Notice of Violation from Insp on 960728-0907.Violation Noted:Licensee Failed to Demonstrate Operability of 1A EDG within Required Time After 1B EDG Was Determined to Be Inoperable
ML20128H663
Person / Time
Site: Mcguire, McGuire  Duke energy icon.png
Issue date: 10/02/1996
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20128H654 List:
References
50-369-96-07, 50-369-96-7, 50-370-96-07, 50-370-96-7, NUDOCS 9610100027
Download: ML20128H663 (2)


Text

. - - - - _ . . . - . - - - - - - . - - . - . - . . - - - . - - -

4 f

NOTICE OF VIOLATION Duke Power Company Docket Nos. 50-369 and 50-370 McGuire Nuclear Plant License Nos. NPF-9 and NPF-17 During an NRC inspection conducted on July 28 through September 7,1996, violations of NRC requirements were identified. In accordance with the

" General Statement of Policy and Procedure for NRC Enforcement Actions "

NUREG-1600, the violations are listed below:

A. Technical Specification 3.8.1.1 (d) requires that with a diesel generator ino)erable, the operability of the other diesel must be demonstrated )y performing surveillance requirement 4.8.1.1.2.a.4 and 4.8.1.1.2.a.5 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

1 Contrary to the above, on July 19, 1996. the licensee failed to demonstrate the operability of the 1A emergency diesel generator within the recuired time after the 1B emergency diesel generator was determinec to be inoperable.

This is a Severity Level IV violation (Supplement I).

B. 10 CFR 50.59 (a)(1) authorizes the licensee to conduct tests or experiments not described in the safety analysis report, without prior commission approval, unless the proposed test or experinent involves a change in the technical specifications incorporated in the license or an unreviewed safety question 10 CFR 50.59 (b)(1) requires the licensee to maintain reccrds of the conduct of tests and experiments not described in the safety analysis report. These records must include a written safety evaluation that provides the basis for the determination that the test or experiment did not involve an unreviewed safety question.

Contrary to the above, on August 6,1996, the licensee conducted a test not described in the FSAR to verify an operability determination that a water hammer event would not occur with the presence of steam voids in auxiliary feedwater piping. An adequate 50.59 safety evaluation to provide the basis for the determination that the test did not involve an unreviewed safety question was not performed prior to conducting this test.

This is a Seve-ity Level IV violation (Supplement I).

l Enclosure 1 1

9610100027 961002 gDR ADOCK 0500o369 PDR

- .. - ~ . -- _ - - - - - - - - - _ _ _ - - .-

Notice of Violation 2 l i C. 10 CFR 50 Appendix B. Criterion XVI. " Corrective Actions." states that measures shall be established to ensure that conditions

. adverse to quality.such as failures, malfunctions, deficiencies. l deviations, defective material and ecuipment, and nonconformances  ;

i are promptly identified and correctec. In the cases of l significant conditions adverse to quality, the measures shall assure that the cause of the condition is determined and 1

corrective action is taken to preclude repetition. l

) Contrary to the above, during the period from June 19. 1996, to i July 30. 1996, adequate corrective actions were not taken to  !

3reclude repetition of a fuel line coupling failure on the McGuire l Jnit 1 B Emergency Diesel Generator.

l i This is a Severity Level IV violation (Supplement I).

Pursuant to the provisions of 10 CFR 2.201. Duke Power Com)any is hereby ,

, required to submit a written statement or explanation to tie U.S. Nuclear  !

Regulatory Commission. ATTN: Document Control Desk. Washington. D.C. 20555 l with a copy to the Regional Administrator, Region II, and a copy to the NRC l i

Resident Inspector at the McGuire Nuclear Plant, within 30 days of the date of '

the letter transmitting this Notice of Violation (Notice). This reply should I

be clearly marked as a " Reply to a Notice of Violation" and should include for each violation: (1) the reason for the violation, or, if contested, the basis for disputing the violation. (2) the corrective steps that have been taken and

, the results achieved. (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved.

Your response may reference or include previous docketed correspondence, if the correspondence adequately addresses the recuired res)onse. If an adequate reply is not received within the time specifiec in this lotice, an order or

! Demand for Information may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be 3 roper i should not be taken. Where good cause is shown, consideration will 3e given to extending the response time.

Because your res)onse will be placed in the NRC Public Document Room (PDR) to the extent possi]le, it should not include any personal privacy. 3roprietary, or safeguards information so that it can be placed in the PDR witlout

redaction. However, if you find it necessary to include such information, you should clearly indicate the specific information that you desire not to be placed in the PDR and provide the legal basis to support your request for
withholding the information from the public.

Dated at Atlanta, Georgia this 2nd day of October, 1996

}

Enclosure 1 i