Letter Sequence Other |
---|
|
Results
Other: A04824, Submits ATWS Rule Schedule Required by 10CFR50.62(d),per Generic Ltr 85-06.Facilities Participating in NRC Integrated Safety Assessment Program.Justification for Absence of Schedules for Haddam Neck & Millstone Unit 1 Provided, A07296, Forwards First Half of Responses to 880608 Request Re ATWS Mods.Remaining Responses Will Be Submitted by 880712, B11677, Advises of Current Plans to Address Requirements of 10CFR50.62,per Generic Ltr 85-06 Re QA Guidance for nonsafety-related ATWS Equipment, B12922, Requests Review & Concurrence on Design Mods Proposed to Address Requirements of ATWS rule,10CFR50.62(d),by 880729. Implementation of Mods Will Be Resheduled If NRC Concurrence Not Obtained by 880729, B12980, Clarifies 880627 & 0711 Responses to Questions Re Proposed ATWS Mods Concerning Common Mode Failure Affecting Reactor Protection Sys Power Distribution Sys.Procedure Revised to Assure One Set of Alarms Tested Each Outage, ML20151A460, ML20210A244, ML20211B373
|
MONTHYEARB11677, Advises of Current Plans to Address Requirements of 10CFR50.62,per Generic Ltr 85-06 Re QA Guidance for nonsafety-related ATWS Equipment1985-09-0909 September 1985 Advises of Current Plans to Address Requirements of 10CFR50.62,per Generic Ltr 85-06 Re QA Guidance for nonsafety-related ATWS Equipment Project stage: Other A04824, Submits ATWS Rule Schedule Required by 10CFR50.62(d),per Generic Ltr 85-06.Facilities Participating in NRC Integrated Safety Assessment Program.Justification for Absence of Schedules for Haddam Neck & Millstone Unit 1 Provided1985-10-11011 October 1985 Submits ATWS Rule Schedule Required by 10CFR50.62(d),per Generic Ltr 85-06.Facilities Participating in NRC Integrated Safety Assessment Program.Justification for Absence of Schedules for Haddam Neck & Millstone Unit 1 Provided Project stage: Other ML20211B3731987-02-12012 February 1987 Provides Info Re Implementation Schedules for Compliance W/Requirements of ATWS Rule (10CFR50.62).NRC Should Be Contacted 30 Days After Ltr Receipt Re Implementation Schedules Using Guidance Provided Project stage: Other A06368, Responds to NRC 870212 Request for Addl Info Re Implementation Schedule for Compliance W/Requirements of ATWS rule,10CFR50.62.Mods Will Be Completed by End of Cycle 10 Refueling Outage Scheduled to Begin in June 19891987-03-19019 March 1987 Responds to NRC 870212 Request for Addl Info Re Implementation Schedule for Compliance W/Requirements of ATWS rule,10CFR50.62.Mods Will Be Completed by End of Cycle 10 Refueling Outage Scheduled to Begin in June 1989 Project stage: Request ML20210A2441987-05-0101 May 1987 Reconfirms 851011 Proposed Design Mods to Address 10CFR50.62 Requirements,Per 870319 Commitment to Reevaluate Design.Mods Will Be Installed by Cycle 10 Refueling Outage in June 1989. Review of Mods Requested by 870901 Project stage: Other B12922, Requests Review & Concurrence on Design Mods Proposed to Address Requirements of ATWS rule,10CFR50.62(d),by 880729. Implementation of Mods Will Be Resheduled If NRC Concurrence Not Obtained by 8807291988-05-27027 May 1988 Requests Review & Concurrence on Design Mods Proposed to Address Requirements of ATWS rule,10CFR50.62(d),by 880729. Implementation of Mods Will Be Resheduled If NRC Concurrence Not Obtained by 880729 Project stage: Other A07296, Forwards First Half of Responses to 880608 Request Re ATWS Mods.Remaining Responses Will Be Submitted by 8807121988-06-27027 June 1988 Forwards First Half of Responses to 880608 Request Re ATWS Mods.Remaining Responses Will Be Submitted by 880712 Project stage: Other ML20151A4601988-07-11011 July 1988 Forwards Responses to Questions on Proposed ATWS Mods,Per NRC 880608 Request.Spare Parts Will Be Kept for All Dss/Atws Mitigating Sys Actuation Circuitry Components Project stage: Other B12980, Clarifies 880627 & 0711 Responses to Questions Re Proposed ATWS Mods Concerning Common Mode Failure Affecting Reactor Protection Sys Power Distribution Sys.Procedure Revised to Assure One Set of Alarms Tested Each Outage1988-07-25025 July 1988 Clarifies 880627 & 0711 Responses to Questions Re Proposed ATWS Mods Concerning Common Mode Failure Affecting Reactor Protection Sys Power Distribution Sys.Procedure Revised to Assure One Set of Alarms Tested Each Outage Project stage: Other 1987-05-01
[Table View] |
Submits ATWS Rule Schedule Required by 10CFR50.62(d),per Generic Ltr 85-06.Facilities Participating in NRC Integrated Safety Assessment Program.Justification for Absence of Schedules for Haddam Neck & Millstone Unit 1 ProvidedML20133K567 |
Person / Time |
---|
Site: |
Millstone, Haddam Neck, 05000000 |
---|
Issue date: |
10/11/1985 |
---|
From: |
Fee W, Opeka J CONNECTICUT YANKEE ATOMIC POWER CO., NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES |
---|
To: |
Butcher E, Zwolinski J Office of Nuclear Reactor Regulation |
---|
References |
---|
A04824, A4824, B11738, FL-85-6, GL-85-06, GL-85-6, TAC-59114, NUDOCS 8510220158 |
Download: ML20133K567 (7) |
|
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARDD-99-12, Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 9910281999-10-28028 October 1999 Informs That Time Provided by NRC Regulation within Which Commission May Act to Review DD-99-12 Has Expired.With Certificate of Svc.Served on 991028 ML20217N8261999-10-25025 October 1999 Discusses Errata Re 991021 Filing of Northeast Nuclear Energy Co Answer to Request for Hearing & Petition to Intervene ML20217K3161999-10-19019 October 1999 Forwards Amend 195 to License DPR-61 & Safety Evaluation. Amend Deletes Certain TSs Either No Longer Applicable to Permanently Shutdown & Defueled State of Reactor or Duplicate Regulatory Requirements B17901, Submits Statement of Personal Qualification (NRC Form 398) Along with Supporting Certification of Medical Exam by Facility Licensee (NRC from 396) in Support of License Renewal for PM Miner.Encls Withheld,Per 10CFR2.790(a)(6)1999-10-18018 October 1999 Submits Statement of Personal Qualification (NRC Form 398) Along with Supporting Certification of Medical Exam by Facility Licensee (NRC from 396) in Support of License Renewal for PM Miner.Encls Withheld,Per 10CFR2.790(a)(6) B17886, Requests Permission to Utilize Code Case N-623, Deferral of Insps of Shell-to-Flange & Head-to-Flange of Reactor Vessel,Section Xi,Div 1, for Millstone Unit 21999-10-18018 October 1999 Requests Permission to Utilize Code Case N-623, Deferral of Insps of Shell-to-Flange & Head-to-Flange of Reactor Vessel,Section Xi,Div 1, for Millstone Unit 2 05000336/LER-1999-012, Forwards LER 99-012-00,re Unrecoverable CEA Misalignment Entry Into TS 3.0.3 on 990917.Commitments Made by Util Are Encl1999-10-15015 October 1999 Forwards LER 99-012-00,re Unrecoverable CEA Misalignment Entry Into TS 3.0.3 on 990917.Commitments Made by Util Are Encl ML20217G9491999-10-14014 October 1999 Forwards Exemption from Requirements of 1-CFR50,App E, Section IV.F.2.c,re Conduct of full-participation Exercise in Sept 1999,at Plant,Units 1,2 & 3 B17900, Forwards Revised Assumptions Used in Fuel Handling Accident Analysis & Summary of Results.List of Regulatory Commitments Are Listed in Attachment 11999-10-14014 October 1999 Forwards Revised Assumptions Used in Fuel Handling Accident Analysis & Summary of Results.List of Regulatory Commitments Are Listed in Attachment 1 ML20217D9671999-10-12012 October 1999 Forwards Copy of Transcript of Public Meeting Held by NRC Staff & NNECO on 990825 at Waterford,Connecticut on Decommissioning Program for Millstone,Unit 1.Without Encl CY-99-137, Notifies NRC of Intent to Apply Haddam Neck Plant 10CFR50 App B,Qa Program to Activities Related to Development of ISFSI at Haddam1999-10-12012 October 1999 Notifies NRC of Intent to Apply Haddam Neck Plant 10CFR50 App B,Qa Program to Activities Related to Development of ISFSI at Haddam