Informs That Due to Timing of Unit 2 Design Change Mods & Issuance of Amends 106 & 99 for Each Unit,Ts Page 3/4 3-13 Must Be Corrected to Reflect Deletion of Steam/Fw Flow Mismatch on Amends 106 & 99.Updated TS Page 3/4 3-13 Encl
ML20069J967
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 06/09/1994
From: Dennis Morey
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20069J971 List:
References
NUDOCS 9406150197
Download: ML20069J967 (2)


Text

,

  • Southern Nuclear Operarng Company

,,k Post Cnce Box 1295 B;rmingham. A:abama 35201 Te;ephone (205) 868-5131 L

o, umy Southern Nudear Operating Company

$iefe$ the southem e'ectnc system June 9,1994 10 CFR 50.90 Docket No.: 50-364 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Joseph M. Farley Nuclear Plant Unit 2 Amendment No. 99 Technical Specifications Page Correction Ladies and Gentlemen:

Amendment Nos.104 and 97 to the Farley Unit I and Unit 2 Technical Specifications were issued December 29,1994. These amendments changed the Technical Specifications to allow elimination of the steam /feedwater flow mismatch reactor trip (Table 4.3-1, Functional Unit No.14). The amendments were to be implemented upon completion of necessary design modifications following each unit's next refueling outage. Subsequently, Amendment Nos.106 and 99 (Units 1 and 2, respectively,) were issued May 16,1994.

These Technical Specifications amendments changed the surveillance test intervals and allowed outage times for the Reactor Trip System and Engineered Safety Features Actuation System which afTected Table 4.3-1. At the time Amendment Nos.106 and 99 were issued, the plant modification to eliminate the steam /feedwater flow mismatch reactor trip had been completed on Unit 1, but had not been completed for Unit 2. (The Unit 2 modification is scheduled for the spring 1995 refueling outage.) Due to the timing of the design change modifications and the issuance of the two amendments for each unit, Page 3/4 3-13 must be corrected to reflect deletion of the steam /feedwater flow mismatch 1 on Amendment Nos.106 and 99. The updated page for the Unit 2 Technical j Specifications is attached to this letter. The updated Unit I page was provided by i Southern Nuclear to the NRC by letter dated June 3,1994.

The updated page provided with this letter is purely an editorial change not subject to 10 CFR 50.90 since Unit 2 Amendment Nos. 97 and 99 have both been approved under this  !

process.

a/

9406150197 940609 i PDR ADOCK 05000364 I p PDR

U. S. Nuclear Regulatory Commission Page 2 If you have any questions, please advise.

Respectfully submitted, A

(Y /&)/ Dave Morey e SWORN TO AND SUBSCRIBED BEFORE ME THIS 90 DAY OF hw 1994 Maxt/o Yle A0w Notary Public ~ V My Commission Expires: //,/C/,/9 7 Attachment Ill.M' cit rtsts2 doe cc: Mr. S. D. Ebneter Mr. B. L. Siegel Mr. T. M. Ross Dr. D. E. Williamson _ _ - _ .}}