|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000293/19990051999-10-0808 October 1999 Insp Rept 50-293/99-05 on 990726-0905.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19990041999-08-27027 August 1999 Insp Rept 50-293/99-04 on 990610-0725.Non-cited Violations Noted.Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support ML20209G2331999-07-0909 July 1999 Insp Rept 50-293/99-03 on 990419-0609.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Operations,Maint,Engineering & Plant Support.Response to Main Transformer Fire by Fire Brigade Members Was Good IR 05000293/19990021999-05-17017 May 1999 Insp Rept 50-293/99-02 on 990308-0418.Two Level 4 Violations Occurred & Being Treated as Ncv.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000293/19990011999-04-20020 April 1999 Insp Rept 50-293/99-01 on 990125-0307.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Also Included Routine Core Insp of Security Program During Period of 990301-05 IR 05000293/19980101998-12-22022 December 1998 Insp Rept 50-293/98-10 on 981020-1208.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support,Including Implementation of Fire Protection Program IR 05000293/19980081998-12-0101 December 1998 Insp Rept 50-293/98-08 on 980907-1019.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19982031998-11-24024 November 1998 Insp Rept 50-293/98-203 on 980928-1023.No Violations Noted. Major Areas Inspected:Capability of Selected Sys to Perform Safety Functions Required by Design Bases,Adherence of Sys to Design & Licensing Bases & Consistency of Configuration IR 05000293/19980071998-10-0707 October 1998 Insp Rept 50-293/98-07 on 980726-0906.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19980061998-08-28028 August 1998 Insp Rept 50-293/98-06 on 980609-0725.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19980091998-08-20020 August 1998 Insp Rept 50-293/98-09 on 980713-24.No Violations Noted. Major Areas Inspected:Engineering Activities in Areas Including Evaluations to Address Operability Concerns,C/A Process & Actions Associated W/Findings from Previous Insps IR 05000293/19980051998-07-0909 July 1998 Insp Rept 50-293/98-05 on 980421-0608.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support.Concerns W/Fire Proctection Area Were Identified ML20217P7801998-04-0303 April 1998 Insp Rept 50-293/98-03 on 980302-05 & 11-12.Apparent Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Licensee Security Force Capability IR 05000293/19980011998-03-24024 March 1998 Insp Rept 50-293/98-01 on 980107-0224.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19970131998-02-0606 February 1998 Insp Rept 50-293/97-13 on 971111-980106.Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19970121997-12-17017 December 1997 Insp Rept 50-293/97-12 on 971006-10 & 1119.Violations Noted. Major Areas Inspected:Eq Documents for EQ Equipment That Required Requalification Due to Containment Environ Changes Resulting from CS Flow Rate Reduction in 1988 IR 05000293/19970111997-12-11011 December 1997 Insp Rept 50-293/97-11 on 970914-1110.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970101997-11-26026 November 1997 Insp Rept 50-293/97-10 on 971104-07.No Violations Noted. Major Areas Inspected:Emergency Response Organization, Simulated Events,Mitigation Actions Emergency Declarations & off-site Agencies IR 05000293/19970081997-10-24024 October 1997 Insp Rept 50-293/97-08 on 970805-0913.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20198L9231997-10-21021 October 1997 Insp Rept 50-293/97-05 on 970514-0828.Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Engineering IR 05000293/19970071997-09-15015 September 1997 Insp Rept 50-293/97-07 on 970625-0816.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970801997-09-12012 September 1997 Insp Rept 50-293/97-80 on 970721-0801.Violations Noted.Major Areas Inspected:Effectiveness of Processes for Identifying Resolving & Preventing Issues That Degrade Quality of Plant Operations & Safety ML20216G8181997-09-0404 September 1997 Insp Rept 50-293/97-09 on 970827-28.No Violations Noted. Major Areas Inspected:Licensee Access Authorization Program IR 05000293/19970041997-08-0707 August 1997 Insp Rept 50-293/97-04 on 970505-23.No Violations Noted. Major Areas Inspected:Effectiveness of Licensees Efforts in Maintaining Design Basis of safety-related Sys ML20149K0431997-07-22022 July 1997 Insp Rept 50-293/97-03 on 970429-0624.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20141K7861997-05-22022 May 1997 Insp Rept 50-293/97-02 on 970303-0428.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20137E5671997-03-18018 March 1997 Insp Rept 50-293/97-01 on 970112-0302.Violations Noted.Major Areas Inspected:Operations,Engineering & Plant Support ML20134K5951997-02-0707 February 1997 Insp Rept 50-293/96-10 on 961123-970111.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19960081996-12-18018 December 1996 Insp Rept 50-293/96-08 on 960924-1122.Violation Noted.Major Areas Inspected:Engineering,Maint,Plant Support,Radioactive Effluent Controls Program,Radiological Environmental Monitoring & Meteorological Monitoring.Meeting Slides Encl IR 05000293/19960061996-10-30030 October 1996 Insp Rept 50-293/96-06 on 960729-0923.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20129A0441996-10-11011 October 1996 Insp Rept 50-293/96-09 on 960916-20.Violations Noted. Major Areas Inspected:Miscellaneous Security & Safeguard Issues,Access Authorization Program & Administration Organization & Background Investigation Elements ML20129D8361996-09-20020 September 1996 Insp Rept 50-293/96-07 on 960708-12,0722-26 & 0828-0903. Non Cited Violation Noted.Major Areas Inspected:C/As After Licensee Had Identified Potentially Inoperable Primary Containment as Documented in LER 96-04 IR 05000293/19930201994-01-10010 January 1994 Insp Rept 50-293/93-20 on Stated Date.No Violations Noted. Major Areas Inspected:Operations,Maintenance & Surveillance, Engineering & Plant Support IR 05000293/19930801993-12-21021 December 1993 Insp Rept 50-293/93-80 on 931018-23.No Violations Noted. Major Areas Inspected:Station Blackout Coping Sys,Onsite Ac Supplies & Reliability Program,Plant Mods & QA & Maint Practices for Station Blackout Equipment IR 05000293/19930191993-11-23023 November 1993 Insp Rept 50-293/93-19 on 930928-1101.No Violations Noted. Major Areas Inspected:Plant Operations,Maint & Surveillance, Engineering,Plant Support,W/Regard to Security & NRC Info Notice 93-079 ML20058D4771993-11-19019 November 1993 Insp Rept 50-293/93-16 on 930830-1015.Violations Noted.Major Areas Inspected:Audits & Surveillances,Training & Qualifications,Radiological Problem Repts & Associated C/A IR 05000293/19930151993-10-15015 October 1993 Insp Rept 50-293/93-15 on 930817-0927.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls Maint & Surveillance,Emergency Preparedness,Security,Safety Assessment & Quality Verification IR 05000293/19930171993-09-24024 September 1993 Insp Rept 50-293/93-17 on 930830-0903.No Violations Noted. Major Areas Inspected:Mgt Controls,Qa Audits & ODCM IR 05000293/19930141993-09-0808 September 1993 Insp Rept 50-293/93-14 on 930713-0816.No Violations Noted. Major Areas Inspected:Plant Operations,Maintenance & Surveillance,Engineering & Plant Support IR 05000293/19930111993-08-0404 August 1993 Insp Rept 50-293/93-11 on 930606-11.No Violations Noted. Major Areas Inspected:Licensee Corrective Actions of Previously Identified Electrical Distribution Sys Functional Insp Findings & Observations IR 05000293/19930011993-02-0303 February 1993 Insp Rept 50-293/93-01 on 930111-14.Weaknesses Noted.Major Areas Inspected:Eop Review,Rev,Approval Process,Qa Involvement in EOP Program & Operator Training in EOPs IR 05000293/19920811993-02-0202 February 1993 Probabilistic Risk Assessment Based Insp Rept 50-293/92-81 on 921130-1218.Violation Noted.Major Areas Inspected:Review of Emergency Diesel Generators & Hpcis.App a Encl IR 05000293/19920281993-01-28028 January 1993 Insp Rept 50-293/92-28 on 921124-1231.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security,Safety Assessment & Quality Verification IR 05000293/19920261993-01-21021 January 1993 Insp Rept 50-293/92-26 on 921207-11.No Violations or Deviations Noted.Major Areas Inspected:Ep Program Changes, Emergency Response Facilities,Equipment,Instrumentation, Supplies & Organization & Mgt Control IR 05000293/19920231992-12-29029 December 1992 Safety Insp Rept 50-293/92-23 on 921020-1123.No Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security & Safety Assessment & Quality Verification IR 05000293/19920241992-11-23023 November 1992 Insp Rept 50-293/92-24 on Stated Date.No Safety Concerns or Violations Noted.Major Areas Inspected:Audits & Surveillances,Collective Personnel Exposure Status,Outage Radiological Controls & Implementation of Exposure Programs IR 05000293/19900201990-11-0707 November 1990 Safety Insp Rept 50-293/90-20 on 900816-1008.Violation Noted.Major Areas Inspected:Plant Operations,Security, Maint & Surveillance,Engineering & Technical Support, Radiological Controls,Emergency Preparedness & Safety IR 05000293/19900211990-10-11011 October 1990 Insp Rept 50-293/90-21 on 900905-07.Major Areas Inspected: 900902-03 Event Involving Number of Component Malfunctions & Operational Complications Following Shutdown.Operating Procedures Lacked Adequate Guidance for Operators IR 05000293/19900091990-08-20020 August 1990 Insp Rept 50-293/90-09 on 900806-10.No Violations or Deviations Noted.Major Areas Inspected:Control of Design, Design Changes,Mods,Engineering & Technical Support Organization,Staffing,Communications,Qa & Training IR 05000293/19900161990-07-30030 July 1990 Partially Withheld Physical Security Insp Rept 50-293/90-16 on 900625-29 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Mgt Support & Program Plans,Protected & Vital Area Physical Barriers & Detection & Assessment Aids 1999-08-27
