MONTHYEARBVY-99-127, Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-112, Monthly Operating Rept for Aug 1999 for Vermont Yankee.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Vermont Yankee.With BVY-99-102, Monthly Operating Rept for July 1999 for Vermont Yankee. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Vermont Yankee. with BVY-99-090, Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-077, Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-068, Monthly Operating Rept for Apr 1999 for Vynp.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Vynp.With BVY-99-046, Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-035, Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With BVY-99-001, Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station BVY-98-163, Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-154, Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-149, Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-135, Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With BVY-98-122, Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station BVY-98-098, Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station BVY-98-081, Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station BVY-98-068, Monthly Operating Rept for Apr 1998 for Vermont Yankee Nuclear Power Station1998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Vermont Yankee Nuclear Power Station BVY-98-053, Monthly Statistical Rept for Mar 1998 for Vynp1998-03-31031 March 1998 Monthly Statistical Rept for Mar 1998 for Vynp ML20248L1581998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Vermont Yankee Nuclear Power Station ML20217M7801998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Vynp Station ML20198L6111997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Vynp Station BVY-97-161, Monthly Operating Rept for Nov 1997 for Vermont Yankee Nuclear Power Station1997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Vermont Yankee Nuclear Power Station BVY-97-145, Monthly Operating Rept for Oct 1997 for Vermont Yankee Nuclear Power Station1997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Vermont Yankee Nuclear Power Station BVY-97-126, Monthly Operating Rept for Sept 1997 for Vermont Yankee Nuclear Power Station1997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Vermont Yankee Nuclear Power Station BVY-97-111, Monthly Operating Rept for Aug 1997 for Vermont Yankee Nuclear Power Station1997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Vermont Yankee Nuclear Power Station BVY-97-098, Monthly Operating Rept for Jul 1997 for Vermont Yankee Nuclear Power Station1997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Vermont Yankee Nuclear Power Station BVY-97-088, Monthly Operating Rept for June 1997 for Nynps1997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Nynps BVY-97-074, Monthly Operating Rept for May 1997 for Vermont Yankee Nuclear Power Station1997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Vermont Yankee Nuclear Power Station BVY-97-059, Monthly Operating Rept for Apr 1997 for Vermont Yankee Nuclear Station1997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Vermont Yankee Nuclear Station BVY-97-042, Monthly Operating Rept for Mar 1997 for Vermont Yankee Nuclear Power Station1997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Vermont Yankee Nuclear Power Station BVY-97-033, Monthly Operating Rept for Feb 1997 for Vermont Yankee Power Station1997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Vermont Yankee Power Station BVY-97-021, Monthly Operating Rept for Jan 1997 for VYNPS1997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for VYNPS BVY-97-001, Monthly Operating Rept for Dec 1996 for Vermont Yankee Nuclear Power Station1996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Vermont Yankee Nuclear Power Station BVY-96-154, Monthly Operating Rept for Nov 1996 for Vermont Yankee Nuclear Power Station1996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Vermont Yankee Nuclear Power Station BVY-96-138, Monthly Operating Rept for Oct 1996 for Vermont Yankee Nuclear Power Station1996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Vermont Yankee Nuclear Power Station BVY-96-114, Monthly Operating Rept for Sept 1996 for Vynp1996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Vynp BVY-96-103, Monthly Operating Rept for Aug 1996 for Vermont Yankee