|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217M1851999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates JPN-99-035, Forwards Comments on Version 2 of Reactor Vessel Integrity Database for Plant.Table Listing Recommended Changes to Info in Rvid,Encl as Attachment 11999-10-15015 October 1999 Forwards Comments on Version 2 of Reactor Vessel Integrity Database for Plant.Table Listing Recommended Changes to Info in Rvid,Encl as Attachment 1 JPN-99-034, Forwards Proposed risk-informed ISI Program,Provided from NRC Review & Approval as Alternative to Current ASME Section XI Insp Requirements for Class 1 & 2 Piping1999-10-13013 October 1999 Forwards Proposed risk-informed ISI Program,Provided from NRC Review & Approval as Alternative to Current ASME Section XI Insp Requirements for Class 1 & 2 Piping JPN-99-033, Provides Response to Questions Contained in 990712,facsimile from NRC Re Ja FitzPatrick USI A-46 Program.Questions Were Also Discussed Between Members of Util & NRC Staff During Telcon1999-10-0808 October 1999 Provides Response to Questions Contained in 990712,facsimile from NRC Re Ja FitzPatrick USI A-46 Program.Questions Were Also Discussed Between Members of Util & NRC Staff During Telcon JPN-99-030, Forwards Application for Amend to License DPR-59,proposing Change to TS 3.5.B.3 & Associated Bases to Extend LCO Allowable Out of Service Time for RHRSW Sys from 7 Days to 11 Days1999-09-29029 September 1999 Forwards Application for Amend to License DPR-59,proposing Change to TS 3.5.B.3 & Associated Bases to Extend LCO Allowable Out of Service Time for RHRSW Sys from 7 Days to 11 Days JPN-99-032, Forwards Info Re Potential Environ Effects of Alternatives to Proposed Expansion of FitzPatrick Spent Fuel Pool,In Response to NRC Project Manager Request1999-09-29029 September 1999 Forwards Info Re Potential Environ Effects of Alternatives to Proposed Expansion of FitzPatrick Spent Fuel Pool,In Response to NRC Project Manager Request ML20212F8341999-09-22022 September 1999 Forwards Insp Rept 50-333/99-07 on 990718-0828.No Violations Noted JAFP-99-0262, Forwards Voluntary Response to Administrative Ltr 99-03, Re Preparation & Scheduling of Operator Licensing Exams. Completed NRC Form 536,containing Info Re Proposed Exam Preparation Schedule & Initial Operator License Exams,Encl1999-09-16016 September 1999 Forwards Voluntary Response to Administrative Ltr 99-03, Re Preparation & Scheduling of Operator Licensing Exams. Completed NRC Form 536,containing Info Re Proposed Exam Preparation Schedule & Initial Operator License Exams,Encl ML20212A8341999-09-0909 September 1999 Requests That Licensees Affected by Kaowool Fire Barriers Take Issue on Voluntary Initiative & Propose Approach for Resolving Subj Issues.Staff Plans to Meet with Licensees to Discuss Listed Topics ML20212A6951999-09-0909 September 1999 Requests That Licensees Affected by Kaowool Fire Barriers Take Issue on Voluntary Initiative & Propose Approach for Resolving Subj Issues.Staff Plans to Meet with Licensees to Discuss Listed Topics 05000333/LER-1998-015, Forwards LER 98-015-02 Re Logic Sys Functional Test Inadequacies,Per 10CFR50.73(A)(2)(i)(B).Rept Revised to Reflect Scheduled Completion Date for Corrective Action 3 of Jan 15, 2000 & Updates Status of Other C/As as Complete1999-09-0808 September 1999 Forwards LER 98-015-02 Re Logic Sys Functional Test Inadequacies,Per 10CFR50.73(A)(2)(i)(B).Rept Revised to Reflect Scheduled Completion Date for Corrective Action 3 of Jan 15, 2000 & Updates Status of Other C/As as Complete ML20211N4301999-09-0808 September 1999 Discusses Proposed Meeting to Discuss Kaowool Fire Barriers. Staff Requesting That Affected Licensees Take Issue on Voluntary Initative & Propose Approach for Resolving Issues JAFP-99-0258, Forwards Operator License Restriction Change for Tj Pelton, License SOP-10090-3.License Is Requested to Be Reissued with Restriction for Corrective Lenses.Encl Withheld1999-09-0808 September 1999 Forwards Operator License Restriction Change for Tj Pelton, License SOP-10090-3.License Is Requested to Be Reissued with Restriction for Corrective Lenses.Encl Withheld JPN-99-028, Informs That Util Requires Extension from 990901 to 1015,to Complete Review of Rvid & Forward Comments to Nrc,Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity1999-08-30030 August 1999 Informs That Util Requires Extension from 990901 to 1015,to Complete Review of Rvid & Forward Comments to Nrc,Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity JAFP-99-0247, Forwards JAFNPP Effluent & Waste Disposal Semi-Annual Rept for 990101-0630, IAW Amend 93,App B,Section 7.3.C of Plant Ts.Format Used for Rept Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 41999-08-26026 August 1999 Forwards JAFNPP Effluent & Waste Disposal Semi-Annual Rept for 990101-0630, IAW Amend 93,App B,Section 7.3.C of Plant Ts.Format Used for Rept Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 4 JAFP-99-0245, Informs That Two Licensed Operators Have Returned to Site Upon Release for Normal Duties by Physician.R Korthas, License OP-11159,meets ANSI Std 3.4-1983 & R Sarkissian License SOP-10007-3,was Terminated in Mar 19991999-08-19019 August 1999 Informs That Two Licensed Operators Have Returned to Site Upon Release for Normal Duties by Physician.R Korthas, License OP-11159,meets ANSI Std 3.4-1983 & R Sarkissian License SOP-10007-3,was Terminated in Mar 1999 ML20210U2621999-08-12012 August 1999 Forwards Insp Rept 50-333/99-06 on 990601-0717.No Violations Noted JPN-99-025, Forwards Relief Request 17 Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) for Reactor Pressure Vessel Circumferential Shell Weld Exams1999-08-0505 August 1999 Forwards Relief Request 17 Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) for Reactor Pressure Vessel Circumferential Shell Weld Exams JPN-99-026, Forwards Relief Requests 18 & 19 to Jaf ISI Program Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) & Relief from ASME Section XI Code Re Insp of RPV Vertical Shell & Shell to Flange Welds1999-08-0505 August 1999 Forwards Relief Requests 18 & 19 to Jaf ISI Program Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) & Relief from ASME Section XI Code Re Insp of RPV Vertical Shell & Shell to Flange Welds ML20216D9421999-07-28028 July 1999 Forwards Safety Evaluation Granting Requests for Relief from Requirements of ASME Code,Section XI for Second 10-year ISI Interval for James a FitzPatrick NPP JAFP-99-0229, Forwards Three Sets of Corrected Summaries of Changes for Inclusion Into Security Plan for Ja FitzPatrick Nuclear Power Plant,Rev 19 & Security Contingency Plan,Rev 5.Encls Withheld Per 10CFR73.21 & 10CFR2.790)d)(1)1999-07-22022 July 1999 Forwards Three Sets of Corrected Summaries of Changes for Inclusion Into Security Plan for Ja FitzPatrick Nuclear Power Plant,Rev 19 & Security Contingency Plan,Rev 5.Encls Withheld Per 10CFR73.21 & 10CFR2.790)d)(1) JAFP-99-0228, Forwards Rept Re Changes & Errors in ECCS Evaluation Models, Per 10CFR50.46(a)(3)(ii) for Period from 980701-990630.No Commitments Contained in Submittal1999-07-21021 July 1999 Forwards Rept Re Changes & Errors in ECCS Evaluation Models, Per 10CFR50.46(a)(3)(ii) for Period from 980701-990630.No Commitments Contained in Submittal ML20210A7001999-07-16016 July 1999 Forwards Request for Addl Info to Supplement Response Provided for GL 97-05, Steam Generator Tube Insp Techniques JAFP-99-0208, Provides Clarification of Info Re Proposed Its, & 0601.Table Reconciling Differences,Encl1999-07-14014 July 1999 Provides Clarification of Info Re Proposed Its, & 0601.Table Reconciling Differences,Encl ML20209D5511999-07-0606 