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000293/19990051999-10-0808 October 1999 Insp Rept 50-293/99-05 on 990726-0905.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19990041999-08-27027 August 1999 Insp Rept 50-293/99-04 on 990610-0725.Non-cited Violations Noted.Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support ML20209G2331999-07-0909 July 1999 Insp Rept 50-293/99-03 on 990419-0609.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Operations,Maint,Engineering & Plant Support.Response to Main Transformer Fire by Fire Brigade Members Was Good IR 05000293/19990021999-05-17017 May 1999 Insp Rept 50-293/99-02 on 990308-0418.Two Level 4 Violations Occurred & Being Treated as Ncv.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000293/19990011999-04-20020 April 1999 Insp Rept 50-293/99-01 on 990125-0307.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Also Included Routine Core Insp of Security Program During Period of 990301-05 IR 05000293/19980101998-12-22022 December 1998 Insp Rept 50-293/98-10 on 981020-1208.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support,Including Implementation of Fire Protection Program IR 05000293/19980081998-12-0101 December 1998 Insp Rept 50-293/98-08 on 980907-1019.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19982031998-11-24024 November 1998 Insp Rept 50-293/98-203 on 980928-1023.No Violations Noted. Major Areas Inspected:Capability of Selected Sys to Perform Safety Functions Required by Design Bases,Adherence of Sys to Design & Licensing Bases & Consistency of Configuration IR 05000293/19980071998-10-0707 October 1998 Insp Rept 50-293/98-07 on 980726-0906.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19980061998-08-28028 August 1998 Insp Rept 50-293/98-06 on 980609-0725.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19980091998-08-20020 August 1998 Insp Rept 50-293/98-09 on 980713-24.No Violations Noted. Major Areas Inspected:Engineering Activities in Areas Including Evaluations to Address Operability Concerns,C/A Process & Actions Associated W/Findings from Previous Insps IR 05000293/19980051998-07-0909 July 1998 Insp Rept 50-293/98-05 on 980421-0608.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support.Concerns W/Fire Proctection Area Were Identified ML20217P7801998-04-0303 April 1998 Insp Rept 50-293/98-03 on 980302-05 & 11-12.Apparent Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Licensee Security Force Capability IR 05000293/19980011998-03-24024 March 1998 Insp Rept 50-293/98-01 on 980107-0224.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19970131998-02-0606 February 1998 Insp Rept 50-293/97-13 on 971111-980106.Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19970121997-12-17017 December 1997 Insp Rept 50-293/97-12 on 971006-10 & 1119.Violations Noted. Major Areas Inspected:Eq Documents for EQ Equipment That Required Requalification Due to Containment Environ Changes Resulting from CS Flow Rate Reduction in 1988 IR 05000293/19970111997-12-11011 December 1997 Insp Rept 50-293/97-11 on 970914-1110.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970101997-11-26026 November 1997 Insp Rept 50-293/97-10 on 971104-07.No Violations Noted. Major Areas Inspected:Emergency Response Organization, Simulated Events,Mitigation Actions Emergency Declarations & off-site Agencies IR 05000293/19970081997-10-24024 October 1997 Insp Rept 50-293/97-08 on 970805-0913.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20198L9231997-10-21021 October 1997 Insp Rept 50-293/97-05 on 970514-0828.Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Engineering IR 05000293/19970071997-09-15015 September 1997 Insp Rept 50-293/97-07 on 970625-0816.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970801997-09-12012 September 1997 Insp Rept 50-293/97-80 on 970721-0801.Violations Noted.Major Areas Inspected:Effectiveness of Processes for Identifying Resolving & Preventing Issues That Degrade Quality of Plant Operations & Safety ML20216G8181997-09-0404 September 1997 Insp Rept 50-293/97-09 on 970827-28.No Violations Noted. Major Areas Inspected:Licensee Access Authorization Program IR 05000293/19970041997-08-0707 August 1997 Insp Rept 50-293/97-04 on 970505-23.No Violations Noted. Major Areas Inspected:Effectiveness of Licensees Efforts in Maintaining Design Basis of safety-related Sys ML20149K0431997-07-22022 July 1997 Insp Rept 50-293/97-03 on 970429-0624.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20141K7861997-05-22022 May 1997 Insp Rept 50-293/97-02 on 970303-0428.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20137E5671997-03-18018 March 1997 Insp Rept 50-293/97-01 on 970112-0302.Violations Noted.Major Areas Inspected:Operations,Engineering & Plant Support ML20134K5951997-02-0707 February 1997 Insp Rept 50-293/96-10 on 961123-970111.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19960081996-12-18018 December 1996 Insp Rept 50-293/96-08 on 960924-1122.Violation Noted.Major Areas Inspected:Engineering,Maint,Plant Support,Radioactive Effluent Controls Program,Radiological Environmental Monitoring & Meteorological Monitoring.Meeting Slides Encl IR 05000293/19960061996-10-30030 October 1996 Insp Rept 50-293/96-06 on 960729-0923.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20129A0441996-10-11011 October 1996 Insp Rept 50-293/96-09 on 960916-20.Violations Noted. Major Areas Inspected:Miscellaneous Security & Safeguard Issues,Access Authorization Program & Administration Organization & Background Investigation Elements ML20129D8361996-09-20020 September 1996 Insp Rept 50-293/96-07 on 960708-12,0722-26 & 0828-0903. Non Cited Violation Noted.Major Areas Inspected:C/As After Licensee Had Identified Potentially Inoperable Primary Containment as Documented in LER 96-04 IR 05000293/19930201994-01-10010 January 1994 Insp Rept 50-293/93-20 on Stated Date.No Violations Noted. Major Areas Inspected:Operations,Maintenance & Surveillance, Engineering & Plant Support IR 05000293/19930801993-12-21021 December 1993 Insp Rept 50-293/93-80 on 931018-23.No Violations Noted. Major Areas Inspected:Station Blackout Coping Sys,Onsite Ac Supplies & Reliability Program,Plant Mods & QA & Maint Practices for Station Blackout Equipment IR 05000293/19930191993-11-23023 November 1993 Insp Rept 50-293/93-19 on 930928-1101.No Violations Noted. Major Areas Inspected:Plant Operations,Maint & Surveillance, Engineering,Plant Support,W/Regard to Security & NRC Info Notice 93-079 ML20058D4771993-11-19019 November 1993 Insp Rept 50-293/93-16 on 930830-1015.Violations Noted.Major Areas Inspected:Audits & Surveillances,Training & Qualifications,Radiological Problem Repts & Associated C/A IR 05000293/19930151993-10-15015 October 1993 Insp Rept 50-293/93-15 on 930817-0927.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls Maint & Surveillance,Emergency Preparedness,Security,Safety Assessment & Quality Verification IR 05000293/19930171993-09-24024 September 1993 Insp Rept 50-293/93-17 on 930830-0903.No Violations Noted. Major Areas Inspected:Mgt Controls,Qa Audits & ODCM IR 05000293/19930141993-09-0808 September 1993 Insp Rept 50-293/93-14 on 930713-0816.No Violations Noted. Major Areas Inspected:Plant Operations,Maintenance & Surveillance,Engineering & Plant Support IR 05000293/19930111993-08-0404 August 1993 Insp Rept 50-293/93-11 on 930606-11.No Violations Noted. Major Areas Inspected:Licensee Corrective Actions of Previously Identified Electrical Distribution Sys Functional Insp Findings & Observations IR 05000293/19930011993-02-0303 February 1993 Insp Rept 50-293/93-01 on 930111-14.Weaknesses Noted.Major Areas Inspected:Eop Review,Rev,Approval Process,Qa Involvement in EOP Program & Operator Training in EOPs IR 05000293/19920811993-02-0202 February 1993 Probabilistic Risk Assessment Based Insp Rept 50-293/92-81 on 921130-1218.Violation Noted.Major Areas Inspected:Review of Emergency Diesel Generators & Hpcis.App a Encl IR 05000293/19920281993-01-28028 January 1993 Insp Rept 50-293/92-28 on 921124-1231.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security,Safety Assessment & Quality Verification IR 05000293/19920261993-01-21021 January 1993 Insp Rept 50-293/92-26 on 921207-11.No Violations or Deviations Noted.Major Areas Inspected:Ep Program Changes, Emergency Response Facilities,Equipment,Instrumentation, Supplies & Organization & Mgt Control IR 05000293/19920231992-12-29029 December 1992 Safety Insp Rept 50-293/92-23 on 921020-1123.No Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security & Safety Assessment & Quality Verification IR 05000293/19920241992-11-23023 November 1992 Insp Rept 50-293/92-24 on Stated Date.No Safety Concerns or Violations Noted.Major Areas Inspected:Audits & Surveillances,Collective Personnel Exposure Status,Outage Radiological Controls & Implementation of Exposure Programs IR 05000293/19900201990-11-0707 November 1990 Safety Insp Rept 50-293/90-20 on 900816-1008.Violation Noted.Major Areas Inspected:Plant Operations,Security, Maint & Surveillance,Engineering & Technical Support, Radiological Controls,Emergency Preparedness & Safety IR 05000293/19900211990-10-11011 October 1990 Insp Rept 50-293/90-21 on 900905-07.Major Areas Inspected: 900902-03 Event Involving Number of Component Malfunctions & Operational Complications Following Shutdown.Operating Procedures Lacked Adequate Guidance for Operators IR 05000293/19900091990-08-20020 August 1990 Insp Rept 50-293/90-09 on 900806-10.No Violations or Deviations Noted.Major Areas Inspected:Control of Design, Design Changes,Mods,Engineering & Technical Support Organization,Staffing,Communications,Qa & Training IR 05000293/19900161990-07-30030 July 1990 Partially Withheld Physical Security Insp Rept 50-293/90-16 on 900625-29 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Mgt Support & Program Plans,Protected & Vital Area Physical Barriers & Detection & Assessment Aids 1999-08-27