Nuclear Power Station1996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Vermont Yankee Nuclear Power Station BVY-96-095, Monthly Operating Rept for July 1996 for VT Yankee Nuclear Power Station1996-07-31031 July 1996 Monthly Operating Rept for July 1996 for VT Yankee Nuclear Power Station BVY-96-087, Monthly Operating Rept for June 1996 for Vermont Yankee Nuclear Power Station1996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Vermont Yankee Nuclear Power Station BVY-96-072, Monthly Operating Rept for May 1996 for Vermont Yankee Nuclear Power Station1996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Vermont Yankee Nuclear Power Station BVY-96-057, Monthly Operating Rept for Apr 1996 for VT Yankee Power Station1996-04-30030 April 1996 Monthly Operating Rept for Apr 1996 for VT Yankee Power Station BVY-96-041, Monthly Operating Rept for Mar 1996 for Vynp1996-03-31031 March 1996 Monthly Operating Rept for Mar 1996 for Vynp BVY-96-018, Monthly Statistical Rept for Feb 1996 for VT Yankee Nuclear Power Station1996-02-29029 February 1996 Monthly Statistical Rept for Feb 1996 for VT Yankee Nuclear Power Station BVY-96-009, Monthly Operating Rept for Jan 1996 for Vermont Yankee Nuclear Power Station1996-01-31031 January 1996 Monthly Operating Rept for Jan 1996 for Vermont Yankee Nuclear Power Station BVY-96-001, Monthly Operating Rept for Dec 1995 for Vermont Yankee Nuclear Power Station1995-12-31031 December 1995 Monthly Operating Rept for Dec 1995 for Vermont Yankee Nuclear Power Station ML20095F6601995-11-30030 November 1995 Last Page of Monthly Operating Rept for Nov 1995 for Vermont Yankee BVY-95-131, Monthly Operating Rept for Nov 1995 for Vermont Yankee Nuclear Power Station1995-11-30030 November 1995 Monthly Operating Rept for Nov 1995 for Vermont Yankee Nuclear Power Station BVY-95-118, Monthly Operating Rept for Oct 1995 for Vynp1995-10-31031 October 1995 Monthly Operating Rept for Oct 1995 for Vynp BVY-95-106, Monthly Operating Rept for Sept 1995 for Vynp1995-09-30030 September 1995 Monthly Operating Rept for Sept 1995 for Vynp ML20092F5901995-08-31031 August 1995 Monthly Operating Rept for Aug 1995 for Vermont Yankee Nuclear Station 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217L8831999-10-21021 October 1999 Safety Evaluation Supporting Proposed Alternatives to Code Requirements Described in RR-V17 & RR-V18 ML20217G2041999-10-13013 October 1999 Safety Evaluation Supporting Amend 179 to License DPR-28 BVY-99-127, Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Vermont Yankee Nuclear Power Station.With ML20212C2551999-09-17017 September 1999 Safety Evaluation Supporting Amend 175 to License DPR-28 BVY-99-112, Monthly Operating Rept for Aug 1999 for Vermont Yankee.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Vermont Yankee.With BVY-99-109, Ro:On 990812,stack Ng Effluent Instrumentation for PAM Was Declared Oos.Caused by Instrument Drift Due to Electronic Components Based on Insps by Instrumentation & Controls Dept.Detector & Preamplifier Will Be Replaced on 9908311999-08-19019 August 1999 Ro:On 990812,stack Ng Effluent Instrumentation for PAM Was Declared Oos.Caused by Instrument Drift Due to Electronic Components Based on Insps by Instrumentation & Controls Dept.Detector & Preamplifier Will Be Replaced on 990831 BVY-99-102, Monthly Operating Rept for July 1999 for Vermont Yankee. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Vermont Yankee. with ML20209J0081999-07-14014 July 1999 Special Rept:On 990615,diesel Driven Fire Pump Failed to Achieve Rated Flow of 2500 Gallons Per Minute.Pump Was Inoperable for Greater than 7 Days.Corrective Maint Was Performed to Reset Pump Lift Setting BVY-99-090, Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Vermont Yankee Nuclear Power Station.With ML20196G5071999-06-23023 June 1999 Vynp Assessment of On-Site Disposal of Contaminated Soil by Land Spreading BVY-99-077, Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Vermont Yankee Nuclear Power Station.With BVY-99-068, Monthly Operating Rept for Apr 1999 for Vynp.