ML20133B869

From kanterella
Jump to navigation Jump to search
Insp Rept 50-267/85-14 on 850501-31.Violation Noted:Failure to Follow Procedural Requirements & Failure to Follow Controlled Work Procedure Manual Checklist Requirements
ML20133B869
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 08/01/1985
From: Ireland R, Plumlee G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20133B837 List:
References
50-267-85-14, GL-85-04, GL-85-4, NUDOCS 8508060278
Download: ML20133B869 (8)


See also: IR 05000267/1985014

Text

_ _ - _ _ . _ _ - _ _ _ _ _ _ . . _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ - _ - _ _ _ _

i ,

-; *

i ,t

i *-

, ,

'

%

> h t

,

4

i

,

APPENDIX B

' '

'

'

U. S. NUCLEAR REGULATORY COMMISSION

REGION IV

'

<

'

.

-

NRC Inspection Report: 50-267/85-14 License: DPR-34 .

Docket: 50-267

'

,

.

Licdnsee: Public Service Company of Colorado (PSC) ,

P. O. Box 840

'

Denver, Colorado 80201

,

Facility Name: Fort St. Vrain Nuclear Generating Station

Inspection At: Fort St. Vrain (FSV) Site, Platteville, Colorado

Inspection Conducted: May 1-31, 1985

Inspectors: M dru M; A j ////g

p G.Senior

L. Plumlet IIIInspector (SRI) / ' Date

Resident

Other Accompanying Personnel: Harold Miller, EG&G Consultant

Approved: [d. M

R. E. Ireland, Chief, Spdcial Projects and

2% /r'c

Date' ~

Engineering Section, Reactor Project Branch 1

Inspection Summary

Inspection Conducted May 1-31, 1985 (Report 50-267/85-14)

Areas Inspected: Routine, unannounced inspection of the control rod

drive event, followup on violations and deviations, generic letter followup,

licensee event report, maintenance, management meetings, operational safety

verification, and periodic and special reports. The inspection involved

92 inspector-hours onsite by one NRC inspector and 108 inspector-hours by one

NRC consultant.

t

l

i

'

i

8508060278 e!K)S02

PDR AEK)CK O!KhDO267

O PEWt

l

,

'

I l

- .

. _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

'

.

.

.

.

2

Results: Within the eight areas inspected, two violations (failure to

follow procedures, paragraphs 2 and 6), and two open items (G-9 procedure

deficiencies, paragraph 3, and operator knowledge, paragraph 8) were

identified.

__

-

i

. _ _ _ _ _ _ _ _ _ _

'

.

'

,

3

DETAILS

1. Persons Contacted

Principal Licensee Employees

  • T. Borst, Support Services Manager

D. Brown, I&C Supervisor

  • W. Craine, Superintendent of Maintenance
  • R. Craun, Site Engineering Manager

M. Deniston, Shift Supervisor

D. Evans, Shift Supervisor

  • M. Ferris, QA Operations Manager
  • W. Franek, Superintendent Operations
  • C. Fuller, Station Manager
  • J. Gahm, Manager Nuclear ~ Production

D. Hood, Shift Supervisor

J. Jackson, QA/QC Supervisor

J. McCauley, Results Engineering Supervisor

P. Moore, QA Technical Support Supervisor

  • F. Novachek, Technical / Administrative Services Manager

H. O'Hagen, Shift Supervisor

  • T. Orlin, Superintendent QA Services
  • G. Powers, Scheduling / Stores Supervisor
  • T. Prenger, QA Engineering Supervisor
  • G. Redmond, MQC Supervisor

G. Reigel, Shift Supervisor

T. Schleiger, Health Physics Supervisor

  • L. Singleton, Manager QA

H. Starner, Coordinator Nuclear Site Construction

R. Webb, Maintenance Supervisor

S. Willford, Training Supervisor

The SRI also contacted other plant personnel including administrative,

electrical, maintenance, reactor operators, and technicians.

  • Denotes those attending the exit interview.

2. Control Rod Drive (CRD) Event

During this reporting period, the licensee's progress on their CRD refur-

bishment program has been monitored on a periodic basis by both the SRI

and NRC consultant. The NRC inspectors noted the following findings.

. On May 6, 1985, the licensee made a 4-hour nonemergency event

notification concerning the determination that a purified helium

interspace pressurizing line, to refueling penetration Region 4, was

. _ _ _ _ _ _ _ - - - - _

. . , . . - . . . . , - . - - _ . , _ _ - - - - - - - - -

.

,

.

t

,

4

I

plugged. Followup to this report indicated that a special test

T-272 had identified several blocked pressurization lines. T-272

was subsequently terminated and T-283 was developed to test and

remove residual material from all refueling interspace pressurizing

lines. T-283 is being performed on each region upon completion of

that region's CRD refurbishment. Upon issuance, the SRI will review

the licensee's LER on this event.

.

On May 9, 1985, the NRC inspectors reviewing the procedure to

refurbish CRD 31 determined that:

. Refurbishment of CRD 31 was near completion when its back-EMF

test failed.

. A small squeak was heard in the cable drum area.

Site-nuclear engineering (NED) decided to disassemble the 200 assembly

to locate the problem. It was discovered that the wrong slinger

washer had been installed on the third stage causing the gears to

rub and that the two second stage duplex bearings had been installed

reversed. Task Step 48.1 to install the bearings and Task Step 48.5 to

install the slinger had the required workman and QC signatures.

Violation of the procedure by both the workman and the QC inspector -

was the cause of this problem.

A rework procedure was written to correct the problem and to continue

the assembly of the CRD.

The licensee was informed that this failure to follow procedural

requirements is considered a violation (8514-01) similar to Viola-

tion 8507-02. Upon request by the SRI, this subsequent violation and

corrective action were also discussed in the licensee's response to

Violation 8507-02, dated May 21, 1985 (P-85172). The SRI determined

! that the licensee's corrective action for the previous event, now

being implemented, should prevent further violations.

The NRC inspectors had no further comments in this area.

3. Followup on Violations and Deviations

l The SRI reviewed the licensee's response for the following violations

l

'

and deviations to verify conformance with regulatory requirements and

that corrective measures were completed:

a. (OPEN) Violation (50-267/8414-01): System in Deviation Status

Without Operation's Knowledge. The reactor equipment operator's

(EO) log was not revised as stated in the licensee's response dated

August 3, 1984 (P-84255). The licensee stated that a revised

corrective action would be i.csued explaining why the logs were not

permanently revised. A specific requirement to check the N p

cover

gas is currently being written on the E0 logs and is not a con-

trolled formal requirement.

_.

..

,

-

.

.

-

5

.

b. (OPEN) Violation (50-267/8414-02): Failure to Follow Fire Protec-

tion and Housekeeping Requirements. Corrective action was not - -

adequate to avoid further violations. Closeout is pending review

of response to NRC Inspection Report 85-07, Violation 8507-08.

c.

