|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000348/19990051999-09-0202 September 1999 Insp Repts 50-348/99-05 & 50-364/99-05 on 990627-0807.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000348/19990041999-07-26026 July 1999 Insp Repts 50-348/99-04 & 50-364/99-04 on 990516-0626.One Noncited Violation Identified.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000348/19990031999-06-10010 June 1999 Insp Repts 50-348/99-03 & 50-364/99-03 on 990404-0515.No Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000348/19990021999-04-29029 April 1999 Insp Repts 50-348/99-02 & 50-364/99-02 on 990221-0403.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20205Q1721999-04-0606 April 1999 Partially Withheld Insp Repts 50-348/99-09 & 50-364/99-09 on 990308-10 (Ref 10CFR73.21).Non-cited Violation Identified. Major Areas Inspected:Area of Plant Support Re Physical Security Program for Power Reactors IR 05000348/19990011999-03-19019 March 1999 Insp Repts 50-348/99-01 & 50-364/99-01 on 990110-0220. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000348/19980081999-02-0202 February 1999 Insp Repts 50-348/98-08 & 50-364/98-08 on 981129-990109.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000348/19980141999-01-0808 January 1999 Partially Withheld Insp Repts 50-348/98-14 & 50-364/98-14 on 981207-10 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Procedures & Representative Records,Interviews with Personnel & Observations of Activities in Progress IR 05000348/19980071998-12-28028 December 1998 Insp Repts 50-348/98-07 & 50-364/98-07 on 981018-1128.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000348/19980061998-11-10010 November 1998 Insp Repts 50-348/98-06 & 50-364/98-06 on 980830-1017.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000348/19980101998-11-0303 November 1998 Insp Repts 50-348/98-10 & 50-364/98-10 on 980908-11.No Violations Noted.Major Areas Inspected:Observation & Evaluation of Biennial Emergency Preparedness Exercise & Response in Control Room Simulator & Technical Support Ctr IR 05000348/19980051998-09-28028 September 1998 Insp Repts 50-348/98-05 & 50-364/98-05 on 980712-0829.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19980041998-08-10010 August 1998 Insp Repts 50-348/98-04 & 50-364/98-04 on 980601-0711.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support ML20236J7021998-07-0101 July 1998 Insp Repts 50-348/98-03 & 50-364/98-03 on 980412-0530.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19980091998-05-11011 May 1998 Special Insp Repts 50-348/98-09 & 50-364/98-09 on 980323-25. Violations Noted.Major Areas Inspected:Follow Up on OI Rept 2-97-011 Issued on 980209 Re Improper Weld Repair IR 05000348/19980021998-05-0808 May 1998 Insp Repts 50-348/98-02 & 50-364/98-02 on 980221-0411.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19980011998-03-23023 March 1998 Insp Repts 50-348/98-01 & 50-364/98-01 on 980111-0221. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19970151998-02-0909 February 1998 Insp Repts 50-348/97-15 & 50-364/97-15 on 971130-980110. No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20198N9961997-12-29029 December 1997 Insp Repts 50-348/97-14 & 50-364/97-14 on 971019-1129. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000348/19970131997-11-20020 November 1997 Partially Withheld Insp Repts 50-348/97-13 & 50-364/97-13 on 971021-24 (Ref 10CFR73.21).Major Areas Inspected:Physical Security Program for Power Reactors ML20199H1541997-11-17017 November 1997 Insp Repts 50-348/97-11 & 50-364/97-11 on 970907-1018. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000348/19970071997-10-10010 October 1997 Insp Repts 50-348/97-07 & 50-364/97-07 on 970825-29.No Violations Noted.Major Areas Inspected:Licensee Corrective Action Program,Including Problem Identification & Resolution IR 05000348/19970101997-10-0606 October 1997 Insp Repts 50-348/97-10 & 50-364/97-10 on 970803-0906. Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000348/19970121997-09-26026 September 1997 Insp Repts 50-348/97-12 & 50-364/97-12 on 970818-22. Violations Noted.Major Areas Inspected:Review of Fire Protection Program Activities to Support Design Basis of Silicone Foam Fire Barrier Penetration Seals IR 05000348/19970081997-08-28028 August 1997 Insp Repts 50-348/97-08 & 50-364/97-08 on 970622-0802. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19970061997-07-18018 July 1997 Insp Repts 50-348/97-06 & 50-364/97-06 on 970511-0621.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20148K6511997-06-0909 June 1997 Insp Repts 50-348/97-05 & 50-364/97-05 on 970330-0510. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19972011997-05-13013 May 1997 Insp Repts 50-348/97-201 & 50-364/97-201 on 970127-0314.No Violations Noted.Major Areas Inspected:Engineering, Auxiliary Feedwater Sys,Component Cooling Water Sys & Sys Interface Design Review ML20138J6661997-04-28028 April 1997 Insp Repts 50-348/97-03 & 50-364/97-03 on 970216-0329. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support,Including Health Physics ML20137U6021997-04-0202 April 1997 Insp Repts 50-348/97-04 & 50-364/97-04 on 970125-0314. Violations Noted.Major Areas Inspected:Detailed Esfs Review & Walkdown of Units 1 & 2 PRF Sys,Including Associated Surveillance Test & Sys Design Requirements ML20140B7921997-03-17017 March 1997 Insp Repts 50-348/97-01 & 50-364/97-01 on 970104-0215. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19960151997-02-0303 February 1997 Insp Repts 50-348/96-15 & 50-364/96-15 on 961124-970104.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20134G3961997-01-24024 January 1997 Insp Repts 50-348/96-14 & 50-364/96-14 on 961209-13.No Violations Noted.Major Areas Inspected:Biennial Emergency Preparedness Exercise ML20133F6921996-12-23023 December 1996 Insp Repts 50-348/96-13 & 50-364/96-13 on 961013-1123. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20134J4391996-11-0808 November 1996 Insp Repts 50-348/96-09 & 50-364/96-09 on 960901-1012. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19960111996-10-11011 October 1996 Insp Repts 50-348/96-11 & 50-364/96-11 on 961007-11.No Violations Noted.Major Areas Inspected:Plant Support ML20128J9761996-09-27027 September 1996 Insp Repts 50-348/96-07 & 50-364/96-07 on 960721-0831. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering,Plant Support ML20128H8371996-09-27027 September 1996 Insp Repts 50-348/96-10 & 50-364/96-10 on 960812-16 & 26-30. Violations Noted.Major Areas Inspected:Radiation Monitoring Sys Radwaste Processing & Storage & Operational Radiation Protection Programs IR 05000348/19930301994-01-0606 January 1994 Insp Repts 50-348/93-30 & 50-364/93-30 on 931206-1210.No Violations or Deviations Noted.Major Areas Inspected: Process & Effluent Monitors,Post Accident Sampling Sys, Annual Radiological Environmental Operating Rept IR 05000348/19930291994-01-0505 January 1994 Insp Repts 50-348/93-29 & 50-364/93-29 on 931206-10.No Violations Noted.Major Areas Inspected:Observation & Evaluation of Annual Emergency Preparedness Exercise IR 05000348/19930281993-12-14014 December 1993 Insp Repts 50-348/93-28 & 50-364/93-28 on 931022-1122. Noncited Violation Identified.Major Areas Inspected:Licensee Operations,Maint/Surveillance Activities & Unit 2 Refueling Activities IR 05000348/19930251993-12-0202 December 1993 Insp Repts 50-348/93-25 & 50-364/93-25 on 931018-22 & 931101-05.Noncited Violation Identified.Major Areas Inspected:Sg Tubes,Review Laser Welding Procedures to Be Used for Securing Sleeves & Review Design Changes IR 05000348/19930271993-11-24024 November 1993 Insp Repts 50-348/93-27 & 50-364/93-27 on 931025-29.No Violations Noted.Major Areas Inspected:Licensee Corrective Actions for safety-significant Findings Identified During Electrical Distribution Sys Functional Insp IR 05000348/19930221993-11-17017 November 1993 Insp Repts 50-348/93-22 & 50-364/93-22 on 930925-1022.No Violations Noted.Major Areas Inspected:Maintenance, Surveillance,Industry Technical Issues,Event Repts,Unit 2 Refueling Activities & Continuing Review of self-assessment IR 05000364/19934001993-11-10010 November 1993 Insp Rept 50-364/93-400 on 931004-15.No Violations Noted. Majors Areas Inspected:Review of Licensee ISI Program Submittal & Nondestructive Exams of safety-related Weldments,Hanger & Supports Selected from SI IR 05000348/19930231993-11-10010 November 1993 Insp Repts 50-348/93-23 & 50-364/93-23 on 931012-15.No Violations Noted.Major Areas Inspected:Organization & Mgt Controls,Audits & Appraisals,External & Internal Control, Control of Radioactive Matl & Contamination IR 05000348/19930261993-11-0404 November 1993 Insp Repts 50-348/93-26 & 50-364/93-26 on Stated Dates. Violation Being Considered for Escalated Enforcement Action. Major Areas Inspected:Review of Plant Conditions Re Recent Listed Events IR 05000348/19930241993-11-0101 November 1993 Insp Repts 50-348/93-24 & 50-364/93-24 on 931012-15.No Violations or Deviations Noted.Major Areas Inspected:Isi, Including Nondestructive Exam Procedures & Observation of Work & Work Activities IR 05000348/19930211993-10-21021 October 1993 Insp Repts 50-348/93-21 & 50-364/93-21 on 930830-0925.No Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Industry Technical Issues,Event Repts,Unit 2 Refueling Activities & Licensee self-assessment ML20057E4981993-09-29029 September 1993 Insp Repts 50-348/93-13 & 50-364/93-13 on 930816-0903. Violations Noted.Major Areas Inspected:Sws 1999-09-02