DD-99-11, Informs That Time Provided by NRC Regulation within Which Commission May Act to Review Director'S Decision (DD-99-11) Expired & That Commission Declined Any Review.Decision Became Final Action on 9910041999-10-0808 October 1999 Informs That Time Provided by NRC Regulation within Which Commission May Act to Review Director'S Decision (DD-99-11) Expired & That Commission Declined Any Review.Decision Became Final Action on 991004 ML20217D3011999-10-0707 October 1999 Forwards Request for Addl Info Re Util 990118 Request for Amend to License NPF-49 to Allow full-core Offloads to Spent Fuel Pool During Core Offloads to Spent Fuel Pool During Core Offload Events ML20217P1201999-10-0606 October 1999 Informs NRC of Proposed Acquisition of Parent Holding Company of Central Maine & Requests NRC Concurrence,Based on Threshold Review,That Proposed Acquisition Does Not,In Fact, Constitute Transfer Subject to 10CFR50.80 ML20217F0031999-10-0606 October 1999 Forwards Original Petition to Intervene Being Filed on Behalf of Clients,Connecticut Coalition Against Millstone & Long Island Coalition Against Millstone,Iaw Provisions of 10CFR2.714 B17892, Requests Withdrawal of License Amend Application Re 24-month SG Tube Insp Surveillance Extensions,Submitted in Util 950726 & s to NRC1999-10-0505 October 1999 Requests Withdrawal of License Amend Application Re 24-month SG Tube Insp Surveillance Extensions,Submitted in Util 950726 & s to NRC ML20217B4711999-10-0404 October 1999 Informs That Staff Did Not Identify Any Safety Concerns Re Licensee Proposals to Modify Commitments Made for Action Items 4.2.1,4.2.2,4.5.1 & 4.5.2 of GL 83-28 by Providing Addl Justifications or Safety Bases for Changes ML20212L1261999-10-0404 October 1999 Forwards Viewgraphs Presented by Licensee at 990923 Meeting with Nrc,In Response to Request ML20212L2171999-10-0101 October 1999 Responds to Recent Ltr to President Wj Clinton,Chairman Jackson & Commissioners,Wd Travers & Ferc,Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island ML20212L2081999-10-0101 October 1999 Responds to Recent Ltrs to President Wj Clinton,Chairman Jackson & Commissioners & Wd Travers,Expressing Concerns Re Millstone NPPs & Continued Lack of Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance ML20212L1971999-10-0101 October 1999 Responds to Recent Ltr to Chairman Jackson & Commissioners Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Plant Performance to Ensure Public Health & Safety ML20212L1831999-10-0101 October 1999 Responds to Recent Ltr to Wd Travers Expressing Concerns Re Millstone NPPs & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Continues to Monitor Performance of Millstone to Ensure Adequate Protection to Public Health ML20212K1241999-10-0101 October 1999 Responds to Recent Ltrs to Chairman Jackson,Commissioners & Wd Travers,Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performace of Millstone to Ensure That Public Health & Safety,Adequately Protected ML20212J9991999-10-0101 October 1999 Responds to Recent Ltr to President Clinton,H Clinton, Chairman Jackson &/Or Wd Travers Expressing Concern Re Millstone Npps.Nrc Continues to Monitor Performance of Plant to Ensure That Public Health & Safety Adequately Protected ML20212J3051999-10-0101 October 1999 Discusses GL 97-06 Re Degradation of SG Internals,Dtd 971230.GL Requested Each PWR Licensee to Submit Info That Will Enable NRC Staff to Verify Whether PWR SG Internals Comply & Conform to Current Licensing Basis for Facilities ML20212J2451999-10-0101 October 1999 Informs That Util 980807 & 990629 Responses to GL 98-01, Y2K Readiness of Computer Sys at NPPs Acceptable.Nrc Considers Subj GL to Be Closed for Units 2 &3 ML20212J6621999-09-30030 September 1999 Informs of Completion of mid-cycle PPR of Units 2 & 3 on 990916.Identified Several Recent Instances in Which Condition Repts Were Not Initiated,Resulting in Untimely or Inadequate C/As.Historical Listing of Plant Issues Encl ML20217A9271999-09-30030 September 1999 Discusses Investigation Conducted at Millstone Nuclear Power Station by NRC OI Region I on 980319 to Determine If Contract Training Instructor Was Terminated for Raising Concerns About Quality of Training Matls ML20217B3221999-09-30030 September 1999 Refers to Investigation Rept 1-1997-035 Conducted at Millstone Nuclear Power Station by NRC Ofc of Investigation Field Ofc,Region I on 970915 to Determine Whether Former Health Physics Technician Discriminated Against B17887, Requests Exemption from Requirements of 10CFR140.11(a)(4) Which Requires Licensees to Maintain Secondary Financial Protection Beyond Primary Layer1999-09-28028 September 1999 Requests Exemption from Requirements of 10CFR140.11(a)(4) Which Requires Licensees to Maintain Secondary Financial Protection Beyond Primary Layer ML20216J1341999-09-28028 September 1999 Ltr Contract:Task Order 49, Millstone Units 2 & 3 Employee Concerns Program Insp, Under Contract NRC-03-98-021 B17890, Provides Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-09-27027 September 1999 Provides Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal B17883, Forwards Mnps Unit 3 ISI Summary Rept,Cycle 6, IAW ASME Section XI,IWA-62301999-09-27027 September 1999 Forwards Mnps Unit 3 ISI Summary Rept,Cycle 6, IAW ASME Section XI,IWA-6230 B17888, Informs That There No Longer Exists Need to Maintain Millstone Unit 2 SRO License for CA Hines,License SOP-10741-01,effective 9909151999-09-24024 September 1999 Informs That There No Longer Exists Need to Maintain Millstone Unit 2 SRO License for CA Hines,License SOP-10741-01,effective 990915 B17884, Forwards NRC Form 536, Operator Licensing Exam Data, for Mnps,Units 2 & 3,per Administrative Ltr 99-031999-09-24024 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, for Mnps,Units 2 & 3,per Administrative Ltr 99-03 ML20212D0341999-09-20020 September 1999 Expresses Appreciation for Accepting NRC Request for Tour of Haddam Neck Facility During on 991014.Invites R Mellor to Participate in NRC 1999 Decommissioninng Power Reactor Work- Shop:Nrc Insp Program at Decommissioning Power Reactors ML20212F4961999-09-20020 September 1999 Forwards Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations of NRC Requirements Occurred & Being Treated as Ncvs,Consistent with App C of Enforcement Policy 05000336/LER-1999-001, Forwards LER 99-001-00 Re Thermal Reactor Power Limit That Was Exceeded.Commitments Made by Util Encl1999-09-20020 September 1999 Forwards LER 99-001-00 Re Thermal Reactor Power Limit That Was Exceeded.Commitments Made by Util Encl B17867, Requests Relief from Requirements of 10CFR50.55a(g),IAW ASME Section XI for Millstone,Unit 3.Util Requests Relief from Performing Visual Exam of Reactor Pressure Supports to Extent Required by Code for Class 1 Supports1999-09-17017 September 1999 Requests Relief from Requirements of 10CFR50.55a(g),IAW ASME Section XI for Millstone,Unit 3.Util Requests Relief from Performing Visual Exam of Reactor Pressure Supports to Extent Required by Code for Class 1 Supports B17865, Provides NRC Staff with Updated Proposed Rev of FSAR Section 14.6.3, Radiological Consequences of SG Tube Failure. Updated Proposed Rev Will Replace Info Provided in Attachment 3 of Initial Submittal1999-09-16016 September 1999 Provides NRC Staff with Updated Proposed Rev of FSAR Section 14.6.3, Radiological Consequences of SG Tube Failure. Updated Proposed Rev Will Replace Info Provided in Attachment 3 of Initial Submittal B17876, Informs That Util Will Adopt Last Approved Northeast Util QA Program (Nuqap) Tr,Rev 21,dtd 990630,as Unit 1 Nuqap,Per Decision to Permanently Cease Operations at Subject Plant1999-09-16016 September 1999 Informs That Util Will Adopt Last Approved Northeast Util QA Program (Nuqap) Tr,Rev 21,dtd 990630,as Unit 1 Nuqap,Per Decision to Permanently Cease Operations at Subject Plant B17880, Forwards