'

(OPEN) Violation (50-267/8414-03): Failure to Follow Startup

Procedures. Both the shift supervisor and senior reactor operator

involved have been admonished for their omission and were warned

that any further failures to follow procedures would result in

disciplinary actions. However, the. memoranda that documented the

above were not placed in the individual's personnel files as stated in

the licensee's response (P-84255). The memoranda were actually

placed in the superintendent of operation's personnel file. The SRI

is awaiting the licensee's resolution of this issue prior to

closecut of this violation. The SRI informed the licensee of the

need for accurate responses and obtained the licensee's agreement

to ensure that future responses are accurate.

d. (CLOSED) Violation (50-267/8414-04): Failure to Install Check

Valves in Accordance With Procedures. Maintenance Procedure MP 11-3,

Issue 11, dated May 1, 1985, and Surveillance SR 5.2.16f-RX, Issue 5,

dated August 8, 1984, incorporated QC hold and witness points to

ensure that work is stopped before check valve installation and that

the installation is independently observed. SR 5.2.16f-RX, Issue 6, -

dated January 17, 1985, subsequently incorporated proof testing upon

completion of installation in accordance with SR-RE-52-X (for verifying

purge-helium-check valve installation) and SR 5.1.2ad-Q (for verifying i

reserve-shutdown-helium-check valve installation). The responsible

QC inspector was admonished. '

e. (CLOSED) Deviation (50-267/8414-05): Deviation from Response to

Previous Violation. A memorandum (NFG-84-0135, dated August 1,

1984) was issued to people in the control work procedure (CWP)

cycle to ensure efforts were made to utilize the correct CWP cover

page. The CWP manual was subsequently revised to include the

correct CWP cover page.

s

f. (CLOSED) Violation (50-267/8414-12): CWP Process / Inadequate Proce-

dure. Administrative Procedure G-9, " Controlled Work Procedures,"

Issue 6, dated December 5, 1984, and Controlled Work Procedure

Manual (CWPM), Issue 2, dated January 31, 1985, prescribed the

appropriate instructions / procedures for performing / controlling

CWPs, procedure / inspection / test / reports (PITRs), and deviation

reports (DRs). During a review of G-9, the SRI identified the

following problems:

. Step 5.5.1.2 as worded allows the use of a " prefab /nonsafety-

related" PITR for prefab of safety-related items.

. Page 9 of 21, fourth paragraph, has a "(4)" that appears not

to have any meaning.

__- _ _ - _ _ - _

.. . _ . _ _

,;;

-

.

.

.

6

. Step 4.1.18 does not require updated control room and shift

supervisor design documents prior to return of the modified

system to service.

.

G-9 does not require an independent design verification of DRs

as does the CWPM Step 5.6.11.

The licensee was informed that these procedure deficiencies are

considered an open item (8514-02) pending the necessary procedure

revisions.

g. (CLOSED) Violation (50-267/8415-02): Fire Water Pump House Fans

, Inoperable Without Operator Knowledge. The licensee was unable to

determine the reason for the fans being in the ACM position, but

" '

y ' believes it may have occurred during the checkout of the 480-volt  :

power system after the modifications to the 480-volt buses. The L. '

Surveillance SR 5.2.21-SA, "ACM Pneumatically and Electrically

. Operated Valves and Transfer Switch Functional Test," Issue 19,

dated September 28, 1984, used ta test the ACM was revised to

provide independent verification of system return to " normal.",

b. (CLOSED) Deviation (50-267/8415-06): TMI Action Item I.C.2 Commit-

ment. The effectiveness ,cf shift turnover procedures was evaluated

during performance of the Atgust - September 1984, NFSC ;g.

Audit A-84-01 and duringe.he quarterly performance of QA Monitor *

Procedure QAMP P1-1, " Plant Operations Shift Turnover Activities,"

Issue 1, dated December 27, 1984, which was developed in response *o

, Violation 8416-01. A QA commitment tracking system has also been

l established via a computerized report distributed monthly to QA

management. QA General Procedure QAGP-6, "QA Commitment System,"

is being issued to document this tracking system. ,

,

i. (CLOSED) Violation (50-267/8416-01): No shift Turnover Proceduce.

Station Manager Administrative Procedure SMAP-8, " Plant Operations

Shift Turnover Procedure," Issue 1, dated October 10, 1984, estab-

lished the instructions to be followed by operations personnel

during shift relief and turnover.

4

4. Generic Letter Followup

The SRI reviewed the licensee's response dated May 10, 1985 (P-85165),

'

to Generic Letter 85-04, " Operator Licensing Examinations." The

response addressed the information discussed in the generic letter. ,

No violations or deviations were identified. I)[

3,;

5. Licensee-Event report (LER) -

^

-

/ I e,

The SRI reviewed licensee event reporting activities to verify that they 'F. * -

were in accordane.e with Technical Specification, Section 7, including ,3 -

identification details, corrective action, review, and evaluation of , <'

,

aspects relative to operations and accuracy of reporting. '

_ -;

.c

h

i

e?',

_ _ _ __ _ - _ _ _ _ _ _ _ _ _ ._ _

. _ _ - _ -

.

.

.

7

The following LERS were reviewed for adequacy and/or closeout:

(CLOSED)79-028 (CLOSED)83-052

(CLOSED)80-030 (CLOSED)83-053

(CLOSED)81-068 (CLOSED)83-054

(CLOSED)82-048 (CLOSED)83-055

(CLOSED)82-049 (CLOSED)84-001

(CLOSED)83-018 (CLOSED)84-003

(CLOSED)83-028 (CLOSED)84-004

(CLOSED)83-045 (CLOSED)84-006

(CLOSED)83-049 (CLOSED)84-007

(CLOSED)83-050 (OPEN)84-014

(CLOSED)83-051

(CLOSED)83-052

6. Maintenance (Monthly)

The NRC inspectors reviewed records and observed work in progress to

ascertain that the following maintenance activities were being conducted

as required by approved procedures, Technical Specifications, and appro-

priate codes and standards. The following maintenance activities were

reviewed and observed:

SSR 85506015 HV2251 Inspection / Repair in accordance with

MP 22, " Maintenance and Repair of

Rockwell-Edwards Valves, Pressure Seal Type"

CN 1976 A,B/CWP 85-500 Replace Exiting Bolts with New Inconel Bolts,

"D" Circulator (C-2101)

SSR 85505605 Replace Helium Ducting Bolts in accordance with

MP 21-18, " Helium Circulator Compressor

Assembly Retaining Bolt Replacement"

CN 1886/CWPs85-330 Reorganization, Functional Grouping, Relabeling,

through 85-343 and Demarcation of Instrumentation

Components and Systems on I-01/02

t CN 1907/CWPs 85-74, Replace Existing Flow Meters on Each CRD Purge

CW 85-75, CWP 85-78, Line; Provide Remote Alarm and Continuous

CW 85-145 through through CWP 85-100, and Recording for Each CRD

CW 85-195 Purge Flow

During a review of the control room design review (CROR) modification

CN 1886 on May 28, 1985, the SRI determined a significant breakdown in

housekeeping / cleanliness. Both the vertical and bench boards as well as

the rear of panels I-01/-02 contained significant amounts of metal

shavings / filings on recorders, handswitches, controllers, and terminal

boards. The amounts of shavings / filings indicated a degradation of

housekeeping / cleanliness requirements. The SRI immediately informed the

licensee and an immediate investigation was initiated by the licensee.

--

.y

< 3

..

instances of QA deficiencies relied upon by -Intervenors and the

documents related to such deficiencies such instances are

identified in the ' body of our amended contention with citations

to the related documents and relevant portions of such documents

are reproduced and attached as exhibits. This information

regarding our contention has already been fully disclosed to the

NRC Staff and Applicant.

The NRC Staff seeks the production of documents from

Intervenors for inspection and copying. Documents so identified

in~ the answers to the following' interrogatories, except for

those'which are privileged, will be made available for inspection

and copying at counsel's office in Chicago, Illinois, at a

, time to be agreed upon. In the course of preparing for the

litigation of this contention and advising Intervenors ,

.

documents are prepared which are privileged and not subject to

discovery pursuant to 10 CFR Section 2.740(b)(1) . Such

documents as trial preparation materials are subject to a

work product privilege and an attorney-client privilege protects

from disclosure the mental impressions and opinions of counsel.

10 CFR Section 2. 740(b)(2) .

Such documents as the handwritten notes prepared by

Intervenors' counsel are privileged and protected from disclosure.

Intervenors obj ect to the production of such documents and ask

the Board to enter an order protecting such materials from

! disclosure.