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Vynp.With ML20206E8741999-04-29029 April 1999 SER Determined That Flaw Evaluation Meets Rules of ASME Code & Assumed Crack Growth Rate Adequate for Application ML20206D9301999-04-27027 April 1999 1999 Emergency Preparedness Exercise 990427 Exercise Manual (Plume Portion) ML20205S4211999-04-16016 April 1999 Non-proprietary Version of Revised Page 4-3 of HI-981932 Technical Rept for Vermont Yankee Spent Fuel Pool Storage Expansion ML20205K7581999-04-0707 April 1999 Safety Evaluation Supporting Alternative Proposal for Reexamination of Circumferential Welds with Detected Flaw Indications in Plant RPV BVY-99-046, Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Vermont Yankee Nuclear Power Station.With ML20205F6631999-03-0404 March 1999 Jet Pump Riser Weld Leakage Evaluation BVY-99-035, Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Vermont Yankee Nuclear Station.With ML20205P8241999-02-28028 February 1999 Rev 2 to Vermont Yankee Cycle 20 Colr ML20203H9881999-02-18018 February 1999 SER Accepting Alternative to 10CFR50.55a(g)(6)(ii)(A) Augmented Reactor Vessel Exam at Vermont Yankee Nuclear Power Station.Technical Ltr Rept Encl ML20203A6951999-02-0404 February 1999 Revised Rev 2,App B to Vermont Yankee Operational QA Manual (Voqam) ML20199K7151999-01-21021 January 1999 Corrected Safety Evaluation Supporting Amend 163 Issued to FOL DPR-28.Pages 2 & 3 Required Correction & Clarification ML20199K6991999-01-20020 January 1999 Safety Evaluation Concluding That Request to Use YAEC-1339, Yankee Atomic Electric Co Application of FIBWR2 Core Hydraulics Code to BWR Reload Analysis, at Vermont Yankee Acceptable ML20199L5951999-01-14014 January 1999 Safety Evaluation Accepting Licensee Proposed Alternative to Code Requirement,Described in Rev 2 to Pump Relief Request RR-P10 Pursuant to 10CFR50.55a(a)(3)(i) BVY-99-071, Corp 1998 Annual Rept. with1998-12-31031 December 1998 Corp 1998 Annual Rept. with BVY-99-001, Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Vermont Yankee Nuclear Power Station ML20198H5481998-12-23023 December 1998 Rev 2 to Vermont Operational QA Manual,Voqam ML20196H8641998-12-0101 December 1998 Cycle 19 Operating Rept BVY-98-163, Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Vermont Yankee Nuclear Power Station.With ML20195C4161998-11-0909 November 1998 SER Accepting Request That NRC Approve ASME Code Case N-560, Alternative Exam Requirement for Class 1,Category B-J Piping Welds BVY-98-154, Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Vermont Yankee Nuclear Power Station.With ML20155B6471998-10-26026 October 1998 Safety Evaluation Accepting Jet Pump Riser Insp Results & Flaw Evaluation,Conducted During 1998 Refueling Outage ML20154N0891998-10-16016 October 1998 Rev 1 to Vermont Operational QA Program Manual (Voqam) ML20154B6951998-10-0101 October 1998 SER Re Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Vermont Yankee Nuclear Power Station BVY-98-149, Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Vermont Yankee Nuclear Power Station.With ML20239A1361998-09-0202 September 1998 SER Re License Request for NRC Review & Concurrence W/Changes to NRC-approved Fire Protection Program BVY-98-135, Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Vermont Yankee Nuclear Power Station.With ML20151U0361998-08-28028 August 1998 Non-proprietary Rev 1 to Holtec Rept HI-981932, Vermont Yankee Nuclear Power Station Spent Storage Expansion Project ML20237E9221998-08-20020 August 1998 Vynp 1998 Form NIS-1 Owners Summary Rept for ISI, 961103-980603 BVY-98-122, Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Vermont Yankee Nuclear Power Station ML20205F6491998-07-31031 July 1998 Rev 1 to GE-NE-B13-01935-02, Jet Pump Assembly Welds Flaw Evaluation Handbook for Vermont Yankee ML20236G0011998-06-30030 June 1998 Individual Plant Exam External Events BVY-98-098, Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Vermont Yankee Nuclear Power Station ML20248C5081998-05-31031 May 1998 Rev 2 to 24A5416, Supplemental Reload Licensing Rept for Vermont Yankee Nuclear Power Station Reload 19 Cycle 20 ML20248C4951998-05-31031 May 1998 Rev 1 to Vermont Yankee Nuclear Power Station Cycle 20 Colr BVY-98-081, Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Vermont Yankee Nuclear Power Station ML20247J8341998-05-31031 May 1998 Peak Suppression Pool Temp Analyses for Large Break LOCA Scenarios, for May 1998 ML20247G4001998-05-12012 May 1998 Interview Rept of Ej Massey ML20247E6351998-04-30030 April 1998 Rev 1 to GE-NE-B13-01935-LTR, Jet Pump Riser Welds Allowable Flaw Sizes Ltr Rept for Vermont Yankee 1999-09-30
[Table view] |
Text
- _ _ _ _ - _ _ _
VERMONT YANKEE '
NbCLEAR POWER CORPORATION
~ _.