NRC Form 398 & NRC Form 396 for Rf Martin,License SOP-10397-0.Encls Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Form 398 & NRC Form 396 for Rf Martin,License SOP-10397-0.Encls Withheld Per 10CFR2.790(a)(6) B17881, Forwards NRC Form 398 & NRC Form 396 for Le Olsen,License SOP-10398-2.Encl Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Form 398 & NRC Form 396 for Le Olsen,License SOP-10398-2.Encl Withheld Per 10CFR2.790(a)(6) B17859, Forwards up-to-date Distribution Lists for NRC Correspondence to NNECO & NUSCO.Side-bars Indicate Changes from Previous Lists Provided to NRC on 9801281999-09-15015 September 1999 Forwards up-to-date Distribution Lists for NRC Correspondence to NNECO & NUSCO.Side-bars Indicate Changes from Previous Lists Provided to NRC on 980128 B17882, Forwards NRC Forms 398 & 369 in Support of License Renewal for Bb Parrish,License SOP-10399-2.Encl Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Forms 398 & 369 in Support of License Renewal for Bb Parrish,License SOP-10399-2.Encl Withheld Per 10CFR2.790(a)(6) B17872, Informs of Election to Consolidate Previous Commitments Re Work Observation Program with Two New Programmatic Commitments Listed in Attachment 11999-09-14014 September 1999 Informs of Election to Consolidate Previous Commitments Re Work Observation Program with Two New Programmatic Commitments Listed in Attachment 1 B17838, Forwards Revs 34 & 35 to Physical Security Plan.Explanation of Changes Provided as Attachment 1.Without Encls1999-09-10010 September 1999 Forwards Revs 34 & 35 to Physical Security Plan.Explanation of Changes Provided as Attachment 1.Without Encls ML20212A9011999-09-10010 September 1999 Forwards Environ Assessment & Finding of No Significant Impact Re Application for Exemption,Dtd 990803.Proposed Exemption Would Provide Relief from Requirement of 10CFR50 ML20212A7501999-09-10010 September 1999 Forwards Staff Requirements Memo Response,Dtd 990525,which Provides Actions NRC Plans for Continued Oversight of safety-conscious Work Environ & Employee Concerns Program ML20212A3171999-09-10010 September 1999 Discusses Investigation Rept 1-1998-045 Conducted on 981112 to Determine If Former Senior Health Physics Technician Being Denied Employment at Millstone in Retaliation for Having Raised Safety Concerns in Past.Synopsis Encl ML20211J9291999-09-0303 September 1999 Forwards mark-ups & Retypes of Proposed Conforming License Changes Required in Connection with Transfers Being Sought in 990615 Application of Montaup Electric Co & New England Power Co for Transfer of Licenses & Ownership Interests 1999-09-30
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217N8261999-10-25025 October 1999 Discusses Errata Re 991021 Filing of Northeast Nuclear Energy Co Answer to Request for Hearing & Petition to Intervene B17901, Submits Statement of Personal Qualification (NRC Form 398) Along with Supporting Certification of Medical Exam by Facility Licensee (NRC from 396) in Support of License Renewal for PM Miner.Encls Withheld,Per 10CFR2.790(a)(6)1999-10-18018 October 1999 Submits Statement of Personal Qualification (NRC Form 398) Along with Supporting Certification of Medical Exam by Facility Licensee (NRC from 396) in Support of License Renewal for PM Miner.Encls Withheld,Per 10CFR2.790(a)(6) B17886, Requests Permission to Utilize Code Case N-623, Deferral of Insps of Shell-to-Flange & Head-to-Flange of Reactor Vessel,Section Xi,Div 1, for Millstone Unit 21999-10-18018 October 1999 Requests Permission to Utilize Code Case N-623, Deferral of Insps of Shell-to-Flange & Head-to-Flange of Reactor Vessel,Section Xi,Div 1, for Millstone Unit 2 05000336/LER-1999-012, Forwards LER 99-012-00,re Unrecoverable CEA Misalignment Entry Into TS 3.0.3 on 990917.Commitments Made by Util Are Encl1999-10-15015 October 1999 Forwards LER 99-012-00,re Unrecoverable CEA Misalignment Entry Into TS 3.0.3 on 990917.Commitments Made by Util Are Encl B17900, Forwards Revised Assumptions Used in Fuel Handling Accident Analysis & Summary of Results.List of Regulatory Commitments Are Listed in Attachment 11999-10-14014 October 1999 Forwards Revised Assumptions Used in Fuel Handling Accident Analysis & Summary of Results.List of Regulatory Commitments Are Listed in Attachment 1 CY-99-137, Notifies NRC of Intent to Apply Haddam Neck Plant 10CFR50 App B,Qa Program to Activities Related to Development of ISFSI at Haddam1999-10-12012 October 1999 Notifies NRC of Intent to Apply Haddam Neck Plant 10CFR50 App B,Qa Program to Activities Related to Development of ISFSI at Haddam ML20217P1201999-10-0606 October 1999 Informs NRC of Proposed Acquisition of Parent Holding Company of Central Maine & Requests NRC Concurrence,Based on Threshold Review,That Proposed Acquisition Does Not,In Fact, Constitute Transfer Subject to 10CFR50.80 ML20217F0031999-10-0606 October 1999 Forwards Original Petition to Intervene Being Filed on Behalf of Clients,Connecticut Coalition Against Millstone & Long Island Coalition Against Millstone,Iaw Provisions of 10CFR2.714 B17892, Requests Withdrawal of License Amend Application Re 24-month SG Tube Insp Surveillance Extensions,Submitted in Util 950726 & s to NRC1999-10-0505 October 1999 Requests Withdrawal of License Amend Application Re 24-month SG Tube Insp Surveillance Extensions,Submitted in Util 950726 & s to NRC B17887, Requests Exemption from Requirements of 10CFR140.11(a)(4) Which Requires Licensees to Maintain Secondary Financial Protection Beyond Primary Layer1999-09-28028 September 1999 Requests Exemption from Requirements of 10CFR140.11(a)(4) Which Requires Licensees to Maintain Secondary Financial Protection Beyond Primary Layer B17890, Provides Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-09-27027 September 1999 Provides Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal B17883, Forwards Mnps Unit 3 ISI Summary Rept,Cycle 6, IAW ASME Section XI,IWA-62301999-09-27027 September 1999 Forwards Mnps Unit 3 ISI Summary Rept,Cycle 6, IAW ASME Section XI,IWA-6230 B17884, Forwards NRC Form 536, Operator Licensing Exam Data, for Mnps,Units 2 & 3,per Administrative Ltr 99-031999-09-24024 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, for Mnps,Units 2 & 3,per Administrative Ltr 99-03 B17888, Informs That There No Longer Exists Need to Maintain Millstone Unit 2 SRO License for CA Hines,License SOP-10741-01,effective 9909151999-09-24024 September 1999 Informs That There No Longer Exists Need to Maintain Millstone Unit 2 SRO License for CA Hines,License SOP-10741-01,effective 990915 05000336/LER-1999-001, Forwards LER 99-001-00 Re Thermal Reactor Power Limit That Was Exceeded.Commitments Made by Util Encl1999-09-20020 September 1999 Forwards LER 99-001-00 Re Thermal Reactor Power Limit That Was Exceeded.Commitments Made by Util Encl B17867, Requests Relief from Requirements of 10CFR50.55a(g),IAW ASME Section XI for Millstone,Unit 3.Util Requests Relief from Performing Visual Exam of Reactor Pressure Supports to Extent Required by Code for Class 1 Supports1999-09-17017 September 1999 Requests Relief from Requirements of 10CFR50.55a(g),IAW ASME Section XI for Millstone,Unit 3.Util Requests Relief from Performing Visual Exam of Reactor Pressure Supports to Extent Required by Code for Class 1 Supports B17876, Informs That Util Will Adopt Last Approved Northeast Util QA Program (Nuqap) Tr,Rev 21,dtd 990630,as Unit 1 Nuqap,Per Decision to Permanently Cease Operations at Subject Plant1999-09-16016 September 1999 Informs That Util Will Adopt Last Approved Northeast Util QA Program (Nuqap) Tr,Rev 21,dtd 990630,as Unit 1 Nuqap,Per Decision to Permanently Cease Operations at Subject Plant B17865, Provides NRC Staff with Updated Proposed Rev of FSAR Section 14.6.3, Radiological Consequences of SG Tube Failure. Updated Proposed Rev Will Replace Info Provided in Attachment 3 of Initial Submittal1999-09-16016 