- lii -

l

.

E

'

l

~ ,

f I

These interrogatories are being answered by the under-

signed counsel fo.r Intervenors . No consultants or other

advisors are relied upon for such answers. Intervenors have

not, at this time, identified the witnesses they expect to

call at hearing with regard to the subject matter of these

interrogatories. However, pursuant to 10 CFR Section 2.740(e),

1

Intervenors intend to seasonably supplement this response

to identify persons expected to be called as experts.

1

l

- iv -

t

i

I

L u ._

a

y n

INTERROGATORY RESPONSES:

Q-1.- Are there instances other than those cited in subpart

A.-F. of paragraph 1 which support your allegation that

Applicant's QA program violates Criterion I of 10 C.F.R. Part 50,

Appendix B by failing to oversee the performance of their site

contractors?

A-1. No.

Q-2. If the answer to Interrogatory 1 above is yes:

a. Describe each instance in detail, including the '

time period during which it occurred.

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-2. Not applicable.

-Q-3 Are you aware of corrective actions which have been

taken to remedy the situation set forth in paragraph 17

A-3 Yes.

Q-4. If the answer to Interrogatory 3 above is yes:

a. Describe such corrective actions with particular-

ity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 1. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 3

i

A 4. a. Intervenors are aware generally that Applicant has

undertaken a number of corrective action programs, at least in

part as required by the NRC Staff, to address quality assurance

deficiencies at the Braidwood station. The " top twenty"

corrective action programs at Braidwood are identified and

described by Mr. David H. Smith of Commonwealth Edison in his

1

L 1

. '

April 8, 1985, letter to NRC Regional Administrator James G.

Keppler. Exhibit 7 to the May 24, 1985, Motion To Admit Amended

Quality Assurance Contention. The status and scheduling of these

corrective action programs is further described in the June 7,

1985, Affidavit of Michael J. Wallace, filed by Applicant in this

proceeding. There, at page 2, Mr. Wallace states the Applicant's

position regarding the relationship between such programs and

Intervenors' contention:

Counsel advised that the admission of such a

contention could necessitate litigation of the

'

following corrective action programs: the

heating, ventilation, and air conditioning

("HVAC") configuration program, the HVAC duct

fitting verification program, the HVAC housing

and air risers program, the concrete expansion

anchor ("CEA") inspection program, the safety-

related mechanical equipment reinspection

program, and the electrical document review.

Counsel further advised that such litigation

could not be undertaken and the record in the NRC

licensing proceeding could not be closed on such

a contention until these corrective actions and

programs have been implemented to the point

where reasonably complete actions have been

taken or reasonably final results are available.

In addition, Commonwealth Edison has been required by NRC to

institute the Braidwood Construction Assessment Program (BCAP)

which was described in a June 22, 1984, transmittal letter from

James J. O'Connor, Chairman and President of Commonwealth Edison

Company to Mr. Keppler. Id., Exhibit 8. The BCAP program

elements may either directly or indirectly represent corrective

actions for previously identified quality assurance deficiencies.

BCAP includes a Construction Sample Reinspection (CSR) of

selected safety related hardware, a Reverification of Procedures

2

i

j * ,

!

!

- _ _ . - _ . _ - _ _ _ _ _ _ ._

'l

,

. '

to Specification Requirements (RPSR) element which reviews

installation and inspection procedures, and a Review of

Significant Corrective Action Program (RSCAP) element which

purports to review the effectiveness of existing major corrective

actions.

Finally, for items of noncompliance, identified by the NRC

Staff and acknowledged by Applicant, Intervenors understand that

Applicant generally undertakes some measures characterized as

corrective actions. Intervenors have sought information

regarding such corrective action in discovery requests which are

pending. Interrogatory No. 58, for example, served July 2, 1985,

seeks information regarding the corrective actions taken to

remedy deficiencies referred to in our amended contention. It

was objected to, in part, by Applicant in a July 29, 1985,

pleading. No answer to this interrogatory was provided by

Applicant in its July 30, 1985, First Partial Response; any

answers to the unobjected-to portion of the interrogatory are

expected to be served August 9, 1985.

In Appendix B to the June 1984 BCAP program descriptions a

" Reinspection of Safety-Related Mechanical Equipment" corrective

action program (CAP) is identified which is believed to relate to

this part of the contention. This CAP is described by Applicant

~

as the one corrective action "that drives the schedule" Tr. 201-

202, since it is anticipated that it will not be completed until

October 1, 1985. Id.

Among the " top twenty" Corrective Action Programs identified

by Mr. Smith of Edison in his April 8, 1985, letter, supra, is

3

t

,

'

e

the Material Traceability Verification Program (MTV) which is

believed to relate to this part of the contention.

! b. Intervenors at present have not taken a position

on the adequacy of any such corrective action programs. However,

Intervenors are aware of criticisms and weaknesses which have

l been identified with respect to some of these programs. In

addition, the NRC Construction Assessment Program (CAT) expressed

major concerns at Braidwood about "the ability to manage the

large number (over 20) of ongoing major corrective action

programs and ensure that current work is correctly performed."

Inspection Report 84-44/40, p. 1, Exhibit 10 to the May 24, 1985,

,

Motion To Admit Amended Contention.

Weaknesses and criticisms of the Braidwood corrective action

programs are discussed in Intervenors' May 24 Motion at pp. 8-11.

These weaknesses included " reinspection discrepancies," improper

" invalidations" of discrepancies when identified, failure of the

BCAP RPSR element to review " current" site procedures, failure of

the BCAP RSCAP element to include actual hardware inspections,

and a concern that the MTV program cannot effectively verify

traceability where either markings or documentation are absent.

Id.

c. All documents relied upon are identified in the

text of the responses given.

Q-5. Explain the meaning of the term " widespread

deficiencies" as used in paragraph 1 on page 19

A-5. " Deficiencies" are instances of noncompliance with

1

applicable codes, specifications, procedures or other

4

'l

r' ,

i

..

requirements. The term " widespread" is intended to reflect the

significance, pervasiveness a,nd frequency of occurrence.

Q-6. Are the instances described in subparts A.-C. of

paragraph 3 the sole instances upon which you rely as your basis

for the contention that Applicant's QA program is not adequately

documen;ed by written policies, procedures and instructions and

does not effectively control activities affecting quality?

A-6. No.

Q-7. If the answer to Interrogatory 6 above is not

a. Describe in detail each additional instance on

which you rely as a basis for paragraph 3

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-7. a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that

Applicant's Quality Assurance program violates this Appendix B

Criterion II.

Other such instances ares

(1) Additional management attention is required to improve

contractor performance in craft and quality control

. inspector training. Paragraph 1, subpart F, page 22.

(2) Phillips, Getschow Quality Procedure regarding uce of a

calibrated instrument to measure pipe bends was not

followed. Paragraph 6, subpart B(3), page 31.

L (3) Purchased piping from a company that did not have an

approved QA program. Paragraph 6, subpart G, page 32.

(4) Adequate traceability records were not maintained

regarding large cap screws which was in part the basis

for imposition of penalties for Quality Assurance

breakdown. Paragraph 8, subpart A, page 34.

5

I

,

e y

, i.

r

t

(5) Civil penalty was imposed for' breakdown of QA program

because of a problem with bolting of the steam

generator supports. Paragraph 12, subpart A, page 41.

t- (6) Applicant failed to implement a QA program for the

l erection of mechanical, safety-related equipment..

-

Paragraph 12, subpart G, page 43

-(7) A number of mechanical safety-related equipment records

~

failed to show compliance with quality assurance

requirements. Paragraph 13, subpart A, page 45.

(8) No follow-up was done to determine the effectiveness of

the quality assurance program regarding installation of

l . most of the critical nuclear steam supply system.