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000293/19990051999-10-0808 October 1999 Insp Rept 50-293/99-05 on 990726-0905.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19990041999-08-27027 August 1999 Insp Rept 50-293/99-04 on 990610-0725.Non-cited Violations Noted.Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support ML20209G2331999-07-0909 July 1999 Insp Rept 50-293/99-03 on 990419-0609.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Operations,Maint,Engineering & Plant Support.Response to Main Transformer Fire by Fire Brigade Members Was Good IR 05000293/19990021999-05-17017 May 1999 Insp Rept 50-293/99-02 on 990308-0418.Two Level 4 Violations Occurred & Being Treated as Ncv.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000293/19990011999-04-20020 April 1999 Insp Rept 50-293/99-01 on 990125-0307.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Also Included Routine Core Insp of Security Program During Period of 990301-05 IR 05000293/19980101998-12-22022 December 1998 Insp Rept 50-293/98-10 on 981020-1208.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support,Including Implementation of Fire Protection Program IR 05000293/19980081998-12-0101 December 1998 Insp Rept 50-293/98-08 on 980907-1019.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19982031998-11-24024 November 1998 Insp Rept 50-293/98-203 on 980928-1023.No Violations Noted. Major Areas Inspected:Capability of Selected Sys to Perform Safety Functions Required by Design Bases,Adherence of Sys to Design & Licensing Bases & Consistency of Configuration IR 05000293/19980071998-10-0707 October 1998 Insp Rept 50-293/98-07 on 980726-0906.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19980061998-08-28028 August 1998 Insp Rept 50-293/98-06 on 980609-0725.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19980091998-08-20020 August 1998 Insp Rept 50-293/98-09 on 980713-24.No Violations Noted. Major Areas Inspected:Engineering Activities in Areas Including Evaluations to Address Operability Concerns,C/A Process & Actions Associated W/Findings from Previous Insps IR 05000293/19980051998-07-0909 July 1998 Insp Rept 50-293/98-05 on 980421-0608.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support.Concerns W/Fire Proctection Area Were Identified ML20217P7801998-04-0303 April 1998 Insp Rept 50-293/98-03 on 980302-05 & 11-12.Apparent Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Licensee Security Force Capability IR 05000293/19980011998-03-24024 March 1998 Insp Rept 50-293/98-01 on 980107-0224.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19970131998-02-0606 February 1998 Insp Rept 50-293/97-13 on 971111-980106.Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19970121997-12-17017 December 1997 Insp Rept 50-293/97-12 on 971006-10 & 1119.Violations Noted. Major Areas Inspected:Eq Documents for EQ Equipment That Required Requalification Due to Containment Environ Changes Resulting from CS Flow Rate Reduction in 1988 IR 05000293/19970111997-12-11011 December 1997 Insp Rept 50-293/97-11 on 970914-1110.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970101997-11-26026 November 1997 Insp Rept 50-293/97-10 on 971104-07.No Violations Noted. Major Areas Inspected:Emergency Response Organization, Simulated Events,Mitigation Actions Emergency Declarations & off-site Agencies IR 05000293/19970081997-10-24024 October 1997 Insp Rept 50-293/97-08 on 970805-0913.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20198L9231997-10-21021 October 1997 Insp Rept 50-293/97-05 on 970514-0828.Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Engineering IR 05000293/19970071997-09-15015 September 1997 Insp Rept 50-293/97-07 on 970625-0816.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970801997-09-12012 September 1997 Insp Rept 50-293/97-80 on 970721-0801.Violations Noted.Major Areas Inspected:Effectiveness of Processes for Identifying Resolving & Preventing Issues That Degrade Quality of Plant Operations & Safety ML20216G8181997-09-0404 September 1997 Insp Rept 50-293/97-09 on 970827-28.No Violations Noted. Major Areas Inspected:Licensee Access Authorization Program IR 05000293/19970041997-08-0707 August 1997 Insp Rept 50-293/97-04 on 970505-23.No Violations Noted. Major Areas Inspected:Effectiveness of Licensees Efforts in Maintaining Design Basis of safety-related Sys ML20149K0431997-07-22022 July 1997 Insp Rept 50-293/97-03 on 970429-0624.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20141K7861997-05-22022 May 1997 Insp Rept 50-293/97-02 on 970303-0428.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20137E5671997-03-18018 March 1997 Insp Rept 50-293/97-01 on 970112-0302.Violations Noted.Major Areas Inspected:Operations,Engineering & Plant Support ML20134K5951997-02-0707 February 1997 Insp Rept 50-293/96-10 on 961123-970111.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19960081996-12-18018 December 1996 Insp Rept 50-293/96-08 on 960924-1122.Violation Noted.Major Areas Inspected:Engineering,Maint,Plant Support,Radioactive Effluent Controls Program,Radiological Environmental Monitoring & Meteorological Monitoring.Meeting Slides Encl IR 05000293/19960061996-10-30030 October 1996 Insp Rept 50-293/96-06 on 960729-0923.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20129A0441996-10-11011 October 1996 Insp Rept 50-293/96-09 on 960916-20.Violations Noted. Major Areas Inspected:Miscellaneous Security & Safeguard Issues,Access Authorization Program & Administration Organization & Background Investigation Elements ML20129D8361996-09-20020 September 1996 Insp Rept 50-293/96-07 on 960708-12,0722-26 & 0828-0903. Non Cited Violation Noted.Major Areas Inspected:C/As After Licensee Had Identified Potentially Inoperable Primary Containment as Documented in LER 96-04 IR 05000293/19930201994-01-10010 January 1994 Insp Rept 50-293/93-20 on Stated Date.No Violations Noted. Major Areas Inspected:Operations,Maintenance & Surveillance, Engineering & Plant Support IR 05000293/19930801993-12-21021 December 1993 Insp Rept 50-293/93-80 on 931018-23.No Violations Noted. Major Areas Inspected:Station Blackout Coping Sys,Onsite Ac Supplies & Reliability Program,Plant Mods & QA & Maint Practices for Station Blackout Equipment IR 05000293/19930191993-11-23023 November 1993 Insp Rept 50-293/93-19 on 930928-1101.No Violations Noted. Major Areas Inspected:Plant Operations,Maint & Surveillance, Engineering,Plant Support,W/Regard to Security & NRC Info Notice 93-079 ML20058D4771993-11-19019 November 1993 Insp Rept 50-293/93-16 on 930830-1015.Violations Noted.Major Areas Inspected:Audits & Surveillances,Training & Qualifications,Radiological Problem Repts & Associated C/A IR 05000293/19930151993-10-15015 October 1993 Insp Rept 50-293/93-15 on 930817-0927.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls Maint & Surveillance,Emergency Preparedness,Security,Safety Assessment & Quality Verification IR 05000293/19930171993-09-24024 September 1993 Insp Rept 50-293/93-17 on 930830-0903.No Violations Noted. Major Areas Inspected:Mgt Controls,Qa Audits & ODCM IR 05000293/19930141993-09-0808 September 1993 Insp Rept 50-293/93-14 on 930713-0816.No Violations Noted. Major Areas Inspected:Plant Operations,Maintenance & Surveillance,Engineering & Plant Support IR 05000293/19930111993-08-0404 August 1993 Insp Rept 50-293/93-11 on 930606-11.No Violations Noted. Major Areas Inspected:Licensee Corrective Actions of Previously Identified Electrical Distribution Sys Functional Insp Findings & Observations IR 05000293/19930011993-02-0303 February 1993 Insp Rept 50-293/93-01 on 930111-14.Weaknesses Noted.Major Areas Inspected:Eop Review,Rev,Approval Process,Qa Involvement in EOP Program & Operator Training in EOPs IR 05000293/19920811993-02-0202 February 1993 Probabilistic Risk Assessment Based Insp Rept 50-293/92-81 on 921130-1218.Violation Noted.Major Areas Inspected:Review of Emergency Diesel Generators & Hpcis.App a Encl IR 05000293/19920281993-01-28028 January 1993 Insp Rept 50-293/92-28 on 921124-1231.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security,Safety Assessment & Quality Verification IR 05000293/19920261993-01-21021 January 1993 Insp Rept 50-293/92-26 on 921207-11.No Violations or Deviations Noted.Major Areas Inspected:Ep Program Changes, Emergency Response Facilities,Equipment,Instrumentation, Supplies & Organization & Mgt Control IR 05000293/19920231992-12-29029 December 1992 Safety Insp Rept 50-293/92-23 on 921020-1123.No Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security & Safety Assessment & Quality Verification IR 05000293/19920241992-11-23023 November 1992 Insp Rept 50-293/92-24 on Stated Date.No Safety Concerns or Violations Noted.Major Areas Inspected:Audits & Surveillances,Collective Personnel Exposure Status,Outage Radiological Controls & Implementation of Exposure Programs IR 05000293/19900201990-11-0707 November 1990 Safety Insp Rept 50-293/90-20 on 900816-1008.Violation Noted.Major Areas Inspected:Plant Operations,Security, Maint & Surveillance,Engineering & Technical Support, Radiological Controls,Emergency Preparedness & Safety IR 05000293/19900211990-10-11011 October 1990 Insp Rept 50-293/90-21 on 900905-07.Major Areas Inspected: 900902-03 Event Involving Number of Component Malfunctions & Operational Complications Following Shutdown.Operating Procedures Lacked Adequate Guidance for Operators IR 05000293/19900091990-08-20020 August 1990 Insp Rept 50-293/90-09 on 900806-10.No Violations or Deviations Noted.Major Areas Inspected:Control of Design, Design Changes,Mods,Engineering & Technical Support Organization,Staffing,Communications,Qa & Training IR 05000293/19900161990-07-30030 July 1990 Partially Withheld Physical Security Insp Rept 50-293/90-16 on 900625-29 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Mgt Support & Program Plans,Protected & Vital Area Physical Barriers & Detection & Assessment Aids 1999-08-27
[Table view] Category:UTILITY
MONTHYEARIR 05000293/19900201990-11-0707 November 1990 Safety Insp Rept 50-293/90-20 on 900816-1008.Violation Noted.Major Areas Inspected:Plant Operations,Security, Maint & Surveillance,Engineering & Technical Support, Radiological Controls,Emergency Preparedness & Safety IR 05000293/19900211990-10-11011 October 1990 Insp Rept 50-293/90-21 on 900905-07.Major Areas Inspected: 900902-03 Event Involving Number of Component Malfunctions & Operational Complications Following Shutdown.Operating Procedures Lacked Adequate Guidance for Operators IR 05000293/19900091990-08-20020 August 1990 Insp Rept 50-293/90-09 on 900806-10.No Violations or Deviations Noted.Major Areas Inspected:Control of Design, Design Changes,Mods,Engineering & Technical Support Organization,Staffing,Communications,Qa & Training IR 05000293/19900161990-07-30030 July 1990 Partially Withheld Physical Security Insp Rept 50-293/90-16 on 900625-29 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Mgt Support & Program Plans,Protected & Vital Area Physical Barriers & Detection & Assessment Aids IR 05000293/19900181990-07-26026 July 1990 Insp Rept 50-293/90-18 on 900709-13.No Violations Noted. Major Areas Inspected:Inservice Insp Activities to Ascertain Whether Licensee Activities Conducted in Compliance W/Asme Code & Regulatory Requirements IR 05000293/19900171990-07-25025 July 1990 Insp Rept 50-293/90-17 on 900624-29.No Violations Noted. Major Areas Inspected:Radiological & Nonradiological Chemistry Programs IR 05000293/19900131990-06-29029 June 1990 Safety Insp Rept 50-293/90-13 on 900501-0611.No Violations Noted.Major Areas Inspected:Actions on Previous Insp Findings,Plant Operations,Security,Maint & Surveillance, Engineering Support & Radiological Controls IR 05000293/19900141990-06-26026 June 1990 Insp Rept 50-293/90-14 