July 1999 Informs That as Result of NRC Review of Licensee Response to GL 92-01,rev 1,suppl 1,staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2 ML20210C9031999-06-30030 June 1999 Summarizes Impact of Changes & Errors in Methodology Used by GE to Demonstrate Compliance with ECCS Requirements of 10CFR50.46.Summary of Changes & Errors Provided in Attached Table JPN-99-021, Forwards Application for Amend to License DPR-59,changing to Pressure Temp Limits.Pressure Temp Curves & Associated LCO & Bases Changes Included in Proposed Amend1999-06-22022 June 1999 Forwards Application for Amend to License DPR-59,changing to Pressure Temp Limits.Pressure Temp Curves & Associated LCO & Bases Changes Included in Proposed Amend JPN-99-020, Submits Response to RAI Re ISI Program Relief Requests for Second 10-yr Interval Closeout & Summary Rept,Per 990426 Telcon with Nrc.Info Provided to Clarify or Withdraw Individual Relief Requests Contained in Summary Rept1999-06-21021 June 1999 Submits Response to RAI Re ISI Program Relief Requests for Second 10-yr Interval Closeout & Summary Rept,Per 990426 Telcon with Nrc.Info Provided to Clarify or Withdraw Individual Relief Requests Contained in Summary Rept ML20196G2981999-06-18018 June 1999 Forwards Insp Rept 50-333/99-04 on 990412 to 0529.Violations Being Treated as non-cited Violations ML20212J0541999-06-17017 June 1999 Responds to Requesting That NRC Staff ...Allow BWR Plants Identified to Defer Weld Overlay Exams Until March 2001 or Until Completion of NRC Staff Review & Approval of Proposed Generic Rept,Whichever Comes First JPN-99-019, Withdraws Recent Exemption Request Re 10CFR50,App R, Use of Core Spray to Achieve Safe Shutdown. Exemption Dealt with Use of Core Spray for Reactor Coolant Makeup to Achieve Safe Shutdown in One Fire Area at Plant1999-06-15015 June 1999 Withdraws Recent Exemption Request Re 10CFR50,App R, Use of Core Spray to Achieve Safe Shutdown. Exemption Dealt with Use of Core Spray for Reactor Coolant Makeup to Achieve Safe Shutdown in One Fire Area at Plant ML20196L1451999-06-0707 June 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Ss Bajwa Will Be Section Chief for Ja Fitzpatrick & Indian Point NPPs JPN-99-018, Forwards Revised Application,Previously Submitted,For Amend to Plant TS for Converting CTS to ITS Consistent with Improved Std TS (NUREG-1433,Rev 1)1999-06-0101 June 1999 Forwards Revised Application,Previously Submitted,For Amend to Plant TS for Converting CTS to ITS Consistent with Improved Std TS (NUREG-1433,Rev 1) ML20207D9191999-05-27027 May 1999 Informs That on 990521 NRC Staff Held Planning Meeting to Identify Insp Activities at Facility Over Next Six Months JAFP-99-0171, Forwards Revised Ja FitzPatrick Nuclear Power Plant 1999 FSAR Update. Update Also Includes Changes to Chapter 17, QA Program Which Described in Attachment 1.No Commitments Contained in Ltr1999-05-20020 May 1999 Forwards Revised Ja FitzPatrick Nuclear Power Plant 1999 FSAR Update. Update Also Includes Changes to Chapter 17, QA Program Which Described in Attachment 1.No Commitments Contained in Ltr JPN-99-016, Forwards Application for Amend to License DPR-59,requesting 14 Day AOT for EDG Sys.Commitment Made by Util,Encl1999-05-19019 May 1999 Forwards Application for Amend to License DPR-59,requesting 14 Day AOT for EDG Sys.Commitment Made by Util,Encl ML20207A6751999-05-17017 May 1999 Forwards RAI Re 960626 Submittal & Suppl Related to IPEEEs for Plant.Licensee Committed to Revise Plant Fire IPEEE to Reflect Issues Associated with EPRI Fire PRA Implementation Guide within 120 Days of Issues Resolution JAFP-99-0168, Forwards Eight Operator License Renewal Applications for Listed Individuals.Without Encls1999-05-13013 May 1999 Forwards Eight Operator License Renewal Applications for Listed Individuals.Without Encls ML20206N0721999-05-11011 May 1999 Forwards Insp Rept 50-333/99-03 on 990301-0411.Four Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy JAFP-99-0160, Forwards 1998 Annual Radiological Environ Operating Rept for Ja FitzPatrick Nuclear Power Plant. Distribution for Rept Is IAW Reg Guide 10.1,Rev 41999-04-30030 April 1999 Forwards 1998 Annual Radiological Environ Operating Rept for Ja FitzPatrick Nuclear Power Plant. Distribution for Rept Is IAW Reg Guide 10.1,Rev 4 ML20206C8551999-04-27027 April 1999 Informs That Util 990406 Submittal, Licensing Rept for Reracking of Ja FitzPatrick Spent Fuel Pool,Rev 7, Will Be Marked as Proprietary & Will Be Withheld from Public Disclosure Pursuant to 10CFR2.790(b)(5) & Section 103(b) ML20205T1141999-04-22022 April 1999 Provides Comments from Technical Review of Draft Info Notice Re Unanticipated Reactor Water Draindown at Quad Cities Nuclear Power Station,Unit 2,ANO,Unit 2 & JAFNPP JPN-99-012, Informs That Authority Identified Typographical Error on Page 3 of Attachment 3 of 990331 Response to NRC RAI Re App R.Corrected Response to NRC Question 3 Is Attached1999-04-16016 April 1999 Informs That Authority Identified Typographical Error on Page 3 of Attachment 3 of 990331 Response to NRC RAI Re App R.Corrected Response to NRC Question 3 Is Attached ML20205P4641999-04-15015 April 1999 Forwards for Review & Comment Draft Info Notice That Describes Unanticipated Reactor Water Draindown at Quad Cities Nuclear Power Station Unit 2,Arkansas Nuclear One Unit 2 & Ja Fitzpatrick NPP ML20205P1991999-04-0909 April 1999 Discusses 990224 PPR & Forwards Plant Issues Matrix & Insp Plan.Advises of Planned Insp Effort Resulting from Plant PPR Review JAFP-99-0129, Submits Comments on Technical Review of Draft Info Notice Describing Unanticipated Reactor Water Draindown at Quad Cities Unit 2,ANO & FitzPatrick1999-04-0909 April 1999 Submits Comments on Technical Review of Draft Info Notice Describing Unanticipated Reactor Water Draindown at Quad Cities Unit 2,ANO & FitzPatrick JAFP-99-0127, Forwards Affidavit Signed by Holtec Which Describes Proprietary Nature of Licensing Rept & Addresses Considerations Listed in 10CFR2.790.Attachment 4 in Util Re Design Features Should Be Withheld1999-04-0808 April 1999 Forwards Affidavit Signed by Holtec Which Describes Proprietary Nature of Licensing Rept & Addresses Considerations Listed in 10CFR2.790.Attachment 4 in Util Re Design Features Should Be Withheld JAFP-99-0124, Forwards Rev 19 to JAFNPP Security Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Safeguards Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1)1999-04-0707 April 1999 Forwards Rev 19 to JAFNPP Security Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Safeguards Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1) ML20205M8941999-04-0707 April 1999 Forwards Rev 21 to App C of JAFNPP Emergency Plan & Rev 1 to EAP-32, Recovery Support Group Manager JAFP-99-0125, Forwards Rev 5 to JAFNPP Security Contingency Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1)1999-04-0707 April 1999 Forwards Rev 5 to JAFNPP Security Contingency Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1) 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARJPN-99-035, Forwards Comments on Version 2 of Reactor Vessel Integrity Database for Plant.Table Listing Recommended Changes to Info in Rvid,Encl as Attachment 11999-10-15015 October 1999 Forwards Comments on Version 2 of Reactor Vessel Integrity Database for Plant.Table Listing Recommended Changes to Info in Rvid,Encl as Attachment 1 JPN-99-034, Forwards Proposed risk-informed ISI Program,Provided from NRC Review & Approval as Alternative to Current ASME Section XI Insp Requirements for Class 1 & 2 Piping1999-10-13013 October 1999 Forwards Proposed risk-informed ISI Program,Provided from