CODE ACTION TO  !

NO. DATE E (HOURS) N D NUMBER ME (SUBCODE) PREVENT RECURRENCE i

97-001 970123 S 0.0 B 5 N/A CH FILTER Shift reduced load to approximately

, 450 GMWe to remove "A" Reactor RC FUELXX Feedwater Pump from service to replace lube oil filters, perform a HA VALVOP Rod Pattern Adjustment, Turbine (C) ControlValve Testing, and inspect and replace selected servo-strainers

] HB FILTER in the Turbine EHC System.

l l

J TYPE: REASON: METHOD: EVENTS REPORTED INVOLVE A GREATER THAN 20%

F FORCED A-EQUIPMENT FAILURE (EXPLAIN) 1-MANUAL REDUCTION IN AVERAGE S-SCHEDULED B-MAINTENANCE OR TEST 2-MANUAL SCRAM DAILY POWER LEVEL FOR C-REFUELING 3-AUTOMATIC SCPAM THE PRECEDING 24 HOURS.

D-REGULATORY RESTRICTION 4 CONTINUATIONS E-OPERATOR TRAINING & LICENSE 5-LOAD REDUCTION F-ADMINISTRATIVE 9-OTHER (EXPLAIN)

G-OPERATIONAL ERROR (EXPLAIN)

H-OTHER (EXPLAIN)

E2-4