on 900620-22.No Violations Noted. Major Areas Inspected:Observation of Licensee Partial Participation Annual Emergency Preparedness Exercise IR 05000293/19890061989-07-20020 July 1989 Insp Rept 50-293/89-06 on 890411-0524.No Violations Noted. Major Areas Inspected:Assessment of Licensee Mgt Controls, Conduct of Operation & Licensee Approach to Investigation & Resolution of Events During 5 - 25% Power Plateau IR 05000293/19890091989-07-0606 July 1989 Insp Rept 50-293/89-09 on 890619-22.No Violations Noted. Major Areas Inspected:Changes to Emergency Preparedness Program,Emergency Facilities,Equipment,Instrumentation & Supplies,Organization & Mgt Control IR 05000293/19890051989-06-0909 June 1989 Insp Rept 50-293/89-05 on 890311-0410.Unresolved Item Noted Re Util Method for Disabling Annunciators in Control Room. Major Areas Inspected:Assessment of Licensee Mgt Controls, Conduct of Operations & Startup Testing ML20247D5561989-05-0808 May 1989 Augmented Insp Team Rept 50-293/89-80 on 890413-15 & 17-26. No Violations Noted.Major Areas Inspected:Causes,Safety Implications & Util Response to 890412 RCIC Sys Suction Piping Overpressurization IR 05000293/19890041989-04-28028 April 1989 Mgt Meeting Rept 50-293/89-04 on 890328-30.Major Areas Discussed:Emergency Plan & Implementing Procedures, Emergency Operations Ctr Staffing & Equipment,Reception Ctrs & Public Info Brochure IR 05000293/19890011989-04-24024 April 1989 Insp Rept 50-293/89-01 on 890206-0310.Violations Noted.Major Areas Inspected:Licensee Mgt Controls,Conduct of Operations & Startup Testing Activities During Licensee Power Ascension Program IR 05000293/19890431989-04-0606 April 1989 Mgt Meeting Rept 50-293/89-43 on 890309 Re Licensee Followup to 890304 Reactor Scram & Util Overview of Turbine Control Sys IR 05000293/19880371989-03-30030 March 1989 Insp Rept 50-293/88-37 on 881227-890205.Violation Noted Re Failure to Control Locked High Radiation Area Access.Major Areas Inspected:Licensee Mgt Controls,Conduct of Operations & Startup Testing During Power Ascension Program IR 05000293/19890031989-02-21021 February 1989 Meeting Rept 50-293/89-03 on 890131-0202.Major Areas Discussed:Emergency Operating Conditions,Training,Staffing, Emergency Plan & Implementing Procedures & Equipment IR 05000293/19880341989-02-14014 February 1989 Safety Insp Rept 50-293/88-34 on 881114-1226.No Violations Noted.Major Areas Inspected:Plant Operations,Radiation Protection,Physical Security,Plant Events,Maint, Surveillance,Part 21 Repts & Outage Activities IR 05000293/19870991989-01-0606 January 1989 Mgt Meeting Rept on 881003 to Review Licensee Actions to Address Radiation Protection Program Weaknesses Described in SALP Rept 50-293/87-99 ML20206L4581988-11-21021 November 1988 Insp Rept 50-293/88-30 on 881027-1118.No Violations Noted. Major Areas Inspected:Licensee Followup Activities Re Loose Anchor Bolts in Pipe Support Base Plate,Safety Significance of Subj Discrepancy & Response to Bulletins 79-002 & 79-014 IR 05000293/19880311988-10-24024 October 1988 Insp Rept 50-293/88-31 on 880829-0926.Violations Noted.Major Areas Inspected:Radiation Protection,Physical Security, Plant Events,Maint,Surveillance & Outage Activities IR 05000293/19880321988-10-13013 October 1988 Insp Rept 50-293/88-32 on 880912-16.Violations Noted.Major Areas Inspected:Corrective Actions That Resulted from IE Bulletin 85-003 That Addressed Improper Limit Switch & Torque Switch Settings in motor-operated Valves IR 05000293/19880271988-09-20020 September 1988 Insp Rept 50-293/88-27 on 880718-0828.No Violations Noted. Major Areas Inspected:Licensee Actions on Previous Insp Findings,Plant Operations,Radiation Protection & Physical Security.One Unresolved Item Identified Re Valve Yoke Clamp ML20154C2791988-09-0707 September 1988 Integrated Assessment Team Insp Rept 50-293/88-21 on 880808- -24.No Violations Noted.Major Areas Inspected:Degree of Readiness of Licensee Mgt Controls,Programs & Personnel to Support Safe Restart & Plant Operation IR 05000283/19880291988-09-0707 September 1988 Insp Rept 50-283/88-29 on 880818-20.No Violations or Deviations Noted.Major Areas Inspected:Use of NRC Mobile Radioanalytical Lab to Perform Independent Measurements of Soil to Determine Existence & Level of Contamination ML20154L5851988-09-0606 September 1988 Meeting Rept 50-293/M88-312 on 880831.Discusses NRC Concerns Re Rosemount 1153 Transmitter Ringing Problem & Util Approach to Resolving Issue ML20153D3051988-08-23023 August 1988 Insp Rept 50-293/88-23 on 880620-30.No Violations Noted. Major Areas Inspected:Licensee Corrective Actions in Response to NRC Info Notices 86-003 & 053 Re Limitorque Valves & Raychem Heat Shrink Tubing,Respectively IR 05000293/19880251988-08-15015 August 1988 Insp Rept 50-293/88-25 on 880601-0717.No Violations Noted. Major Areas Inspected:Plant Operations,Radiation Protection, Physical Security,Plant Events,Maint,Surveillance,Outage Activities & Repts to NRC IR 05000293/19880281988-07-26026 July 1988 Insp Rept 50-293/88-28 on 880718-21.No Violations Noted. Major Areas Inspected:Changes to Emergency Preparedness Program,Shift Staffing & Augmentation,Knowledge & Performance of Duties & Emergency Detection IR 05000293/19880241988-07-22022 July 1988 Insp Rept 50-293/88-24 on 880531-0609.No Violations Noted. Major Areas Inspected:Licensee Followup & Corrective Actions Re Several Previously Identified Open Items IR 05000293/19880201988-07-18018 July 1988 Insp Rept 50-293/88-20 on 880502-0610.No Violations Noted. Major Areas Inspected:Qa Aspects of Mod Covering Matls, Welding & NDE IR 05000293/19880181988-07-11011 July 1988 Physical Security Insp Rept 50-293/88-18 on 880425-29 & 0503-04.No Violations Noted.Major Areas Inspected:Mgt Effectiveness of Licensee Proprietary Security Organization ML20150E8141988-06-30030 June 1988 Mgt Meeting Rept 50-293/88-26 on 880627.Major Issues Discussed:Licensee Response to NRC Maint Team Insp 50-293/88-17,status of Licensee Evaluation of RHR Valve Yoke Cracking & Followup of Assessment of Readiness for Restart IR 05000293/19880191988-06-28028 June 1988 Insp Rept 50-293/88-19 on 880418-0531.Concerns Noted.Major Areas Inspected:Plant Operations,Radiation Protection, Physical Security,Plant Events,Maint,Surveillance,Outage Activities & Repts to NRC IR 05000293/19880121988-05-31031 May 1988 Insp Rept 50-293/88-12 on 880306-0417.Violations Noted. Major Areas Inspected:Radiation Protection,Physical Security,Plant Events,Maint,Surveillance,Outage Activites & Repts to NRC IR 05000293/19880171988-05-25025 May 1988 Insp Rept 50-293/88-17 on 880425-0505.No Violations Noted. Major Areas Inspected:Exam of Identified Maint Problems, Correction of Problems & Maint Section Interfaces W/ Engineering,Operations,Qa & Health Physics Personnel ML20154F9341988-05-17017 May 1988 Insp Rept 50-293/88-11 on 880314-18.No Violations or Deviations Noted.Major Areas Inspected:Emergency Operating Procedures,Including Comparison of Plant Specific Guidelines & BWR Owners Group Guidelines with Emergency Procedures IR 05000293/19880141988-05-16016 May 1988 Insp Rept 50-293/88-14 on 880418-22.No Violations Noted. Major Areas Inspected:Previous Insp Findings & Power Ascension Test Program IR 05000293/19880161988-05-13013 May 1988 Partially Withheld Physical Security Insp Rept 50-293/88-16 on 880411-14 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Program Upgrades,Program Audits,Physical barriers-protected & Vital Areas & Lighting IR 05000293/19880131988-05-10010 May 1988 Insp Rept 50-293/88-13 on 880411-15.No Violations Noted. Major Areas Inspected:Review of Licensee Followup & Corrective Actions Re Previously Identified Open Items in Area of Matls Component Integrity & Plant Mods IR 05000293/19880431988-05-0909 May 1988 Mgt Meeting Rept 50-293/88-43 on 880408.Major Topic Discussed:Licensee Power Ascension Program.Viewgraphs Encl IR 05000293/19880071988-05-0606 May 1988 Insp Rept 50-293/88-07 on 880120-0305.Violations Noted.Major Areas Inspected:Insp of Plant Operations,Radiation Protection,Physical Security,Plant Events,Maint, Surveillance,Outage Activities & Repts to NRC IR 05000293/19880151988-04-27027 April 1988 Insp Rept 50-293/88-15 on 880404-08.No Violations Noted. Major Areas Inspected:Liquid Radwaste Sys,Solid Radwaste Sys & Gaseous Radwaste Sys IR 05000293/19880081988-04-19019 April 1988 Insp Rept 50-293/88-08 on 880201-05.Violations Noted.Major Areas Inspected:Electrical Power Sys,Including Verification of as-built Drawings,Adequacy of Breaker & Fuse Coordination & Emergency Loading of Diesel Generator IR 05000293/19880021988-04-14014 April 1988 Insp Rept 50-293/88-02 on 880125-0204.No Violations Noted. Major Areas Inspected:Matl Condition Improvement Action Program ML20151C5891988-03-31031 March 1988 Mgt Meeting Rept 50-293/87-30 on 870930.Major Areas Discussed:Followup of 870909 Enforcement Conference,Licensee Responses to Apparent Violations Identified in Insp Rept 50-293/87-30 & Programmatic Security Improvements IR 05000293/19880101988-03-14014 March 1988 Mgt Meeting Insp Rept 50-293/88-10 on 880224.Major Areas Discussed:Util Self Assessment Process Designed to Determine Readiness for Requesting Restart ML20153A8581988-03-11011 March 1988 Insp Rept 50-293/87-57 on 871207-880119.Violation Noted. Major Areas Inspected:Plant Operations,Radiation Protection, Physical Security,Plant Events,Maint & Surveillance.One Unresolved Item Identified IR 05000293/19880091988-03-10010 March 1988 Insp Rept 50-293/88-09 on 880124-25.No Violations Noted. Major Areas Inspected:Conditions Surrounding Classification & Reporting of Notification of Unusual Event Identified on 880211 IR 05000293/19880011988-03-0303 March 1988 Insp Rept 50-293/88-01 on 880125-29.No Violations Noted. Major Areas Inspected:Status of Previously Identified Items, Organization & Staffing,Control of Locked High Radiation Areas & Control of Hot Particles 1990-08-20