NRC Review & Approval as Alternative to Current ASME Section XI Insp Requirements for Class 1 & 2 Piping JPN-99-033, Provides Response to Questions Contained in 990712,facsimile from NRC Re Ja FitzPatrick USI A-46 Program.Questions Were Also Discussed Between Members of Util & NRC Staff During Telcon1999-10-0808 October 1999 Provides Response to Questions Contained in 990712,facsimile from NRC Re Ja FitzPatrick USI A-46 Program.Questions Were Also Discussed Between Members of Util & NRC Staff During Telcon JPN-99-030, Forwards Application for Amend to License DPR-59,proposing Change to TS 3.5.B.3 & Associated Bases to Extend LCO Allowable Out of Service Time for RHRSW Sys from 7 Days to 11 Days1999-09-29029 September 1999 Forwards Application for Amend to License DPR-59,proposing Change to TS 3.5.B.3 & Associated Bases to Extend LCO Allowable Out of Service Time for RHRSW Sys from 7 Days to 11 Days JPN-99-032, Forwards Info Re Potential Environ Effects of Alternatives to Proposed Expansion of FitzPatrick Spent Fuel Pool,In Response to NRC Project Manager Request1999-09-29029 September 1999 Forwards Info Re Potential Environ Effects of Alternatives to Proposed Expansion of FitzPatrick Spent Fuel Pool,In Response to NRC Project Manager Request JAFP-99-0262, Forwards Voluntary Response to Administrative Ltr 99-03, Re Preparation & Scheduling of Operator Licensing Exams. Completed NRC Form 536,containing Info Re Proposed Exam Preparation Schedule & Initial Operator License Exams,Encl1999-09-16016 September 1999 Forwards Voluntary Response to Administrative Ltr 99-03, Re Preparation & Scheduling of Operator Licensing Exams. Completed NRC Form 536,containing Info Re Proposed Exam Preparation Schedule & Initial Operator License Exams,Encl JAFP-99-0258, Forwards Operator License Restriction Change for Tj Pelton, License SOP-10090-3.License Is Requested to Be Reissued with Restriction for Corrective Lenses.Encl Withheld1999-09-0808 September 1999 Forwards Operator License Restriction Change for Tj Pelton, License SOP-10090-3.License Is Requested to Be Reissued with Restriction for Corrective Lenses.Encl Withheld 05000333/LER-1998-015, Forwards LER 98-015-02 Re Logic Sys Functional Test Inadequacies,Per 10CFR50.73(A)(2)(i)(B).Rept Revised to Reflect Scheduled Completion Date for Corrective Action 3 of Jan 15, 2000 & Updates Status of Other C/As as Complete1999-09-0808 September 1999 Forwards LER 98-015-02 Re Logic Sys Functional Test Inadequacies,Per 10CFR50.73(A)(2)(i)(B).Rept Revised to Reflect Scheduled Completion Date for Corrective Action 3 of Jan 15, 2000 & Updates Status of Other C/As as Complete JPN-99-028, Informs That Util Requires Extension from 990901 to 1015,to Complete Review of Rvid & Forward Comments to Nrc,Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity1999-08-30030 August 1999 Informs That Util Requires Extension from 990901 to 1015,to Complete Review of Rvid & Forward Comments to Nrc,Per GL 92-01,Rev 1,Suppl 1, Reactor Vessel Structural Integrity JAFP-99-0247, Forwards JAFNPP Effluent & Waste Disposal Semi-Annual Rept for 990101-0630, IAW Amend 93,App B,Section 7.3.C of Plant Ts.Format Used for Rept Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 41999-08-26026 August 1999 Forwards JAFNPP Effluent & Waste Disposal Semi-Annual Rept for 990101-0630, IAW Amend 93,App B,Section 7.3.C of Plant Ts.Format Used for Rept Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 4 JAFP-99-0245, Informs That Two Licensed Operators Have Returned to Site Upon Release for Normal Duties by Physician.R Korthas, License OP-11159,meets ANSI Std 3.4-1983 & R Sarkissian License SOP-10007-3,was Terminated in Mar 19991999-08-19019 August 1999 Informs That Two Licensed Operators Have Returned to Site Upon Release for Normal Duties by Physician.R Korthas, License OP-11159,meets ANSI Std 3.4-1983 & R Sarkissian License SOP-10007-3,was Terminated in Mar 1999 JPN-99-025, Forwards Relief Request 17 Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) for Reactor Pressure Vessel Circumferential Shell Weld Exams1999-08-0505 August 1999 Forwards Relief Request 17 Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) for Reactor Pressure Vessel Circumferential Shell Weld Exams JPN-99-026, Forwards Relief Requests 18 & 19 to Jaf ISI Program Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) & Relief from ASME Section XI Code Re Insp of RPV Vertical Shell & Shell to Flange Welds1999-08-0505 August 1999 Forwards Relief Requests 18 & 19 to Jaf ISI Program Re Proposed Alternatives IAW 10CFR50.55a(a)(3)(i) & Relief from ASME Section XI Code Re Insp of RPV Vertical Shell & Shell to Flange Welds JAFP-99-0229, Forwards Three Sets of Corrected Summaries of Changes for Inclusion Into Security Plan for Ja FitzPatrick Nuclear Power Plant,Rev 19 & Security Contingency Plan,Rev 5.Encls Withheld Per 10CFR73.21 & 10CFR2.790)d)(1)1999-07-22022 July 1999 Forwards Three Sets of Corrected Summaries of Changes for Inclusion Into Security Plan for Ja FitzPatrick Nuclear Power Plant,Rev 19 & Security Contingency Plan,Rev 5.Encls Withheld Per 10CFR73.21 & 10CFR2.790)d)(1) JAFP-99-0228, Forwards Rept Re Changes & Errors in ECCS Evaluation Models, Per 10CFR50.46(a)(3)(ii) for Period from 980701-990630.No Commitments Contained in Submittal1999-07-21021 July 1999 Forwards Rept Re Changes & Errors in ECCS Evaluation Models, Per 10CFR50.46(a)(3)(ii) for Period from 980701-990630.No Commitments Contained in Submittal JAFP-99-0208, Provides Clarification of Info Re Proposed Its, & 0601.Table Reconciling Differences,Encl1999-07-14014 July 1999 Provides Clarification of Info Re Proposed Its, & 0601.Table Reconciling Differences,Encl ML20210C9031999-06-30030 June 1999 Summarizes Impact of Changes & Errors in Methodology Used by GE to Demonstrate Compliance with ECCS Requirements of 10CFR50.46.Summary of Changes & Errors Provided in Attached Table JPN-99-021, Forwards Application for Amend to License DPR-59,changing to Pressure Temp Limits.Pressure Temp Curves & Associated LCO & Bases Changes Included in Proposed Amend1999-06-22022 June 1999 Forwards Application for Amend to License DPR-59,changing to Pressure Temp Limits.Pressure Temp Curves & Associated LCO & Bases Changes Included in Proposed Amend JPN-99-020, Submits Response to RAI Re ISI Program Relief Requests for Second 10-yr Interval Closeout & Summary Rept,Per 990426 Telcon with Nrc.Info Provided to Clarify or Withdraw Individual Relief Requests Contained in Summary Rept1999-06-21021 June 1999 Submits Response to RAI Re ISI Program Relief Requests for Second 10-yr Interval Closeout & Summary Rept,Per 990426 Telcon with Nrc.Info Provided to Clarify or Withdraw Individual Relief Requests Contained in Summary Rept JPN-99-019, Withdraws Recent Exemption Request Re 10CFR50,App R, Use of Core Spray to Achieve Safe Shutdown. Exemption Dealt with Use of Core Spray for Reactor Coolant Makeup to Achieve Safe Shutdown in One Fire Area at Plant1999-06-15015 June 1999 Withdraws Recent Exemption Request Re 10CFR50,App R, Use of Core Spray to Achieve Safe Shutdown. Exemption Dealt with Use of Core Spray for Reactor Coolant Makeup to Achieve Safe Shutdown in One Fire Area at Plant JPN-99-018, Forwards Revised Application,Previously Submitted,For Amend to Plant TS for Converting CTS to ITS Consistent with Improved Std TS (NUREG-1433,Rev 1)1999-06-0101 June 1999 Forwards Revised Application,Previously Submitted,For Amend to Plant TS for Converting CTS to ITS Consistent with Improved Std TS (NUREG-1433,Rev 1) JAFP-99-0171, Forwards Revised Ja FitzPatrick Nuclear Power Plant 1999 FSAR Update. Update Also Includes Changes to