'

Paragraph'14, subpart A, page 46.

l b. Documents reflecting the instance described in

t

Interrogatory 7a(1)~ above are cited on page 22 of Intervenors'

May 24, 1985, Motion To Admit Amended Quality Assurance Contention ,

and relevant portions are included in the exhibits attached

thereto.(Exh. 10). f

Documents reflecting the instance described in Interrogatory

l i

7a(2). above are cited on page 31 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

! portions are included in the exhibits attached thereto (Exh. 5).

I Documents reflecting the' instance described in Interrogatory

l

_

7a(3) above are cited on page 32 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are inel,uded in the exhibits attached thereto (Exh. 21).

Documents reflecting the instance described in Interrogatory

l

7a(4) above are cited on page 34 of Intervenors' May 24, 1985,

.

' Motion To Admit Amended Quality Assurance Contention and relevant

dortionsare'includedintheexhibitsattachedthereto(Exh. 3).

,

Documents reflecting the instance described in Interrogatory

!

!

-

6

l

>

<

Y

,

'

.

7a(5) above are cited on page 41 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 3).

Documents reflecting the instance described in Interrogatory

7a(6) above are cited on page 43 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 20).

Dccuments reflecting the instance described in Interrogatory

7a(7) above are cited on page 45 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 3).

Documents reflecting the instance described in Interrogatory

7a(8) above are cited on page 46 of Intervenors' May 24, 1985,

Motion To Admit Ameaded Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 3).

Q-8. Are you aware of corrective actions which Applicant

has taken to correct the deficiencies cited in paragraph 3

A-8. Yes.

Q-9 If the answer to Interrogatory 8 above is yes:

a. Describe such corrective actions with particular-

ity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 3 State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 8.

A-9. a. Please refer to the answer given to

Interrogatory 4a above. In addition, by letter of July 3, 1985,

7

L

3

.

.

Applicant circulated their June 21, 1985, response to the

noncompliances in Inspection Report 85-15/16. They state that no

specific corrective action has been taken with regard to the

unauthorized modification of structural beams because, in their

judgment, other existing corrective action programs were l

adequate to assure that either the problem would not recur; and

that other instances had been, or would be, identified.

b. Please refer to the answer given in Interrogatory

4b above. l

c. Please refer to the answer given in Interrogatory

4c above.

Q-10. Are the instances cited in subparts A. and B. of

paragraph 4 the only instances which form the basis for the

contention that training and indoctrination of those performing

activities affecting quality was inadequate?

A-10. No.

Q-11. If the answer to Interrogatory 10 above is no:

a. Describe in detail the other instances upon which

you rely as the basis for this contention, including the date of

their occurrence.

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-11. a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that

Applicant's Quality Assurance program violates this Appendix B

Criterion II.

8

O__

~ a

...

Other such instances are:

~(1) .A welder documented as performing welding was not

qualified. Paragraph 9, subpart D, page 36.

(2) Craft personnel improperly repaired welds. Paragraph

11, subpart D, page 40.

b. Documents reflecting the instance described in

Interrogatory 11a(1) above are cited on page 36 of Intervenors'

May 24, 1985, _ Motion To Admit Amended Quality Assurance Contention

and relevant' portions are included in the exhibits attached

thereto (Exh. 21).

Documents reflecting the instance described in Interrogatory

11a(2) above are cited on page 40 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 18).

~Q-12. Are you aware of corrective actions which Applicant.has

taken to remedy the situations in subparts A. and B. of paragraph 4.

~A-12. No.

Q-13 If the answer to Interrogatory 12 above is yes:

a. Describe such corrective actions with

particularity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 4. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 12.

A-13 Not applicable.

Q-14. Are the instances alleged in subparts A.-C. of

paragraph 5 of your contention concerning quality assurance the

only instances upon which you rely as the basis for your

contention that there is inadequate program to assure that

9

M

.

applicable regulatory requirements and design basis are correctly

translated into specifications, drawings, procedures, and

instructions?

A-14. No.

Q-15. If your answer to Interrogatory 14 above is no:

a. Describe in detail all other instances upon which

you rely as the basis for subparagraph 5 of your contention.

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-15. a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that

Applicant's Quality Assurance program violates this Appendix B

Criterion III.

Other such instances includes

(1) Edison and Sargent and Lundy did not provide sufficient

assessments and verifications of Phillips, Gotschow

design capabilities prior to authorizing field routing

of Class 2 and 3 small bore piping and field design of

supports / restraints. Paragraph 3, subpart A(4)(a),

page 26.

(2) Phillips, Getschow small bore pipe routing procedures

lacked specific quantitative field design criteria to

meet specifications. Paragraph 3, subpart A(4)(6),

page 26.

(3) Use of the Field Change Request system compromised the

final design change acceptance review and approval.

Paragraph 3, subpart A(4)(f), page 27.

(4) Phillips, Getschow piping crews failed to adequately '

control the mocifications of beams. Paragraph 3,

subpart B, page 27.

(5) bargent and Lundy did not prescribe clearance criteria

for safety-related HVAC components or safety related

10

L t

_ _ _ _ _ _ - _ _ _ _ _ _ _ ___ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

. *

, large bore piping and electrical items in relation to

l other items. Paragraph 6, subpart D, page 32. i

  • '

! (6) Craft personnel made field changes to drawings being

made during the installation of ASME Section II piping. '

Paragraph 7, subpart A, page 33

(7) Some piping was installed that did not meet design

requirements. Paragraph 10, subpart B, page 37

,

i (8) Applicant's QA inspectors failed to identify areas

where Phillips, Getschow siesmic category I and other

pipe supports / restraints have not been constructed in

accordance with design requirements. Paragraph 10,

subpart C, page 38.

(9) Records relative to installation of mechanical safety-

related equipment failed to show compliance with design ,

requirements. Paragraph 13, subpart A, page 45.  !

b. Documents reflecting the instance described in

l Interrogatory 15a(1) above are cited on page 26 of Intervenors'

l May 24, 1985, Motion To Admit Amended Quality Assurance Conten-

tion and relevant portions are included in the exhibits attached  !

thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

[

15a(2) above are cited on page 26 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5). '

Documents reflecting the instance described in Interrogatory

15a(3) above are cited on page 27 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

,

Documents reflecting the instance described in Interrogatory

15a(4) above are cited on page 27 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assursuce Contention and relevant

,

portions are included in the exhibits attached thereto (Exh. 17).

11

l

  • .

r-

,

Documents reflecting the instance described in Interrogatory

15a(5) above are cited on page 32 of Intervenors' May 24, 1985,

Hotion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 22).

Documents rerlecting the instance described in Interrogatory

15a(6) above are cited on page 33 or Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions aru included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

15a(7) above are cited on page 37 or Intervenors' May 24, 1985,

'

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 6).

Documents reflecting the instance described in Interrogatory

15a(8) above are cited on page 38 or Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 10).

Documents reflecting the instance described in Interrogatory

15a(9) above are cited on page 45 or Intervenors' May 24, 1985,

Hotion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 3).

Q-16. Are you aware or any corrective actions being taken

by Applicant to correct the situations described in subparts A.-

C. or paragraph 5 or your contention?

A-16. No.

"

Q-17 If the answer to Interrogatory 16 above is yes:

a. Describe what you understand to be the corrective

actions being taken by Applicant.

b. State your position as to whether such corrective

12

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

actions would or would not be adequate to remedy the situation

described in paragraph 5. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatories 15 and 16.

A-17. Not applicable.

Q-18. Are the instances specified in subparts A.-I. of

paragraph 6 of your quality assurance contention the only

instances on which you rely as the basis for your contention that

there is inadequate prescription of activities affecting quality

by documented procedures, instructions and drawings?

A-18. No.