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000293/19990051999-10-0808 October 1999 Insp Rept 50-293/99-05 on 990726-0905.Violations Noted.Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19990041999-08-27027 August 1999 Insp Rept 50-293/99-04 on 990610-0725.Non-cited Violations Noted.Major Areas Inspected:Aspects of Licensee Operations, Engineering,Maint & Plant Support ML20209G2331999-07-0909 July 1999 Insp Rept 50-293/99-03 on 990419-0609.Violations Noted & Being Treated as non-cited Violations.Major Areas Inspected: Operations,Maint,Engineering & Plant Support.Response to Main Transformer Fire by Fire Brigade Members Was Good PNO-I-99-026A, on 990518,main Transformer Was Damaged During Testing of Replacement Bushing While Unit Was in Refueling Outage.Current Refueling Outage Was Originally Scheduled to Be Completed on 990607,with Return to Full Power Operation1999-06-0101 June 1999 PNO-I-99-026A:on 990518,main Transformer Was Damaged During Testing of Replacement Bushing While Unit Was in Refueling Outage.Current Refueling Outage Was Originally Scheduled to Be Completed on 990607,with Return to Full Power Operation PNO-I-99-026, on 990518,fire Occurred at Pilgrim Station in Main Electrical Transformer.Licensee Requested off-site Firefighting Assistance.Resident Inspector Responded to Site Upon Notification of Event.Licensee Issued Press Release1999-05-19019 May 1999 PNO-I-99-026:on 990518,fire Occurred at Pilgrim Station in Main Electrical Transformer.Licensee Requested off-site Firefighting Assistance.Resident Inspector Responded to Site Upon Notification of Event.Licensee Issued Press Release IR 05000293/19990021999-05-17017 May 1999 Insp Rept 50-293/99-02 on 990308-0418.Two Level 4 Violations Occurred & Being Treated as Ncv.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000293/19990011999-04-20020 April 1999 Insp Rept 50-293/99-01 on 990125-0307.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support.Also Included Routine Core Insp of Security Program During Period of 990301-05 IR 05000293/19980101998-12-22022 December 1998 Insp Rept 50-293/98-10 on 981020-1208.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support,Including Implementation of Fire Protection Program IR 05000293/19980081998-12-0101 December 1998 Insp Rept 50-293/98-08 on 980907-1019.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19982031998-11-24024 November 1998 Insp Rept 50-293/98-203 on 980928-1023.No Violations Noted. Major Areas Inspected:Capability of Selected Sys to Perform Safety Functions Required by Design Bases,Adherence of Sys to Design & Licensing Bases & Consistency of Configuration IR 05000293/19983011998-11-24024 November 1998 NRC Operator Licensing Exam Rept 50-293/98-301OL (Including Completed & Graded Tests) for Tests Administered on 981016- 23.Exam Results:All Applicants Passed All Portions of Exam ML20154J8991998-10-0707 October 1998 Notice of Violation from Insp on 980726-0906.Violation Noted:Licensee Did Not Establish Measures to Assure Regulatory Requirements & Design Basis of Control Room High Efficiency Air Filtration Sys IR 05000293/19980071998-10-0707 October 1998 Insp Rept 50-293/98-07 on 980726-0906.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20239A1231998-08-28028 August 1998 Notice of Violation from Insp on 980609-0725.Violation Noted:From 1980 to 980609,licensee Failed to Maintain Provisions to Ensure That One Train of Cables Were Free from Fire Damage IR 05000293/19980061998-08-28028 August 1998 Insp Rept 50-293/98-06 on 980609-0725.No Violations Noted. Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support IR 05000293/19980091998-08-20020 August 1998 Insp Rept 50-293/98-09 on 980713-24.No Violations Noted. Major Areas Inspected:Engineering Activities in Areas Including Evaluations to Address Operability Concerns,C/A Process & Actions Associated W/Findings from Previous Insps ML20237A3031998-08-0606 August 1998 Notice of Violation from Insp on 980427-0515.Violation Noted:From 960710-970427,licensee Elected Not to Monitor Performance or Condition of Control Rod Drive Sys Against Established Goals IR 05000293/19980051998-07-0909 July 1998 Insp Rept 50-293/98-05 on 980421-0608.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support.Concerns W/Fire Proctection Area Were Identified ML20247N8441998-05-19019 May 1998 Partially Deleted Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $55,000 (Ref 10CFR2.790(b) for Violations Noted During Insp on 980302-05 & 11-12 ML20247P0221998-05-19019 May 1998 Notice of Violation from Insp on 980225-0418.Violations Noted:Work Plan to Replace External Cooling Water Flexible Hoses to a Core Spray Pump Motor Not Commensurate with Complexity of Task.As Result,Physical Damage Occurred ML20248J3981998-05-14014 May 1998 EN-98-038:on 980519,notice of Proposed Imposition of Civil Penalty in Amount of $55,000 Issued to Licensee.Action Based on One Violation Involving Apparent Failures Associated W/Assessment Aids at Facility ML20217N5971998-04-27027 April 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $165,000.Violations Noted:Between Jan 1995 & 970120 Licensee Failed to Take Prompt & Effective Corrective Action for Significant Condition Adverse to Quality ML20247M3891998-04-22022 April 1998 EN-98-032:on 980427,notice of Proposed Imposition of Civil Penalty in Amount of $165,000 Issued to Licensee.Action Based on Two Severity Level III Violations & One Severity Level III Problem Re Failure to Identify & Take C/As ML20217P7801998-04-0303 April 1998 Insp Rept 50-293/98-03 on 980302-05 & 11-12.Apparent Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Licensee Security Force Capability ML20217F0101998-03-24024 March 1998 Notice of Violation from Insp on 980107-0224.Violation Noted:Nrc Identified That Condition Outside Design Basis of Plant Involving EDG Fuel Oil Storage Sys Was Not Reported to NRC within 1 Hour IR 05000293/19980011998-03-24024 March 1998 Insp Rept 50-293/98-01 on 980107-0224.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support ML20202D2441998-02-0606 February 1998 Notice of Violation from Insp on 971111-980106.Violations Noted:Util Did Not Properly Evaluate Cause & Implement Corrective Actions to Preclude Repetition of Temporary Temp Detectors Deficiencies from Reactor Vessel Flange IR 05000293/19970131998-02-0606 February 1998 Insp Rept 50-293/97-13 on 971111-980106.Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000293/19970121997-12-17017 December 1997 Insp Rept 50-293/97-12 on 971006-10 & 1119.Violations Noted. Major Areas Inspected:Eq Documents for EQ Equipment That Required Requalification Due to Containment Environ Changes Resulting from CS Flow Rate Reduction in 1988 ML20197K1101997-12-17017 December 1997 Notice of Violation from Insp on 971006-10 & 1119.Violation Noted:Nine Penetrations Were Not Qualified in That Qualification Methodology Used by Boston Edison Had Not Been Validated by Test Results to Be Equivalent to Type Testing ML20197H2411997-12-11011 December 1997 Notice of Violation from Insp on 970914-1110.Violation Noted:On 971001,licensee Identified That,Tagout T97-61-162 Was Incorrectly Prepared & Applied;Breaker 1021 Was Placed in Closed Vice Open Position as Required by Tagout IR 05000293/19970111997-12-11011 December 1997 Insp Rept 50-293/97-11 on 970914-1110.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970991997-11-26026 November 1997 Correction to SALP Rept 50-293/97-99.Page 2 of Subj Rept Corrected IR 05000293/19970101997-11-26026 November 1997 Insp Rept 50-293/97-10 on 971104-07.No Violations Noted. Major Areas Inspected:Emergency Response Organization, Simulated Events,Mitigation Actions Emergency Declarations & off-site Agencies PNO-I-97-072, on 971123,operators Initiated Plant Shutdown When Main Steam Isolation Valves AO-203-1C & AO-203-2B Were Declared Inoperable During Surveillance Test1997-11-24024 November 1997 PNO-I-97-072:on 971123,operators Initiated Plant Shutdown When Main Steam Isolation Valves AO-203-1C & AO-203-2B Were Declared Inoperable During Surveillance Test ML20198P8241997-11-0404 November 1997 SALP Rept 50-293/97-99 for Period 960407-970913 IR 05000293/19970081997-10-24024 October 1997 Insp Rept 50-293/97-08 on 970805-0913.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support ML20198L9231997-10-21021 October 1997 Insp Rept 50-293/97-05 on 970514-0828.Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Engineering PNO-I-97-061, on 970922,util Informed Region I of Receipt of Internal Nuclear Safety Concern Potentially Involving Instance of Falsification of Control Room Log in 1989.Formal Investigation Initiated & Press Release Issued1997-09-23023 September 1997 PNO-I-97-061:on 970922,util Informed Region I of Receipt of Internal Nuclear Safety Concern Potentially Involving Instance of Falsification of Control Room Log in 1989.Formal Investigation Initiated & Press Release Issued ML20211A2741997-09-17017 September 1997 Notice of Violation from Insp on 970721-0801.Violation Noted:For Problem Rept PR97.9220,trip of B Residual Heat Removal Pump,Individual Performing Root Cause Analysis Was Not Formally Trained in HPI Methodology IR 05000293/19970071997-09-15015 September 1997 Insp Rept 50-293/97-07 on 970625-0816.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000293/19970801997-09-12012 September 1997 Insp Rept 50-293/97-80 on 970721-0801.Violations Noted.Major Areas Inspected:Effectiveness of Processes for Identifying Resolving & Preventing Issues That Degrade Quality of Plant Operations & Safety ML20216G8181997-09-0404 September 1997 Insp Rept 50-293/97-09 on 970827-28.No Violations Noted. Major Areas Inspected:Licensee Access Authorization Program PNO-I-97-053, on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR1997-08-22022 August 1997 PNO-I-97-053:on 970826,special Security Insp Will Be Performed,That Will Examine Security Activities at Vermont Yankee,Pilgrim & Indian Point 3.Team Will Include Security Specialists from Region I & NRR IR 05000293/19970041997-08-0707 August 1997 Insp Rept 50-293/97-04 on 970505-23.No Violations Noted. Major Areas Inspected:Effectiveness of Licensees Efforts in Maintaining Design Basis of safety-related Sys ML20149K0431997-07-22022 July 1997 Insp Rept 50-293/97-03 on 970429-0624.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20149K0401997-07-22022 July 1997 Notice of Violation from Insp on 970429-0624.Violation Noted:On 970602,station Services Dept Worker Tied Open Boiler Room Door Which Forms Part of Radiologically Controlled Area & Action Not Directed by RP Personnel ML20149K1311997-07-18018 July 1997 NRC Operator Licensing Exam Rept 50-293/97-06 (Including Completed & Graded Tests) for Tests Administered on 970505-09 ML20149K1291997-07-18018 July 1997 Notice of Violation from Exam on 970505-09.Violation Noted: Two SRO Applications Dtd 970418,documented Five Manipulations Based on Credit Taken for Multiple Manipulations Due to Power Change & One Should Be Credited ML20141K7861997-05-22022 May 1997 Insp Rept 50-293/97-02 on 970303-0428.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support 1999-08-27
[Table view] |
See also: IR 05000293/1985013
Text
_ _ .
m ,
'
.