Chapter 17, QA Program Which Described in Attachment 1.No Commitments Contained in Ltr1999-05-20020 May 1999 Forwards Revised Ja FitzPatrick Nuclear Power Plant 1999 FSAR Update. Update Also Includes Changes to Chapter 17, QA Program Which Described in Attachment 1.No Commitments Contained in Ltr JPN-99-016, Forwards Application for Amend to License DPR-59,requesting 14 Day AOT for EDG Sys.Commitment Made by Util,Encl1999-05-19019 May 1999 Forwards Application for Amend to License DPR-59,requesting 14 Day AOT for EDG Sys.Commitment Made by Util,Encl JAFP-99-0168, Forwards Eight Operator License Renewal Applications for Listed Individuals.Without Encls1999-05-13013 May 1999 Forwards Eight Operator License Renewal Applications for Listed Individuals.Without Encls JAFP-99-0160, Forwards 1998 Annual Radiological Environ Operating Rept for Ja FitzPatrick Nuclear Power Plant. Distribution for Rept Is IAW Reg Guide 10.1,Rev 41999-04-30030 April 1999 Forwards 1998 Annual Radiological Environ Operating Rept for Ja FitzPatrick Nuclear Power Plant. Distribution for Rept Is IAW Reg Guide 10.1,Rev 4 ML20205T1141999-04-22022 April 1999 Provides Comments from Technical Review of Draft Info Notice Re Unanticipated Reactor Water Draindown at Quad Cities Nuclear Power Station,Unit 2,ANO,Unit 2 & JAFNPP JPN-99-012, Informs That Authority Identified Typographical Error on Page 3 of Attachment 3 of 990331 Response to NRC RAI Re App R.Corrected Response to NRC Question 3 Is Attached1999-04-16016 April 1999 Informs That Authority Identified Typographical Error on Page 3 of Attachment 3 of 990331 Response to NRC RAI Re App R.Corrected Response to NRC Question 3 Is Attached JAFP-99-0129, Submits Comments on Technical Review of Draft Info Notice Describing Unanticipated Reactor Water Draindown at Quad Cities Unit 2,ANO & FitzPatrick1999-04-0909 April 1999 Submits Comments on Technical Review of Draft Info Notice Describing Unanticipated Reactor Water Draindown at Quad Cities Unit 2,ANO & FitzPatrick JAFP-99-0127, Forwards Affidavit Signed by Holtec Which Describes Proprietary Nature of Licensing Rept & Addresses Considerations Listed in 10CFR2.790.Attachment 4 in Util Re Design Features Should Be Withheld1999-04-0808 April 1999 Forwards Affidavit Signed by Holtec Which Describes Proprietary Nature of Licensing Rept & Addresses Considerations Listed in 10CFR2.790.Attachment 4 in Util Re Design Features Should Be Withheld JAFP-99-0124, Forwards Rev 19 to JAFNPP Security Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Safeguards Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1)1999-04-0707 April 1999 Forwards Rev 19 to JAFNPP Security Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Safeguards Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1) JAFP-99-0125, Forwards Rev 5 to JAFNPP Security Contingency Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1)1999-04-0707 April 1999 Forwards Rev 5 to JAFNPP Security Contingency Plan,Which Enhances Requirements of 10CFR73.55.Changes Do Not Decrease Effectiveness of Plan.Plan Withheld IAW 10CFR73.21 & 2.790(d)(1) ML20205M8941999-04-0707 April 1999 Forwards Rev 21 to App C of JAFNPP Emergency Plan & Rev 1 to EAP-32, Recovery Support Group Manager JPN-99-011, Forwards Application for Amend to License DPR-59,removing Position Title of General Manager from Sections & Will Delegate Responsibilities to Another Staff Member,In Writing1999-04-0505 April 1999 Forwards Application for Amend to License DPR-59,removing Position Title of General Manager from Sections & Will Delegate Responsibilities to Another Staff Member,In Writing ML20205G4111999-03-31031 March 1999 Forwards Rev 7 to JAFNPP EP App J & Rev 6,pages 7 & 8 to EAP-5.3 05000333/LER-1999-001, Forwards LER 99-001-01 Re Incorrect EDG line-up During Fire Placing Plant in Outside Design Basis.Suppl Contains Results of Completed Root Cause Evaluations & Subsequent Corrective Actions Taken.Rept Contains No Commitments1999-03-31031 March 1999 Forwards LER 99-001-01 Re Incorrect EDG line-up During Fire Placing Plant in Outside Design Basis.Suppl Contains Results of Completed Root Cause Evaluations & Subsequent Corrective Actions Taken.Rept Contains No Commitments JPN-99-008, Forwards Application for Amend to License DPR-59,converting CTS to Be Consistent with Improved Std TS in NUREG-1433, Rev 1.Synopsis of LAR for Conversion to Its,Pending Lars, List of Subsections,Scope of Changes & Commitments,Encl1999-03-31031 March 1999 Forwards Application for Amend to License DPR-59,converting CTS to Be Consistent with Improved Std TS in NUREG-1433, Rev 1.Synopsis of LAR for Conversion to Its,Pending Lars, List of Subsections,Scope of Changes & Commitments,Encl JPN-99-010, Transmits Revised Exemption Request from Some of Requirements of 10CFR50,App R.Exemption Would Permit Use of CS for Rc Makeup to Achieve Safe Shutdown in Fire Area XI at JAFNPP1999-03-31031 March 1999 Transmits Revised Exemption Request from Some of Requirements of 10CFR50,App R.Exemption Would Permit Use of CS for Rc Makeup to Achieve Safe Shutdown in Fire Area XI at JAFNPP JAFP-99-0114, Requests That License OP-11037,for Bs Brooks,Be re-issued Without Restriction for Corrective Lenses.Nrc Form 369,encl. Without Encl1999-03-29029 March 1999 Requests That License OP-11037,for Bs Brooks,Be re-issued Without Restriction for Corrective Lenses.Nrc Form 369,encl. Without Encl JAFP-99-0112, Informs of Util Determination That Listed Individuals No Longer Need to Maintain Operating License for Ja FitzPatrick Nuclear Plant.Termination of Listed Licenses,Requested1999-03-29029 March 1999 Informs of Util Determination That Listed Individuals No Longer Need to Maintain Operating License for Ja FitzPatrick Nuclear Plant.Termination of Listed Licenses,Requested JAFP-99-0097, Forwards JAFNPP Referenced Simulation Facility Four Year Performance Testing Rept, Containing Description of Performance Testing Completed During Past Four Years & Description of Testing Scheduled During Next Four Years1999-03-17017 March 1999 Forwards JAFNPP Referenced Simulation Facility Four Year Performance Testing Rept, Containing Description of Performance Testing Completed During Past Four Years & Description of Testing Scheduled During Next Four Years ML20204B6241999-03-17017 March 1999 Forwards Plant Referenced Simulation Facility Four Year Performance Testing Rept, Per 10CFR55.45(b)ii 05000333/LER-1999-003, Forwards LER 99-003-00,per 10CFR50.73(a)(2)(i)(B).One New Commitment Is Contained in Rept1999-03-16016 March 1999 Forwards LER 99-003-00,per 10CFR50.73(a)(2)(i)(B).One New Commitment Is Contained in Rept ML20204C7371999-03-15015 March 1999 Forwards Revised EP Coversheets for Sections to Vol 1 & Rev 26,Vol 3 to EPIP SAP-10, Meteorological Monitoring Sys Surveillance JAFP-99-0085, Submits in-vessel Visual Insp Summary Rept for RFO 13 for Ja FitzPatrick Nuclear Power Plant.All Relevant Indications Recorded During Insp Were Satisfactorily Dispositioned IAW Util Internal C/A Tracking Sys & Were Found Acceptable1999-03-0808 March 1999 Submits in-vessel Visual Insp Summary Rept for RFO 13 for Ja FitzPatrick Nuclear Power Plant.All Relevant Indications Recorded During Insp Were Satisfactorily Dispositioned IAW Util Internal C/A Tracking Sys & Were Found Acceptable ML20207J3201999-03-0505 March 1999 Forwards Form NRC-369,requesting That Restriction for Corrective Lenses Be Placed on Current License SOP-10089-3, for Ks Allen.Encl Withheld Per 10CFR2.790(a)(6).Without Encl JAFP-99-0073, Submits Annual Rept on SRV Challenges & Failures,Per Plant TS 6.9.A.2.b.No Challenges to SRVs from Automatic Control Circuits or from RCS Pressure