Q-19 In the answer to Interrogatory 18 above is not

a. Describe in detail the other instances upon which

you rely as the basis for paragraph 6 of your contention.

b. Identify all documents which relate to such

instances by title, author, if any, date or issuance and, if

other than NRC documents, provide a summary of their contents.

A-19 a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that

Applicant's Quelity Assurance program violates this Appendix B

Criterion V.

Other such instances includes

(1) Detailed drawings regarding small bore pipes were not

losued by Sargent and Lundy or Phillips, Getschow.

Paragraph 3, subpart A(4)(a), page 26.

(2) Phillips, Getschow did not follow procedure

requirements for small bore piping calculations.

Paragraph 3, subpart A(4)(c), page 27

(3) NRC CAT found design change control problems, including

design change documents written against superceded

13

,

4

_ . _ . . _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _

'

.

l

revisions or the approved design drawings. Paragraph

5, subpart A, page 29

(4) Field changes were made to drawings by craft personnel

during installation or ASME Boiler and Pressure Vessel

Code. Paragraph 7, subpart A, page 33

(5) A procedure for setting major nuclear steam supply

system components was not developed. Paragraph 10,

subpart A, page 37.

b. Documents reflecting the instance described in

1

Interrogatory 19a(1) above are cited on page 26 or Intervenors'

May 24, 1985, Motion To Admit Amended Quality Assurance Contention

and relevant portions are included in the exhibits attached

thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

19a(2) above are cited on page 27 or Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

..

Documents reflecting the instance described in Interrogatory

19a(3) above are cited on page 29 or Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 10).

Documents reflecting the instance described in Interrogatory

19a(4) above are cited on page 33 or Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

19a(5) above are cited on page 37 or Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention .and relevant

portions are included in the exhibits attached thereto (Exh. 3).

14

'~

_ _ _ _ _ _ _ _ _

r ,

. *

Q-20. Is the instance set forth in subpart A. of paragraph

7 of your contention the sole instance of inadequate document

control which provides the basis for your contention that

Applicant has failed to establish a program of adequate document

i control?

A-20. No.

! Q-21. If the answer to Interrogatory 20 above is no:

l

l a. Describe your detail the other instances you

allege form the basis of paragraph 7 of your contention,

including the date of occurrence of each instance.

'

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

l

A-21. a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

i serve as the basis for that contention, other instances of

l

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that

l

!

Applicant's Quality Assurance program violates this Appendix B

Criterion VI.

Other such instances include:

l

(1) Sargent and Lundy calculations which provided the

original justification for the factor design

methodology and magnitude were not retrievable.

Paragraph 13, subpart B, page 45.

, b. Documents reflecting the instance described in

Interrogatory 21a(1) above are cited on page 45 of Intervenors'

l

May 24, 1985, Motion To Admit Amended Quality Assurance Conten-

tion and relevant portions are included in the exhibits attached

thereto (Exh.19).

Q-22. Are you aware of any corrective actions taken by

Applicant to provide adequate document control?

l

15 ,

,

._ _ _ _ _ - _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ . . _ .

.

A-22. Yes.

Q-23 If the answer to Interrogatory 22 above is yes:

a. Describe such corrective actions with

particularity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 7. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 22.

A-23 a. Please refer to the answer given to Interrogatory

4a above.

b. Please refer to the answer given in Interrogatory

4b above.

c. Please refer to the answer given in Interrogatory

4c above.

Q-24. Are the instances specified in subparts A.-F. of

paragraph 8 of your contention the sole basis for your contention

that Applicant's program for material and parts control is

inadequate?

A-24. No.

Q-25. If the answer to Interrogatory 24 above is not

'

a. Describe each instance in detail, including the

time period during which it occurred.

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-25. a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

16

i

.

.

amended contention provide further support for our claim that

Applicant's Quality Assurance program violates this Appendix B

Criterion VIII.

.

Other such instances include:

(1) Additional support plates were not identified during QC

inspections. Paragraph 6, subpart D, page 32.

(2) Piping contractor found piping that violated minimum

requirements. Paragraph 6, subpart F, page 32.

(3) Material installed for the pipe whip restraint plate

was not of proper specifications. Paragraph 6, subpart

I, page 33

(4) Quality structural steel was not approved for use by

the Architect-Engineer but was released for use in

installation by the structural steel contractor and

documented as being used for cover plate welds.

Paragraph 9, subpart D, page 36.

(5) Seventy to seventy-two steam generator support bolts

were received in January 1979 and identified as

nonconforming. There is no record as to dispostion of

these bolts. Paragraph 11, subpart A, page 39

(6) Rejected safety-related pipe was installed. Paragraph

11, subpart C, page 40.

b. Documents reflecting the instance described in

Interrogatory 25a(1) above are cited on page 32 of Intervenors' May

24, 1985, Motion To Admit Amended Quality Assurance Contention

and relevant portions are included in the exhibits attached

thereto (Exh.14).

Documents reflecting the instance described in Interrogatory

25a(2) above are cited on page 32 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 20).

Documents reflecting the instance described in Interrogatory

25a(3) above are cited on page 33 of Intervenors' May 24, 1985,

17

___ - _-__ - _-_____ _ _ ___ _ 2 -

. _ _ _ _ _ _ _ _ _ - _ _ _

'

.

Motion To Admit Amended Quality Assurance Contentien and relevant

portions are included in the exhibits attached thereto (Exh. 22).

Documents reflecting the instance described in Interrogatory

25a(4) above are cited on page 36 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 21).

Documents reflecting the instance described in Interrogatory

, 25a(5) above are cited on page 39 of Intervenors' May 24, 1985,

l

l Motion To Admit Amended Quality Assurance Contention and relevant

l

portions are included in the exhibits attached thereto (Exh. 3).

Documents reflecting the instance described in Interrogatory

25a(6) above are cited on page 40 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 21).

Q-26. Are you aware of any corrective actions which have

been taken by Applicant to improve materials and parts control at

the Braidwood site?

A-26. Yes.

Q-27. If the answer to Interrogatory 26 above is yes:

a. Describe such corrective actions with

particularity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 8. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 26.

A-28. a. Please refer to the answer given to Interrogatory

4a above.

b. Please refer to the answer given in Interrogatory

18

.

_ _ _ . _ _ _ _ _ _ _ _

.

l

4b above.

l c. Please refer to the answer given in Interrogatory

4c above.

Q-28. Are the instances set forth in subparts A.-E. of

paragraph 9 of your contention the sole basis for your contention

that Applicant's program does not provide adequate control of

special process and adequate ensurance that these special

processes are accomplished in accordance with applicable codes

and standards?

A-28. No.

Q-29 If the answer to Interrogatory 28 above is not

a. Describe in detail each other instance of

inadequate control or oversight of special processes which forms

l the basis for your contention in paragraph 9.

b. Identify all documents which relate to such

i

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

l A-29. a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this intorrogatory,

serve as the basis for that contention, other instances of

l

Quality Assurance deficiencies identified elsewhere in our

,

amended contention provide further support for our claim that

l

Applicant's Quality Assurance program violates this Appendix B

Criterion IX.

Other such instancen includes

(1) Qun11ty control inspection activities need to be

improved in the welding nren. Paragraph 1, subpart D,

pnge 21.

(2) Instructionn were not approprinto to the circumntances

in that welding procedures npecifying the essentini

variablen were not prencribed on drawings or welding

sequences for each specific flVAC inntnlintion und

Qualtiy Control innpoetionn during the wolding procenn

were not of adequate scope und frequency to nasure the

19

,

. 1

,

'

use of correct welding variables. Paragraph 3, subnart ,

A(1), page 25.

(3) Quality control inspectors were not given appropriate

instructions regarding fillet weld gaps. Paragraph 3,',

subpart A(2), page 25.