September 1999 Provides NRC Staff with Updated Proposed Rev of FSAR Section 14.6.3, Radiological Consequences of SG Tube Failure. Updated Proposed Rev Will Replace Info Provided in Attachment 3 of Initial Submittal B17859, Forwards up-to-date Distribution Lists for NRC Correspondence to NNECO & NUSCO.Side-bars Indicate Changes from Previous Lists Provided to NRC on 9801281999-09-15015 September 1999 Forwards up-to-date Distribution Lists for NRC Correspondence to NNECO & NUSCO.Side-bars Indicate Changes from Previous Lists Provided to NRC on 980128 B17881, Forwards NRC Form 398 & NRC Form 396 for Le Olsen,License SOP-10398-2.Encl Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Form 398 & NRC Form 396 for Le Olsen,License SOP-10398-2.Encl Withheld Per 10CFR2.790(a)(6) B17880, Forwards NRC Form 398 & NRC Form 396 for Rf Martin,License SOP-10397-0.Encls Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Form 398 & NRC Form 396 for Rf Martin,License SOP-10397-0.Encls Withheld Per 10CFR2.790(a)(6) B17882, Forwards NRC Forms 398 & 369 in Support of License Renewal for Bb Parrish,License SOP-10399-2.Encl Withheld Per 10CFR2.790(a)(6)1999-09-15015 September 1999 Forwards NRC Forms 398 & 369 in Support of License Renewal for Bb Parrish,License SOP-10399-2.Encl Withheld Per 10CFR2.790(a)(6) B17872, Informs of Election to Consolidate Previous Commitments Re Work Observation Program with Two New Programmatic Commitments Listed in Attachment 11999-09-14014 September 1999 Informs of Election to Consolidate Previous Commitments Re Work Observation Program with Two New Programmatic Commitments Listed in Attachment 1 B17838, Forwards Revs 34 & 35 to Physical Security Plan.Explanation of Changes Provided as Attachment 1.Without Encls1999-09-10010 September 1999 Forwards Revs 34 & 35 to Physical Security Plan.Explanation of Changes Provided as Attachment 1.Without Encls ML20211J9291999-09-0303 September 1999 Forwards mark-ups & Retypes of Proposed Conforming License Changes Required in Connection with Transfers Being Sought in 990615 Application of Montaup Electric Co & New England Power Co for Transfer of Licenses & Ownership Interests ML20216H0591999-09-0202 September 1999 Responds to Re Issues Submitted by Cullen on Behalf of Several Petitioners Concerning Offsite Emergency Prepardeness for Millstone Nuclear Power Station 05000336/LER-1999-010, Forwards LER 99-010-00,documenting 990804 Event of Failure to Perform ASME Section XI IST on Pressurizer Relief Line Flow Control Sample Valve Following Maint Activities.List of Util Commitments Contained in Attachment 11999-09-0202 September 1999 Forwards LER 99-010-00,documenting 990804 Event of Failure to Perform ASME Section XI IST on Pressurizer Relief Line Flow Control Sample Valve Following Maint Activities.List of Util Commitments Contained in Attachment 1 CY-99-111, Submits Clarification of Changes Made to Connecticut Yankee QA Program,Per Util 990810 Submittal.Change Will Be Submitted to NRC in Dec 1999 as Part of Annual Update1999-09-0202 September 1999 Submits Clarification of Changes Made to Connecticut Yankee QA Program,Per Util 990810 Submittal.Change Will Be Submitted to NRC in Dec 1999 as Part of Annual Update ML20211N9241999-09-0101 September 1999 Forwards Document Classification Form for Insertion Into Emergency Planning Services Department Procedures B17851, Forwards Semiannual fitness-for-duty Program Performance Data for 990101-990630 for Millstone Nuclear Power Station, Units 1,2 & 3,IAW 10CFR26.71(d)1999-08-27027 August 1999 Forwards Semiannual fitness-for-duty Program Performance Data for 990101-990630 for Millstone Nuclear Power Station, Units 1,2 & 3,IAW 10CFR26.71(d) B17855, Forwards NRC Forms 398 & 396 in Support of License Renewal for SRO TE Grilley,SOP-4053-04.Encl Withheld,Per 10CFR2.7901999-08-17017 August 1999 Forwards NRC Forms 398 & 396 in Support of License Renewal for SRO TE Grilley,SOP-4053-04.Encl Withheld,Per 10CFR2.790 B17849, Forwards Second Quarter Backlog Performance Rept for 1999, Which Represents Fourth Rept on Mnps Performance Since Restart of Unit 3 & First Status Update for Unit 2.No Regulatory Commitments Are Contained in Ltr1999-08-16016 August 1999 Forwards Second Quarter Backlog Performance Rept for 1999, Which Represents Fourth Rept on Mnps Performance Since Restart of Unit 3 & First Status Update for Unit 2.No Regulatory Commitments Are Contained in Ltr B17854, Forwards Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 2,per TS 6.9.1.7.Revised Repts for May & June Also Encl Which Reflect Correct Faulty Printometer Readings1999-08-14014 August 1999 Forwards Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 2,per TS 6.9.1.7.Revised Repts for May & June Also Encl Which Reflect Correct Faulty Printometer Readings B17850, Forwards First Lhc Quarterly Assessment Rept for Assessment Performed 990621 to 990701.NNECO Taking Appropriate Actions to Address Observations in Rept1999-08-11011 August 1999 Forwards First Lhc Quarterly Assessment Rept for Assessment Performed 990621 to 990701.NNECO Taking Appropriate Actions to Address Observations in Rept B17837, Forwards COLR for Cycle 7, for Millstone Unit 3,IAW TS 6.9.1.6.Explanation of Changes to COLR Also Encl1999-08-0707 August 1999 Forwards COLR for Cycle 7, for Millstone Unit 3,IAW TS 6.9.1.6.Explanation of Changes to COLR Also Encl B17657, Requests Schedular Exemption from Emergency Plan Exercise Requirements of 10CFR50,App E,Part Iv,Section F,Paragraph 2.c.Requests That Nrc/Fema Evaluated Exercise Be Conducted in Mar 2000 Rather than Sept 19991999-08-0303 August 1999 Requests Schedular Exemption from Emergency Plan Exercise Requirements of 10CFR50,App E,Part Iv,Section F,Paragraph 2.c.Requests That Nrc/Fema Evaluated Exercise Be Conducted in Mar 2000 Rather than Sept 1999 B17845, Forwards Revised Commitment for Surveillance Scheduling & Tracking.Options for Surveillance Scheduling & Tracking Methodologies to Be Incorporated in Standardized Station Surveillance Program Are Currently Being Reconsidered1999-08-0202 August 1999 Forwards Revised Commitment for Surveillance Scheduling & Tracking.Options for Surveillance Scheduling & Tracking Methodologies to Be Incorporated in Standardized Station Surveillance Program Are Currently Being Reconsidered CY-99-048, Forwards Cyap Rept CY-HP-0031,Rev 0, Bounding Dose Assessment for Offsite Radioactive Matls1999-07-29029 July 1999 Forwards Cyap Rept CY-HP-0031,Rev 0, Bounding Dose Assessment for Offsite Radioactive Matls B17831, Informs NRC Staff That Change 3 to Rev 25 of Mnps Emergency Plan Was Implemented on 990715.Change Removes Facility Organizational Charts from Emergency Plan & Identifies Relocation to Nuqap1999-07-26026 July 1999 Informs NRC Staff That Change 3 to Rev 25 of Mnps Emergency Plan Was Implemented on 990715.Change Removes Facility Organizational Charts from Emergency Plan & Identifies Relocation to Nuqap B17834, Forwards Proprietary Revised NRC Form 398,which Certifies That SL Doboe Has Completed Eligibility Requirements for Sro,Per 10CFR55.31.Proprietary Info Withheld1999-07-20020 July 1999 Forwards Proprietary Revised NRC Form 398,which Certifies That SL Doboe Has Completed Eligibility Requirements for Sro,Per 10CFR55.31.Proprietary Info Withheld B17811, Submits Response to NRC AL 99-02,requesting That Licensees Provide Numerical Estimates of Licensing Actions to Be Expected to Be Submitted in Fy 2000 & 20011999-07-20020 July 1999 Submits Response to NRC AL 99-02,requesting That Licensees Provide Numerical Estimates of Licensing Actions to Be Expected to Be Submitted in Fy 2000 & 2001 B17836, Forwards Revised NRC Form 396 & Supporting Physician Rept for Licensed Operator Restricted from Licensed Duties, Effective 990628,due to Medical Condition.Without Encl1999-07-20020 July 1999 Forwards Revised NRC Form 396 & Supporting Physician