Transients,Occurred.Ltr Contains No New Commitments1999-02-26026 February 1999 Submits Annual Rept on SRV Challenges & Failures,Per Plant TS 6.9.A.2.b.No Challenges to SRVs from Automatic Control Circuits or from RCS Pressure Transients,Occurred.Ltr Contains No New Commitments JAFP-99-0071, Forwards Semi-Annual Radioactive Effluent Release Rept for Period of 980701-1231. Format Used for Effluent Data Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 41999-02-25025 February 1999 Forwards Semi-Annual Radioactive Effluent Release Rept for Period of 980701-1231. Format Used for Effluent Data Is Outlined in App B of Reg Guide 1.21,Rev 1.Distribution Is IAW Reg Guide 10.1,Rev 4 JAFP-99-0068, Forwards Form NRC-5 Equivalent Records of All Individuals Monitored at JAFNPP from 980101-1231 on Electronic Media, Per 10CFR20.2206(b) & App a of NRC Reg Guide 8.7, Instruction for Recording & Reporting..1999-02-22022 February 1999 Forwards Form NRC-5 Equivalent Records of All Individuals Monitored at JAFNPP from 980101-1231 on Electronic Media, Per 10CFR20.2206(b) & App a of NRC Reg Guide 8.7, Instruction for Recording & Reporting.. JAFP-99-0019, Informs of Licensee Intent to Upgrade ERDS at Ja FitzPatrick in Preparation for Year 2000 (Y2K) Readiness,Per GL 98-01. Encl Contains Brief Summary of Proposed Changes to ERDS1999-01-25025 January 1999 Informs of Licensee Intent to Upgrade ERDS at Ja FitzPatrick in Preparation for Year 2000 (Y2K) Readiness,Per GL 98-01. Encl Contains Brief Summary of Proposed Changes to ERDS JAFP-99-0012, Documents Util Position Re Methodology for LPRM Calibr During Reactor Operation Using Traversing In-core Probe Sys1999-01-18018 January 1999 Documents Util Position Re Methodology for LPRM Calibr During Reactor Operation Using Traversing In-core Probe Sys 1999-09-08
[Table view] Category:UTILITY TO NRC
MONTHYEARJPN-90-063, Responds to NRC Re Deviations Noted in Insp Rept 50-333/90-19.Interim Corrective Action:Temporary Procedure Change Implemented to Administratively Prohibit Concurrent Closure of Upstream Feeder Breakers Until Issue Resolved1990-09-18018 September 1990 Responds to NRC Re Deviations Noted in Insp Rept 50-333/90-19.Interim Corrective Action:Temporary Procedure Change Implemented to Administratively Prohibit Concurrent Closure of Upstream Feeder Breakers Until Issue Resolved JPN-90-061, Forwards Analyses Re Installation of Hardened Wetwell Vent, Including Benefits of Elevated Vs Ground Level Gas Release. Analyses Provide Further Evidence That Addition of Elevated Release to Existing Hardened Vent Not Cost Beneficial1990-09-0707 September 1990 Forwards Analyses Re Installation of Hardened Wetwell Vent, Including Benefits of Elevated Vs Ground Level Gas Release. Analyses Provide Further Evidence That Addition of Elevated Release to Existing Hardened Vent Not Cost Beneficial JPN-90-060, Forwards Info to Satisfy 900716 Commitment Re Switchgear Deficiency,Per SSFI Insp Rept 50-333/89-80.Waiver Requested Re Design Requirements for Three Phase Bolted Fault Criteria for Switchgear Configuration for Diesel Generator Testing1990-09-0404 September 1990 Forwards Info to Satisfy 900716 Commitment Re Switchgear Deficiency,Per SSFI Insp Rept 50-333/89-80.Waiver Requested Re Design Requirements for Three Phase Bolted Fault Criteria for Switchgear Configuration for Diesel Generator Testing JPN-90-057, Forwards GE Supplemental Rept of Ultrasonic Indications in Top Head Weld VC-TH-1-2 at Ja Fitzpatrick Power Station1990-08-14014 August 1990 Forwards GE Supplemental Rept of Ultrasonic Indications in Top Head Weld VC-TH-1-2 at Ja Fitzpatrick Power Station JAFP-90-0581, Forwards Proposed Rev 6 to IAP-2, Classification of Emergency Conditions, Per Insp Rept 50-333/90-15,Unresolved Item 89-11-03.Rev Incorporates Changes Assuring That Applicable Initiating Conditions,Per NUREG-0654,addressed1990-07-30030 July 1990 Forwards Proposed Rev 6 to IAP-2, Classification of Emergency Conditions, Per Insp Rept 50-333/90-15,Unresolved Item 89-11-03.Rev Incorporates Changes Assuring That Applicable Initiating Conditions,Per NUREG-0654,addressed JPN-90-055, Forwards Comments on Installation of Hardened Wetwell Vent at Plant,Per 891027 Response to Generic Ltr 89-16.Concludes That Hardened Vent Not Cost Beneficial & Consideration of Mods Be Deferred Until Individual Plant Evaluation Complete1990-07-25025 July 1990 Forwards Comments on Installation of Hardened Wetwell Vent at Plant,Per 891027 Response to Generic Ltr 89-16.Concludes That Hardened Vent Not Cost Beneficial & Consideration of Mods Be Deferred Until Individual Plant Evaluation Complete 05000333/LER-1990-012, Advises That Suppl Rept to LER 90-012 Re Svc Water Check Valves Will Be Submitted by 9008201990-07-18018 July 1990 Advises That Suppl Rept to LER 90-012 Re Svc Water Check Valves Will Be Submitted by 900820 05000333/LER-1989-012, Advises That Suppl to LER 89-012-00 Re Postulated Fault 4 Kv Bus Fault Will Be Submitted by 9009041990-07-16016 July 1990 Advises That Suppl to LER 89-012-00 Re Postulated Fault 4 Kv Bus Fault Will Be Submitted by 900904 ML20044A9311990-07-0606 July 1990 Responds to NRC 900611 Ltr Re Violations Noted in Insp Rept 50-333/90-17.Corrective Action:Suspended Surveillances Reinstated on 900507 ML20043J0101990-06-21021 June 1990 Forwards Application for Amend to License DPR-59,making Temporary Change Re LPCI Pump Flow Permanent,Per 900228 Ltr. Change Reduced Surveillance Test Flow Acceptance Value for RHR Pump JAFP-90-0468, Informs That Licensed Operator Requalification Training Program at Plant Completed Transition to Program Based on Sys Approach to Training as Ref to in 10CFR55.4 & 591990-06-14014 June 1990 Informs That Licensed Operator Requalification Training Program at Plant Completed Transition to Program Based on Sys Approach to Training as Ref to in 10CFR55.4 & 59 ML20043G2491990-06-12012 June 1990 Forwards Application for Amend to License DPR-59,revising Tech Specs to Reflect Containment Isolation Valves in RHR & Core Spray keep-full Sys ML20043F5931990-06-11011 June 1990 Forwards GE Nonproprietary Rept, GE11 Lead Test Assembly Fo Ja Fitzpatrick Nuclear Power Plant Reload 9 Cycle 10 & Proprietary Rept GE11 Lead Test Assembly Fuel Bundle.... Proprietary Rept Withheld (Ref 10CFR2.790) ML20043G6131990-06-11011 June 1990 Responds to Notice of Violation & Proposed Imposition of Civil Penalties in Amount of $75,000 Re Radiation Exposure. Corrective Actions:Worker Decontaminated & Examined by Physician.Civil Penalty Fee Transferred Electronically ML20043H0851990-06-11011 June 1990 Forwards Reload 9/Cycle 10 Core Operating Limits Rept. ML20043G7561990-06-11011 June 1990 Forwards Application for Amend to License DPR-59 Re Performance Discharge Testing of 125-volt Dc Batteries & LPCI Motor Operated Valve Independent Power Supplies ML20043H0451990-06-0808 June 1990 Responds to NRC 900509 Ltr Re Violations Noted in Insp Rept 50-333/90-02.Corrective Actions:Refuel Floor Work Stopped, Chief Radiation Protection Technician Disciplined & Importance of Following Procedural Guidelines Reinforced ML20043E8911990-06-0707 June 1990 Forwards IGSCC Insp 1990 Refueling Outage Summary Rept Addendum ML20043C3381990-05-31031 May 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec 5.5.B to Increase Number of Spent Fuel Assemblies That Can Be Stored in Spent Fuel Pool ML20043C5091990-05-30030 May 1990 Forwards Application for Amend to License DPR-59,updating Tech Spec Tables 3.2-8 & 4.2-8 to Reflect Installation of post-accident Monitoring Instrumentation,Per Reg Guide 1.97 & Deleting Tables 3.2-6,4.2-6 & 4.7-1 ML20043C7411990-05-25025 May 1990 Forwards Structural