(4) The piping contractor, Phillips, Getschow, did not have

a procedure or documented instruction stipulating a

systematic method for producing an accurate In-service

Inspection drawing, including determining the number -

und location of all field welds and shop welds.

Paragraph 6, subpart C, pages 31-32.

(5) Weld sizes in structural pipe support /rentrainto were

not identitled to be proper weld configurations.

Paragraph 10, subpart E, page 39.

(6) Comstock weld inspectors allowed craf t personnel to

repair / work weld defects identified during final QC ,

inspections. Paragraph 11, subpart D, page 40.

(7) Through August 4, 1983, numerous welding deriotency and

deviation notelces were written by the ilVAC contractor

but the the contractor's Quality Assurance Psegrne did

not require that Correction flotices be analyzed for

nignificance. Paragraph 12, subpart B(2), page 42.

(8) Corrective action was not adequate concerning

lionconformance Report flo. BR-08, dated June 15, 1981,

since the nonconforming welds completed by unknown

welders were " accepted-us-in" after only a visual

examination. The acceptance of the weld by visual

examination pursuant to AWS D1.1 is bneed on the fact

that n qun11ried welder performed the weldin6 in

accordance with the qualified procons. Paragraph 12,

subpart D(3), pages 42-43 s .

(9) flo documentation supporting ntatement that corredrive

action concerning defective wolds was "N/A" and,' hver.

on numeroun wold doriciencien af ter reworY, the

'

corrective action for thin ilCH wnn inerrno'i te.

Paragrnph 12, nubpart D, page 43 '

,

(10) I:dinon QA identirled innpection defici,neien but ralled

to take corrective action with respoet' to llapoleon

Steel Contractorn' punt weiding 1.lopoetten activities

to nasure that defecto do not exist in muitt-pann

weldn. Paragraph 12, nubpart I, ptge 44

b. Documenta rurlocting the inntnnce doncribed in

Interrogntory 29a(1) above are cited on page 21 of Intervenorn'

20

"

, _ __ _ _2 _ .

_

.

.. . .

o

l

May 24, 1985, Motion To Admit Amended Quality Assurance Conten-

tion and relevant portions are included in the exhibits attached

j thereto (Exh.10).

Documents reflecting the instance described in Interrogatory

29a(2) above are cited on page 25 of Intervenors' May 24, 1985,

,

Motion To Admit Amended Quality Assurance Contention and relevant

'

portions are included in the exhibits attached thereto (Exh. 5).

f,. ,-

1

Documents reflecting the instance described in Interrogatory

29a(3) above are cited on page 25 or Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

f portions are included in the exhibits attached thereto (Exh. 5).

,

4

Documents reflecting the instance described in Interrogatory

) ,

29a(4) above are atted on pages 31-32 of Intervenors' May 24,

4'

1985, Motion To Admit Amended Quality Assurance Contention and

relevant portions are included in the exhibits attached thereto

(Exh. 14).

Documents reflecting the instance described in Interrogatory

29a(5) above are cited on page 39 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant I

e

portions are included in the exhibits attached thereto (Exh. 10). ,

1

Documents reflecting the instance described in Interrogatory

29a(6) above are cited on page 40 of Intervenors' May 24, 1985,

',

Motion To Admit Amended Quality Assurance Contention and relevant

?

portions are included in the exhibits attached thereto (Exh. 18).

,

Documents reflecting the instance described in Interrogatory

f, [' 29a(7) above are cited on page 42 of Intervenors' May 24, 1985,

\, Motion To Admit Amended Qusitty Assurance Contentio.1 nnd relevant

I' 21

6

. .

  • __

-

, .

f

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

29a(8) above are cited on 'pages 42 43 of Intervenors' May 24,

1985, Motion To Admit Amended Quality Assurance Contention and

, relevant portions are included in the exhibits attached thereto

s

(Exh. 5).

Documents reflecting the instance described in Interrogatory

1

29a(9) 'above are cited on page 43 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 10). j

Documents reflecting the instance described in Interrogatory

29a(10) above are cited on page 44 of Intervenors' May 24, 1985,

,

/ .\

' Motion To Admit Amended Quality Assurance Contention and relevant

portions 4 'are included in the exhibits attached thereto (Exh. 25).

,

'Q- 3 0. Are you aware of any corrective actions taken by

Applicant to improve control of special processes and to ensure

compliance with applicable codes and standards? l

A-30. Yes.

Q-31. If your answer-to Interrogatory 30 above is yes:

a. Describe such corrective ac,tions with

particularity.

b. State your position as' to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 9.' State with' particularity.four basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 30, 4

A-31,. _ a. Please refer to the answer given to Interrogatory

)

4a above( ,g' -

b. Please refer to the answer given in Interrogatory

'

, 1

L 1

22

.9

L

b q.

___ - ____________________-_____ _ _____ _ _ _

?

4b above.

c. Please refer to the answer given in Interrogatory

4c above.

Q-32. Are the instances set forth in subparts A.-F. of

paragraph 10 of your contention the sole basis for your

contention that Applicant's inspection program is inadequate?

A-32. No.

l

Q-33 If your answer to Interrogatory 32 above is no:

a. Describe in detail each other instance of an

inadequate inspection on which you rely for your contention.

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-33, a. While the instances cited in that part of amended  !

, Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended ~ contention provide further support for our claim that

Applicant's Quality Assurance program violates this Appendix B

Criterion' X.

Other.such instances include:

(1) An NRC CAT inspection found examples of inadequate

hardware inspection and raised concerns as to

dependence on Final Walkdown inspections late in the

program. Paragraph 1, subpart C, pages 20-21.

hs

"- (2) An NRC CAT found that first level quality control

inspection activities need to be improved, especially

in pipe support / restraints and welding areas.

Paragraph 1, subpart D(1), page 21.

(3) ' Edison has failed to assure that activities affecting

,, quality are appropriately verified for quality by

inspection. Paragraph 3, page 24-25.

1/

.

23

e

__ _ - _ _ _ - _ _ _ _ _ - _ - _ _ _ _ _ _ _ - - - _ _ _ _ _ _ _ _ -

'

.

(4) Quality Control inspections during the welding process

were not of adequate scope and frequency to assure the

process of correct welding variables. Paragraph 3,

l subpart A(1), page 25.

!

(5) Quality control inspectors were given inappropriate

instructions as to Visual Weld Inspection Procedure.

Paragraph 3, subpart A, page 25.

(6) Quality control was not required to examine the base

metal prior to welding to assure that surfaces and

edges were free of discontinuities. Paragraph 3,

subpart A, page 26.

(7) Phillips, Getschow small bore pipe routing procedures

lacked inspection criteria. Paragraph 3, subpart

A(4)(b), page 26.

(8) Applicant had not established an inspection program for

structural beams that were modified during piping

installations. Paragraph 3, subpart B, page 27

,

!

(9) Applicant's electrical contractor utilized Level I

Quality Control inspectors for inspection and

acceptance of electrical welds. Paragraph 3, subpart

l C, page 27.

(10) Approved procedures for installation inspection of

mechanical safety-related equipment did not exist until

July 16, 1980, although numerous pieces of this

equipment were finally or partially installed prior to

this date. Paragraph 6, subpart A, page 30.

f

(11) There was no documented record or log specifying that a

I calibrated instrument was used to measure numerous pipe

bends for ovality requiring inspection measurements to

, the thousands of an inch. Paragraph 6, subpart B(3),

page 31.

(12) Required random visual checks of interface dimensions

7

of piping components were not being done. Paragraph 6,

subpart B(2), page 31.

(13) The piping contractor did not have a procedure for

producing an accurate In-Service Inspection drawing.

Paragraph 6, subpart C, page 31.

(14) Cables 2AF307 and 2AF154 were not routed by Comstock

per pull cards, and the QC inspector accepted the cable

pulls documenting that the cables were pulled in

accordance with the pull cards. Paragraph 6, subpart

E, page 32.