Rept for Licensed Operator Restricted from Licensed Duties, Effective 990628,due to Medical Condition.Without Encl CY-99-066, Forwards Revised Plan for Recovery of Licensed Matl from Offsite Locations.Completion of Implementation of Plan During Summer of 1999 Is Planned,Contingent on Support Extended by Property Owners,Weather & Uncontrolled Factors1999-07-20020 July 1999 Forwards Revised Plan for Recovery of Licensed Matl from Offsite Locations.Completion of Implementation of Plan During Summer of 1999 Is Planned,Contingent on Support Extended by Property Owners,Weather & Uncontrolled Factors ML20210S9911999-07-18018 July 1999 Requests NRC Intervene for All Shareholders of New England Electric System & to Help with Merger with National Grid Group & That NRC Petition Security & Exchange Commission to Investigate Matter Relative to No Shareholder Options B17835, Forwards Rev 33 to Millstone Station Physical Security Plan, Per 10CFR50.54(p)(2).Licensee Determined That Changes Do Not Decrease Effectiveness of Plan.Rev Withheld from Public Disclosure,Per 10CFR2.790(d)(1)1999-07-16016 July 1999 Forwards Rev 33 to Millstone Station Physical Security Plan, Per 10CFR50.54(p)(2).Licensee Determined That Changes Do Not Decrease Effectiveness of Plan.Rev Withheld from Public Disclosure,Per 10CFR2.790(d)(1) B17818, Provides NRC Staff with Change to TS Bases Sections 3/4.5.2 & 3/4.5.3, ECCS Subsystems for Info Only.Change Was Reviewed & Approved by Unit 3 Plant Operations Review Committee IAW Provisions of 10CFR50.591999-07-16016 July 1999 Provides NRC Staff with Change to TS Bases Sections 3/4.5.2 & 3/4.5.3, ECCS Subsystems for Info Only.Change Was Reviewed & Approved by Unit 3 Plant Operations Review Committee IAW Provisions of 10CFR50.59 B17824, Forwards Monthly Oeprating Rept for June 1999 & Revised Monthly Operating Rept for May 1999 for Millstone Unit 21999-07-13013 July 1999 Forwards Monthly Oeprating Rept for June 1999 & Revised Monthly Operating Rept for May 1999 for Millstone Unit 2 ML20212K1701999-07-13013 July 1999 Submits Concerns Re Millstone & Continued Lack of Emergency Mgt Plan for Eastern Long Island.Nrc Should Provide Adequate Emergency Planning in Case of Radiological Accident B17816, Provides Certification That M Lettrich,Has Completed Eligibility Requirements,Per 10CFR55.31 for Operator License.Util Requests That Licensing Action Be Taken for Named Individual1999-07-0101 July 1999 Provides Certification That M Lettrich,Has Completed Eligibility Requirements,Per 10CFR55.31 for Operator License.Util Requests That Licensing Action Be Taken for Named Individual ML20209C3911999-06-30030 June 1999 Forwards TS Page 6-3 for Haddam Neck Plant 1999-09-03
[Table view] Category:UTILITY TO NRC
MONTHYEARA08900, Responds to Expressing NRC Views on Access to Util Internal or third-party Assessment Repts.Believes Internal Analysis to Support Amend of One of Util NRC OLs to Authorize Higher Power Level Is within NRC Purview & Access1990-09-11011 September 1990 Responds to Expressing NRC Views on Access to Util Internal or third-party Assessment Repts.Believes Internal Analysis to Support Amend of One of Util NRC OLs to Authorize Higher Power Level Is within NRC Purview & Access ML20064A8071990-09-11011 September 1990 Forwards Core Operating Limits Rept for Four & Three Loop Operation,Per Tech Spec 6.9.1.6.d B13628, Forwards Correction to Error Discovered in Util 900727 Response to Notice of Violation from Insp Rept 50-336/90-09. Statement Corrected to Read That Contract Personnel That Have long-term Assignments,Certified as Testing Personnel1990-09-0707 September 1990 Forwards Correction to Error Discovered in Util 900727 Response to Notice of Violation from Insp Rept 50-336/90-09. Statement Corrected to Read That Contract Personnel That Have long-term Assignments,Certified as Testing Personnel B13624, Forwards Addl Info Re Relief Request from ASME Code Section XI Requirements for Temporary Repair to Piping Adjacent to Valve 2-SW-97A,per 900817 Telcon1990-09-0505 September 1990 Forwards Addl Info Re Relief Request from ASME Code Section XI Requirements for Temporary Repair to Piping Adjacent to Valve 2-SW-97A,per 900817 Telcon A08977, Advises of Commitment to Install Hardened Wetwell Vent at Facility,In Response to NRC .Util Will Be Proceeding W/Initial Design & Engineering of Hardened Vent, to Support Installation During 1993 Refueling Outage1990-09-0404 September 1990 Advises of Commitment to Install Hardened Wetwell Vent at Facility,In Response to NRC .Util Will Be Proceeding W/Initial Design & Engineering of Hardened Vent, to Support Installation During 1993 Refueling Outage B13626, Informs That Info Provided in Re safety-related Equipment Classification Programs Also Applicable for Unit 3 of Facility1990-08-31031 August 1990 Informs That Info Provided in Re safety-related Equipment Classification Programs Also Applicable for Unit 3 of Facility B13596, Forwards Millstone Unit 3 Individual Plant Exam for Severe Accident Vulnerabilities, Per Generic Ltr 88-20.Rept Identified That No Major Severe Accident Vulnerabilities Requiring Corrective Action Needed1990-08-31031 August 1990 Forwards Millstone Unit 3 Individual Plant Exam for Severe Accident Vulnerabilities, Per Generic Ltr 88-20.Rept Identified That No Major Severe Accident Vulnerabilities Requiring Corrective Action Needed B13622, Forwards Crdr Human Engineering Discrepancy Info for Plant1990-08-30030 August 1990 Forwards Crdr Human Engineering Discrepancy Info for Plant B13618, Forwards Addl Info on Util 900815 Relief Request from ASME Code Section XI Requirements,Per 10CFR50.55a(g)(6)(i),for Repairs to Pipe 3SWP-006-050-031990-08-24024 August 1990 Forwards Addl Info on Util 900815 Relief Request from ASME Code Section XI Requirements,Per 10CFR50.55a(g)(6)(i),for Repairs to Pipe 3SWP-006-050-03 ML20059C2061990-08-23023 August 1990 Forwards Vols 1 & 2 to Semiannual Radioactive Effluents Release Rept Jan-June 1990, Per 10CFR50.36a.Rept Includes Summary of Quantities of Solid Radwaste & Liquid & Gaseous Effluents A08918, Responds to Notice of Violation & Proposed Imposition of Civil Penalty Re Insp Rept 50-245/90-08.Mitigation of Civil Penalty Requested.Corrective Action:List of Procedural Changes Provided1990-08-22022 August 1990 Responds to Notice of Violation & Proposed Imposition of Civil Penalty Re Insp Rept 50-245/90-08.Mitigation of Civil Penalty Requested.Corrective Action:List of Procedural Changes Provided B13617, Requests NRC Revise Confirmatory Order for Plant to Specify New Completion Date of Cycle 16 Refueling Outage for Item II.E.1.2.Util Intends to Implement Design Change During Next Refueling Outage to Resolve Listed Issues1990-08-22022 August 1990 Requests NRC Revise Confirmatory Order for Plant to Specify New Completion Date of Cycle 16 Refueling Outage for Item II.E.1.2.Util Intends to Implement Design Change During Next Refueling Outage to Resolve Listed Issues B13615, Requests That 900705 Request for Amend to License DPR-61 Be Approved on Emergency Basis & That Temporary Waiver of Compliance from Tech Spec 4.4.6.2.1.g Be Given Until NRC Acts on Emergency Amend1990-08-20020 August 1990 Requests That 900705 Request for Amend to License DPR-61 Be Approved on Emergency Basis & That Temporary Waiver of Compliance from Tech Spec 4.4.6.2.1.g Be Given Until NRC Acts on Emergency Amend B13611, Forwards, Semiannual Radioactive Effluents Release Rept for Jan-June 19901990-08-16016 August 1990 Forwards, Semiannual Radioactive Effluents Release Rept for Jan-June 1990 B13610, Requests Relief from ASME Boiler & Pressure Vessel Code Section XI Requirements Re Mods to Pipe 3SWP-006-050-03. Results of Insps & Required Repairs Will Determine Schedule for Future Insps1990-08-15015 August 1990 Requests Relief from ASME Boiler & Pressure Vessel Code Section XI Requirements Re Mods to