Evaluation of Indications in Reactor Top Head at Ja Fitzpatrick Power Station, Based on Evaluation Analyses for Flaw Indications Identified During Routine Inservice Insps ML20043A7681990-05-16016 May 1990 Responds to NRC Bulletin 90-002, Loss of Thermal Margin Caused by Channel Box Bow. Channel Boxes Not Reused After First Lifetime.Methodology Developed by Ge,Vendor for Plant, Used to Account for Channel Bow ML20043B1021990-05-14014 May 1990 Responds to NRC 900412 Ltr Re Violations Noted in Insp Rept 50-333/90-01.Corrective Actions:Disciplinary Actions Taken & Job Performance Counseling Provided Re Responsibilites for Control Room Operations & Command in Control Room ML20043A7471990-05-14014 May 1990 Responds to NRC 900413 Ltr Re Violations Noted in Insp Rept 50-333/90-13.Util Requests That Notice of Violation Be Withdrawn & Reclassified as Deviation & That Submittal of Inaccurate Info Be Considered Isolated Case ML20042G8271990-05-0909 May 1990 Responds to NRC 900410 Ltr Re Violations Noted in Insp Rept 50-333/90-11.Corrective Actions:Mod Error Corrected,New Transmitters Installed & Mod Procedures to Be Revised to Assign Responsibility for Calibr Points Value Calculation ML20042F3891990-04-30030 April 1990 Responds to Generic Ltr 89-19, Request for Action Re Resolution of USI A-47, 'Safety Implication of Control Sys in LWR Nuclear Power Plants.' ML20042E6251990-04-20020 April 1990 Forwards Application for Amend to License DPR-59,changing Tech Specs to Remove cycle-specific Parameter Limits & Ref Core Operating Limits Rept Which Contains Limits,Per Generic Ltr 88-16 ML20012F0361990-04-0505 April 1990 Forwards Temporary Addendum Rept for Rev 1 to Security Plan. Rept Withheld (Ref 10CFR73.21 & 2.790(d)(1)) ML20012F2161990-04-0202 April 1990 Forwards Application for Amend to License DPR-59,revising Sections 3.5.F & 4.5.F of Tech Specs, Min ECCS Availability. ML20012C9821990-03-13013 March 1990 Forwards Application for Amend to License DPR-59,changing Tech Spec Section 4.9.F, LPCI Motor-Operated Valve Independent Power Supplies, on Page 222a.Changes Purely Editorial in Nature & Revises Surveillance Requirement ML20012C0441990-03-0909 March 1990 Forwards Application for Amend to License DPR-59,clarifying Spec 3.9.B.3 Re Diesel Generator Operability to Eliminate Erroneous Ref to Both Diesel Generator Sys ML20012A1021990-03-0101 March 1990 Forwards Inservice Insp Hydrostatic Test Program for Class 2 & 3 Sys Conducted During First 10-Yr Insp Interval. Relief Requested for Second 10-yr Insp Interval for Hydrostatic Relief Requests Contained in Encl ML20012A0201990-02-28028 February 1990 Forwards Response to NRC SALP Initial Rept 50-333/88-99 for May 1988 - Sept 1989.Emergency Operating Procedures Being Upgraded to Rev 4 of Emergency Procedures Guidelines & Will Be in Place Upon Startup from Spring Refueling Outage ML20012A9301990-02-28028 February 1990 Forwards New York Power Authority Ja Fitzpatrick Nuclear Power Plant Effluent & Waste Disposal Semiannual Rept Jul-Dec 1989 & Rev 7 to Odcm. JPN-90-016, Requests That 900209 Application for Amend to License DPR-59 Be Processed on Emergency Basis & Approved by 900225 to Avoid Premature Plant Shutdown1990-02-21021 February 1990 Requests That 900209 Application for Amend to License DPR-59 Be Processed on Emergency Basis & Approved by 900225 to Avoid Premature Plant Shutdown ML20006E3921990-02-13013 February 1990 Forwards Response to Generic Ltr 89-13, Svc Water Sys Problems Affecting Safety-Related Equipment. Testing of Circulating Water/Svc Water Sys for Mussels Will Begin Spring 1990 ML20006E2681990-02-0909 February 1990 Forwards Application for Amend to License DPR-59,revising Tech Specs Re RHR Pump Operability ML20006E3321990-02-0808 February 1990 Notifies Second 10-yr Inservice Insp Interval Scheduled to End in Jul 1995 & Valve Insp During 1990,91 & 93 Refueling Outages ML20006C8271990-01-29029 January 1990 Responds to NRC 891229 Ltr Re Violations Noted in Insp Rept 50-333/89-21.Corrective Action:Background Instrumentation Results Will Be Reviewed on Periodic Basis ML20006C3811990-01-29029 January 1990 Forwards Preoutage IGSCC Insp Plan for Upcoming 1990 Refueling Outage.Util Will Not Routinely Submit Preoutage Plans in Future Per Generic Ltr 88-01 & NUREG-0313 ML20006A7771990-01-19019 January 1990 Responds to NRC Bulletin 89-002, Stress Corrosion Cracking of High Hardness Type 410 Stainless Steel Internal Preloaded Bolting in Anchor Darling Model S350W Swing-Check Valves or Valves of Similar Design. No Insp of Valves Performed ML19354E0341990-01-16016 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec 4.11.B.2, Crescent Area Ventilation to Require Calibr of Existing Temp Indicator Controllers or New Temp Control Switches ML19354E0321990-01-16016 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec Section 4.7.A.2 & Associated Bases Re Primary Containment Leak Rate Testing Requirements ML19354E0421990-01-16016 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Specs Re Augmented Inservice Insp of Main Steam & Feedwater Piping Welds.Spec 4.6.F.2, Structural Integrity & Associated Bases on Pages 144 & 153 Deleted ML19354D8861990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,modifing Tech Spec Table 3.7.1, Process Pipeline Primary Containment & Table 4.7.2, Exception to Type C Tests to Replace Traversing in-core Probe Sys ML19354D8701990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,revising Note 16 to Table 3.1-1 & Note 9 to Table 3.2-1 to Increase Main Steam Line High Radiation Monitor Trip Level Setpoint During Operating Cycle 10 ML19354E0531990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec 3.6.A, Pressurization & Thermal Limits, to Comply W/Generic Ltr 88-11 & Reg Guide 1.99,Rev 2 ML20005G7191990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,revising Tech Spec Table 3.2-2, Instrumentation That Initiates or Controls Core & Containment Cooling Sys to Change Second Level Undervoltage Trip Setpoint for 1990 Refueling Outage ML20006A4021990-01-12012 January 1990 Forwards Application for Amend to License DPR-59,removing cycle-specific Parameter Limits from Tech Specs & Relocating Limits to Core Operating Limits Rept,Per Generic Ltr 88-16 ML20005G2671990-01-0909 January 1990 Forwards Application for Amend to License DPR-59,changing Safety Limit Min Critical Power Ratio from Current Value of 1.04 to 1.07 to Support Cycle 10 Reload Fuel Design 1990-09-07
[Table view] |
Text
"; i 6 James A.MtsPetrick
< . 3 w 6 -s . Nuoteer Power Mont
.s. c. P.o. Box 41 .
[a4V. t Lycoming, Neo York 13093 :
315 342 3840 .
.[
E 2 4
"i. William Femandez 11
- Resident Manager 1
' June l11, 1990 m JAFP-90-0456 United States Nuclear Regulatory Commission Mail Station Pl-137
, Washington, DC 20555 Attention: Director, Office of Enforcement J
SUBJECT:
RESPONSE TO-NOTICE OF VIOLATION AND PROPOSED IMPOSITION OF CIVIL PENALTY NRC INSPECTION NO. 50-333/90-12
REFERENCE:
a) USNRC letter dated May 10,-1990 on the same subject m EXPOSURES: 1) Response to Notice of Violation.
- 2) Long Term Corrective Actions Gentlemen:
The Authority agrees with the collective findings in the Notiet of Violations:and proposed imposition of civil penalties promulgated by reference (a).
Funds in'the amount of $75,000 for the assessed civil penalty have been transferred. electronically to the treasurer of the United States.
The Authority does request that the NRC review the decision basis for: the portion of the civil penalty above the base amount.
Reference (a) cited'several reasons why mitigation of the base penalty was not warranted.- As detailed in enclosure (1), several of these reasons are incorrect.