(15) Visual weld inspections were not performed on safety-

24

,

4

.

I

related full penetration welds completed under the

jurisdiction of Structural Specifications F/L-2735 and

F/L-2722. Paragraph 9, subpart A, page 35.

(16) Napolean Steel Contractors, Inc. QA program did not

require fit-up inspections for safety-related

structural steel members joined by welds and therefore,

QC personnel did not inspect and insure acceptable gaps

for weld joints. Paragraph 9, subpart E, page 36.

(17) Nonconforming welds completed by unknown welders were

" accepted-as-is" af ter only a visual examination.

Paragraph 12, subpart B(3), page 42.

(18) Phillips, Getschow identified numerous pieces of

equipment that had been installed without QC

verification of internal cleanliness. Paragraph 12,

subpart G, page 44.

(19) BCAP inspection effort needs to be improved in areas of

supports / restraints and piping runs. Paragraph 12,

subpart J, page 44.

b. Documents reflecting the instance described in

Interrogatory 33a(1) above are cited on page 21 of Intervenors'

May 24, 1985, Motion To Admit Amended Quality Assurance Conten-

tion and relevant portions are included in the exhibits attached

thereto (Exh.10).

Documents reflecting the instance described in Interrogatory

33a(2) above are cited on page 21 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 10).

Documents reflecting the instance described in Interrogatory

33a(3) above are cited on page 27 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(4) above are cited on page 27 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

25

. _ _ _ -. _ _ m.

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . . _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _

-

.

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(5) above are cited on page 27 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(6) above are cited on page 27 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(7) above are cited on page 27 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(8) above are cited on page 27 of Intervenors' May 24, 1985,

1

'

Motion To Admit Amended Quality Assurance Contention and relevant

'

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(9) above are cited on page 28 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 11).

L Documents reflectin6 the instance described in Interrogatory

33a(10) above are cited on page 30 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 3).

Documents reflecting the instance described in Interrogatory

33a(11) above are cited on page 31 of Intervenors' May 24, 1985,

26

t

e *

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(12) above are cited on page 31 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(13) above are cited on pages 31-32 of Intervenors' May 24,

1985, Motion To Admit Amended Quality Assurance Contention and

relevant portions are included in the exhibits attached thereto

(Exh. 14).

Documents reflecting the instance described in Interrogatory

33a(14) above are cited on page 32 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 13).

Documents reflecting the instance described in Interrogatory

33a(15) above are cited on page 35 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 20).

Documents reflecting the instance described in Interrogatory

33a(16) above are cited on page 36 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 25).

Documents reflecting the instance described in Interrogatory

33a(17) above are cited on pages 42 43 of Intervenors' May 24,

1985, Motion To Admit Amended Quality Assurance Contention and

relevant portions are included in the exhibits attached thereto

27

C

. .

,

(Exh. 5).

Documents reflecting the instance described in Interrogatory

33a(18) above are cited on page 44 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 20).

Documents reflecting the instance described in Interrogatory

33a(19) above are cited on page 44 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 10).

Q-34. Are you aware of any corrective actions proposed by

Applicant to improve its inspection program?

A-34. Yes.

Q-35. If the answer to Interrogatory 34 above is yes:

a. Describe such corrective actions with

particularity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 10. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 34.

A-35. a. Please refer to the answer given to Interrogatory

4a above. In addition, by letter of July 3, 1985, Applicant

circulated its June 21, 1985, response to the noncompliances in

inspection reports 85-15/16. They stated that this was an

isolated case and assert that no further corrective action is

required.

b. Please refer to the answer given in Interrogatory

4b above.

28

u

-t

-

.

.

c. Please refer to the answer given in Interrogatory

4c above.

Q-36. Are the instances set forth in subparts A.-D. of

paragraph 11 of your contention the sole basis for your

contention that the Applicant's program for the maintenance of

records is adequate?

A-36. No.

Q-37. If your answer to Interrogatory 36 above is no:

a. Describe in detail the other instances of

inadequate maintenance of records which form the basis for

paragraph 11 of your contention.

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, i f

other than NRC documents, provide a summary of their contents.

A-37 a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that

Applicant's Quality Assurance program violates this Appendix B

Criterion XV.

Other such instances include:

(1) Some General Electric "VULKENE" wire has been installed

without appropriate qualification to IEEE 383-1974.

Paragraph 8, subpart B, page 34.

(2) Piping material has been installed that did not meet

design requirements. Paragraph 10, subpart B, page 37

(3) Pipe installations were discoverd in Section III

installations without material test reports or records

of test reports or records of receiving and receipt

inspections. Paragraph 12, subpart B, page 42.

(4) Supports were found that were not procured and examined

in accordance with ASME Section III, section NF.

29

m

O

Paragraph 12, subpart C, page 43

b. Documents reflecting the instance described in

Interrogatory 37a(1) above are cited on page 34 of Intervenors'

May 24, 1985, Motion To Admit Amended Quality Assurance Conten-

tion and relevant portions are included in the exhibits attached

thereto (Exh.10).

Documents reflecting the instance described in Interrogatory

37a(2) above are cited on page 38 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 6).

Documents reflecting the instance described in Interrogatory

37a(3) above are cited on page 43 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

37a(4) above are cited on page 43 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 17).

Q-38. Are you aware of any corrective actions taken by

Applicant to improve the maintenance of QA records?

A-38. Yes.

Q-39 If the answer to Interrogatory 38 above is yes:

a. Describe such corrective actions with

particularity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 11. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

30

k

._

-

.

Interrogatory 38.

A-39 a. Please refer to the answer given to Interrogatory

4a above.

b. Please refer to the answer given in Interrogatory

4b above.

c. Please refer to the answer given in Interrogatory

4c above.

Q-40. Are the instances set forth in subparts A.-J. of

paragraph 12 of your contention the sole basis for your conten-

tion that Applicant has provided an inadequate program for the

identification and correction of conditions adverse to quality.

A-40. No.

Q-41. If the answer to Interrogatory 40 above is yes:

a. Describe in detail such other instances the date of

occurrence of each such instance.

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-41. a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that

Applicant's Quality Assurance program violates this Appendix B

Criterion XVI.

Other such instances include:

(1) Edison failed to take timely and effective corrective

action after identifying related significant problems

that occurred at its Byron station. Paragraph 1,

subpart A, page 19

(2) NRC CAT expressed concern over ability to manage the

31

L

.

large number of ongoing major corrective action

programs. Paragraph 1, subpart C, page 21.

(3) NRC CAT inspection concluded that additional management

attention is required to improve contractor performance

in the ares of contractor deficiency trending, and

craft and quality control inspector training.

Paragraph 1, subpart F, page 22.

(4) No corrective action documents were written to identify

and track nonconforming conditions (loose crimps at the 1

determination blocks). Paragraph 11, subpart B, page 40.

b. Documents reflecting the instance described in

Interrogatory 41a(1) above are cited on page 19 of Intervenors'

May 24, 1985, Motion To Admit Amended Quality Assurance Conten-

tion and relevant portions are included in the exhibits attached

thereto (Exh. 3).

Documents reflecting the instance described in Interrogatory

41a(2) above are cited on page 21 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 10).

Documents reflecting the instance described in Interrogatory

41a(3) above are cited on page 22 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 10).

Documents reflecting the instance described in Interrogatory

41a(4) above are cited on page 40 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 26).

Q-42. Are you aware of any corrective actions which have

been taken by Applicant to improve the identification and correc-

tion of conditions adverse to quality?

A-42. Yes.

32

't

F

.

.

Q-43 If the answer to Interrogatory 42 above is yes:

a. Describe such corrective actions with

particularity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 12. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 42.