Pipe 3SWP-006-050-03. Results of Insps & Required Repairs Will Determine Schedule for Future Insps B13602, Submits Addendum to Plant Control Room Design Review Summary Rept,Per .Lists 10CFR50 App R-related Mods Outside Control Room That Could Not Be Reviewed Until After Final Implementation of Changes1990-08-14014 August 1990 Submits Addendum to Plant Control Room Design Review Summary Rept,Per .Lists 10CFR50 App R-related Mods Outside Control Room That Could Not Be Reviewed Until After Final Implementation of Changes B13595, Notifies NRC That Utils Volunteer to Participate in Emergency Response Data Sys Project for All Four Nuclear Units,Per Generic Ltr 89-15 & NUREG-13941990-08-14014 August 1990 Notifies NRC That Utils Volunteer to Participate in Emergency Response Data Sys Project for All Four Nuclear Units,Per Generic Ltr 89-15 & NUREG-1394 B13607, Requests Relief from ASME Code Section XI to Reflect Mod to Piping Adjacent to Valve 2-SW-97A,in Response to Generic Ltr 90-051990-08-10010 August 1990 Requests Relief from ASME Code Section XI to Reflect Mod to Piping Adjacent to Valve 2-SW-97A,in Response to Generic Ltr 90-05 B13580, Discusses Revised Tech Spec Conversion Program,Reflecting Conversion of Tech Spec to Westinghouse Sts.Future Upgrade of Tech Specs Should Be Conducted on Voluntary Basis Consistent W/Nrc Policy Statement1990-08-10010 August 1990 Discusses Revised Tech Spec Conversion Program,Reflecting Conversion of Tech Spec to Westinghouse Sts.Future Upgrade of Tech Specs Should Be Conducted on Voluntary Basis Consistent W/Nrc Policy Statement A08845, Responds to NRC Backfit Analyses of Hardened Wetwell Vent, Contained in .Benefit of Installing Hardened Wetwell Vent to Satisfy Basic Design Objective of Preventing core-melt Event Not Sufficient for Immediate Decision1990-08-0808 August 1990 Responds to NRC Backfit Analyses of Hardened Wetwell Vent, Contained in .Benefit of Installing Hardened Wetwell Vent to Satisfy Basic Design Objective of Preventing core-melt Event Not Sufficient for Immediate Decision ML20058M8321990-08-0707 August 1990 Discusses Spent Fuel Racks Poison Surveillance Coupon Boraflex Degradation.Visual Exam of Remaining Surveillance Coupons Revealed Similar Situation Existed in All Coupon Samples ML20058N2181990-08-0707 August 1990 Notification of Change in Senior Operator Status.Util Determined That Need to Maintain Senior OL of LS Allen No Longer Exists.Determination Effective 900719 B13603, Withdraws 900731 Request for Temporary Waiver of Compliance W/Tech Spec 3.7.1.2 Re Inoperability of Auxiliary Feedwater Pumps1990-08-0202 August 1990 Withdraws 900731 Request for Temporary Waiver of Compliance W/Tech Spec 3.7.1.2 Re Inoperability of Auxiliary Feedwater Pumps B13590, Responds to NRC 900718 Request for Addl Info Re Util 900418 Request for Schedular Exemption from 10CFR50,App E,Section IV.F.3 to Allow Dec 1990 Full Participation Exercise to Be Exchanged W/Oct 1991 Partial Participation Exercise1990-08-0101 August 1990 Responds to NRC 900718 Request for Addl Info Re Util 900418 Request for Schedular Exemption from 10CFR50,App E,Section IV.F.3 to Allow Dec 1990 Full Participation Exercise to Be Exchanged W/Oct 1991 Partial Participation Exercise A08881, Responds to NRC Re Violations Noted in Insp Rept 50-423/90-08.Corrective Action:Operators Directly Involved W/Event Removed from Licensed Duties & Counseled by Operations Manager on Causes of Event1990-07-31031 July 1990 Responds to NRC Re Violations Noted in Insp Rept 50-423/90-08.Corrective Action:Operators Directly Involved W/Event Removed from Licensed Duties & Counseled by Operations Manager on Causes of Event B13601, Requests Temporary Waiver of Compliance from Tech Spec 3.7.1.2,allowing Plant to Remain in Mode 3 for Addl 14 Days Beyond Current Action Statement Limits W/One or of Two Auxiliary Feedwater Pumps Inoperable1990-07-31031 July 1990 Requests Temporary Waiver of Compliance from Tech Spec 3.7.1.2,allowing Plant to Remain in Mode 3 for Addl 14 Days Beyond Current Action Statement Limits W/One or of Two Auxiliary Feedwater Pumps Inoperable B13594, Forwards Rev 13 to Physical Security Plan.Rev Withheld (Ref 10CFR73.21(b) & 2.790(a))1990-07-30030 July 1990 Forwards Rev 13 to Physical Security Plan.Rev Withheld (Ref 10CFR73.21(b) & 2.790(a)) ML20055J4621990-07-27027 July 1990 Advises That Need to Maintain OL or Senior OL for Listed Individuals No Longer Exists,Effective 900701 B13585, Provides Supplemental Response to Generic Ltr 89-19 Re Request for Action Concerning Resolution of Unresolved Safety Issue A-47.Plant Procedures Modified to Provide Operability Verification of Steam Generator Protection Sys1990-07-26026 July 1990 Provides Supplemental Response to Generic Ltr 89-19 Re Request for Action Concerning Resolution of Unresolved Safety Issue A-47.Plant Procedures Modified to Provide Operability Verification of Steam Generator Protection Sys A08565, Responds to NRC 900302 Request for Addl Info Re LPCI Swing Bus Transfer Design & Single Failure Vulnerabilities1990-07-26026 July 1990 Responds to NRC 900302 Request for Addl Info Re LPCI Swing Bus Transfer Design & Single Failure Vulnerabilities B13592, Requests Extension to Respond to NRC Backfit Analyses of Hardened Wetwell Vent1990-07-24024 July 1990 Requests Extension to Respond to NRC Backfit Analyses of Hardened Wetwell Vent ML20063P9791990-07-23023 July 1990 Notification of Change in SL Jackson Status Effective 900701,due to Permanent Reassignment within Util B13563, Discusses Util Comprehensive Review of Options Re Degraded Grid Undervoltage Protection.Confirms Previous Conclusion That Splitting Loss of Normal Power Logic Would Have Overall Adverse Impact on Plant Safety1990-07-20020 July 1990 Discusses Util Comprehensive Review of Options Re Degraded Grid Undervoltage Protection.Confirms Previous Conclusion That Splitting Loss of Normal Power Logic Would Have Overall Adverse Impact on Plant Safety B13566, Advises That Util Has Reasonable Assurance That Safety Relief Valves Operable & Will Perform as Expected Until Next Outage1990-07-20020 July 1990 Advises That Util Has Reasonable Assurance That Safety Relief Valves Operable & Will Perform as Expected Until Next Outage B13571, Clarifies 900625 Tech Spec Change Request Re Limit of 160 Failed Fuel Rods for Cycle 16 Operation1990-07-19019 July 1990 Clarifies 900625 Tech Spec Change Request Re Limit of 160 Failed Fuel Rods for Cycle 16 Operation ML20055G5331990-07-18018 July 1990 Forwards Decommissioning Financial Assurance Certification Rept A08822, Submits Addl Info Requested Re Util Response to Generic Ltr 88-11, Radiation Embrittlement of Reactor Vessel Matls. Charpy Impact Use Values for Welds Provided in Evaluation of Irradiated Capsule W-971990-07-18018 July 1990 Submits Addl Info Requested Re Util Response to Generic Ltr 88-11, Radiation Embrittlement of Reactor Vessel Matls. Charpy Impact Use Values for Welds Provided in Evaluation of Irradiated Capsule W-97 B13588, Corrects 900703 Submittal of Results of Second in-cycle Insp of Steam Generators.All Tubes W/Cracks Stacked & Plugged1990-07-18018 July 1990 Corrects 900703 Submittal of Results of Second in-cycle Insp of Steam Generators.All Tubes W/Cracks Stacked & Plugged B13569, Forwards, Haddam Neck Plant Decommissioning Financial Assurance Certification Rept1990-07-18018 July 1990 Forwards, Haddam Neck Plant Decommissioning Financial Assurance Certification Rept B13587, Requests Temporary Waiver of Compliance from Tech Spec 3.5.F.2 Re Emergency Diesel Generator (EDG) Limiting Condition for Operation.Waiver Would Extend Available Time to Repair Damaged Electrical Components1990-07-16016 July 1990 Requests Temporary Waiver of Compliance from Tech Spec 3.5.F.2 Re Emergency Diesel Generator (EDG) Limiting Condition for Operation.Waiver Would Extend Available Time to Repair Damaged