P.O. Box 157, Governor Hunt Road (Y
s Vernon, Vermont 05354-0157 x
sf) s/
)
't J .- (802) 257-7711
'$$f
.. g , _
Febmary 10, 1993 VY-RCE-93-006 BVY 93-013 U.S. Nuclear Regulatory Commission Washington, D.C. 20:55 Attn: Document Control Desk
Reference:
a) License No. DPR-28 (Docket No. 50-271)
Dear Sir:
Submitted herewith is the Monthly Statistical Report for the Vermont
, Yankee Nuclear Power Station for the month of January 1993.
Very tmly yours, Vermont Yankee Nuclear Power Corporation rgo d --
" James P. Pelletier Vice President, Engineering cc: USNRC, Region I USNRC Resident Inspector, VYNPS DP 0411 Rev. 4 Page 1 of1 18 124 I
93021801Bx 930131 ,
PDR R
ADOCK 05000271 f,hy I PDR /v l
- - - - - _ . _ - _ _ - _ - - - _ _ _ _ _ _ __--_______ _ __ _ ___ Q
g, q
.4 . , 1 .. ;
.3.,-
af y:
E s
I k
<)-
VERMONT YANKEE NUCLEAR' POWER STATION . .
MONTIILY STATISTICAL REPORT 93-01. t
' FOR TIIE MONTII OF JANUARY 1993 7 c- . .
' DP 0411 Rev. 4 Page l 'of I :
s l - d
.: }
-)
[
'95 t . , s s , I 'd.,, J h
. x.
OPERATING DATA REPORT
,_ . DOCKET NO.50-271
.DATE-930210 COMPLETED BY G.A. WALLIN
- TELEPHONE '802)257-7711 OPERATING STATUS-
- 1. Unit Name: Vermont Yankee
- 2. Reporting Period: Janua ry.__ NOTES:
- 3. Licensed Thermal Power (MWt) 1593
- 4. Nameplate Rating (Gross MWe): EAR
- 5. Design Electrical Rating (Net MWe) : 514 (oc) 504 (cc) ,
6-. Maximum Dependable Capacity (Gross MWe) : 111
- 7. Maximum Dependable Capacity (Net MWe): EDA
- 8. If changes, occur in capacity ratings (Items Number 3 through 7) since last report, give reasons:
N/A
- 9. Po 'er level to which- restricted, if any(Net-MWe): N/A
- 10. Reasons for restrictions, if any: N/A This Month Yr-to-Date LCumulative
- 11. Hours in Reporting Period ~744.00 744.00' 176808.00
- 12. Number Of Hours Reactor was Critical 744.00 744.00 144940.35.
- 13. Reactor Reserve Shutdown Hours 0.00 0.00' O.00
- 14. Hours Generator On-Line 744.00 744.00. 141998;64-
- 15. Unit Reserve Shutdown Hours 0 . QQ.. 0.00 0 ~. 0 0 :
16.-Gross Thermal Energy Generated (MWH) -1184133.50 1184133.50 211255199.50
_17. Gross Electrical'Energ/ Generated 399919.00 399919.00l 70385077.00:
- 18. Net Electrical Energy Generated (MNH) 384517.00 304517.00 66859392'00 .