.
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Report No. 50-293/85-13
Docket No. 50-293
License No. DPR-35 Priority --
Category C
Licensee: Boston Edison Company M/C Nuclear
25 Braintree Hill Office Park
Braintree, Massachusetts
Facility Name: Pilgrim Nuclear Power Station
Inspection At: Plymouth, Massachusetts
Inspection Conducted: May 20-24, 1985
Inspectors: bl. dd
R. L. Nimitz, Senior Radtttion
'lk9b65
date
Specialist
hfML w
L. E. M9 f ,
n
Do S cialist
,19195
tf tb
Approved by: / .
4
W. fiscfali,~ Chfdf, BWR Radiation
7 /d ef3
'/ ' d6te
/ Safety Section
Inspection Summary: Inspection on May 20-24, 1985 (Report No. 50-293/85-13)
Areas Inspected: Routine, announced inspection of the following: licensee
implementation of improvement items identified in the Radiological Improvement
Program; implementation of requirements contained in IE Bulletin 80-10; review
of radiological controls for fuel pool work; and radioactive waste management.
The inspector involved 70 inspector-hours on-site by two region based
inspectors.
Results: One violation was found in one area (failure to adhere to the
requirements of T. S. 6.8 relative to the approval and adherence of
procedures, two examples; paragraph 5). One Deviation was identified in one
area (failure to implement the requirements of IE Bulletin 80-10; paragraph
4). The licensee was found to be closely monitoring implementation of the
Radiological Improvement Program.
l
l
,
l
8507220387 850716 l
PDR ADOCK 05000293 i
G PDR l
,. - . _ _ _ _. , . _ . _ _ _
, _
_. _ . - _ -
,
'
-
.
i
!
DETAILS
1.0 Individuals Contacted
1.1 Boston Edison Comrany (BECo)
- A. L. Oxsen, Vice President-Nuclear Operations
- C. J. Mathis, Nuclear Operations Manager
- W. H. Deacon, Assistant to the Senior Vice President-Nuclear
- R. A. Smith, Chief Chemical Engineer
- R. D. Smith, Chief Technical Engineer
- P. E. Mastrangelo, Chief Operating Engineer
- A. R. Trudeau, Chief Radiological Engineer
- E. T. Graham, Compliance Management Group Leader
- E. J. Ziemianski, Nuclear Operations Support Manager
- D. J. Sukanek, Station Services Group Leader
1.2 Contractors
- G. H. Smith, Hydro-Nuclear Inc.
1.3 NRC
- M. McBride, Resident Inspector, Pilgrim Station
- Denotes attendance at the NRC/ licensee exit meeting on May 24, 1985.
The inspector also contacted other licensee personnel.
2. Purpose of Inspection
The purpose of this routine, announced radiological controls inspection
was to review the following program elements:
- Implementation of licensee commitments presented to NRC in the
Radiological Improvement Program
Nonradioactive System and Resulting Potential for Unmonitored,
Uncontrolled Release to Environment"
Radioactive Waste Management, including:
- radioactive waste storage and handling
- new Rad Waste Compactor Facility
! * Implementation of Radiological Controls During Spent Fuel Pool
l- Work.
l
l
'
__ _ - - - _ _ . _ _ - - - - , _ _ _ _ _ _ - _ - - _ _ , _ , ,
j ..
'
. .
3
3. Implementation of Licensee Commitments Presented to NRC in the
Radiological Improvement Program.
3.1 General
The inspector reviewed the implementation of licensee commitments
presented to the NRC. The review was with respect to criteria and/or
information contained in the following documents:
Order Modifying Licensee, Notice of Violation, and Notice of
Deviation (NRC Inspection No. 50-293/84-25 and 50-293/84-29), dated
November 29, 1984.
Letter (W. D. Harrington, Senior Vice President-Nuclear, Boston
Edison, to T. E. Murley, Regional Administrator, NRC Region I),
dated February 28,1985 (BECo LTr No 85-042).
Licensee Completed Regulatory Requirement Analysis Forms (various)
relative to Radiological Improvement Plan (RIP) Milestones.
Licensee Radiological Activity Assessment Reports (RAAR) (various).
Radiological Oversight Committee (ROC) Meeting Minutes (various).
The purpose of this review was to determine if,
a
the licensee met the commitments (i.e. milestones) specified in the
Radiological Improvement Program (RIP);
the material or actions taken/ generated by the licensee satisfac-
torily met the commitments made to NRC in the RIP;
the material or actions taken/ generated were properly implemented.
The following aspects of RIP implementation were noted:
a tracking program was in place to identify milestones due;
adequate management controls were in place to monitor implementation
of milestones and initiate proper action when milestones were
identified as potentially not being met;
- adequate review was performed of the material or actions
taken/ generated to determine its adequacy prior to its acceptance
and implementation.
3.2 Findings
The inspector reviewed a total of 65 commitments that were to have been
completed by the licensee by April 30, 1985. The commitments reviewed
are identified in the attachment to this report.
,
.
.
,
4
The review indicated that the licensee satisfactorily completed his
committed action on 63 of the commitments. Several commitments were left
open due to the need for additional NRC review. These are identified in
the attachment to this report.
Within the scope of this review, the following positive attributes of the
RIP were noted:
The licensee's Senior Vice President-Nuclear is closely monitoring
implementation of the Radiological Improvement Program (RIP)
The RIP milestones have been inputted into the licensee's Planning
and Scheduling Computer for monitoring. The monitoring program has
appropriate flags to notify management in a timely manner when a
task may potentially fall behind schedule. The licensee initiates
appropriate action when this is identified.
- The licensee's contractor is also monitoring implementation of RIP
milestones.
- The RIP material or actions taken/ generated have been, where appro-
priate, properly implemented.
- The licensee's RIP Program Manager is: periodically auditing
compliance with the Order Modifying License (referenced above);
auditing RIP implementation; and reviewing the RIP product.
Within the scope of this review, the following additional matter was
identified:
- The licensee Senior Management identified a concern involving timely
resolution by the Radiological Oversight Committee (ROC) of items
brought to its attention. The licensee took action to ensure the
ROC implemented its charter responsibilities in an appropriate
manner.
- Based on NRC findings identified during review of Spent Fuel Pool
work (see Section 5 of this report) the licensee stated that the
Radiological Assessor, who reports his findings to the ROC, would be
requested to place additional emphasis on personnel use of approved
procedures during work and training of personnel in job specific
procedures.
Conclusion
Based on the above review, the licensee is aggressively monitoring
implementation of the RIP deficiencies identified, and is meeting
commitments provided to NRC Region I.
<
-
.
~
..
5
4.0 IE Bulletin 80-10
The inspector reviewed the licensee's implementation of the requirements
contained in IE Bulletin 80-10, " Contamination of Nonradioactive System
and Resulting Potential for Unmonitored/ Uncontrolled Release to the
Environment." This review followed up Open Item No. 50-293/85-07-03.
Within the scope of the review, the following Deviation was identified:
IE Bulletin 80-10 requires among other matters that: 1) a review of
facility design and operation be performed to identify systems that are
considered as nonradioactive, but could possibly become contaminated
through interfaces with contaminated systems; 2) a routine sampling /
analysis or monitoring program for these systems be established in order
to promptly identify any contaminating events which could lead to
unmonitored, uncontrolled, liquid or gaseous releases to the environment,
including releases to on-site leaching fields and; 3) the specifics of
these reviews be documented and made available to the NRC for review
during future on-site inspection efforts. In particular, special consider-
ation was to be given to the instrument air system and the sanitary waste
system.
The licensee's July 11, 1980 response to this Bulletin indicated that the
above was implemented.
Contrary to the above, as of May 24, 1985, 1) the instrument air system
and sanitary waste system had not been reviewed to determine if these
systems could become radioactive through interfaces with nonradioactive
systems; 2) no routine sampling / analysis or monitoring program (as
appropriate) was established in order to promptly identify any contam-
inating events which could lead to unmonitored/ uncontrolled releases from
these systems; and 3) no specifics relative to the above was documented
and made available to the NRC.
This matter remains open.
Within the scope of this review, the following additional matters were
identified:
- The licensee did not have clearly established action levels to be
used to identify a potentially contaminated, normally uncontaminated,
system in order that appropriate personnel can be notified in a
timely manner to implement the requirements of Section 3 of IE
Bulletin 80-10.
Licensee representatives indicated such guidance would be established by
June 3,1983. (50-293/85-13-01)
,
The licensee did not.have clearly established guidance for operations
personnel relative to what action to take if they were notified that
a normally clean system was identified as contaminated.
. . _ _ _ - - . . - _ _ . .
. _ _ -
,
..
6
Licensee representatives indicated such guidance would be established by
June 3, 1983. (50-293/85-13-02)
Within the scope of the review, the following additional matter was
,
identified:
Inspector review indicated that a licensee special instruction dated
June 7, 1984, appeared to supersede a licensee approved procedure
(No. 7.3.41-1) for sampling and analysis of service water. This
matter is unresolved. (50-293/85-13-03)
5.0 Spent Fuel Pool Work
The inspector reviewed the implementation of Radiological Controls for
work in the Spent Fuel Pool. The licensee was cutting control rod blades
and low power range monitors for disposal.
The review was perforced to determine if,
procedures for the operation were properly reviewed and approved in
accordance with station administrative requirements;
a
personnel, were appropriate, were properly trained and qualified in
the applicable procedures;
radiological controls personnel, overseeing the work, were properly
trained and qualified in accordance with Technical Specification
requirements;
radiological controls for the task were adequate;
established radiological controls were properly implemented (e.g.,
RWP controls);
a
radiation survey equipment used for the task was properly
calibrated.