Electrical Components ML20055E6791990-07-0606 July 1990 Responds to NRC Bulletin 88-008, Thermal Stresses in Piping Connected to Rcs. All Socket Welded Joints from Header Isolation motor-operated Valves to RCS for All 4 Loops Examined.No Recordable Indications Found ML20055D3461990-07-0303 July 1990 Responds to NRC Bulletin 90-001 Re Loss of Fill Oil Transmitters Mfg by Rosemount.Operability Determinations Performed & Documented for All Rosemount 1153 & 1154 Transmitters at Facility ML20055D7191990-06-29029 June 1990 Amends 900604 Rev 13 to QA Program ML20055D3481990-06-29029 June 1990 Forwards Addl Info Re Facility Crdr & Isap,Including Justification for Human Engineering Discrepancies Dispositioned for No Corrective Action B13564, Provides NRC W/Info Re Plant Pressurizer as follow-up to 900607 Meeting.Info Particularly Concerns Disposition of Three Indications on Pressurizer Inner Surface & Discussion of Resolution of Previous Indication1990-06-29029 June 1990 Provides NRC W/Info Re Plant Pressurizer as follow-up to 900607 Meeting.Info Particularly Concerns Disposition of Three Indications on Pressurizer Inner Surface & Discussion of Resolution of Previous Indication B13545, Forwards Rev 3 to Updated FSAR for Millstone Unit 31990-06-29029 June 1990 Forwards Rev 3 to Updated FSAR for Millstone Unit 3 B13550, Responds to Generic Ltr 90-04, Request for Info on Status of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions. Implementation & Completion Tables for staff-imposed Requirements Encl1990-06-27027 June 1990 Responds to Generic Ltr 90-04, Request for Info on Status of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions. Implementation & Completion Tables for staff-imposed Requirements Encl B13499, Forwards Corrected Tech Specs Page 3/4 9-1 for Incorporation Into Proposed Amend 36 to License DPR-21 Re Auxiliary Electrical Sys1990-06-26026 June 1990 Forwards Corrected Tech Specs Page 3/4 9-1 for Incorporation Into Proposed Amend 36 to License DPR-21 Re Auxiliary Electrical Sys ML20043F8721990-06-11011 June 1990 Corrects Name of Vendor Supplying Replacement Plug Valves, Per Util 900511 Ltr.Replacement Bolts,Not Valves,Purchased from Cardinal Industrial Products Corp ML20043H0161990-06-0808 June 1990 Requests Exemption from App J to 10CFR50 for 12 Valves in Reactor Bldg Closed Cooling Water Sys.Valves Not within Definition of Containment Isolation Valves in App J & Not Required to Be Tested 1990-09-07
[Table view] |
Text
O r
WWES con.r.i Ore,c.. . s io n sir..i. e.,iin. conn.ci cut
'^ ,b 2[
m ..,a *-a wa' P O BOX 270 HARTFORD. CONNECTICUT 06141-0270 L t ; *",;**' C '))[Z",",
,, (203) 665-5000 October 11,1985 Docket No. 50-336 A04824 Bl1738 Director of Nuclear Reactor Regulation Attn: Mr. Edward J. Butcher, Chief Operating Reactors Branch //3 Mr. John A. Zwolinski, Chief Operating Reactors Branch //5 U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Gentlemen:
Millstone Nuclear Power Station, Unit Nos. I and 2 Haddam Neck Plant ATWS Rule Schedule required by 10 CFR 50.62(dj On April 22, 1985, Northeast Nuclear Energy Company (NNECO) and Connecticut Yankee Atomic Power Company (CYAPCO) received Generic Letter 85-06(1) concerning quality assurance guidance for ATWS equipment that is not safety related. Generic Letter 85-06 indicated that issuance of the quality assurance guidance shall be considered the reference date initiating the schedule in 10 CFR 50.62(d). Section 30.62(d) of the ATWS rule requires each licensee to develop and submit a proposed schedule for meeting the requirements of the rule within 180 days, af ter issuance of the QA guidance. Additionally, the ATWS rule requires any schedule for completion, beyond the second refueling outage af ter July 26, 1984 to be justified. The purpose of this letter is to satisfy the requirements of 10 CFR 50.62(d) for Millstone Unit Nos. I and 2 and the Haddam Neck Plant.
Millstone Unit No.1 Millstone Unit No. I is participating in the NRC's integrated Safety Assessment Program. On May 17, 1985,(2) NNECO proposed that the scope of work required by 10 CFR 50.62 be explici considered in the context of the ISAP program. By letter dated July 31,1985, the NRC formally documented the results of the ISAP screening raview process for Millstone Unit No.1, and identified the issues or " topics" which the Staf f had concluded should be consider ed in ISAP.
Enclosure 2 to the July 31,19851ctter specifically identifies the requirements of 10 CFR 50.62 as 15AP Topic 1.18 for Millstone Unit No.1.
(1) H. L. Thompson Generic Letter 85-06 to All Licensees and Applicants, dated April 16, 1985.
(2) 3. F. Opeka let ter to C. I. Grimes, dated May 17,1985.
(3) H. L. Thompson letter to J. F. Opeka, dated July 31,1985.
k P
[ }
(
J
]
j 10 CFR 50.62(d) requires that all modifications necessary to address the ATWS
- issue be completed by the second refueling outage af ter July 26,1984, or, if the i schedule calls for implementation later than this time, that justification be
- provided and a final schedule mutually agreed upon by the Commission and the
, licensee. In the case of Millstone Unit No.1, the second refueling outage af ter 1 July 26,1984 is currently scheduled to begin in August,1987.
! On August 13, 1985,(4) NNECO provided a review of the current Millstone Unit i No. I design agqinst the requirements of 10 CFR 50.62. Additionally, on j August 23,1985,W NNECO provided an analysis of the public safety impact of i l the proposed ATWS modifications based on the Millstone Unit No.1 Probabilistic Safety Study which was performed in support of our ISAP ef forts. These !
i evaluations concluded that there would be a slight reduction in risk resulting !
j from implementation of these modifications. However, in keeping with the j philosophy of the ISAP program, this issue must be evaluated with respect to all other ISAP issues before a final determination and schedule for implementation can be proposed. As such, we are unable to provide a firm schedule for l
implementation at this time.
As interim justification, until a decision and schedule for implementation can be i determined through ISAP, we refer you to the NRC's ISAP Program Plan, [
l SECY-84-133, which states: )
I "To provide a stable environment to conduct ISAP, the Commission j has authorized the (NRC) Staff to suspend specific existing l implementation schedule requirements for the plants to be reviewed. '
} Each affected license will be expected to propose and justify deferras t
for specific implementation requirements that warrant further
- evaluation. The associated implementation requirements and other safety issues will be evaluated collectively in an integra ted !
assessmen t."
i Additionally, the NRC's raf t report on the risk-based evaluation of ISAP issues l
} ~
for Millstone Unit No.1(6 concludes that "the maximum potential risk reduction l i from the installation of an 86 gpm St.CS is rather small." The report also states i
that "a plant-specific ATWS analysis should be performed to finalize the priority j of this issue." And finally, the report concluded that the analysis would demonstrate that the issue should have a low priority.
Itased on the fact that Millstone Unit No. I currently complies with two of the !
- three specific requirements for boiling water reactors, and that the one i remaining issue has been shown to not be a significant safety concern requiring near-term action, we conclude that the absence of a firm schedule at this time is justified. As stated earlier, a schedule for 1rnplementation of all outstanding
, plant backfits will be mutually agreed upon by NNECO and the NRC Staf f in the l context of the ISAP program. ;
(4) 3. F. Opeka letter to C. I. Grimes, dated August 13,1985.
,f i
($) 3. F. Opeka letter to C. I. Grimes, dated August 23,1985. )
(6) C.1. Grimes letter to R. M. Kacich, dated September 23,1985.
