Corrected Operating Status Sheets for Feb 1995 for Jm Farley Nuclear Plant Units 1 & 2,revising Cummulative Unit Capacity Factors (Using MDC Net) from 93.3 to 75.6 for Unit 1 & from 94.0 to 82.8 for Unit 2
ML20087H079
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 02/28/1995
From: Hill R
SOUTHERN NUCLEAR OPERATING CO.
To:
Shared Package
ML20087H074 List:
References
NUDOCS 9504180336
Download: ML20087H079 (2)


Text

L.. f *. .

OPERATING DATA REPORT DOCKET NO. 50-348 L DATE March 6,1995 COMPLETED BY R. D. Hill TELEPHONE (334) 899-5156 ,

OPERATINGSTATUS

~1. Unit Name: Joseph M. Farley - Unit 1 Notes

2. Reporting Period: February 1995' 1) Cumulative data since 12-01-77,
3. Licensed Thermal Power (MWt): 2.652 date ofcommercial operation.

. 4. Nameplate Rating (Gross MWe): 860

- 5. Design Electrical Rating (Net MWe): 829

6. Maximum Dependable Capacity (Gross MWe): 855.7
7. Maximum Dependable Capacity (Net MWe): 812
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons: N/A
9. Power Level To Which Restricted, If Any (Net MWe): N/A i
10. Reasons For Restrictions, if Any: N/A This Month Yr. to Date Cumulative
11. Hours in Reporting Period 672.0 1,416.0 151,176.0
12. Number Of Hours Reactor Was Critical 672.0 1,325.7 120,582.5
13. Reactor Reserve Shutdown Hours 0.0 0.0 3,650.0 >
14. Hours Generator On-line 672.0 1,305.9 118,759.8
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1,772,517.2 3,441,156.4 305,576,873.4 i
17. Gross Electrical Energy Generated (MWH) 584,115.0 1,133,102.0 98,546,807.0
18. Net Electrical Energy Generated (MWH) 555,371.0 1,072,826.0 93,072,815.0
19. Unit Service Factor 100.0 92.2 78.6
20. Unit Availability Factor 100.0 92.2 78.6
21. Unit Capacity Factor (Using MDC Net) 101.8 93.3 '/5.6 9M i
22. Unit Capacity Factor (Using DER Net) 99.7 91.4 74.3
23. Unit Forced Outage Rate 0.0 7.8 6.0
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

N/A

25. If Shut Down at End Of Report Period, Estimated Date of Startup: N/A
26. Units In Test Status (Prior To Commercial Operation): Forecast Achieved Initial Criticality 08/06/77 08/09/77 Initial Electricity 08/20/77 08/18/77 Commercial Operation 12/01/77 12/01/77 950418o336 950413 DR ADOCK0500g8

w, o

OPERATING DATA REPORT

  • DOCKET NO. 50-364

^

DATE March 6,1995 COMPLETED BY R. D. Hill .

TELEPHONE (334) 899-5156 iOPERATINGSTATUS

1. Unit Name: Joseph M. Farley - Unit 2 Notes
2. Reporting Period: February 1995 1) Cumulative data since 07-30-81,
3. Licensed Thermal Power (MWt): 2,652 date ofcommercial operation.
4. Nameplate Rating (Gross MWe): 860
5. Design Electrical Rating (Net MWe): 829 -
6. Maximum Dependable Capacity (Gross MWe): 863.6
7. Maximum Dependable Capacity (Net MWe): 822
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since-Last Report, Give Reasons: N/A
9. Power Level To Which Restricted, If Any (Net MWe): N/A
10. Reasons For Restrictions, If Any: N/A This Month Yr. to Date Cumulative
11. Hours in Reporting Period 672.0 1,416.0 119,089.0
12. Number Of Hours Reactor Was Critical 672.0 1,338.4 102,996.1
13. Reactor Reserve Shutdown Hours 0.0 0.0 138.0
14. Ilours Generator On-line 672.0 1,326.8 101,549.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1,742,523.1 3,470,548.5 259,810.254.2
17. Gross Electrical Energy Generated (MWH) 579,256.0 1,150,948.0 85,205,490.0
18. Net Electrical Energy Generated (MWH) 551,934.0 1,094,568.0 80,816,866.0
19. Unit Service Factor 100.0 93.7 85.3
20. Unit Availability Factor 100.0 93.7 85.3
21. Unit Capacity Factor (Using MDC Net) 99.9 94.0 82.8 M
22. Unit Capacity Factor (Using DER Net) 99.1 93.2 81.9

-23. Unit Forced Outage Rate 0.0 0.0 3.9

24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Refueling / Maintenance outage, March 10,1995 Approximately 39 days.

25. If Shut Down at End Of Report Period, Estimated Date of Startup: N/A
26. Units In Test Status (Prior To Commercial Operation): Forecast Achieved Initial Criticality 05/06/81 05/08/81 Initial Electricity 05/24!81 05/25/81 Commercial Operation 08/01/81 07/30/81