The evaluation of the licensee's performance in the above areas was based
on:
independent radiation surveys performed by the inspector;
- discussions with personnel;
- - . - _ __
.
. . - . - - . - - - _ - - _ - . - . , . -. - --
..
.
.
7
The following documents were selectively reviewed:
Procedure 1.3.4, " Procedures," Revision 27, dated April 24, 1985;
Procedure 1.5.3, " Maintenance Requests," Revision 16 dated
April 1985;
Procedure 3.M.1-19, " Spent Fuel Pool Cleaning," Revision 1, dated
February 6, 1985;
- Procedure TP85-14, " Transfer of Control Rod Blades and Poison
Curtains in the Spent Fuel Pool," Revision 0, dated
December 31, 1985;
Procedure TP85-23, " Waste Characterization," Revision 0, dated
March 6, 1985;
Procedure FP-0P-008-442, " Operating Procedure for Use of Abrasive
Underwater Saw at Pilgrim Station," dated March 24, 1965,
Chem-Nuclear Systems, Inc.;
Procedure FP-0P-007-442, " Procedure for Processing LPRM ' Hot' and
' Cold' Ends at Pilgrim For Disposal," dated March 15, 1985,
Chem-Nuclear Systems, Inc.;
- Procedure 6.4-079, " Operation of the Technical Associates CPMU
Underwater Survey Meter," Revision 3, dated August 26, 1985;
Procedure 6.5-079, " Calibration of the Technical Associates CPMU,
Underwater Model," Revision 2, dated January 27, 1982; and
Certificates of Calibration for CPMU, Serial Nos. 945131 and 3870.
Within the scope of this review, the following violation was identified:
Technical Specification 6.8 requires that written procedures and adminis-
trative policies be established, implemented and maintained, that meet or
exceed the requirements and recommendation of Appendix 'A' of Regulatory
Guide 1.33. Appendix 'A' of Regulatory Guide 1.33, 1972 recommends, in
part, that. procedures for procedure review and approval be prepared. It
also recommends that procedures for the repair or replacement of equipment
be prepared. (50-293/85-13-04)
1. Procedure 1.3.4, Revision 27, " Procedures," specifies, in part, in
section C.3, that the Operation Review Committee (ORC) shall
indicate its approval of a procedure to be included in Category
.Three Group Procedures.
Contrary to the above, as of May 23, 1985, two procedures
(FP-0P-007-442 and FP-0P-008-442), used to provide guidance for
.
.
"
..
8
cutting of control rod blades and LPRMs were not presented to ORC
for approval as Category Three procedures. The procedures were used
since about May 1, 1985 to provide guidance for on going cutting
work.
2. Procedure No. 3.M.1-19, Revision 1, " Spent Fuel Pool Cleaning,"
specifies in section IV that the obtaining of a valid Maintenance
Request (MR) is a prerequisite for procedure use. The procedure
provides general guidance for performing cutting of radioactive
materials in the spent fuel pool. In addition, Vendor Procedure No.
FP-0P-007-442, " Procedure for Processing LPRM Hot and Cold Ends for
Disposal," specifies in-section 4 that the obtaining of a valid
maintenance request is a prerequisite for procedure use.
Contrary to the above, as of May 23, 1985, and for an undetermir.ed period
of time prior to this time, control rod blades and LPRMs were being cut
in the spent fuel pool in preparation for planned disposal but no valid
maintenan ? request was in effect.
The above matters were brought to the. licensee's attention on
May 23, 1985. The licensee performed the following:
halted all work on the Refueling Floor on May 23, 1985;
a
presented the vendor procedures to ORC on May 24, 1985;
issued a maintenance request for the work;
ensured all personnel were cognizant of their procedural
responsibilities.
Within the scope of the review, the following additional matters were
identified:
Licensee radiological control technicians, providing oversight of
the cutting work, had not been provided copies of or instructed in
the specific radiological controls requirements in vendor procedures.
One of the procedures required sign-offs by the technicians.
The licensee referenced on the applicable RWP three station approved
procedures for control of selected activities associated with work
in the spent fuel pool. However, the inspectors were unable to
identify any specific supervisory control in place to ensure that
all appropriate technicians had read and understood the referenced
procedures.
These matters were brought to the licensee's attention.
.
'
.
.
9
On May 29, 1985, licensee compliance personnel contacted the inspector
and indicated that all appropriate personnel had reviewed the applicable
procedures.
Licensee representatives indicated the Contractor Onsite Assessor would
be requested in his reviews to ensure personnel were using appropriately
reviewed procedures and were knowledgeable in the procedure requirements.
6.0 Radioactive Waste Transportation
On May 23, 1984, the inspector reviewed selected aspects of a radioactive
waste shipment prepared for transport. The shipment consisted of
miscellaneous material from the spent fuel pool. The shipment contained
an estimated 70 curies.
The following aspects were reviewed:
radiation levels at various locations on the shipment were within
applicable regulatory limits;
a
contamination levels on the shipment were within applicable limits;
quantities of radioactive material contained in the shipment were
properly determined;
a
selected aspects of the shipping papers were completed in accordance
with procedure requirements;
notifications, were appropriate, were made.
.The review was with respect to criteria contained in the following:
Temporary Procedure TP85-39, " Handling and Loading Procedure for
CNSI 3-55 Cask," Revision 0, dated April 24, 1985;
Temporary Procedure T85-23, " Waste Characterization," Revision 0,
dated December 31, 1985;
Procedure 6.9-160, " Shipment of Radioactive Material, " Revision 20,
dated April 14, 1985; and
- Certificate of Compliance of cask CNSI 3-55, No. 5805, Revision 13.
- - Applicable NRC and DOT Regulatory requirements.
The evaluation of the licensee's performance in this area was based on:
performance of independent radiation surveys by the inspector;
.
.
.
$
10
performance of contamination surveys by the inspector;
discussions with cognizant personnel.
Within the scope of this review, no violations were identified. The
licensee implemented the applicable requirements.
Within the scope of this review, the following items for improvement were
identified:
The check-off list for procedure T85-39 did not contain a check-off
for satisfactory performance of a cask leak test. The licensee
issued a procedure change notice to address this matter.
The check-off list for the shipping procedures does not contain a
check-off for satisfactory determination that cask seals have been
replaced within the specified time interval. The licensee should
add such a check-off to the applicable procedure. (50-293/85-13-05)
7.0 _ Trash Compactor Facility
The inspector reviewed operations at the Trash Compactor Facility. The
following matters were reviewed:
control of radioactive material;
airborne radioactivity monitoring;
ventilation system operation;
control of liquid radioactive material;
performance of appropriate safety evaluations for operation of the
facility.
The review was with respect to criteria contained in the following:
=
Procedure TP 84-64, Revision 0, " Radiological Controls for the Trash
Compactor Facility (TCF)";
Procedure No. 6.9-179, Revision 1, " Radioactive Waste Press
,
(Steel Box - Compactor)";
10 CFR 20, " Standards for Protection Against Radiation";
,
.
.
'11
- 10 CFR 50.59, " Changes, Tests, Experiments";
NRC Generic Letter 81-38, " Storage of Low-Level Radioactive Wastes
At Power Reactor Sites," dated November 30, 1981;
IE Circular 80-18, "10 CFR 50.59 Safety Evaluation for Changes To
Radioactive Waste Treatment Systems".
The evaluation of the licensee's performance in the area was based on:
inspector tour of the Trash Compactor Facility;
discussions with cognizant personnel;
a
review of documentation including review of the following safety
evaluation and calculations:
10 CFR 50.59 Safety Evaluation for New Trash Compactor
Facility, (N0P83ES), dated March 1, 1984;
- Calculation No. ERHS-XIII*B-10-0;
Calculation No. ERHS-XIII*B-9-0.
Within the scope of the review, the following was noted:
The new Trash Compacting Facility is not being utilized as an
interim low level waste storage facility. Rather the licensee is
using it as a holding area for material to be shipped.
No radioactive liquids are to be introduced to the facility
.
The licensee established package radiation dose rate and
contamination level criteria for packages to be held at the
facility.
The licensee is using the trash compactor to compact trash in the
facility. Procedures have been established for the purpose
.
The licensee is not using the radioactive waste segregation and
sorting capabilities of the facility pending installation of
appropriate airborne radioactivity effluent monitoring equipment.
Within the scope of the review, the following matters are unresolved and
will be reviewed during a subsequent inspection (50-293/85-13-06):
- The licensee's safety evaluation for offsite doses to members of the
public did not clearly indicate that the doses would be below those
specified in 40 CFR 190 (Reference 10 CFR 20.105 (c)).
-. - _- . ._ . - . ..
_
4
.
.
12
- *
The licensee has established a routine radiological survey program
for the facility (Reference TP84-64). However, appropriate action
level criteria were not established to ensure all dose limits of 10
.CFR 20.105 (i.e. 40 CFR 190) were met.
The licensee used one open LSA box as a source term for his safety
evaluation. However, the basis of this source term is uncertain.
8.0 Unresolved Items
Unresolved Items are. items which need additional review to determine if
they are acceptable. One Unresolved Item is discussed in section 4 of
the report. (50-293/85-13-03)
9.0 Exit Meeting
The inspector met with licensee representatives denoted in section 1 of
-the report, on May 24, 1985. The inspector summarized the purpose, scope
and findings of the inspection.
At no time during this inspection did the inspector provide the licensee
. written material.
f
t
2
-
, . - - _. . _ _ ,_._ . . _ _ _ _ _ . . _ . . _ . , _ , _ _ _ _ _ _ _ . , _ _ . _ , . _ . . . _ _ .
. . _ _ - _ - _ . - .
.
.
.
page 1 of 8
Attachment
Status of Boston Edison Company's
Radiological Improvement Program (RIP)
Commitments to be Completed on or
Before April 30, 1985
Commitment Status NRC Comment
1. 1.1.1 Develop and approve Complete Organization complete
An Interim Organization and implemented.
for the Radiological Described in BECo
Control Group Letter No.85-042
(February 28, 1985) dated February 28,
1985. Distributed via
BECo Memorandum No.
CRE 85-165, dated
March 26, 1985
2. 1.1.2 Define functional and Complete NONE
and administrative
responsibilities for each
position in the interim
organization.