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000348/19990051999-09-0202 September 1999 Insp Repts 50-348/99-05 & 50-364/99-05 on 990627-0807.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000348/19990041999-07-26026 July 1999 Insp Repts 50-348/99-04 & 50-364/99-04 on 990516-0626.One Noncited Violation Identified.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000348/19990031999-06-10010 June 1999 Insp Repts 50-348/99-03 & 50-364/99-03 on 990404-0515.No Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000348/19990021999-04-29029 April 1999 Insp Repts 50-348/99-02 & 50-364/99-02 on 990221-0403.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20205Q1721999-04-0606 April 1999 Partially Withheld Insp Repts 50-348/99-09 & 50-364/99-09 on 990308-10 (Ref 10CFR73.21).Non-cited Violation Identified. Major Areas Inspected:Area of Plant Support Re Physical Security Program for Power Reactors IR 05000348/19990011999-03-19019 March 1999 Insp Repts 50-348/99-01 & 50-364/99-01 on 990110-0220. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000348/19980081999-02-0202 February 1999 Insp Repts 50-348/98-08 & 50-364/98-08 on 981129-990109.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000348/19980141999-01-0808 January 1999 Partially Withheld Insp Repts 50-348/98-14 & 50-364/98-14 on 981207-10 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Procedures & Representative Records,Interviews with Personnel & Observations of Activities in Progress IR 05000348/19980071998-12-28028 December 1998 Insp Repts 50-348/98-07 & 50-364/98-07 on 981018-1128.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000348/19980061998-11-10010 November 1998 Insp Repts 50-348/98-06 & 50-364/98-06 on 980830-1017.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000348/19980101998-11-0303 November 1998 Insp Repts 50-348/98-10 & 50-364/98-10 on 980908-11.No Violations Noted.Major Areas Inspected:Observation & Evaluation of Biennial Emergency Preparedness Exercise & Response in Control Room Simulator & Technical Support Ctr IR 05000348/19980051998-09-28028 September 1998 Insp Repts 50-348/98-05 & 50-364/98-05 on 980712-0829.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19980041998-08-10010 August 1998 Insp Repts 50-348/98-04 & 50-364/98-04 on 980601-0711.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support ML20236J7021998-07-0101 July 1998 Insp Repts 50-348/98-03 & 50-364/98-03 on 980412-0530.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19980091998-05-11011 May 1998 Special Insp Repts 50-348/98-09 & 50-364/98-09 on 980323-25. Violations Noted.Major Areas Inspected:Follow Up on OI Rept 2-97-011 Issued on 980209 Re Improper Weld Repair IR 05000348/19980021998-05-0808 May 1998 Insp Repts 50-348/98-02 & 50-364/98-02 on 980221-0411.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19980011998-03-23023 March 1998 Insp Repts 50-348/98-01 & 50-364/98-01 on 980111-0221. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19970151998-02-0909 February 1998 Insp Repts 50-348/97-15 & 50-364/97-15 on 971130-980110. No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20198N9961997-12-29029 December 1997 Insp Repts 50-348/97-14 & 50-364/97-14 on 971019-1129. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000348/19970131997-11-20020 November 1997 Partially Withheld Insp Repts 50-348/97-13 & 50-364/97-13 on 971021-24 (Ref 10CFR73.21).Major Areas Inspected:Physical Security Program for Power Reactors ML20199H1541997-11-17017 November 1997 Insp Repts 50-348/97-11 & 50-364/97-11 on 970907-1018. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000348/19970071997-10-10010 October 1997 Insp Repts 50-348/97-07 & 50-364/97-07 on 970825-29.No Violations Noted.Major Areas Inspected:Licensee Corrective Action Program,Including Problem Identification & Resolution IR 05000348/19970101997-10-0606 October 1997 Insp Repts 50-348/97-10 & 50-364/97-10 on 970803-0906. Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000348/19970121997-09-26026 September 1997 Insp Repts 50-348/97-12 & 50-364/97-12 on 970818-22. Violations Noted.Major Areas Inspected:Review of Fire Protection Program Activities to Support Design Basis of Silicone Foam Fire Barrier Penetration Seals IR 05000348/19970081997-08-28028 August 1997 Insp Repts 50-348/97-08 & 50-364/97-08 on 970622-0802. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19970061997-07-18018 July 1997 Insp Repts 50-348/97-06 & 50-364/97-06 on 970511-0621.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20148K6511997-06-0909 June 1997 Insp Repts 50-348/97-05 & 50-364/97-05 on 970330-0510. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19972011997-05-13013 May 1997 Insp Repts 50-348/97-201 & 50-364/97-201 on 970127-0314.No Violations Noted.Major Areas Inspected:Engineering, Auxiliary Feedwater Sys,Component Cooling Water Sys & Sys Interface Design Review ML20138J6661997-04-28028 April 1997 Insp Repts 50-348/97-03 & 50-364/97-03 on 970216-0329. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support,Including Health Physics ML20137U6021997-04-0202 April 1997 Insp Repts 50-348/97-04 & 50-364/97-04 on 970125-0314. Violations Noted.Major Areas Inspected:Detailed Esfs Review & Walkdown of Units 1 & 2 PRF Sys,Including Associated Surveillance Test & Sys Design Requirements ML20140B7921997-03-17017 March 1997 Insp Repts 50-348/97-01 & 50-364/97-01 on 970104-0215. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19960151997-02-0303 February 1997 Insp Repts 50-348/96-15 & 50-364/96-15 on 961124-970104.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20134G3961997-01-24024 January 1997 Insp Repts 50-348/96-14 & 50-364/96-14 on 961209-13.No Violations Noted.Major Areas Inspected:Biennial Emergency Preparedness Exercise ML20133F6921996-12-23023 December 1996 Insp Repts 50-348/96-13 & 50-364/96-13 on 961013-1123. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20134J4391996-11-0808 November 1996 Insp Repts 50-348/96-09 & 50-364/96-09 on 960901-1012. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19960111996-10-11011 October 1996 Insp Repts 50-348/96-11 & 50-364/96-11 on 961007-11.No Violations Noted.Major Areas Inspected:Plant Support ML20128J9761996-09-27027 September 1996 Insp Repts 50-348/96-07 & 50-364/96-07 on 960721-0831. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering,Plant Support ML20128H8371996-09-27027 September 1996 Insp Repts 50-348/96-10 & 50-364/96-10 on 960812-16 & 26-30. Violations Noted.Major Areas Inspected:Radiation Monitoring Sys Radwaste Processing & Storage & Operational Radiation Protection Programs IR 05000348/19930301994-01-0606 January 1994 Insp Repts 50-348/93-30 & 50-364/93-30 on 931206-1210.No Violations or Deviations Noted.Major Areas Inspected: Process & Effluent Monitors,Post Accident Sampling Sys, Annual Radiological Environmental Operating Rept IR 05000348/19930291994-01-0505 January 1994 Insp Repts 50-348/93-29 & 50-364/93-29 on 931206-10.No Violations Noted.Major Areas Inspected:Observation & Evaluation of Annual Emergency Preparedness Exercise IR 05000348/19930281993-12-14014 December 1993 Insp Repts 50-348/93-28 & 50-364/93-28 on 931022-1122. Noncited Violation Identified.Major Areas Inspected:Licensee Operations,Maint/Surveillance Activities & Unit 2 Refueling Activities IR 05000348/19930251993-12-0202 December 1993 Insp Repts 50-348/93-25 & 50-364/93-25 on 931018-22 & 931101-05.Noncited Violation Identified.Major Areas Inspected:Sg Tubes,Review Laser Welding Procedures to Be Used for Securing Sleeves & Review Design Changes IR 05000348/19930271993-11-24024 November 1993 Insp Repts 50-348/93-27 & 50-364/93-27 on 931025-29.No Violations Noted.Major Areas Inspected:Licensee Corrective Actions for safety-significant Findings Identified During Electrical Distribution Sys Functional Insp IR 05000348/19930221993-11-17017 November 1993 Insp Repts 50-348/93-22 & 50-364/93-22 on 930925-1022.No Violations Noted.Major Areas Inspected:Maintenance, Surveillance,Industry Technical Issues,Event Repts,Unit 2 Refueling Activities & Continuing Review of self-assessment IR 05000364/19934001993-11-10010 November 1993 Insp Rept 50-364/93-400 on 931004-15.No Violations Noted. Majors Areas Inspected:Review of Licensee ISI Program Submittal & Nondestructive Exams of safety-related Weldments,Hanger & Supports Selected from SI IR 05000348/19930231993-11-10010 November 1993 Insp Repts 50-348/93-23 & 50-364/93-23 on 931012-15.No Violations Noted.Major Areas Inspected:Organization & Mgt Controls,Audits & Appraisals,External & Internal Control, Control of Radioactive Matl & Contamination IR 05000348/19930261993-11-0404 November 1993 Insp Repts 50-348/93-26 & 50-364/93-26 on Stated Dates. Violation Being Considered for Escalated Enforcement Action. Major Areas Inspected:Review of Plant Conditions Re Recent Listed Events IR 05000348/19930241993-11-0101 November 1993 Insp Repts 50-348/93-24 & 50-364/93-24 on 931012-15.No Violations or Deviations Noted.Major Areas Inspected:Isi, Including Nondestructive Exam Procedures & Observation of Work & Work Activities IR 05000348/19930211993-10-21021 October 1993 Insp Repts 50-348/93-21 & 50-364/93-21 on 930830-0925.No Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Industry Technical Issues,Event Repts,Unit 2 Refueling Activities & Licensee self-assessment ML20057E4981993-09-29029 September 1993 Insp Repts 50-348/93-13 & 50-364/93-13 on 930816-0903. Violations Noted.Major Areas Inspected:Sws 1999-09-02
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000348/19990051999-09-0202 September 1999 Insp Repts 50-348/99-05 & 50-364/99-05 on 990627-0807.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000348/19990041999-07-26026 July 1999 Insp Repts 50-348/99-04 & 50-364/99-04 on 990516-0626.One Noncited Violation Identified.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000348/19990031999-06-10010 June 1999 Insp Repts 50-348/99-03 & 50-364/99-03 on 990404-0515.No Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000348/19990021999-04-29029 April 1999 Insp Repts 50-348/99-02 & 50-364/99-02 on 990221-0403.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20205Q1721999-04-0606 April 1999 Partially Withheld Insp Repts 50-348/99-09 & 50-364/99-09 on 990308-10 (Ref 10CFR73.21).Non-cited Violation Identified. Major Areas Inspected:Area of Plant Support Re Physical Security Program for Power Reactors IR 05000348/19990011999-03-19019 March 1999 Insp Repts 50-348/99-01 & 50-364/99-01 on 990110-0220. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000348/19980081999-02-0202 February 1999 Insp Repts 50-348/98-08 & 50-364/98-08 on 981129-990109.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000348/19980141999-01-0808 January 1999 Partially Withheld Insp Repts 50-348/98-14 & 50-364/98-14 on 981207-10 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Procedures & Representative Records,Interviews with Personnel & Observations of Activities in Progress IR 05000348/19980071998-12-28028 December 1998 Insp Repts 50-348/98-07 & 50-364/98-07 on 981018-1128.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000348/19980061998-11-10010 November 1998 Insp Repts 50-348/98-06 & 50-364/98-06 on 980830-1017.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000348/19980101998-11-0303 November 1998 Insp Repts 50-348/98-10 & 50-364/98-10 on 980908-11.No Violations Noted.Major Areas Inspected:Observation & Evaluation of Biennial Emergency Preparedness Exercise & Response in Control Room Simulator & Technical Support Ctr IR 05000348/19980051998-09-28028 September 1998 Insp Repts 50-348/98-05 & 50-364/98-05 on 980712-0829.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19980041998-08-10010 August 1998 Insp Repts 50-348/98-04 & 50-364/98-04 on 980601-0711.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support ML20236J7021998-07-0101 July 1998 Insp Repts 50-348/98-03 & 50-364/98-03 on 980412-0530.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19980091998-05-11011 May 1998 Special Insp Repts 50-348/98-09 & 50-364/98-09 on 980323-25. Violations Noted.Major Areas Inspected:Follow Up on OI Rept 2-97-011 Issued on 980209 Re Improper Weld Repair IR 05000348/19980021998-05-0808 May 1998 Insp Repts 50-348/98-02 & 50-364/98-02 on 980221-0411.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19980011998-03-23023 March 1998 Insp Repts 50-348/98-01 & 50-364/98-01 on 980111-0221. