Forwards Application for Amend to License & Ts,Eliminating Selected Response Time Testing Requirements
ML20112D560
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/30/1996
From: Harry Salmon
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20112D563 List:
References
JPN-96-024, JPN-96-24, NUDOCS 9606040393
Download: ML20112D560 (3)


Text

! 123 Marn Street j , White Plains, New York 10601

, .

  • 914-681 0840 i 914-287 3309 (FAX)
  1. > NewYorkPower wmm. c.mm. u.

l 4# Authority c"*'" ~ o"-

May 30,1996 JPN-96-024 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-137 Washington, DC 20555

SUBJECT:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 l Proposed Change to the Technical Specifications Regarding Response Time Testing Requirements (JPTS-96-006)

REFERENCE:

1. BWR Owners' Group Topical Report, NEDO-32291-A, " System i Analyses For the Elimination of Selected Response Time Testing l Requirements," dated October 1995
2. NRC Letter to BWR Owner's Group Documenting NRC Review of NEDO-32291-A. dated December 28,1994
3. NYPA letter, W. Femandez to the NRC, dated July 19,1990, (JAFP-90-0549) " Response to NRC Bulletin 90-01"
4. NYPA letter, R.E. Beedle to the NRC, dated March 5,1993, (JPN-93-010) " Response to NRC Bulletin 90-01, Supplement 1"

Dear Sir:

This application for an amendment to the James A. FitzPatrick Technical Specifications proposes to eliminate selected response time testing requirements. The affected Technical l

Specifications (TS) are TS 4.1.A, " Surveillance Requirements, Reactor Protection System,"

and TS 4.2.A, " Surveillance Requirements, Instrumentation, Primary Containment isolation Functions." The proposed changes are supported by analyses performed by the Boiling Water Reactor Owners' Group (BWROG) (Reference 1) which demonstrate that other periodic tests required by TS, such as functional tests and calibrations, in conjunction with the actions taken in response to NRC Bulletin 90-01, " Loss of Fill-Oil in Transmitters Manufactured by Rosemount," and Supplement 1 (References 3 and 4), are adequate to l

040019

)

9606040393 960530

' PDR ADOCK 05000333 p PDR ,,

] g

l .

ensure that instrument response times are within acceptable limits. By letter (Reference 2),

the NRC staff provided their acceptance of NEDO-32291-A, subject to certain conditions, for reference in license amendment applications. The Authority has confirmed the applicability of j NEDO-32291-A to the James A. FitzPatrick Nuclear Plant.

The Authority requests NRC approval of this proposed amendment prior to October 1, 1996 in order to implement these changes prior to the upcoming refuel outage currently

scheduled for the Fall of 1990.

The signed original of the Application for Amendment to the Operating Ucense is enclosed for filing. Attachment I contains the proposed new TS pages and Attachment Il is the Safety Evaluation for the proposed changes. A markup of the affected TS pages is included as Attachment Ill. The summary of commitments is contained in Attachment IV.

A copy of this application and the associated attachments is being provided to the Designated New York State Official in accordance with 10 CFR 50.91.

If you have any questions, please contact Ms. C. D. Faison.

Very truly yours, Harry P. almon, Jr., for W. J. Cahill, Jr.

Chief Nuclear Officer att: As stated cc: Next page l

o cc
Regional Administrator U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 l Office of the Resident inspector .

U. S. Nuclear Regulatory Commission l P.O. Box 136 Lycoming, NY 13093 l Ms. K. Cotton, Acting Project Manager Project Directorate 1-1 Division of Reactor Projects-l/ll l U. S. Nuclear Regulatory Commission Mail Stop 14B2 Washington, DC 20555 Mr. F. William Valentino, President New York State Energy, Research, l and Development Authority l 2 Rockefeller Plaza Albany, NY 12223-1253 I