A-43 a. Please refer to the answer given to Interrogatory

4a above. In addition, by letter of July 3, 1985, Applicant

circulated its June 21, 1985, response to the noncompliances in

inspection report 85-15/16. They stated that they believe this

was an isolated case and that to avoid further noncompliance they

will hold a training sesson for QA site personnel.

Q 44. Are there any instances other than those set forth in

subparts A. and B of paragraph 13 of your contention which form

the basis for your contention that maintenance of sufficient

records concerning activities affecting quality is inadequate?

A 44. -Yes.

Q 45. If the answer to Interrogatory 44 above is yes:

a. Describe in detail each such instance and the

date of occurrence of each incident.

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-45. a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that l

l

i

I

33 i

b

a

Applicant's Quality Assurance program violates this Appendix B

Criterion XVII.

Other such instances include:

(1) There was a lack of records documenting conformance

with the requirements of AWS D1.1-1977, Section 3, and

'

the Edison QA Manual. Paragraph 3, subpart A(3), page

26.

(2) A newly designed reactor coolant pump lateral support

anchorage was installed in Units 1 and 2 without

records to establish the material heat number, charpy

impact tests, lamination tests, welder identification,

weld procedure, weld filler material, in-process.

Inspections and other quality related records.

Paragraph 9, subpart B, page 36.

(3) 1/2" S/80, SA-312, Type 304, ASME Boiler and Pressure

Vessel Code, Section III, Class 1, NB pipe heat number

745107 were discovered in Section III installations

without material tests reports or records. Paragraph

12, subpart B, page 42.

(4) Audit did not verify that proper quality records were

being generated and maintained. Paragraph 14, subpart

A, page 46.

b. Documents reflecting the instance described in

Interrogatory 45a(1) above are cited on page 27 of Intervenors'

May 24, 1985, Motion To Admit Amended Quality Assurance Conten-

tion and relevant portions are included in the exhibits attached

thereto (Exh. 5).

Documents reflecting the instance described in Interrogatory

45a(2) above are cited on page 36 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 20).

Documents reflecting the instance described in Interrogatory

45a(3) above are cited on page 42 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached- thereto (Exh. 5).

34

L

-

.

Documents reflecting the instance described in Interrogatory

45a(4) above are cited on page 46 of Intervenors' May 24, 1985,

Motion To Admit Amended Quality Assurance Contention and relevant

portions are included in the exhibits attached thereto (Exh. 3).

Q-46. Are you aware of any corrective actions taken by

Applicant to improve the maintenance of records relating to

activities affecting quality?

A 46. Yes.

Q 47. If the answer to Interrogatory 46 above is yes:

a. Describe such corrective actions with

particularity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 13 State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 46.

A 47. a. Please refer to the answer given to Interrogatory

4a above.

b. Please refer to the answer given in Interrogatory

4b above.

c. Please refer to the answer given in Interrogatory

4c above.

Q-48. Are the instances set forth in subparts A. and B. of

paragraph 14 the sole basis for your contention that Applicant

failed to institute a systematic program of audits of quality

related activities?

A-48. No.

Q 49 If your answer to Interrogatory 48 above is yes:

!

a. Please describe in detail each instance.

35

f

s -

.- .

b. Identify all documents which relate to such

instances by title, author, if any, date of issuance and, if

other than NRC documents, provide a summary of their contents.

A-49 a. While the instances cited in that part of amended

Quality Assurance Contention, identified in this interrogatory,

serve as'the basis for that contention, other instances of

Quality Assurance deficiencies identified elsewhere in our

amended contention provide further support for our claim that

Applicant's Quality Assurance program violates this Appendix B

Criterion XVIII.

Other such instances include:

(1) Edison did not take appropriate corrective action with

regard to Audit QA-20-80-22. Paragraph 13, subpart A,

page 44.

b. Documents reflecting the instance described in

Interrogatory 49a(1) above are cited on page 44 of Intervenors'

May 24, 1985, Motion To Admit Amended Quality Assurance Conten-

tion and relevant portions are included in the exhibits attached

thereto (Exh.18). <

Q-50. Are you aware of any corrective actions taken by

Applicant to improve its program of audits of quality related

activities?

A-50. Yes.

Q-51. If your answer to Interrogatory 50 above is yes:

a. Describe such corrective actions with

particularity.

b. State your position as to whether such corrective

actions would or would not be adequate to remedy the situation

described in paragraph 14. State with particularity your basis

for your position.

c. Identify all documents relied upon in answering

Interrogatory 50.

36

i C

, ..

A-51. a. Please refer to the answer given to Interrogatory

4a above.

. b. Please refer to the answer given in Interrogatory

4b above.

c. Please refer to the answer given in Interrogatory

4c above.

DATbD: August 1, 1985

i

Robert GOild / \

One of the Attorneys for Intervenors

Bridget Little Rorem, et al.

Douglass W. Cassel, Jr.

Robert Guild

Timothy W. Wright, III

109 North Dearborn

Suite 1300

Chicago, Illinois 60602

(312) 641-5570

37

l

-. -.

._- - - . _ - - - . _

Y

.

. < -

!

!

CERTIFICATE OF SERVICE

D $h[

I hereby certify that I have served copies of '65

Agg _5 g;I 38

[Intervenors '] Response to NRC Staff Interrogatories To, .,.. _

'L'

Intervenor Bridget Little Rorem, Et Al. Concerning Its GO${Gy[I(gj-ki;.:

ea fP V!D

Quality Assurance Contention and Motion For Protective

Order on each party listed on the attached service list

by having said copies placed in envelopes, properly addressed

. and postaged (first class), and deposited in the U.S. mail

afterLclose of business on August 1,1985; except that

the NRC Staff counsel was served via Federal Express, also

on this 1st day of August, 1985.

'

\ '

L/

l

l

l

w _

<w

_

BRAIDWOOD SERVICE LIST

50-456/50-457 OL

Lawrence Brenner, Esq. Elaine Chan, Esq.

Chairman and Administrative Judge NRC Staff Counsel

Atomic Safety and Licensing Board U.S. Nuclear Regulatory

U.S. Nuclear Regulatory Commission Commission

Washington D.C. 20555 7335 Old Georgetown Road

Bethesda, MD 20014

Dr. A. Dixon Callihan

Administrative Judge Joseph Gallo, Esq.

102 Oak Lane Isham, Lincoln & Beale

Oak Ridge, TN 37830 Suite 840

1120 Connecticut Avenue N.W.

Dr. Richard F. Cole Washington D.C. 20036

Administrative Judge

Atomic Safety and Licensing Board Docketing & Service Section

U.S. Nuclear Regulatory Commission Office of the Secretary

Washington D.C. 20555 U.S. Nuclear Regulatory

Commission

Rebecca J. Lauer, Esq. Washington D.C. 20555

Isham, Lincoln & Beale

Three First National Plaza Atomic Safety and Licensing

Chicago , IL 60602 Board Panel

U.S. Nuclear Regulatory

Ms. Bridget Little Rorem Commission

117 North Linden Street Washington D.C. 20555

Essex, IL 60935

Atomic Safety and Licensing

C. Allen Bock, Esq. Appeal Board Panel

P.O. Box 342 U.S. Nuclear Regulatory

Urbana, IL 61801 Commission

Washington D.C. 20555

Thomas J. Gordon, Esq.

Waller, Evans & Gordon Michael I. Miller, Esq.

2503 South Neil Isham, Lincoln & Beale

Champaign, IL 61820 Three First National Plaza

Chicago, IL 60602

Lorraine Creek

Route 1, Box 182

Manteno, IL 60950

Region III

U.S. Nuclear Regulatory Commission

Office of Inspection & Enforcement

799 Roosevelt Road

Glen Ellyn, IL 60137

m