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19970151998-02-0909 February 1998 Insp Repts 50-348/97-15 & 50-364/97-15 on 971130-980110. No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20198N9961997-12-29029 December 1997 Insp Repts 50-348/97-14 & 50-364/97-14 on 971019-1129. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000348/19970131997-11-20020 November 1997 Partially Withheld Insp Repts 50-348/97-13 & 50-364/97-13 on 971021-24 (Ref 10CFR73.21).Major Areas Inspected:Physical Security Program for Power Reactors ML20199H1541997-11-17017 November 1997 Insp Repts 50-348/97-11 & 50-364/97-11 on 970907-1018. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000348/19970071997-10-10010 October 1997 Insp Repts 50-348/97-07 & 50-364/97-07 on 970825-29.No Violations Noted.Major Areas Inspected:Licensee Corrective Action Program,Including Problem Identification & Resolution IR 05000348/19970101997-10-0606 October 1997 Insp Repts 50-348/97-10 & 50-364/97-10 on 970803-0906. Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000348/19970121997-09-26026 September 1997 Insp Repts 50-348/97-12 & 50-364/97-12 on 970818-22. Violations Noted.Major Areas Inspected:Review of Fire Protection Program Activities to Support Design Basis of Silicone Foam Fire Barrier Penetration Seals IR 05000348/19970081997-08-28028 August 1997 Insp Repts 50-348/97-08 & 50-364/97-08 on 970622-0802. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19970061997-07-18018 July 1997 Insp Repts 50-348/97-06 & 50-364/97-06 on 970511-0621.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20148K6511997-06-0909 June 1997 Insp Repts 50-348/97-05 & 50-364/97-05 on 970330-0510. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19972011997-05-13013 May 1997 Insp Repts 50-348/97-201 & 50-364/97-201 on 970127-0314.No Violations Noted.Major Areas Inspected:Engineering, Auxiliary Feedwater Sys,Component Cooling Water Sys & Sys Interface Design Review ML20138J6661997-04-28028 April 1997 Insp Repts 50-348/97-03 & 50-364/97-03 on 970216-0329. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support,Including Health Physics ML20137U6021997-04-0202 April 1997 Insp Repts 50-348/97-04 & 50-364/97-04 on 970125-0314. Violations Noted.Major Areas Inspected:Detailed Esfs Review & Walkdown of Units 1 & 2 PRF Sys,Including Associated Surveillance Test & Sys Design Requirements ML20140B7921997-03-17017 March 1997 Insp Repts 50-348/97-01 & 50-364/97-01 on 970104-0215. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19960151997-02-0303 February 1997 Insp Repts 50-348/96-15 & 50-364/96-15 on 961124-970104.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20134G3961997-01-24024 January 1997 Insp Repts 50-348/96-14 & 50-364/96-14 on 961209-13.No Violations Noted.Major Areas Inspected:Biennial Emergency Preparedness Exercise ML20133F6921996-12-23023 December 1996 Insp Repts 50-348/96-13 & 50-364/96-13 on 961013-1123. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20134J4391996-11-0808 November 1996 Insp Repts 50-348/96-09 & 50-364/96-09 on 960901-1012. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19960111996-10-11011 October 1996 Insp Repts 50-348/96-11 & 50-364/96-11 on 961007-11.No Violations Noted.Major Areas Inspected:Plant Support ML20128J9761996-09-27027 September 1996 Insp Repts 50-348/96-07 & 50-364/96-07 on 960721-0831. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering,Plant Support ML20128H8371996-09-27027 September 1996 Insp Repts 50-348/96-10 & 50-364/96-10 on 960812-16 & 26-30. Violations Noted.Major Areas Inspected:Radiation Monitoring Sys Radwaste Processing & Storage & Operational Radiation Protection Programs IR 05000348/19930301994-01-0606 January 1994 Insp Repts 50-348/93-30 & 50-364/93-30 on 931206-1210.No Violations or Deviations Noted.Major Areas Inspected: Process & Effluent Monitors,Post Accident Sampling Sys, Annual Radiological Environmental Operating Rept IR 05000348/19930291994-01-0505 January 1994 Insp Repts 50-348/93-29 & 50-364/93-29 on 931206-10.No Violations Noted.Major Areas Inspected:Observation & Evaluation of Annual Emergency Preparedness Exercise IR 05000348/19930281993-12-14014 December 1993 Insp Repts 50-348/93-28 & 50-364/93-28 on 931022-1122. Noncited Violation Identified.Major Areas Inspected:Licensee Operations,Maint/Surveillance Activities & Unit 2 Refueling Activities IR 05000348/19930251993-12-0202 December 1993 Insp Repts 50-348/93-25 & 50-364/93-25 on 931018-22 & 931101-05.Noncited Violation Identified.Major Areas Inspected:Sg Tubes,Review Laser Welding Procedures to Be Used for Securing Sleeves & Review Design Changes IR 05000348/19930271993-11-24024 November 1993 Insp Repts 50-348/93-27 & 50-364/93-27 on 931025-29.No Violations Noted.Major Areas Inspected:Licensee Corrective Actions for safety-significant Findings Identified During Electrical Distribution Sys Functional Insp IR 05000348/19930221993-11-17017 November 1993 Insp Repts 50-348/93-22 & 50-364/93-22 on 930925-1022.No Violations Noted.Major Areas Inspected:Maintenance, Surveillance,Industry Technical Issues,Event Repts,Unit 2 Refueling Activities & Continuing Review of self-assessment IR 05000364/19934001993-11-10010 November 1993 Insp Rept 50-364/93-400 on 931004-15.No Violations Noted. Majors Areas Inspected:Review of Licensee ISI Program Submittal & Nondestructive Exams of safety-related Weldments,Hanger & Supports Selected from SI IR 05000348/19930231993-11-10010 November 1993 Insp Repts 50-348/93-23 & 50-364/93-23 on 931012-15.No Violations Noted.Major Areas Inspected:Organization & Mgt Controls,Audits & Appraisals,External & Internal Control, Control of Radioactive Matl & Contamination IR 05000348/19930261993-11-0404 November 1993 Insp Repts 50-348/93-26 & 50-364/93-26 on Stated Dates. Violation Being Considered for Escalated Enforcement Action. Major Areas Inspected:Review of Plant Conditions Re Recent Listed Events IR 05000348/19930241993-11-0101 November 1993 Insp Repts 50-348/93-24 & 50-364/93-24 on 931012-15.No Violations or Deviations Noted.Major Areas Inspected:Isi, Including Nondestructive Exam Procedures & Observation of Work & Work Activities IR 05000348/19930211993-10-21021 October 1993 Insp Repts 50-348/93-21 & 50-364/93-21 on 930830-0925.No Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Industry Technical Issues,Event Repts,Unit 2 Refueling Activities & Licensee self-assessment ML20057E4981993-09-29029 September 1993 Insp Repts 50-348/93-13 & 50-364/93-13 on 930816-0903. Violations Noted.Major Areas Inspected:Sws 1999-09-02
[Table view] Category:UTILITY
MONTHYEARIR 05000348/19900281990-10-15015 October 1990 Insp Repts 50-348/90-28 & 50-364/90-28 on 900911-1012.No Violations Noted.Major Areas Inspected:Operational Safety Verification,Monthly Surveillance & Maint Observation,Info Meeting W/Local Officials & self-assessment Capability ML20059N3501990-09-14014 September 1990 Insp Repts 50-348/90-24 & 50-364/90-24 on 900827-31.No Violations or Deviations Noted.Major Areas Inspected:Actions in Response to NRC Bulletin 88-004, Potential Safety- Related Pump Loss IR 05000348/19900201990-08-23023 August 1990 Insp Repts 50-348/90-20 & 50-364/90-20 on 900711-0810.No Violations Noted.Major Areas Inspected:Operational Safety Verification,Monthly Surveillance & Maint Observation,Esf Sys Walkdown & LERs IR 05000348/19900211990-07-30030 July 1990 Insp Repts 50-348/90-21 & 50-364/90-21 on 900709-13.No Violations or Deviations Noted.Major Areas Inspected:Areas of Local Leak Rate Testing & Review of Previous Insp Findings.Five Open Items Re Leak Rate Testing Closed IR 05000348/19900171990-07-10010 July 1990 Insp Repts 50-348/90-17 & 50-364/90-17 on 900618-22.No Violations or Deviations Noted.Major Areas Inspected: Radiological Liquid & Gaseous Effluent Processing & Releases & Radiological Environ Monitoring Programs IR 05000348/19900041990-02-20020 February 1990 Insp Repts 50-348/90-04 & 50-364/90-04 on 900129-0202.No Violations or Deviations Noted.Major Areas Inspected: Followup of Open Items & Review of Activities Re Defects in Unit 1 Steam Generator Tube IR 05000348/19890181989-09-0707 September 1989 Partially Withheld Insp Repts 50-348/89-18 & 50-364/89-18 on 890731-0804 (Ref 10CFR2.790(d) & 10CFR73.21).Violations Noted.Major Areas Inspected:Physical Security Program for Power Reactor,Mgt Support,Security & Vital Area Barriers IR 05000348/19890191989-08-31031 August 1989 Insp Repts 50-348/89-19 & 50-364/89-19 on 890821-25.No Violations or Deviations Noted.Major Areas Inspected:Control Room Operator & Licensed Operator Requalification Training Programs Re How Tasks Analyzed & Objectives Derived IR 05000348/19890171989-08-24024 August 1989 Insp Repts 50-348/89-17 & 50-364/89-17 on 890724-28.No Violations or Deviations Noted.Major Areas Inspected:Design, Design Changes & Plant Mods.Administrative Procedures Weak in Description of Interfaces Between Plant Groups IR 05000348/19890161989-08-17017 August 1989 Insp Repts 50-348/89-16 & 50-364/89-16 on 890711-31.No Violations or Deviations Noted.Major Areas Inspected: Operational Safety Verification & Monthly Surveillance & Maint Observation.List of Backlog of Ungraded Exams Encl IR 05000348/19890101989-07-27027 July 1989 Insp Repts 50-348/89-10 & 50-364/89-10 on 890424-27 & 0508- 2.Violations Noted.Major Areas Inspected:Maint Program & Implementation IR 05000348/19890141989-07-26026 July 1989 Insp Repts 50-348/89-14 & 50-364/89-14 on 890611-0710.No Violations or Deviations Noted.Major Areas Inspected: Operational Safety Verification,Monthly Surveillance Observation,Operator Training,Work Schedule & LERs IR 05000348/19890121989-06-26026 June 1989 Insp Repts 50-348/89-12 & 50-364/89-12 on 890511-0610.No Violations or Deviations Noted.Major Areas Inspected: Operational Safety Verification,Monthly Surveillance Observation,Lers & Design Changes & Mods IR 05000348/19890131989-06-0505 June 1989 Insp Repts 50-348/89-13 & 50-364/89-13 on 890509-10. Violations Noted.Major Areas Inspected:Use of Contaminated Money to Catch Alleged Thief & Failure of Operator to Follow Procedural Requirements Re High Radiation Area ML20246B0261989-05-25025 May 1989 Insp Repts 50-348/89-11 & 50-364/89-11 on 890411-0510. Violations Noted.Major Areas Inspected:Operational Safety Verification,Monthly Surveillance Observation,Monthly Maint Observation,Lers & Unit 2 Startup from Refueling IR 05000348/19890081989-05-11011 May 1989 Insp Repts 50-348/89-08 & 50-364/89-08 on 890410-14.No Violations or Deviations Noted.Major Areas Inspected:Areas of Occupational Exposure,Shipping,Transportation,Solid Waste & Licensee Responses to Info Notices IR 05000348/19890091989-04-24024 April 1989 Insp Repts 50-348/89-09 & 50-364/89-09 on 890410-14.No Violations or Deviations Noted.Major Areas Inspected: Inservice Insp,Including Eddy Current Exam of Unit 2 Steam Generator Tubing & NDE Procedures IR 05000348/19890071989-04-19019 April 