The NRC became involved with the investigative process very promptly after the incident. Accordingly, the NRC became aware of n ny of the issues in parallel with the Authority.
f hY nm% ,
Il
5
. .- c. ,
~. .
Director, Office of Enforcement' '
_ June 11,,1990 U.S. Nuclear Regul'atoryECommission: .
'JAFP-90-0456 ,
Washington, DC 20555 Page ~2- ,
Discussions with NRC staff personnel prior to the enforcement conference focused onsthe desire to, discuss the generic. problems common to the March 8, 1990 event-and.the other non-routine radiologicalievents of the past several years. As a result =,.the broader issues of the event were stressed during the enforcement conference. The Authority believes.that it is inappropriate to use the information thus obtained as a basis for escalating or not mitigating the civil penalty above the base amount.
Very truly yours,
/V ,
WILLIAM FERNhNDEZ WP:ls J Enclosures ~
cc: R. Liseno 'NRC Resident Inspector G,-Vargo .
T. Martin, NRC Region 1 J.C. Brons (NYPA/WPO) NRC Document Control Desk R. Beedle (NYPA/WPO)- WPO Records Management J. Elmers' (NYPA/WPO) M. Knapp, NRC Region 1-DRSS Document Control Center -
CERTIFIED MAIL, RETURN RECEIPT REQUESTED j
n
?
.j
,7 y
' ~ '
i
-U.S._ Nuclear Regulatory Commission- Page 1 of 9-Mail Station F1-l'37 Washington, DC 20555 a BNCLOSURE i NOTICE OF VIOLATION A. 10 , CFR 20.101(a) limits the total occupational radiation exposure to the hands of an_ individual in a restricted area to 18.75 rem'per calendar quarter.
Contrary to the above, during the first calendar quarter of 1990, specifically on March 8, 1990, a Radiation and Environmental Services (RES) technician working in the Sample Sink area of the Radwaste Building, a restricted- area, ;
received a total _ radiation exposure to the thumb of the left I hand of 48.8 rems while providing radiological coverage;for I a job involving the injection of sodium-24 (Na-24) into the reactor feedwater system during a feedwater flow test. The. L exposure on March 8, 1990 resulted in a cumulative extremity I exposure of the individual for the calendar quarter of 49.06 l rems.
B. Technical Specification 6.11 '(Radiation Protection Program) states that procedures for- personnel . radiation protection shall be: prepared and ' adhered to for all plant - operations. ,
These procedures-shall be formulated to maintain radiation- l exposures =. received during operation and maintenance as far
-below the._ limits specified'in 10 CFR 20 as practicable. The procedures shall address planning, preparation,.and training for operation and maintenance activities. They shall also
": include exposure allocation, radiation and contamination'and control techniques, and final debriefing.
- 1. Radiation Work Permit Procedure (RPP-4), Section 1.O, states, in part, that the purpose of the Radiation Work Permit (RWP) is to achieve good- radiation exposure control. Section 6.3.2 states that an RWP-is required-for jobs where special hazards are involved.
Contrary to the above, neither station approved work procedure - NWT-INSOL, Revision 0 (Preparation of Na-24 Injection _ Solution) nor Radiation Work-Permit (RWP).No.
90-0534-S~, both of which were established for a special hazards job involving the injection of Na-24 into'the reactor feedwater system of March 8, 1990, were adequate to maintain radiation exposure as far below the limits specified in 10 CFR Part 20 as practicable in that the work. procedure and the RWP did not achieve good radiological controls. Specifically, these documents did L not:
l
o- ,
, 4 j-I ~
q f' N - . , ,
1
- U.S.cNuclear Regulatory. Commission Page 2 of 9 -1 Mail-Station'P1-137-
- WashingtonF DC 20555 l~ a .' require any protective clothing for the Radiation l and Environmental . Services .(RES) technician
-(providing health physics job coverage) . entering and working in the Na-24 preparation and injection I area.;
kI iu ,
- b. provide any requirements for performing personnel contamination monitoring at or near the Na-24 <
L preparation and injection area;
- c. inform the workers that Na-24 was a beta radiation i emitting isotope necessitating a - beta radiation-survey of;the work area; and
- d. provida any_ special- instructions or precautions cautioning against the direct handling of the Na-24:
capsule or capsule cap because of the potential for substantial levels of- high specific activity contamination remaining on the capsule or cap 'after -
'the removal of its contents, or as how to deal with a Na-24 leak at the preparation and injection area, #
should-one occur.
- 2. Station" a'pproved work procedure NWT-INSOL, . Revision 0-describes: the procedural' steps for opening the Na-24 shipping cask and preparing the injection solution. Step D;
', ;15'(a procedure step designed to minimize contamination)-
l requiresithat the Na-24 capsule cap be removed;by using e , the removal tool and tongs or tweezers, andithat the cap be'placed in a disposable container. ;!
n Contrary to the above, on March 8, 1990, Step 15 of NWT- !
L 'INSOL, Revision 0 was not adherod to in that: <
- a. the NS-24 capsule cap was not placed in a disposable container after it removed from-the capsule'by the-vendor employees; and L,
- b. the RES technician picked up the capsule cap with a glove on his right hand (rather than'a removal-tool, tongs or tweezers) and placed it back on the capsule.
These i violations have been categorized in the aggregate as a
-Severity Level III problem. (Supplement IV)
Civil Penalty - $75,000 (assessed equally among the violations).
o .
e L
U.S. Nuclear-RegulatoryJCommission Page 3 of 9 Mail Station.P1-137 Washington, DC 20555 -
REPLY A. Violation of 10 CFR 20.101(a)
Admission or, Denial-of the Violation:
The~ Authority agrees with the violation of 10 CFR 20.101.
Reason for the violation:
T The violation occurred due to inadequate radiological controls cited in Part B of the Notice of Violation.
Corrective stens and results:
Corrective actions- for this event included decontamination of.
the-worker,. examination of the worker by a physician and a-detailed assessment of the.radiobiologically significant dose received by the worker.
The worker was' restricted from further occupational radiation exposure following'this event through the end of the calendar quarter endingLMarch 31, 1990. The worker was permitted to resume normal activities that involve or potentially involve' occupational radiation exposure with the beginning of the new calendar quarter.
Corrective stens that will' be taken to orevent further violation and-da$e when full comoliance will be achieved:
Enclosure 2 details the Authority's long-term corrective actions to this Notice of Violation.
B. 212Jation of TechniqAl Soecification 6.11' Admission or denial of the Violation:
The Authority agrees with the violation.
Reason for the violation:
The violation cited in B.1 resulted from weaknesses in-the radiation _ work permit (RWP). procedure,. the ALARA review process and training. The violation cited in B. 2 resulted from inadequate review of work procedures.
a -
i
- _U.S.-Nuclear Regulatory Commission Page 4 of 9 Mail Station Pl-137
-Washington,.DC- 20555 Corrective stens and results:
Corrective actions taken prior to the second performance of the sodium-24'(Na-24) feedwater flow test included upgrading of- the radiological controls and protective clothing requirements-for the work activity and specific training of
-workers in the unique circumstances of the task. In addition, a review of the adequacy of the radiological controls was performed by an independent radiation specialist.
The Resident Manager reviewed this incident and the implications to maintenance, construction and radiological supervisors and foremen. Especially stressed was the inappropriate reduction of protective radiological controls for personal' convenience. In a similar fashion,-department.
supervision counseled the radiological protection staff in the need to maintain a conservative and questioning attitude when dealing with non-routine radiologically sensitive. work.
The event was independently evaluated by INPO using their Human Performance Enhancement System (HPES). The review identified weaknesses in procedures (including not using a disposable contain'er) , training . and ' supervision similar to those identified in Inspection Report 90-12 and the Authority's own assessment.
Third-party' review of radiological work requiring an i ALARA review are being performed by an: independent Certified Health Physicist. Management observations of radiological work practices and the adoquacy of radiation work permits have been-increased and the Authority has contracted outside radiological protection specialists to assist in job reviews end observations of radiological protection technician 1
performance and worker practices. These reviews of radiologically _ sensitive work will continue until the long-term ALARA Procedural actions described in Enclosure 1 (paragraph 2A) are implemented.
Corrective steos- that will be taken to avoid further violation:
Refer to 2nclosure 2 which contains the Authority's long-term ec/rrective actions to this Notice of Violation.