- 19. Unit Servica Factor 100~.00- 100 %QQ-_ 79.55'
- 20. Unit Availability Factor _ __
100.00 100.00 79.55'- _
- 21. Unit Capacity Factor (Using MDC Net) - 102.54_ 102.54 74.31E
- 22. Unit Capacity Factor (Using DER Net)- -100.55 100.55 ~ 72.87
=23.' Unit Forced Outage Rate 0.00 0.00 5.17
- 24. Shutdowns scheduled over next 6 months (Type,.Date, and Duration of--
Each: N/A ,
- 25. If sbut down at end of report period, estimated date of startup:N/A
- 26. Units In Test Stacus (prior to commercial operation) : N/A Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY _
COMMERCIAL OPERATION VYDPF 0411.01
' DP 0411 Rev. 4
. Page 1 of 1
' RT No. 13.F01.19F M -
ye
AVERAGE DAILY UNIT POWER LEVEL t .
DOCKET NO. 50-271 UNIT Vermont Yankee DATE 930210 COMPLETED BY G.A. WALLIN TELEPHONE _@D2)257-7711 MONTH ,_Qanparv DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
(MWe-Net)
- 1. 517 17, 3.17
- 2. 517 18, 517
- 3. 516 19. _ 519
- 4. 517 20. 517
, 5. 517
- 21. 517
- 6. 517 22. 517
- 7. 517 23, 517
- 8. 517 24. 517 ,
- 9. 517
)
- 25. 517 .
10, 516 26. 517 11, 536 27. 517
- 12. 516 28. 517
- 13. __ 516 29. 517 14, 516 30. 517
- 15. 516 4
- 31. 516 16, 517 INSTRUCTIONS:
On this format, list the average daily unit power level in MWF-Net for each day in the reporting month. Compute to the nearest whole megawatt.
VYDPF 0411.02 DP 0411 Rev. 4 Page 1 of 1 RT No. 13.F01,18V D
k
~
W UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH JANUARY DOCKET NO 50-271 -
UNIT NAME Vermont Yankee DATE 930210 COMPLETED BY G.A. Wallin TELEPHONE (802)257-7711 2 3 4 5 1 Cause and Corrective Duration Reason Method of License System Component No. Date Type Code Action to Prevent (hours) Shutting Event Code Down Report # Recurrence Reactor j
(None) h l 3 Method: 4 Exhibit G- Instructions 1 F: Forced 2 Reason: for Preparation of Data S: Scheduled A-Equipment Failure (Explain) 1 - Manual Entry Sheets for License B-Maintenance or Test 2 - Manual Scram 3 - Automat ic Scram Event Report (LER) File C-Refueling D-Regulatory Restriction 4 - Other (Explain) (NUREG 0161)
E-Operator Training and 5 Exhibit I - Same Source License Examination VYDPF 0411.03 F-Administrative DP 0411 Rev. 4 G-Operational Error (Explain)
Page 1 of 1 H-(Explain) -
I
.: 4 4-e,q_
DOCKET NO.S50-271
.DATE 930210--
=4'
, COMPLETED BY G.A. WALLIN =;
TELEPHONE (802)257-7711_.
REPORT MONTH Januarv
SUMMARY
OF OPER/1 TING EXPERIENCES Highlighta Vermont Yankee operated-at 9.3_,31 of. rated thermal power for the month.-
Gross electrical generation was 399.919-MWHe or 99.5% design electrical capacity.- ;
Operatinct Summary The_following_is a. chronological description _'of plant operations _ including l other pertinent items of interest for the month:
At the beginning of the reporting period the_ plant was operating at:99.9%-
of rated thermal power.
There were-no items of interest to report--for this month.
k
(
, .At the end of the reporting period the plant was operating at 99.9%.of-rated thermal power.
l s .
'~
VYDPF'0411.04 DP.0411 Rev. 4
- Page .1D of L 1 --
RT No. 13.F01.18X'