1989 Insp Repts 50-348/89-07 & 50-364/89-07 on 890311-0410. Violations Noted.Major Areas Inspected:Review of Operational Safety Verification,Monthly Surveillance Observation,Monthly Maint Observation,Design Changes & Mods & Insp of DHR IR 05000348/19890061989-03-23023 March 1989 Insp Repts 50-348/89-06 & 50-364/89-06 on 890227-0303.No Violations or Deviations Noted.Major Areas Inspected: Radiological Effluent Monitoring,Liquid & Gaseous Radwaste, Plant Chemistry & Plant Radiochemistry ML20236D1301989-03-10010 March 1989 Partically Withheld Insp Repts 50-348/89-03 & 50-364/89-03 on 890123-27 (Ref 10CFR73.21).Violation Noted:Vital Area Door Not Secured as Required in Physical Security Plan IR 05000348/19890031989-03-10010 March 1989 Partically Withheld Insp Repts 50-348/89-03 & 50-364/89-03 on 890123-27 (Ref 10CFR73.21).Violation Noted:Vital Area Door Not Secured as Required in Physical Security Plan IR 05000348/19890011989-03-10010 March 1989 Insp Repts 50-348/89-01 & 50-364/89-01 on 890206-10.No Violations or Deviations Noted.Major Areas Inspected: Emergency Preparedness,Including Emergency Plan & Implementing Procedures & Emergency Facilities & Equipment ML20236E2131989-03-0808 March 1989 Insp Repts 50-348/89-04 & 50-364/89-04 on 890206-10. Violation Noted.Major Areas Inspected:Radiation Protection Preparation for Unit 2 Refueling Outage Scheduled for 890324-0426 & Response to Info Notices IR 05000348/19890021989-02-24024 February 1989 Insp Repts 50-348/89-02 & 50-364/89-02 on 890111-0210. Violation Noted.Major Areas Inspected:Operational Safety Verification,Monthly Surveillance Observation,Monthly Maint Observation,Drawing Sys Verification & LERs IR 05000348/19880291988-11-23023 November 1988 Insp Repts 50-348/88-29 & 50-364/88-29 on 881011-1110.No Violations or Deviations Noted.Major Areas Inspected:Review of Operational Safety Verification,Monthly Surveillance Observation,Info Meeting W/Officials & Emergency Exercise IR 05000348/19880271988-10-28028 October 1988 Insp Repts 50-348/88-27 & 50-364/88-27 on 880926-30. Unresolved Item Noted.Major Areas Inspected:App R Compliance & post-fire Safe Shutdown Capability,Including Plant Mod Review & Reverification of App R Fire Protection Features IR 05000348/19880251988-10-12012 October 1988 Partially Withheld Insp Repts 50-348/88-25 & 50-364/88-25 on 880822-26 (Ref 10CFR2.790 & 73.21).Major Areas Inspected: Security Plan & Implementing Procedures,Mgt Effectiveness, Security Organization,Records & Repts & Testing & Maint IR 05000348/19880261988-09-26026 September 1988 Insp Repts 50-348/88-26 & 50-364/88-36 on 880811-0910. Violations Noted.Major Areas Inspected:Operational Safety Verification,Monthly Surveillance Observation,Engineered Safety Sys Insp & Previous Insp Findings IR 05000348/19880241988-08-19019 August 1988 Insp Repts 50-348/88-24 & 50-364/88-24 on 880711-0810. Violations Noted:Use of Inadequate Procedure to Calculate RCS Inventory Leakage.Major Areas Inspected:Monthly Maint & Surveillance Observations & LERs IR 05000348/19880191988-08-17017 August 1988 Revised Pages 8-12 to Insp Repts 50-348/88-19 & 50-364/88-19 Correcting Grammatical Errors & Incorrect Paragraphs ML20151L5841988-07-21021 July 1988 Insp Repts 50-348/88-23 & 50-364/88-23 on 880611-0710. Violations Noted.Major Areas Inspected:Monthly Surveillance Observation,Operational Safety Verification,Engineered Safety Sys Insp,Radiological Protection & Physical Security ML20151D6531988-07-0707 July 1988 Insp Repts 50-348/88-19 & 50-364/88-19 on 880511-0610.No Violations Noted.Major Areas Inspected:Review of Monthly Surveillance & Monthly Maint Observation,Operational Safety Verification & Physical Security Program IR 05000348/19880221988-07-0606 July 1988 Partially Withheld Insp Repts 50-348/88-22 & 50-364/88-22 on 880613-17 (Ref 10CFR2.790 & 73.21).No Violations or Deviations Noted.Major Areas Inspected:Vital Area Barriers, Assessment Aids & Access Control of Personnel ML20150C1281988-06-23023 June 1988 Insp Repts 50-348/88-20 & 50-364/88-20 on 880516-0610. Violation Noted.Major Areas inspected:post-refueling Startup Tests,Review of Completed Core Surveillance Procedures & Licensee Related Procedures IR 05000348/19880161988-06-0808 June 1988 Errata to Insp Repts 50-348/88-16 & 50-364/88-16 Revising App a to Correct Refs to Asco Solenoid Valves & Valve Numbers IR 05000348/19880181988-06-0202 June 1988 Insp Repts 50-348/88-18 & 50-364/88-18 on 880509-13.No Violations or Deviations Noted.Major Areas Inspected: Containment Tendon Surveillance Program,Snubber Surveillance Program,Ie Info Notice 85-045 IR 05000348/19880171988-05-26026 May 1988 Insp Repts 50-348/88-17 & 50-364/88-17 on 880502-06.No Violations or Deviations Noted.Major Areas Inspected: Inservice Insp Program Activities Associated W/Requested Relief from ASME Code Requirements.Unresolved Item Noted IR 05000348/19880151988-05-25025 May 1988 Insp Repts 50-348/88-15 & 50-364/88-15 on 880411-0510.No Violations or Deviations Noted.Major Areas Inspected:Reviews Previous Enforcement Matters,Montly Surveillance Observation & Montly Maint Observation ML20154P6001988-05-19019 May 1988 Insp Repts 50-348/88-10 & 50-364/88-10 on 880328-0511. Violations Noted.Major Areas Inspected:Liquid & Gaseous Radwaste Mgt,Effluent Monitoring & Followup on Unresolved Item ML20154P6241988-05-17017 May 1988 Insp Repts 50-348/88-16 & 50-364/88-16 on 880419-21.No Violations or Deviations Noted.Major Areas Inspected:Environ Qualification of Electrical Equipment & Followup of Unresolved Items IR 05000348/19880141988-05-11011 May 1988 Insp Repts 50-348/88-14 & 50-364/88-14 on 880411-15.No Violations or Deviations Noted.Major Areas Inspected:Unit 1 Inservice Insp Activities,Including Remote Ultrasonic Exam of Reactor Vessel Welds IR 05000348/19880051988-05-11011 May 1988 Insp Repts 50-348/88-05 & 50-364/88-05 on 880222-26 & 0307-11.Violations Noted.Major Areas Inspected:Evaluation of Effectiveness of Various Plant Groups Including Operations, Maint,Qa,Engineering & Training for Safe Plant Operation IR 05000348/19880131988-05-10010 May 1988 Insp Repts 50-348/88-13 & 50-364/88-13 on 880404-08. Deviation Noted.Major Areas Inspected:Fire Protection & Prevention IR 05000348/19880111988-04-22022 April 1988 Insp Repts 50-348/88-11 & 50-364/88-11 on 880328-31.No Violations or Deviations Noted.Major Areas Inspected: Documentation Review for Welding Activities & NDE Re Safety Injection Sys IR 05000348/19880081988-04-21021 April 1988 Insp Repts 50-348/88-08 & 50-364/88-08 on 880311-0410.No Violations or Deviations Noted.Major Areas Inspected:Review of Monthly Surveillance Observation,Monthly Maint Observation & Physical Security Program ML20151N8811988-04-13013 April 1988 Partially Withheld Insp Repts 50-348/88-09 & 50-364/88-09 on 880321-24 (Ref 10CFR2.790 & 73.21).Violation Noted.Major Areas Inspected:Security Organization,Records,Repts,Testing, Maint,Locks,Keys,Combinations & Physical Barriers IR 05000348/19880011988-03-31031 March 1988 Insp Repts 50-348/88-01 & 50-364/88-01 on 880104-07.No Violations or Deviations Noted.Major Areas Inspected: Allegations Re Facility ML20148M9511988-03-28028 March 1988 Insp Repts 50-348/88-07 & 50-364/88-07 on 880211-0310.No Violations or Deviations Noted.Major Areas Inspected:Review of Monthly Surveillance & Maint Observations,Radiological Protection Program & Physical Security Program ML20148E6271988-03-16016 March 1988 Insp Repts 50-348/88-06 & 50-364/88-06 on 880229-0304. Violations Noted.Major Areas Inspected:Operational Readiness of Site Emergency Preparedness Program & to Determine If Changes to Emergency Preparedness Meet NRC Requirements ML20148E3571988-03-0101 March 1988 Insp Repts 50-348/87-37 & 50-364/87-37 on 871216-18.Util Noted One Violation Re Employee Failure to Sign in on Radiation Work Permit.Major Areas Inspected:Followup on Allegations Pertaining to Radiation Protection Program 1990-09-14
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000348/19990051999-09-0202 September 1999 Insp Repts 50-348/99-05 & 50-364/99-05 on 990627-0807.No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000348/19990041999-07-26026 July 1999 Insp Repts 50-348/99-04 & 50-364/99-04 on 990516-0626.One Noncited Violation Identified.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20210H1591999-07-23023 July 1999 Notice of Violation from Insp on 990308-10.Violation Noted: from Time of Receipt of Alarm Until Arrival at Three Different Vital Areas,Response Objective & Physical Security Plan Were Not Met IR 05000348/19990031999-06-10010 June 1999 Insp Repts 50-348/99-03 & 50-364/99-03 on 990404-0515.No Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000348/19990021999-04-29029 April 1999 Insp Repts 50-348/99-02 & 50-364/99-02 on 990221-0403.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support ML20205Q1721999-04-0606 April 1999 Partially Withheld Insp Repts 50-348/99-09 & 50-364/99-09 on 990308-10 (Ref 10CFR73.21).Non-cited Violation Identified. Major Areas Inspected:Area of Plant Support Re Physical Security Program for Power Reactors IR 05000348/19990011999-03-19019 March 1999 Insp Repts 50-348/99-01 & 50-364/99-01 on 990110-0220. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000348/19980081999-02-0202 February 1999 Insp Repts 50-348/98-08 & 50-364/98-08 on 981129-990109.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support IR 05000348/19980141999-01-0808 January 1999 Partially Withheld Insp Repts 50-348/98-14 & 50-364/98-14 on 981207-10 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Procedures & Representative Records,Interviews with Personnel & Observations of Activities in Progress IR 05000348/19980071998-12-28028 December 1998 Insp Repts 50-348/98-07 & 50-364/98-07 on 981018-1128.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000348/19980061998-11-10010 November 1998 Insp Repts 50-348/98-06 & 50-364/98-06 on 980830-1017.No Violations Noted.Major Areas Inspected:Licensee Operations, Maint,Engineering & Plant Support IR 05000348/19980101998-11-0303 November 1998 Insp Repts 50-348/98-10 & 50-364/98-10 on 980908-11.No Violations Noted.Major Areas Inspected:Observation & Evaluation of Biennial Emergency Preparedness Exercise & Response in Control Room Simulator & Technical Support Ctr IR 05000348/19980051998-09-28028 September 1998 Insp Repts 50-348/98-05 & 50-364/98-05 on 980712-0829.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19980041998-08-10010 August 1998 Insp Repts 50-348/98-04 & 50-364/98-04 on 980601-0711.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support ML20236J6971998-07-0101 July 1998 Notice of Violation from Insp on 980412-0530.Violation Noted:Several Conditions Adverse to Quality Associated W/Cr Ventilation Sys Were Not Promptly Corrected.Conditions Inappropriately Closed Out Before Adequate C/As Completed ML20236J7021998-07-0101 July 1998 Insp Repts 50-348/98-03 & 50-364/98-03 on 980412-0530.