(February 28, 1985)
3. 1.1.3 Define interim Complete Established in
organization chain of accordance with
command. organization chart
(February 28,1985) (See Item 1.1.1(#1))
4. 1.1.4 The interim Radiological Complete NONE
Control Organization will
be fully staffed and
implemented by Boston Edison
or Contractor personnel by
March 31, 1985
5. 1.2.1 Develop and Implement an Complete NONE
Organization for the
Radiological Group. Present
the proposed organization to
Corporate Management -
April 30, 1985
6. 1.2.2 Formally define Complete NRC will review
the approved organization these defined
structure for the Radiological elements to determine
Group (April 30,1985) if they are consistent
with/ adequate to
high priority technical implement actual
support requests approved organization
(Milestone 1.2.2,
group functional May 31, 1985)
responsibilities define NRC Follow-up Item
.
page 2 of 8
Commitment Status NRC Comment
- individual responsibilities 50-293/85-13-07
.
define Assigned to this
,
matter.
'
chart define
,
responsibilities define
7. 1.3 Develop and implement Complete NONE
an RIP implementation plan
and schedule for organization
improvement.
(completedMarch 31,1985)
8. 2.2.1 Publish training Complete NONE
goals and objectives for
Group Training
(April 30, 1985)
9. 2.2.6 Develop a schedule Complete NONE
for implementing desired
training and ensure the
training department has
,
adequate resources to
l meet schedule.
The Nuclear Training
l Department will publish
a training schedule of
training to be offered for
1985. (March 31, 1985)
\
Request additional resources
Approve additional resources
,
Publish Training Schedule
!
! 10. 3.1.1 An evaluation Complete A proposed training
l- will be performed Coordinator Position
l by April 30, 1985 to has been established
l determine the need to (Reference CRE
l permanently assign a Memorandum No.
Radiological Group 85-249)
l Representative to work with
L the Training Group
11. 3.1.1-1 Review and Revise Complete (CRE Memorandum No.
3.1.1-2' General Employee Training 85-148) Revised
Modules by March 31, 1985 program to be
implemented July 31,
1985 (Milestone
3.1.1-3)
'
.
page 3 of 8
~
i- ' Commitment Status NRC Comment l
12. 4.1.1 (c)-Proper location for Complete (CRE Memorandum No.
dosimetry placement 84-834)
will be defined
13. 4.1.2 Procedure No. 6.2-111 Complete NRC to review licensee
Will be revised to include corrective action on
frequency for QA checks Step 4 of procedure.
Correction factor not
correct
(50-293/85-13-08)
14. 4.2.1 Documentation Complete NONE
of R. G. 8.13
~ training to be
completed after training
provided.
15. 5.1.1- An addendum to the Completed NONE
special instruction detailing
with the air quality testing ,
process will be written to identify
the operating compressor during
testing (March 31,1985)
16. 5.1.2 Respirator smear checks Complete Requirement
have been improved contained in
Procedure 6.7-110
17. 5.3.1 The onsite compressor Complete NONE
!
'has been repaired
(complete)
i
l - 18. 6.2.1.a-1 The ANSI standards Complete Licensee review
dealing with whole identified a
.
, body counting number of
- will be reviewed recommendations
. (April 30, 1985) for improvement.
l The improvements
.
'
will be implemented
to meet other
milestones contained
l in RIP section 6.0.
-
!
l -19. 6.2.1.c-1 Review whole Complete NONE
l body counter
i' libraries
'
20. 6.2.1.d-1,2
, Licensee to perform Complete NONE
literature search and
order document to
- -
, _ . . _ . _ - - -- . . - _ _ , _- _ -- . . _ ,
,
'
page 4 of 8
Commitment Status NRC Comment
support whole body
counter operations
( April 30,1985)
'
21. 6.2.1.e-1
Licensee to Complete Personnel instructed
revise and in revisions
approve whole body
counting instructions to
include check of critical
parameters (April 30,1985)
22. 6.2.3.1 A policy statement Complete Provided by
will be developed Memorandum to Staff.
on why it is NRC will review to
appropriate to conduct determine need to
thyroid counts include in procedures
(April 30, 1985) (50-283/85-13-09).
23. -6.2.2.d A Radiation Complete NONE
Protection Supervisor
has been assigned oversight
responsibility of the whole
body counter operation
(February 28,1985)
24. 7.1.2.1 Complete re-instruction Complete Meetings held with
of all appropriate personnel appropriate personnel
regarding unnecessary on March 26, 1985
posting and labeling and March 27, 1985
(March 31, 1985)
25. 7.1.6.1 A Specific Health Physics Complete NONE
Supervisor was assigned
implementation and improvement
of the overall survey program
(February 28,1985)
26. 7.1.7.1 Licensee will evaluate if Ongoing Performed by Onsite
present practice for adequacy Assessor. Revisions
and timeliness of radiation to be made to RWP
surveys is acceptable Program if necessary
(February 28,1985) (7.1.7.2) Current
HP Supervisor noti-
fied of need for
adequate surveys.
27. 7.3.1 Nuclear Operation Manager Complete Memorandum No.
to issue a directive to all AD 85-69 issued
--
.
'
-
page 5 of 8
Commitment Status NRC Comment
management regarding improving March 18, 1985
personnel contamination
monitoring (March 31,1985)
~28. 7.3.2.1 Licensee will review current Complete Licensee issued
practices and implement an May 6, 1985. Policy No. 35,
improved policy for NRC Notified " Radiation,"
minimization of contamination of delay Material and
and control of radioactive Contamination,"
material (April 30,1985) May 6, 1985.
Policy to be
implemented via
other milestones
contained in
Section 7.
29. 7.3.3.1 Licensee to complete Complete Completed on
review of Main Control April 22, 1985
Point (April 30, 1985) (CRE 85-251)
'
30. 7.3.4.1 . Review Access Complete NONE
Control Points
(April 30, 1985)
31, 7.3.4.2 Institute policies / Complete (See 29)
' notify station personnel Findings of Access
of the restriction of Control Point
access points so as to reviews to be used
have minimal operations to improve current
impact (April 30,1985) access control point
situations
32. -7.3.5.1 Evaluate current problem Complete Review performed.
of circumvention of Review concluded
step-off pads and that poor frisking
frisking to determine practices
'if it is procedural combination of
(April 30, 1985) procedural inad-
equacies or poor
worker performance.
Corrective action
on going.
33. 7.4.1 The location and type of Complete Documented in
air sampling equipment Memorandum No.
will be established SS 85-78. Sampling
(April 30, 1985) for set up for compactor,
the Trash Compactor Sorting table use
Facility suspended pending
installation of
acceptable equipment
o
'
.
~
page 6 of 8
Commitment Status NRC Comment
34. 8.1.2.1 Current Radioactive Complete Documented in
8.1.3.1 Waste Storage Areas Memorandum
8.1.4.1 Will be evaluated for: PNOS85-255,
consolidation, enclosure, dated April 30, 1985,
shielding PNOS85-254,
(April 30, 1985) dated April 30, 1985
Note: No commitments due on or before April 30, 1985
contained in section 9, "ALARA"
35. 10.1.1 Correct Water Complete Plan for repairs
related problems (Partial) complete (Memorandum
in HP facilities dated April 17,1985)
10.1.3 -Upgrade house keep Schedule for repairs
and appearance of (Memorandum undated)
HP facilities No apparent action
Develop plan and on 1) housekeeping
schedule to implement 2) appearance.
the necessary repairs (50-293/85-13-10)
(April 30, 1985)
36. 10.2.1.b The thyroid detector Complete NONE
has been repaired on the
APT chair (February 28,1985)
37. 10.2.2.b 1,2
Decontaminate and Complete Background levels
minimize recontamination identified. System
of the Ge(LI) system not contaminated
(March 31, 1985)
38, 10.2.2.d Develop training materials Complete Documented in NTD
in order to properly train #85-0198, dated
personnel to interpret March 27, 1985
Ge(LI) results (March 31,1985)
39. 10.2.5.a.1 ~
An evaluation of the range Complete Documented in
and calibration of R chambers Evaluation
will be completed Memorandum. A .025R
(March 31, 1985) R-chamber to be
ordered
40. 10.2.5.cl Upgrade calibration Complete New jigs in use
10.2.5.c2 jigs. Submit designs
(April 30, 1985)
Irrplement use (August 31,1985)
'
.o
.
.
page 7 of 8
Commitment Status NRC Comment
41. 10.2.7.1 Tag inoperable Complete NRC will review
Eberline instruments need for monitors
at TIP Area and Rad (50-293/85-13-11)
Waste Segregation Area
Out of Service. Assign
responsibility of units.
42. 10.3.1.1 Issue policy statement Complete NONE
-regarding use of yellow (Memorandum CRE
poly (April 30,1985)85-234)
(April 22, 1985)
43. 10.3.5.1 Coordinate activities Complete NONE
relative to use of
substitutions of supplies.
Initiate discussions
(April 30, 1985)
44. 11.1.-1 Complete a Procedure Plan Complete NONE
for procedures
(April 30, 1985)
11.3.1 Incorporate requirements Complete
for task analysis in
procedure plan
'(April 30, 1985)
11.4.1 Incorporate methodology Complete
for cross referencing of
procedures into procedure
plan (April 30, 1985)
11.5.1 A requirement to field Complete
test procedures or
instructions will be
included in the
. procedure plan
45. 111.6.a.1- A video tape segment Complete Video tape to be
will be incorporated into incorporated into
the General Employee GET. NRC to view
Training Program. (50-293/85-13-12)
(April ~30,1985)
46. 11.6.b.1 A memorandum will be Complete Memorandum No.
issued which provides VPN0 85-17, dated
guidance on the sets of
-
.
February 28, 1985
procedures (February 28,1985)
Note: No commitment to be implemented prior to April 30, 1985
in section 12, " Radiation Materials Controls"
r
--
,
~
.
f *
page 8 of 8
i
Commitment Status NRC Comment
47. 13.1.1 Submit Radiological Complete NONE
13.1.2 Improvement Program (RIP)
to NRC (February 28,1985)
Initiate Implementation of
the RIP (March 15,1985)
48. 13.2.1 Establish a detailed RIP Complete NONE
scheduling network
(March 31, 1985)
49. 13.3.3 Implement basic Complete Implemented per
13.3.4 management concepts response to
13.3.5 described in these milestone
13.3.6 recommendations 11.6.a.1 NRC
(11.6.a.1, April 30, 1985) to view tape.
(See No. 45)
50. 13.3.11 Develop or revise a Complete Policy Statement
Nuclear Organization No. 19 revised
Policy to address impacts on April 18,
of changes in staffing, 1985.
organization or policy
.(April 30, 1985)
.
.