I
! 3 4
Millstone Unit No. 2
' 10 CFR 50.62 requires that the following systems be installed at Millstone Unit No. 2 and be diverse from the Reactor Protection System (RPS):
- 1. Diverse Scram System (DSS) i
' 2. ATWS Mitigating System Actuating Circuitry (AMSAC) consisting 1 of:
- a. Auxiliary Feedwater Actuation System (AFAS)
- b. Turbine Trip (TT) l NNECO intends to comply with the ATWS requirements at Millstone Unit No. 2 with the systems that are described below: ,
1 A. Diverse Scram System
)
NNECO proposes to install a DSS at Millstone Unit No. 2 which will utilize !
- the existing pressurizer pressure sensors. The change will involve the j
installation of four channels of pressurizer pressure instrumentation devices consisting of Bistables and logic circuitry arranged in a two out of '
four logic to trip the Motor Generator output contactors in the event of an ATWS (see figure 1). Provisions will be included to bypass any of the sensors and convert the logic to two out of three to allow for maintenance of the sensors. The DSS will have the following design attributes:
- 1. Environmental Qualification - The components of the system will generally be located in mild environments. Where a component is located otherwise, it will be designed and qualified to the j environment that it is located in. l
- 2. Seismic Qualification - When a component is located where its failure i
due to a seismic event will adversely affect other safety related i equipment, that component will be seismically quallfled.
- 3. Power Supply - The DSS will be supplied from reliable power sources.
l j 4. Testing and Calibration - The DSS will be desig:.ed and installed to allow on-line calibration and testing.
1 i 1
- 5. Annunciation and Display - System status indication will be provided in the control room and DSS trip alarm will be annunciated at the i main control board.
- 6. Failure Mode on Loss of Power (LOP) - The DSS will not trip in the event of LOP since the DSS circuitry will be designed such that tripping relays are energized to trip.
I
-4_
- 7. Diversity from Reactor Protection System (RPS)- The DSS will share 4
the existing Pressurizer Pressure Sensors with the RPS (sensors include transmitter and signal conditioning circuitry). All other
, components such as the Bistables (B/S), Matrix circuitry, actuating relays and final actuation devices will be diverse from the RPS.
- 8. Location of Equipment - The Bistables and logic matrix circuitry will be located in the control room. i The trip hardware is located at the Motor Generator control cabinet in the DC switchgear room.
- 9. Reliability - The DSS will have a reliability comparable to the RPS.
Reliability calculations will be completed at a later date.
i
- 10. Setpoints and Response time - The DSS will have a trip setpoint of approximately 2400 psia increasing. Actual setpoint will be determined later to coordinate the DSS tripping with the RPS.
i The response time will be determined by the response times of l sensors, actuating relays and MG output contactor dropout time.
l 11. Quality Assurance - As stated in our December 10,1984 le t ter,(7) we l believe that our existing quality practices now applied to non-safety-i related equipment would be adequate for non-safety-related
- equipment encompassed by the ATWS rule, however, to meet the l
guidance contained in Generic Letter 85-06 the system will be procured, designed and installed under the Northeast Utilities Quality Assurance Program Topical Report, Revision 7.
i j B. Auxiliary Feedwater Actuation System (AFAS)
The existing Millstone Unit No. 2 AFAS will be modified to satisfy the ATWS requirement. The present circuitry includes a timer (3 minutes) which delays the initiation of AFW af ter detection of low steam generator
] (S.G.) level. This circuitry will be modified to have the means to i automatically bypass the timer in the event of an ATWS. It is diverse from i the RPS from the sensor output to the final actuation device. The AFAS is initiated by four channels of 5.G. Instrumentation arranged in a two out of four logic. The trip setpoint is 12% decreasing level. The system is a l Category lE system which was installed in 1981 in response to NUREG-1 0737 item i1.E.1.2.1b.
(7) W. G. Counsil letter to S. M. Goldberg, dated December 10,1984.
i i
i
?
r
l .
l i ,
C. Turbine Trip j
- With the implementation of the DSS at Millstone Unit No. 2, the diverse f turbine trip requirement will also be satisfied. This is because the existing RPS initiated turbine trip is accomplished by undervoltage relays !
7 monitoring the 240 VAC reactor trip bus voltage. While the turbine trip in .
j an ATWS event is accomplished by the same undervoltage relays, the '
initiation of .the undervoltage condition is diverse from the RPS. (See r figure 1). [
j 10 CFR 50.62 requires that the scheduled completion for Millstone Unit No. 2, to i meet the requirements of 10 CFR 50.62, be accomplished prior to restart from <
I the planned August,1986 refueling outage. In light of the lengthy delay in the [
issuance of Generic Letter 85-06, the long lead time required to adequately plan '
- and schedule outage activities, the time and effort necessary to perform detailed j J
engineering and design of systems and the long lead times required in the i procurement of equipment, full compliance with the ATWS requirements for l Millstone Unit No. 2 can be achieved by the end of the first refueling outage 18 "
months af ter the Staf f's concurrence with our proposed approach. ;
! Accordingly, pursuant to 10 CFR 50.56(d), justification for scheduling final l implementation later than the second refueling outage af ter July 26,1985 is '
provided for the above stated reasons. NNECO is prepared to be in full !
compliance with the requirements of 10 CFR 50.62 for Millstone Unit No. 2 by r i the end of the refueling outage scheduled to start in January,1988, provided i NRC Staff concurrence with NNECO's approach for meeting the requirements of 10 CFR 50.62 is received by March 1,1986.
[
t Haddam Neck Plant The Haddam Neck Plant is also participating in the Integrated Safety Assessment t Program. The NRC's July 31, 1985 letter to CYAPCO documenting the results i of the ISAP screening review process specifically identifies the requirements of i j 10 CFR 50.62 as ISAP Topic 1.16 for Haddam Neck. For the same reasons given ,
above for Millstone Unit No.1, we are unable to commit at this time to a firm i schedule for implementation of these modifications at Haddam Neck. Rather, a y decision and schedule for the proposed modifications will be arrived at through l the ISAP process. !
, Evaluations performed to date for the Haddam Neck Plant have shown the plant's transient response to an ATWS event to be significantly less severe than the generic Westinghouse plant evaluated in the development of the final rule, i
A plant specific analysis of the limiting ATWS event for the Haddam Neck Plant !
has previously been provided to the Staff.(8) This event was the loss of ;
feedwater ATWS. !
j i (8) D. C. Switzer letter to A. Giambusso, dated February 28,1975.
t
Since that time, several plant modifications have been implemented that would further reduce 'the consequences of an ATWS event. For. example, new Power Operated Relief Valves (PORVs) have been installed, and they have been upgraded to safety grade. The new PORVs each have a relieving capacity of more than three times that assumed in the earlier analysis. When normalized to core power, the PORY relief capacity is significantly greater than that assumed for the generic Westinghouse plant, which would result in a substantial reduction in calculated peak pressure from the earlier analysis.
There are other additional factors which would result in less severe consequences for the Haddam Neck Plant than for the generic Westinghouse plant. Haddam Neck operates at a lower core power level, only 53% of the Westinghouse generic value. Also, Haddam Neck has a more favorable moderator temperature coefficient and operates with a lower nominal primary system pressure and average temperature. All of these factors result in a more mild plant response to an ATWS event. In fact, our analyses predict a peak RCS pressure in the range of 2800 to 2850 psi for an ATWS, which is well within original system and vessel hydrostatic test limits. Also, our earlier ATWS analysis predicted no clad damage and thus minimal offsite radiological consequences.
We believe that the above information provides adequate technical justification to conclude that ATWS is not a significant safety issue requiring prompt action for Haddam Neck, and that the absence of a firm schedule at this time is acceptable. As with Milistone Unit No.1, a decisi;n on modifications and a schedule for implementation will be determined duong the ISAP review for the Haddam Neck Plant.
We trust you will find the above information satisfactory, and look forward to receiving your concurrence with ciur approach.
Very truly yours, CONNECTICUT YANKEE ATOMIC POWER COMPANY NORTHEAST NUCLEAR ENERGY COMPANY 3QlOpeka f Senior Vice President By: W. F. Fee
l Executive Vice President l l
ZR. S . G,. .
PRFSS. ILVEL YIIIGli ~
L- - - - 9 TIMER -
- -p AFl\S
~
g I
(>
i i e y y - - - - - _ _ _
r;
_j r---'
RXik7rTIUPPED TURBITE .
'I l l- - --e TRIP l l I
! ,_ ._ ._ __ _j .
"1 l g U.V.
d V s' 01
- k. T I l l
V > CEPR i 11
^ {'
Ii g POIOR GE ERA'IOR M. G. OUTPUT RX TRIP (m) SETS CG.TACIORS BREAKEI6 FIGUPE 1 Sinplified Representation of the Mi.llstone Unit 2 Proposcd Aws Systen