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support ML20236J8121998-06-29029 June 1998 SALP Repts 50-348/98-99 & 50-364/98-99 Covering Period 961124-980530 IR 05000348/19980091998-05-11011 May 1998 Special Insp Repts 50-348/98-09 & 50-364/98-09 on 980323-25. Violations Noted.Major Areas Inspected:Follow Up on OI Rept 2-97-011 Issued on 980209 Re Improper Weld Repair IR 05000348/19980021998-05-0808 May 1998 Insp Repts 50-348/98-02 & 50-364/98-02 on 980221-0411.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19983001998-04-0606 April 1998 NRC Operator Licensing Exam Repts 50-348/98-300 & 50-364/98-300 (Including Completed Tests) for Exams Administered on 980312-13.Concluded Candidates Performance on Written & JPM re-take Exams Satisfactory ML20217E5921998-03-23023 March 1998 Notice of Violation from Insp on 980111-0212.Violation Noted:While Performing Maint on 1A Centrifugal Charging Pump,Maint Personnel Violated Requirements of FNP-0-M-001, Rev 13 IR 05000348/19980011998-03-23023 March 1998 Insp Repts 50-348/98-01 & 50-364/98-01 on 980111-0221. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support PNO-II-98-013, on 980308,util Declared NOUE Due to High River Level & Subsequent Flooding.Licensee Established Constant Communications W/Early,Ga & Houston County,Al.Resident Inspectors Are Monitoring Licensee Activities1998-03-0909 March 1998 PNO-II-98-013:on 980308,util Declared NOUE Due to High River Level & Subsequent Flooding.Licensee Established Constant Communications W/Early,Ga & Houston County,Al.Resident Inspectors Are Monitoring Licensee Activities IR 05000348/19970151998-02-0909 February 1998 Insp Repts 50-348/97-15 & 50-364/97-15 on 971130-980110. No Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20198N9961997-12-29029 December 1997 Insp Repts 50-348/97-14 & 50-364/97-14 on 971019-1129. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support ML20198N9481997-12-29029 December 1997 Notice of Violation from Insp on 971019-1129.Violation Noted:As Early as June 1985,licensee Identified Degradation of Cork Seal Between Containment & Auxiliary Bldg Walls, Condition Adverse to Quality IR 05000348/19970131997-11-20020 November 1997 Partially Withheld Insp Repts 50-348/97-13 & 50-364/97-13 on 971021-24 (Ref 10CFR73.21).Major Areas Inspected:Physical Security Program for Power Reactors ML20199H1281997-11-17017 November 1997 Notice of Violation from Insp on 970907-1018.Violations Noted:Battery Capacity After Svc Test Was Inadequate & Check Valve V003 & V002D F & H Were Not Flow Tested in Manner That Proves That Disk Travels to Seat on Cessation ML20199H1541997-11-17017 November 1997 Insp Repts 50-348/97-11 & 50-364/97-11 on 970907-1018. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000348/19970071997-10-10010 October 1997 Insp Repts 50-348/97-07 & 50-364/97-07 on 970825-29.No Violations Noted.Major Areas Inspected:Licensee Corrective Action Program,Including Problem Identification & Resolution IR 05000348/19970101997-10-0606 October 1997 Insp Repts 50-348/97-10 & 50-364/97-10 on 970803-0906. Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support ML20211Q9391997-10-0606 October 1997 Notice of Violation from Insp on 970803-0906.Violation Noted:As of 970906 Licensee Installed One 1-inch Thick Wrap of Kaowool on Sides & Bottoms of Raceways BDE-9 & BDE-15, Carrying Train B Charging Pump Power Cable in Fire Area IR 05000348/19970121997-09-26026 September 1997 Insp Repts 50-348/97-12 & 50-364/97-12 on 970818-22. Violations Noted.Major Areas Inspected:Review of Fire Protection Program Activities to Support Design Basis of Silicone Foam Fire Barrier Penetration Seals ML20211K8161997-09-26026 September 1997 Notice of Violation from Insp on 970818-22.Violation Noted: Noted:Nrc Identified That Licensee Failed to Correctly Translate Applicable Design Specfication Input Requirements for Kaowool Electrical Raceway Fire Barrier Sys at Plant IR 05000348/19970081997-08-28028 August 1997 Insp Repts 50-348/97-08 & 50-364/97-08 on 970622-0802. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support ML20217R2021997-08-28028 August 1997 Notice of Violation from Insp on 970622-0802.Violation Noted:On 970616,most of M&TE Used Onsite Did Not Have Written & Approved Calibration Procedures PNO-II-97-039A, on 970720,Hurricane Danny Downgraded to Depression.Storm Disipated Without Reaching Farley Nuclear Plant.Farley Nuclear Plant Experienced Light Rain W/Both Units Remaining at Full Power1997-07-21021 July 1997 PNO-II-97-039A:on 970720,Hurricane Danny Downgraded to Depression.Storm Disipated Without Reaching Farley Nuclear Plant.Farley Nuclear Plant Experienced Light Rain W/Both Units Remaining at Full Power PNO-II-97-039, on 970718,response Was Made to Hurricane Danny.Region II State Liason Officer Has Been in Contact W/Fema & State of Al.Plant Staff Taking Precautionary Measures in Preparation for High Wind Conditions1997-07-18018 July 1997 PNO-II-97-039:on 970718,response Was Made to Hurricane Danny.Region II State Liason Officer Has Been in Contact W/Fema & State of Al.Plant Staff Taking Precautionary Measures in Preparation for High Wind Conditions IR 05000348/19970061997-07-18018 July 1997 Insp Repts 50-348/97-06 & 50-364/97-06 on 970511-0621.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20148K6431997-06-0909 June 1997 Notice of Violation from Insp on 970330-0510.Violation Noted:On 970321,facility Licensee Physician Determined That Licensed Operator Eyesight No Longer Met Min Stds Required by 10CFR55.33(a)(1) as Measured by Std of ANSI/ANS-3.4-1983 ML20148K6511997-06-0909 June 1997 Insp Repts 50-348/97-05 & 50-364/97-05 on 970330-0510. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000348/19972011997-05-13013 May 1997 Insp Repts 50-348/97-201 & 50-364/97-201 on 970127-0314.No Violations Noted.Major Areas Inspected:Engineering, Auxiliary Feedwater Sys,Component Cooling Water Sys & Sys Interface Design Review ML20196G4241997-05-0606 May 1997 Notice of Violation from Insp Completed on 970314.Violation Noted:Prior to 970314,licensee Failed to Prescribe Documented Instructions or Procedures to Implement Listed Activities Affecting Quality of Operation of PRF Sys ML20138J6661997-04-28028 April 1997 Insp Repts 50-348/97-03 & 50-364/97-03 on 970216-0329. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support,Including Health Physics IR 05000348/19973001997-04-22022 April 1997 Exam Repts 50-348/97-300 & 50-364/97-300 on 970324-27.Exam Results:Two of 5 Applicants Passed Exam.One Was Grades as Marginal Pass ML20137U6021997-04-0202 April 1997 Insp Repts 50-348/97-04 & 50-364/97-04 on 970125-0314. Violations Noted.Major Areas Inspected:Detailed Esfs Review & Walkdown of Units 1 & 2 PRF Sys,Including Associated Surveillance Test & Sys Design Requirements ML20140B7851997-03-17017 March 1997 Notice of Violation from Insp on 970105-0215.Violation Noted:Test Engineer Failed to Comply W/Procedural Requirements of FNP-1-STP-124.0 During Performance Testing of Plant Penetration Room Filtration Sys Train a ML20140B7921997-03-17017 March 1997 Insp Repts 50-348/97-01 & 50-364/97-01 on 970104-0215. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000348/19960151997-02-0303 February 1997 Insp Repts 50-348/96-15 & 50-364/96-15 on 961124-970104.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20134G3961997-01-24024 January 1997 Insp Repts 50-348/96-14 & 50-364/96-14 on 961209-13.No Violations Noted.Major Areas Inspected:Biennial Emergency Preparedness Exercise 1999-09-02
[Table view] |
See also: IR 05000348/1985017
Text
r- 2
a
.
UNITED STATES "
i , [ pet att\;
-
'
' NUCLEAR REGULATORY COMMISSION
-g -
, REGION II
g 'j^ 101 MARIETTA STREET, N.W.
~
ATLANTA, GEORGI A 30323
.
...../
' Report Nos.: 50-348/85-17 and 50-364/85-17
Licensee:- Alabama-Power Company _ '
'600 North 18th Street
[, : Birmingham AL 35291
Docket Nos.: 50-348 and 50-364 License Nos.: NPF-2 and NPF-8
Facility Name: Farley 1 and 2'
Inspection Conducted: March 18-22, 1985
. Inspection at' Farley site near Dothan, Alabama
.
Inspectors: -
7
L. E. Foster Team Leader Date Signed
Y [
N._Merriwe fier D8te Signed-
EW /??L /O/ 7-ff
H. Bibb
-
'
Date Signed
. .
JConsultant: P.-M. Ch -Lawrence Livermore National Laboratory i
, , .;
Approved by /
~ T. E.' Conlon, SecTion Chief
.
- -#g Aft / YDate/ Signed.
7- f[ - ( ~,
"
, . Engineering Branch
.
'
Division of Reactor Safety
'
3'
. ~t ,
, ,
SUMMARY
'
'
E >
.< ,
-
>;
E>. Scope: This routine, announced inspection entailed 135 inspector-hours at the
- ' site concerning licensee response to Generic. Letter 83-28 Required Actions Based
,' *
L.,
~
on Generic Implications of- Salem Anticipated Transient without Scram (ATWS)-
Events. Areas inspected included: post-trip review; equipment classification;)
<-
, ivendor~ interface and manual control; post-maintenance testing; and reactor trip
, ,
system reliability.
- -
- *
i Results: One violation was identified - Failure to-Follow Procedure FNP-0-AP-52
.i i on Maintenance Work Request No. 107514 - paragraph 8.c.
. .
7
'505210037 850423
9
'
'
PDR ADOCK 05000348
G PDR
i
[
!.
'
. ... -
. .
.
REPORT DETAILS
1.- Persons Contacted
Licensee Employees
- D. N. Morey, Assir tant Plant Manager - Operations
- W. B. Shipman, Assistant Plant Manager - Support
- B. R. Yance, Section Supervisor - Electrical
- W. G.. Ware, Safety Audit Engineering Review (SAER) Supervisor
- L. A. Ward, Maintenance Superintendent
L. Williams, Training Representative
L. Bradshaw, General Plant Technical Service (GPTS) Supervisor
- R. D. Hill, Operations Supervisor
K. Kendricks, General Plant Technical Service (GPTS) Technician
C. Nesbitt, Technical Superintendent
J. R. Gibson, Electrician Foreman
S. Taylor, Electrician
R. Rogers, Computer Services Supervisor
L. M. Stinson, Modification Supervisor
R. G. Berryhill, System Performance and Planning Superintendent
J. Hudspeth, Document Control Supervisor
J.. Luckie, Electrician
R. Cobb, Document Control
- P. W. Trotter, Systems Engineer
R. Morrow, Planner-
-D. Sherer, Planner
H. R. Garland, Mechanical Supervisor
T. W. Cherry, I&C Supervisor
- B. W. Vanlandingham, Unit 2 Supervisor
L. Enfinger, Materials Supervisor
R. Johnson, Systems Engineer
Other licensee employees contacted included engineers, technicians,
operators, mechanics, electricians, security force members, and office
personnel.
NRC Resident Inspector
W. Bradford, Senior Resident Inspector
'
2. Exit Interview
The inspection scope and findings were summarized on March 22, 1985, with
those. persons indicated in paragraph 1 above. The inspectors described the
areas inspected and discussed in detail the inspection findings listed
below. The licensee had dissenting comments which are discussed in
paragraph 8.c.
-A
Violatibn 348/85-17-02,. Failure to Follow .. Procedure FNP-AP-0-52 on
Maintenance Work Request No.~107514 - paragraph 8.c.
. Inspector' Followup Item 348, 364/85-17-01 Training Licensed Operators on
Interpretation of Printout Data - paragraph 5.
Inspector Followup Item 348, 364/85-17-03, Review of Vendor Manuals (DS-416
Breakers) To Determine Applicability to the As-Installed DS-416 Breakers -
paragraph 7._ 1
Inspector . Followup Item 348, 364/85-17-04, Review of . Vendor Manual
.No. U212498 and Revision Notices to Ensure Incorporation of Approved
Revisions - paragraph 7.
Inspector Followup Item. 348, 364/85-17_05 . Evaluate and Revise Procedure
MP-28.114 to Include all Vendor Recommended Measurements and Include
-
Measuring Equipment List'in the Procedure - paragraph 8.
-The licensee did not identify as proprietary any of the material provided to
or reviewed _ by the inspectors during this inspection.
3. Licensee Action on Previous Enforcement Matters
This subject was not addressed in the inspection.
4. Background-
In February 1983, the Salem Nuclear Power Station experienced two failures
of the reactor trip system upon the receipt of trip signals. These failures
were attributed to Westinghouse - Type DB-50_ reactor trip _ system (RTS)
circuit breakers. The failures at Salem on February 22 and 25, 1983, were
believed to have been caused-by a binding action within the undervoltage
l-
.
trip attachment (UVTA) located inside the breaker cubicle. Due to problems.
-
L of the circuit breakers at Salem'and at other plants, NRC issued Generic
Letter 83-28, Required Action Based on Generic Implementations of Salem ATWS
Events, dated July 8, 1983. This letter required the licensees to respond
j on immediate-term actions to ensure reliability of the RTS.- Actions to be '
L performed included development of programs to provide for post-trip review,
i classification of equipment, vendor interface, post-maintenance testing,.and
RTS reliability improvements. . The -licensee responded to Generic Letter
83-28 by correspondence with the following dates: September 6 and
November 4,1983; and February 6, February 15, and June 25, 1984. This
.
inspection was performed to review Alabama Power Company (APCOs) current
l _ program, planned program improvements, and implementation of present
'
procedures associated with post trip review equipment classification, vendor
interface, post maintenance testing, and reactor trip system reliability for
.the Joseph M. Farley Nuclear Plant - Units 1 and 2.
i
,
. . . . . . - . . . - _ - . ~.
,
'
- -
'
.. .
.,
..' 3
L_
I
!
5. . Post-Trip Review
'
The licensee was requested in_GL-83-28 to describe their program procedures
_
- . and _ data collection _ capbility- to assure that the causes for unscheduled
reactor shutdowns, as well;as the response of safety-related equipment, are '
fully understood prior to plant restart. The_ licensee's response to
GL 83-28 :gives' a detailed -description of the program - and procedures
.
pertinentL to performing post-trip - reviews. The inspector reviewed their
~
3
resp'onse. appropriate procedures, and interviewed responsible licensee
4
personnel to assess. the adequacy of the licensee's program for post-trip
reviews. The result of this inspection are identified below:
The licensee has prepared and revised several procedures to more clearly
define responsibilities, authorities, methods of assessment, training, and
equipment needed to perform a timely technical post-trip review.
' Administrative Procedure FNP-0-AP-16,' Revision 13. " Conduct of Operations -
Operations Group," provides a clear and concise description of the actions
to .be taken by the shift supervisor subsequent to a reactor trip. These
actions include:
Ensure that the plant is placed in a safe condition (Reactor Trip
~
.a.
Procedure FNP-1-E0P-5.0)
b. Notify the Emergency Director
c. Make other off-site notifications as required
'd. Direct a review of plant conditions prior to,_ during, and subsequent to
.
the trip to detennine the cause and to verify proper operation' of all
systems
Administrative Procedure FNP-0-AP-30, Preparation and Processing of Incident
Reports, Plant Event Reports and Licensee Event Reports, specifies ,the
'
requirements for the preparation and processing of reports. A Reactor. Trip ,
Report and Incident-Report must be completed upon a reactor trip and the
Emergency Director must give permission prior to returning the-reactor to a
critical state. If the review and analysis by the Shift Supervisor does not
positively determine the cause of the transient or verify proper operation
and response of the reactor and associated equipment systems, it will be the
responsibility of the on-call Emergency. Director to determine the need for,
and the. appropriate individuals or group for, independent assessment of the
trip.
The completed Reactor Trip . Report 'must be accompanied by the computer
post-trip printout, the alarm typewriter printout, the sequence of events,
and incident report. This package is prepared by the shift supervisor,
reviewed by the_ Operations Supervisor, Unit Supervisor and Technical Group
' Supervisor, and finally reviewed within 30 days by the Systems Performance
Supervisor.
t
= _. _______ _ ____ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ . - -
-
- .
-
4'
The.planIfor return to power includes (a) any corrective action required to
correct the cause of the trip, (b) any maintenance required and (c) any
surveillances required to change modes. Other plant procedures associated
with post-. trip review were examined and are listed below:
'
FNP-1-E0P-5.0 Reactor Trip
FNP-1-E0P-15.0 Anticipated Transients Without Trip (ATWT)
FNP-0-AP-3 Plant Organization and Responsibility
FNP-0-AP-45 FNP Training Plan
-Plant personnel involved with the preparation or review of post trip review
documentation receive initial . and refresher training in post-trip review
- procedures through a formal program for licensed operators. FNP-0-AP-16
delineates the qualifications and training required for personnel
participating in the post-trip review process. Specific duties of key
individuals are identified in FNP-0-AP-3 and FNP-0-AP-16.
Discussions with the training department indicated that formalized training
has been conducted for the engineering staff in the systems performance
group on the interpretation of information available from the sequence of
events and post-trip printouts. Further discussions revealed that the above
formal training was not being given to the licensed operators. Until formal
training on the interpretation of information available from the Sequence of
Events and Post-Trip printouts is incorporated into licensed operator
training, this will be considered an Inspector Followup Item 348,
364/85-17-01, Training on Interpretation of Printout Data.
A review of training records revealed that records of initial and
requalification training were being maintained.
The sources of plant information necessary to conduct a review and analysis
of a transient causing an unscheduled reactor trip include:
a. The plant computer alarm typewriter printout,
b. The plant computer sequence of event report,
l c. The post-trip report,
j d. The main control board recorders,
!
e. An interview of on-duty plant operators,
- f. The plant operator's log,
g. The listing of any outstanding limiting condition of operation, and
h. The listing of any major maintenance currently in progress.
In the event that the plant computer alarms typewriter (sequence of events
j recorder)' is out of service, the computer will automatically dump its
information to the following printers in descending order of preference:
a. Trend typewriter
i b. Line printer
j c.. Auxiliary typewriter
l
l
, - -
. _ _ _ ,
m
-
. .
5
The licensee stated that the capability to gather and analyze post-trip data
and gain:more precise time separation between distinct occurrences will be
enhanced with the installation of the safety parameter display system, which
is expected to be installed in mid-1986.
The post-trip review package, after completion of review by the system
'
performance group, ;is forwarded to document control for permanent retention
within 30 days of the trip. Additionally, a 1.icensee event report (LER) is~
< generated for~each reactor trip. The inspector reviewed 11 post-trip review
packages to- verify thoroughness of preparation and proper preservation of-
physical evidence needed to perform post-trip reviews. While it.was found
' that all necessary. data were preserved, it was noted that- the record keeping
' was - a bit fragmented and difficult to track down. A given-incident is.
. presently filed in' the-Quality Control (QC) vault by two different methods,-
'(a) by the incident report number and (b).by_the reactor-trip number. [The
supporting evidence is sometimes filed with (a) and other times with (b).
The disadvantage of not using a singular filing method was discussed with.
thelicensee.]
-The inspector inquired and found that incident reports, reactor-trip
-
reports, and Licensee Event Reports (LERs) are routed through the training
department for possible incorporation into site specific simulator training
for new or.requalified licensed operators. The classic ATWS incidents are
also simulated for training purposes.
-
Within the areas examined, no violations or deviations were identified.
6. Equipment Classification
.-The inspector reviewed the licensee's response-which described their program
for equipment classification. Their response described the following:
The- program for identifying safety-related systems and components at Farley
is contained within plant procedures, design procedures, the- Operations
Quality Assurance Policy Manual, and Section 17.3 of the APC0 Final Safety
Analysis Report (FSAR). The systems utilized by the licensee to identify
safety-related components consists of the Q-list, safety-related
classification numbering, design documents, and prior procurement packages.
The inspector conducted a review of appropriate licensee procedures and
records and interviewed responsible licensee personnel to confirm that the
licensee's program for equipment classification was adequate and consistent
with their response to Generic' Letter 83-28. The inspector confirmed that
. the licensee's program for equipment classification iceluded the following
-elements:
Plant and component controls for classification of structures, systems,
and components as safety-related were being implemented.
~
. . .
-
.6
' The-licensee has devel'oped a program-to assure that safety-related .or
non-safety-related maintenance activities are identified during the-
~
planning stage.
The 'Q-Listing' is' reviewed by design personnel during the modification.
process .to' determine -if the; modification affects safety-related
structures, systems or components.
Personnel participating in: activities impacting safety-related
structures, systems, and components were aware of the appropriate level
of QA controls.
i- Written directives. assigned principal responsibility for. satisfactory
- completion of procurement, maintenance, and modification activities
associated with safety-related structures, systems, and components.
' Repairs, - maintenance, or modifications to equiptient to correct
. failures, malfunctions, ' deficiencies, deviations, defective- material
and equipment, and nonconformances were performed, documented, and
reviewed to determine reliability of replacement components.
L The inspector examined the following procedures and docuaents:
Administrative Procedure FNP-0-AP-52, Equipment Status Control and
Maintenance Authorization
'
- Administrative Procedure FNP-0-AP-8, Design Modification Control
- Administrative Procedure FNP-0-AP-9, Procurement and Procurement
2 Document Control
Q-List, Section 17.3 of FSAR-
i-
l : Maintenance Work Requests Nos.-101440, 101441, 101442,.101443, 35789,
K 37166, 24040,.19393, and 88454
Purchase Order Nos. 13627 and 35957~
Plant Change Notice PCN-B-83-2410
Maintenance Procedure FNP-0-NP-28.114, Inspection, Maintenance and
, Testing of Reactor-Trip Breakers
a .
L The information systems utilized at Farley Plant to identify safety-related
!
- components are identified as follows:
'
Safety-related Q-List contained in Section 17.3 of the FSAR
l'
Total Plant Numbering System Safety-Related Classification Numbering
l
I'
l
,
J.t, -. -- - 3 p.m, .-..-,r..-s,#,,-, . . - c , ., ,-..w-- ,,-w, . - - >
-
, - . - - - . . - - - , . . , . < - .
.m
-
. .
~
.
7
Prior _ Procurement Packages *
Design Documents
The FNP Q-List identifies safety-related systems, major components,
supports, and structures. The Q-List also . identifies categories of
safety-related components which are not explicitly identified within the
Q-List. Changes and additions to the Q-List are initiated by design changes
' to the . plant. .The Q-List is controlled and updated as part of the FSAR.
~
- The Q-List is considered by the inspector to be very general ..in detail. The
-licensee acknowledged .the inspector's observations and stated that manage-
-ment was considering'developement of a more detailed Q-List.
The Total iPlant Numbering System ('TPNS) is another method used by the
licensee.~ for. identifying safety-related or nonsafety-related components.
EThe TPNS. classification numbering is assigned by the licensee's design
l organizations as part of the design process. The TPNS numbers consist of a-
"Q" or. "N" prefix followed by a unit designator (i.e, Unit 1 or 2), a
three-character code for identifying the system, and additional characters
which identify the component type and unique. component identification. The
TPNS numbers for safety-related components are identified with a "Q" prefix-
and nonsafety-related components are-identified with a "N" prefix. The TPNS
~
classification numbering is given in design documents such as the electrical
equipment index,- instrument index, _ design drawings, and equipment
specifications.-
Discussions with the licensee-revealed that the reactor-trip breakers do not
have unique TPNS numbers. The TPNS numbers are assigned to each train of
the reactor trip switchgear. In addition, the TPNS numbers assigned to the
- reactor trip switch and full length ~ rod motion control switch have
non-safety; TPNS numbers._ The . inspector asked the licensee ~ if. these
nonsafety. TPNS . numbers would be upgraded to safety-related. The licensee
indicated that there were no plans to revise the TPNS numbers for these
components at this time.
4
'
The licensee's Administrative Procedure FNP-0-AP-52 is the procedure used
for identifying, . controlling, scheduling, authorizing and documenting
maintenance. ~This procedure requires the TPNS number and equipment name be
~1dentified on the Maintenance Work Request (MWR)-Form.- The TPNS number is
used . by the licensee on the MWR form to identify safety-related or -
'
nonsafety-related equipment. The TPNS number is the only safety
'
_ classification given on the MWR fonn. The reviews and approvals required
for ' safety-related and nonsafety-related maintenance work requests are
p basically.the same. However, one distinguishing difference exists on the
handling of MWRs for safety-related equipment that cannot be functionally
tested following completion of, work due to plant conditions. The procedure
also identifies critical plant systems and the special pre and.
post-maintenance requirements.
,
9
O-.
-
- .
~
8
The. inspector'~ selected MWRs 101440, 101441, 101442 and 101443 - which
-described work to be done on the Undervoltage Trip Attachment (UVTA). These
- MWRs' were examined to verify that the maintenw:e activities were performed -
and . documented in accordance with procedure FNP-0-AP-52. ~The above MWRs
.were issued to replace the UVTAs on the reactor trip breakers for Unit 2.
Replacement of the UVTAs . eliminated the requirement to cool the UVTAs with.
compressed N2fduring performance of surveillance procedures STP-33.2A and B
to lower the resistance of. the coil so that breaker closing could be
accomplished. All records were found to be documented and approved in
'accordance with the above procedure.
- Administrative Procedure FNP-0-AP-9 is the procedure used by the licensee to
' administratively control the procurement of assemblies, parts, material,
supplies,'and services. This procedure applies to both safety-related and
. ~ nonsafety-related procurement of components and services. The procedure
t provides criteria- to determine the -QA review codes and the safety
,
classification for assemblies, parts and services. The procedure identifies -
.the following QA code classes:
~
~
.
Code A. Safety-Related or Nonsafety-Related .
'
4
Code C, Nonsafety-Related
, Code D.-Nonsafety-Related ;
The procedure references the Q-List, Westinghouse NSSS Spare Parts Report, ,
and ANSI N18.2-1973 as documents to use in making the QA Code determinations '
! and safety classifications. In addition, the procedure gives description of ,
categories of assemblies, sub-assemblies and parts that are considered
'
,
. safety-related and QA Code A. Likewise, the procedure provides descriptions-
'
.of the' components that are considered QA Codes Class C and D. The procedure
,. also provides controls .for the review, approval, revision 'and storage .of
procurement documentation. - The inspector reviewed the records associated
with purchase order Nos.13627 and.35957 to verify compliance with the above
procedure. Records examined were documented, reviewed and approved in
, accordance with procedures.
'
Within the areas examined, no violations or deviations were identified.
-7. Vendor. Interface and Manual Control
The inspector reviewed the licensee's response which described their program
for vendor interface and control of vendor technical information. Their
response described the following program:
-Licensee response dated February'15,1984, stated that the majority of the
.NSSS components were originally supplied by Westinghouse (W) and that
current -updates were supplied by W Technical Bulletins. l'he licensee
-acknowledges receipt of the information by written confirmation. All
technical information received from other vendors which has an impact on
, ; plant design, maintenance, and safe operation is distributed to appropriate
i - . licensee organizations, Bechtel, and Southern Company Services for review
and action..
i.
.
-
.~ -._.___a . . _ _ . _ . _ . _ , _ . _ _ _ . , _ _ . _ - . .__-.,_1
,-
T
.
&
.
g
-
.
f
Further-licensee f responses dated June 25,1984, stated that APC0 is an
active member of the Nuclear Utility Task Action Committee (NUTAC) which has
formulated the Vendor Equipment Technical Information Program (VETIP). This
program utilizes existing utility / vendor contact, the. Institute _of Nuclear
Power : Operations (INPO) managed Nuclear Plant Reliability Data. System
- (NPRDS),' and Significant Event Evaluation and Information Network (SEE-IN)-
' Program.
The inspector reviewed licensee procedures relative to control of vendor ~
- technical information to determine if they were consistent with his
responses.- Results of examination of procedures 'and interviews with
personnel revealed the following:
a. The licensee had not contacted every vendor of safety-related equipment
to: determine if the vendor technical manuals on site contained the
latest technical information, but was using information from the INP0
administered NPRDs and SEE-IN Programs. Westinghouse was contacted and
.the licensee held extensive meetings concerning NSSS equipment. The
licensee had also contacted Colt Industries and General Electric
Company (GE) concerning equipment supplied _by them. The licensee had
developed some procedures to ensure adequate review of technical
infomation received, and the control and use of this information by
~p lant_ personnel,
b .~ - The licensee had developed Administrative Procedure FNP-0-AP-65, -FNP
Operating Experience Evaluation Program. The objective of this program
was to ensure that lessons learned from industry were used at FNP'and
that lessons learned at FNP were transmitted to other licensees.
Fomal vendor infomation programs have been established with W, GE and
-
Colt Industries'. The licensee has a special group (NETS) that receives
technical information and transmits this information to the System
Performance Group for action. Other groups have. been assigned
responsibilities for reporting, reviewing, and ' utilizing technical
information from such as W Owners Group, INPO, NRC, and vendors.
,
c._ FNP-0-AP-65, Revision 3 dated February 7,1985, assigns plant staff
responsibilities for assuring that vendor technical information is
properly evaluated and handled. This procedure also lists applicable
plant procedures which control and further describe the responsibili-
ties for receiving, distribution, transmittal, and use of vendor
technical information originating from vendors, INP0, other industry
sources, W. Owners Groups, and FNP sources. Paragraph 16 of the
procedure assigns the QC Supervisor the responsibility of perfoming a
program effectiveness review on an annual basis. The inspector
questioned why some technical manuals had not been reviewed per AP-65.
Discussions revealed that vendor manual review verification was only
being performed on new technical manuals and revisions to old manuals.
Based on review of this procedure, the licensee appears to have
,
o
-
. .
-
10
,
provided a means to effectively evaluate .and control current vendor'
technical information; however, the massive amount of old vendor.-
manuals, bulletins, etc., may present problems if not reviewed and
deemed applicable to installed equipment.
d. Administrative Procedure FNP-0-AP-4, Control of Plant Documents and
Records, . Revision 8, .was. presently undergoing review- by the plant
-
staff. This procedure establishes controls to assure satisfactory -
receipt, processing, distribution, storage, and retention of documents
including vendor manuals and other correspondence related- to vendor
technical information. The procedure review request form from AP-1 and
,
' the 10 CFR 50.59 evaluation for AP-4 were reviewed and found to be
satisfactory. AP-4 and AP-65 appear to ensure control of documents and
records. The inspectors examined selected technical manuals, plant
procedures, the control and use of these manuals,' and procedures to
-determine if the controls were adequate and being implemented. Two
Inspector Followup Items were identified and are discussed in the
following details.
e. Examination of Technical Manuals (Instruction Books) Associated with
the Low Voltage Switchgear (Type DS-416 Breakers) revealed the-
following:
-(1) The same manuals are filled under different "U" numbers thereby-
making it difficult to determine which manuals are- valid,
-
up-to-date, and applicable to the installed equipment.
(2)- Measurements _to be taken during maintenance and testing of the
' breakers are not consistent in each instruction book (IB). An
example is that the measurement of the gap between the stationary
arcing contacts is not required in IB U260232A and IB U215471A but
is required in IB U185040.
(3) Two different Architect Engineers have reviewed and approved the
switchgear IBs without documented interfacing.
(4) -It is not apparent that the switchgear IBs (older IBs) have been
reviewed per AP-65. The licensee's statement that the plant
procedures reflect the current IB technical information was not
attached to the IBs.- Note: AP-65 only requires new IBs or
revisions to old IBs be reviewed.
(5) Instruction Books did not- contain a chronological list of
revisions or applicable changes implemented; therefore, a
. component history file was not readily available.
The licensee agreed to review the current instruction books being used
to determine if the IBs reflect the as-installed DS-416 breakers. This
is considered Inspector Followup Item 50-348/364-85-17-03, Review of
Vendor Manuals of D5-416 Breakers.
-
t-
. .
'
11
f.- - Other technical manuals (Instruction Books), vendo'r correspondence, A/E
correspondence, and' review approval forms were reviewed in the Central
File Area are listed below:
IB No.'U185040, controlled copy No. 40
IB No. U276623
Volume
Services Letter dated 3, Book
January 314, T985W Instruments and Southern Company
IB No. U184699, Plant Lighting Switch' gear, Controlled Copy No. 2
IB No. U184789 and.260098, Indoor Low Voltage Metal Enclosed Switchgear
IB No. U185031, Switchgear Renewal Parts Data, Controlled Copy No. 003.
This manual had been updated by a supplement dated July 1981
. Technical Data Transmittal Sheets from Bechtel and Southern Company
Services concerning incorporation cf Plant Change Notices (PCNs) and
Plant Change Requests (PCRs) into technical manuals
Vendor Manual / Drawing Review forms confirming plant departments review
of manual Nos. U162880, 162888, 176697, 184852, 198768, and U214177
The Central File also maintains a computer list of who has checked out
a controlled manual and if the user has returned the copy within the
14-day requirement. Document transmittal form (AP-4, App. B) is used
to transmit documents and record receipts of documents. To further
assure manual control, the Document Control Supervisor issued a letter
dated March 20, 1985, to all supervisors requesting them to review and
verify that the manuals in their possession agree with the current
transmittal form.- Central Files keeps a file card (pink card) on each
manual ~ and keeps updated with the latest revision number and date
received. Central Files personnel were knowledgeable of procedures.
-retrieved documents in a timely manner, and demonstrated the appli-
cation of the document control program,
g. The inspector examined the documentation packet which contained-
information on the H Inner-Cooled Turbine Generator, W
Instruction Book (IB)ydrogen
20891 U No. 212498. Although this is a
nonsafety-related component, this examination was made to determine if
a typical document packet contained the latest information such as
revisions, approval forms, change notices, and vendor correspondence.
Results of examination revealed that the document packet contained
instruction books, three revision sheets, insert instructions, a list
of PCNs affecting the instruction book, status of PCNs (approved or
completed), review foms . signed by Bechtel and Southern Company
Services, and vendor a letter notifying licensee of a manual change.
Further examinations included a detailed check of the IB contents
against the approved revision changes to determine if the approved
._ _ _ .
!
-
. .
12
- changes were being incorporated into the IBs. This review revealed-
that Revision 2.of the Hydrogen Wiring Diagram, No. 1124J51 Figure 1A,
' had been userted into the . IB .without technical justification for.
deleting Revision 1 and . inserting Revision 2.- The licensee agreed to
review the subject IBs and. plant procedures associated with the
Hydrogen System to assure that. technical data has been incorporated.
-This,is Inspector Followup Item 50-348,364/85-17-04, Review of Manual
.No. U212498 and Revisions.
<
Within the areas examined, no violations or deviations were identified.
'
'8. . Post-Maintenance Testing
.
.
i
The inspector reviewed the licensee's post-maintenance testing procedures- ,
'
and activities to verify that the commitments in the licensee's response to
. Generic Letter.83-28 were being implemented at Farley Nuclear Plant. -The i
-inspector examined procedures 'and completed maintenance records,
participated inLa complete maintenance and test of a DS-206 Westinghouse
circuit breaker, and interviewed pertinent licensee personnel to determine
the adequacy of the licensee's post-maintenance test program. The results
of the inspection are as follows:
a. Demonstration
Maintenance Procedure FNP-0-MP-28.114. was used to - demonstrate a
complete (walk-through) maintenance and test on a DS-206, 800A frame
circuit breaker. This type of Westinghouse breaker is similar to the
DS-416, 1600 A frame . breaker used in the reactor trip protection
system. The main differences were the DS-206. breaker used in the
.'~
. demonstration did not have an undervoltage trip attachment and an
operations counter.
In the course of the inspection of the breaker contact. system, as -
delineated in paragraph 4.8.1 of MP-28.114, the inspector noted that
'
'
the licensee's test engineer did not physically perform a measurement ,
of the gap " dimension A" as specified in paragraph 4.8.1. of the ,
procedure which stated that the gap must exceed 0.020 inches. The test !
, engineer visually observed the gap dimension and determined that the
i gap exceeded 0.020 inches and recorded it. The inspector questioned
<
the method of measuring and was advised that the gap in question was so ,
obviously over 20 mil that an actual measurement was unnecessary. The
iL inspector requested that -an appropriate gauge be used to confinn the
!
dimension; however, a suitable feeler gauge could not be located until
[ the next day. Subsequent measurements by feeler gauges of six gaps
! revealed readings of 0.080, 0.071, 0.071, 0.049. 0.033, and 0.025 ,
! . inches. . It was noted by the inspector that the 0.033 and 0.025 inch l
'
l measurements were not obviously over 0.020 inch as gauged by the human
- eye. The inspector questioned the accuracy of the gap measurements
,
L
[ I
t
i
!
l
_ _ _ . . _ . _ . . _ .
_____._ _ _.
_ . _ _ . _ _ . . _ _
. ,
13
'I
,
- taken on previously inspected breakers. Review of data and discussions
with supervisors revealed that previous gap measurements were performed
with a feeler gauge. and . the gap dimension exceeded 0.020 inch as
required. The' use of measuring equipment is discussed further in this
-
report.
Also 'during' the demonstration of the maintenance and testing of the
DS 206 circuit. breaker, the inspector noted the electrician applied the
lubricant with his forefinger and smeared it around the levering device
arm. on the breaker. The licensee was advised that this was. poor
practice as the lubricant and mechanism becomes contaminated when
applied by the fingers. A review of the procedure revealed that the
application of lubricant and solvents is left to the technician's
judgment which is another poor practice.
Trending ~ of parameters from Maintenance Procedure FNP-0-MP-28.114 was
non-existent at the Farley Nuclear Plant. Although GL 83-28 specifi-
cally stated in paragraph 4.2 that the licensee's preventative mainte-
nance program shall include trending of parameters measured during
testing to forecast _ degradation of operability, the licensee only
trends failures and since at Farley there was no failure to date, no.
trending.had been done. The use and effectiveness of trending parame -
'ters (besides failures) were discussed with the licensee and they were
advised that their response did not adequately address trending;
however, the resolution of their response would be performance by NRC.
Nuclear Regulation Branch.
b. Procedure Review
Procedure FNP-0-MP-28.114, Inspection, Maintenance and Testin
Reactor Trip Breakers, Revision 5, was reviewed to determineif (1)g
theof
. procedure reflected vendor technical manual requirements and (2) if the
procedure, if implemented, would help assure reliability of operation.
Results of the procedure review revealed the following:
(1) Reference 2.2 in the procedure has a typographical error as the
Field Mounting Instruction should be W Drawing 588C785 instead of
588C784. This appears to be a minor error, but copld result in
problems if the referenced drawing were used.
(2) Paragraph 4.3 allows the technician to determine what solvent to
use and to determine if the solvent will damage the electrical
component. Approved solvent should be specified by engineering.
(3) Paragraph 4.8, Inspection of Contact System, nor Attachment 4
requires the dimension between the arcing contacts to be measured;
however, vendor Instruction Book U No. 185040 specifies that this
gap dimension be 0.42 1.080 inches. The vendor's instruction
books U260232A and U215471A do not require that the gap measure-
ments be taken.
1
_
__ _ _ _ _ _ - _ _ _ _ _-- .__
,
..
.
-
_ .
.3
.: -
14
-
j (4) Paragraph ~4.8.1 does not specify. how. dimension "A" will be veri-
- fied that it exceeds'0.020 inches, nor how the 1/32" thickness of
the main. contacts will be. measured. No tools are specified in the
- text or in the data sheets. _ The technicians -did not have 'any
3! -
measuring tools to demonstrate measuring or to confirm that the
,
t
,
- gap
- dimension exceeded 0.020 inches.
(5) Paragraph 4.9.3.1 does not specify how the 0.030 inch dimension is
measured or..what type of instrument is needed. Also the statement
"theLgap should be 0.030 minimum" should be similar to the state-
- ment in paragraph 4.8.1, " Dimension A must exceed 0.020 inches."
-These statements could result in misinterpretation by the proce-
dure ~ users.
-(6) Paragraph 4.19 specifies:the type of lubricant to be used and some .
precautions; however, no caution is made concerning the contami-
,
nation of lubricant if applied by. fingers.
! -(7) Some special tools (bent wire gages) are used but are not speci-
l - fied .in the procedure. The above items. were discussed with
l licensee personnel. Justification for not.specifying measuring
! tools and how to measure the required dimensions was presented to
'
the inspectors; however, the licensee agreed to re-evaluate the
procedure in regard to the inspector's concerns and to revise the
procedure as necessary. Until the procedure is reevaluated, this
is Inspector Followup Item 50-348, 364/85-17-05, Evaluate and
Revise Procedure-FNP-0-MP-28.114.
Other procedures reviewed are listed below:
Administrative Procedure FNP-0-AP-1, Development, Review and
Approval of Plant Procedures, Revision 16.
Administrative Procedures FNP-0-AP-65, FNP Operating Experi-
ence Evaluation Program, Revision 3.
Surveillance Test Procedure FNP-1-STP-640, Containment Spray
Pump Discharge Check Valve (Q1E13V002A and B) Full Stroke
Test, Revision 1.
Maintenance Procedure FNP-1MP-49.0, Inspection and Repair of
Accumulation Discharge Check Valve Q1E21V032A, B or C,
Revision B.-
Instrument Maintenance Procedure FNP-0-IMP-438.3, Valve
.
-Actuator and I/P Calibration-(Generic)3 9evision 0.
Instrument Maintenance Procedure FF-0 MP-206.9, RHR Bypass
Flow control Q2E11FT0605A, Revf a a 4.
,
l _ __.___ ______ ________ - m
_ _ _
-
. .
15
c. Review of Maintenance Work Request (MWR)
The' inspectors examined - several safety-related MWRs and associated
procedures to determine procedure . adequacy and implementation. One
-violation and several concerns associated with the processing and
implementation of MWRs were identified and are discussed below:
(1) ~ MWR 62891 - Repair of Check Valve - dated 1/21/83
(a) Check Valve Inspected TPNS Number was not entered on both
pages 1 and 2 of the completion sheets. The licensee ex-
plained this as an oversight and that the ' number would be
entered on both pages.
(b) On page 1 of the completion sheet, a signature was used to
sign off the line on the valve body cleaning. However, the
date was left out. The licensee explained this as an over-
sight and that the importance of dating documents signed
would be discussed with plant personnel.
(2) MWR 83484, Maintenance on Containment Spray Pump Check Valve,
dated 1/4/84
No problems were identified with this MWR,
-(3) MWR 107514, Main Feed Regulator Bypass Valve IC, dated 3/13/85
(a) Item No. 20, " Clearance for Work," was not checked off as
specified in Section 7.5.3 of FNP-0-AP-52. The fact that
such clearance information could have been incorporated into
Item No. 33 did not apply in this case. It was stated'in
Item No. 33 that no special plant conditions need be required
for the work. Clearance for work was not alluded to in Item
No. 33. The licensee explained at the exit meeting that this
was an oversight; however,'the inspectors feel that Item 33
means operating plant conditions and has no connection with
Item 20, clearance for work. The licensee agreed to review
the procedure and revise to eliminate misinterpretations.
(b) Item No. 23, " Work Sequence," originally referenced the
use of Procedure IMP-215.14. Upon review of the data pack-
age, the inspector noted that Procedure IMP-438.3, had been !
used, instead of 215.14, without the MWR being revised and j
re-approved as required by Section 7.5.16.1 of FNP-0-AP-52. '
This is considered a violation. The licensee disagreed with
this violation and stated that the procedure was only a
'
reference; therefore, the MWR did not have to be revised to ,
indicate the new procedure (IMP-438.3). The licensee also !
_ ___ _ _ _______ _ . _ . . - - __ __ . --
.
. .
' -
16
,
stated that NRC inspectors were misinterpreting their admin-
,
istrative procedures; however, the licensee committed to
-
revise Procedure FNP-AP-0-52 to clarify how references are to
be used when specified on Maintenance. Work Requests. The
inspectors acknowledged the licensee's comments and agreed-
that further clarification to the procedure'would be appropri-
ate. ! At the conclusion of the exit, this item was considered -
an Inspector Followup Item; however, subsequent in-office
review and evaluation of this matter concluded that the
-
licensee violated Procedure FNP-AP-0-52, Revision 5.
The licensee was informed of this violation by telecon on
April 15,1985. This is identified as Violation 348/85-17-02,
Failure to Follow Procedure FNP-AP-0-52 on Maintenance Work
Request-No. 107514. In addition to the above, the. inspectors
, - had concerns on the adequacy of " adjust as needed" to
describe the work sequence as this instruction could lead to
,
personnel-errors and mis-adjustment of equipment.
.(4) MWR 107679, RHR.HX Bypass. Flow Control, dated 3/11/85
(a) One page 2 of the data package, both " Table 1" and " Table 2"
are listed on :the same page, are directly adjacent to each
other thus making page 2 very congested. The licensee stated
that Table 2 would be deleted.
(b) The standard data package consists of 'nine pages which are
normally needed to complete a maintenance . test. Since this
MWR necessitates a limited amount of work on the equipment,
it appeared to warrant the use of a partial- data package
which consisted of four pages. It was nevertheless noted on
+ the front page that the data package contained nine pages;
however, only four pages could be found in the package. The
reasons for including all nine pages in the data package and
marking ' the sheets not needed as "NOT APPLICABLE" was dis-
cussed with the licensee.
z9.
'
Surveillance Testing Of The Diverse Reactor Trip Functions of the Reactor
TripSwitchgear(RTS)
The inspector confirmed that the licenseeJs surveillance procedures require
-
Ltesting of the shunt trip attachment and the licensee verifies the ability
, to manually' trip the RTS ' breakers by independent use of the undervoltage
trip attachment ^ or shunt trip device. The surveillance procedures are
. identified as follows:
Surveillance Test Procedure, STP-33.2A, Reactor Trip Breaker Train A
Operability Test
Surveillance Test Procedure, STP-33.2B, Reactor Trip Breaker Train B
Operability Test.
'
,
.
.
.- . _ _ ,
.-
~'
17
,
- Discussion with the -licensee revealed that Plant Change Notices PCN -
83-1-1421,.PCN 83-2-2410 and PCN 84-2-2589 installed the automatic shunt
.
trip actuation device on the reactor trip systems for Units 1 and 2. The
inspector reviewed data package PCN 83-2-2410 for Unit 2. The data package
. appeared to be adequate.
Within the areas examined, no violations or deviations were identified.
4 .
f
4