DJlLtJLwhen 'f ttFL comoliance will be achieved:
Retor to Enclosure 2 for the specific implementation schedule of corrective actions and programmatic upgrades.
y g 4 4
= U.S.; Nuclear' Regulatory Commission Page 5 of 9 Mail Station F1-137 Washington, DC 20555 C. Other Comments:.
After reviewing the t'cansmittal letter of May 10, 1990, the Authority has identified several statements which we believe are in error or require further: clarification:
One paragraph states "Although you promptly reported this-incident to the ERC,' ybu did not identify.several significant
, contributing de 'iciencies in; the planning and preparation for this evolution ... Specifically you did' not identify that inadequate protective clothing l requirements in_ the -RWP contributed!toithe contamination,' noridid you' identify lthat a contamination control stepfin work procedure had not:been
-followed."- This statement is incorrect. At the time the incident was reported to _ the NRC, the investigation was ongoing and incomplete. The reports to the NRC were.made as soon as practical following discovery of the potential significance of the-event. During the enforcement conference, as documented in your meeting report for Inspection 90-12, inadequate- a'ssessment of risk, reductions in' protective clothing requirements and weak procedures were addressed (Tab 1.2 of the Authority's presentation). In addition, the Authority stated' that an- independent human -performance in cstigation.was to.be performed by INPO. Their report was finalized and1 transmitted to the Authority on April 26, 1990.
The same paragraph also states that " . . .- your long term
-corrective actions, as.Let forth-in your presentation at the enforcement conference, .were not considered comprehensive, in that weaknesses in the radiation work permit procedure and technician training to improve awareness of risks associated with infrequent job tasks were not addressed." The Authority disagrees with this assessment. CorrectiveL actions relative to the-radiation work permit program and technician training were addressed during the enforcement- conference, as documented in-your meeting report for Inspection 90-12 (Tab 4.4.B 1 and' 2 of the Authority 8 s presentation) .
While the-specific details of these corrective actions were not presented at the time of the enforcement conference, the Authority clearly recognized the need for improvements in these areno. Specific details were not presented because they had not yet been formalized. Detailed plans and procedures could not be developed due to the relative short time interval More time between the event and the enforcement conference.
was necessary to ensure that long-term corrective actions were sufficiently comprehensive to address the deficiencies identified in this event in addition to other recent events as discussed with the NRC staff. Due to the complex nature
- v. x ' y- ~' - -
- 3 , 7;- ^7
\W +
N4 , ~
v*-
y
-Q u = *: r y n og'
. p.
f_}; ' ' '
a
%l ,
W
.(U.SL Nuclear Regulatory Commission-Page 6 of 9
+ * .' Mail-Station:P1-137 4 , JWashington, DC 20555
- , f a 1 u _of some of the issues identified in our analysis of this and ,
i" ,
other recent events, it was inappropriate to propose specific
_ corrective' actions that might not have been comprehensive.
1{ In pre-conference discussions, NRC' staff members stressed the n -importance of addressing the root causes of the March 8, 1990
'n -
event as related- to: other similar non-routine events- at i g FitzPatrick. The Authority' agreed and consequently avoided' P addressing this most recent event as an isolated incident. .
o Special emphasis was.given_to the broader implications of-the
, [, " '
A March 8, 1990 overexposure.
- n. '
l- The-Authority undertook a considerable effort to accurately
,' 'y assess the actual dose receivrid by the worker from the March L 8,1990 contamination event. This assessment involved outside' j b '
consultants' including' a recognized exrert in radiation l
, dosimetry and a licensed physician. On the basis of these assessments, we believe that the actual 6ose received by the.
worker was 17.39 rems as opposed.to the 49.06 rems cited.
4 ,
A considerable body of scientific evidance published by the P ,
International Commission on Radiological Protection (ICRP ,
Ew J , Report 23) and others, indicates that the critical tissue in 1 the case of the extr% ties (the basal layer of the epidermis) g is. _ at a depth ; co'. iderably greater than the present- NRC .;
Regulatory Guidancu ;f 7' mg/cm' . In this particular case the 1 0 .
depth of _ this layer is' on the order of 64- mg/cm' . The use of-n m the 49.06crem dose assessment is, we believe, given the circumstances;of'the exposure and misrinappropriate epresents the
i m radiobiological. significance-of the contamination event, g< 1 I
k l ?
i ,!; -l l
n, l
'( t m
l' >
h -
1 J. ,
r- I
!l
.), I'
) ,
y-e w 6
R U.S. Nuclear Regulatory Commission Page 7 of 9 Mail Station P1-137 Washington, DC 20555 ENCLOSURE 2 Long-Term corrective and Preventive Actions to Improve Management control and oversight of Non-Routine Radiologically Significant Activities
- 1. Organisation and Personnel Responsibility Improvements Management controls on non-routine radiologically significant activities will be strengthened through the procedures and programs described below. These improvements include progressively higher management approvals proportional to increased radiological risk, especially for first-time or infrequently performed tasks.
As a result of the several radiological events over the past few years, the Authority recognizes that organization and personnel responsibilities and accountabilities need to be clarified, improved and/or changed to ensure that they are not fragmented or diluted. To address these needs, a staffing study and organizational review has been initiated with completion scheduled by the end of 1990. In addition, the expectations and responsibilities required of all personnel to produce a high level of professionalism will be better defined and promulgated by the end of 1990.
- 2. Procedures and Programs A. ALARA Review The existing ALARA Review process will be enhanced significantly. The present procedure is used for various types of ALARA Reviews including design activities, operations, modifications, maintenance and special evolutions such as the sodium-24 feedwater flow test.
Presently, the procedure only requires escalated management approval on the basis of collective dose (i.e.
man-rem) and does not address overall radiological risks (e.g. high dose rates, high airborne or contamination potential.)
The ALARA process and procedure is to be enhanced to require expanded radiological assessments for specific types of work (e.g. spent fuel pool work) as well as for those conditions when actual or anticipated radiological conditions are above some trigger level.
= - ,- .
- ,3 m hh ,
,3.-_.. ,
U~S. Nu$ lear: Regulatory Commission
. Pagei8 of 9
-Mail Station'P1-137 .
n.? Washington,LDC'"205S5 The radiological assessments will include a review:of.the plant operating' experience data base, en evaluation of-
- credible abnormal or accident scenarios 1knd' contingency plans' for - such scenarios. - The procedures - will also require progressively higher levels of management approval based on overall radiological risk, rather than the current requirement for such approvals that is based v strictly on: collective dose.
s i
This' effort will be complated by September 30, 1990.'
B. -Radiation Work Permit s As aJresult of management assessuents previous toithis event, the Authority had already decided to undertakeEa4 major upgrade-of the FitzPatrick-radiation work permit (RWP) program. The= primary purpose of this upgrade.is to enhance the effectiveness of the RWP procedures while
. reducing the unnecessary administrative burdenJimposed
- bythe existing system. One expected benefit of this-upgrade-is-to' allow additional 4 technician resources to be focused ~on,in-plant observation and job' coverage..
=ThisJ upgrade will provide clearer; guidance on minimum
- acceptable protective requirements-and; instructions for.
RWP j ob' coverage' and ~ require progressive: management approval. for variances from -normal , protective-requirements. :The = procedure will also (formalize when -
supervisory - ' approval 'is . required prior) to work commencements.
The Authority expects ' implementation of the upgraded RWP 1 program by December 31, 1990, 1
~ C. Procedures for Radiological Work-Activities The' structure and quality of vendor procedures for the performance of the sodium-24 feedwater flow test was less
> than adequate because the procedures ' were : not in'the , ,!
- Authority's normal format. In addition, radiological .L controls.were not integrated into the vendors procedure which was considered to be the governing document for the test procedure.
i,
- q. The radiological assessment process' defined in 2A above, W' will. include guidelines and thresholds above which g- . radiological controls need to be fully integrated into non-routine significant radiological work procedures,.
rather than relying on a general reference to radiological requirements.
1 l
u f
1'
-y
. {f l t' .,
Lip 01: >
g
< w, , # 37 ;>" , .
- L 6: N s
.U!S.1 Nuclear > Regulatory Commission .Page 9 of 9 MailtStation P1-137, a
[" yLWashington,~DC 20555 ,
,. i
% ^
4_
- 3. Training.
. ,T A. Technician Training
+
b >
H As a result of the non-routine radiological events,over i the past- few years, the need to upgrade the qualification and training . (especiallyc continuing 1 training) programs for radiological technicians has'become quite evident.
p M Y The .present' union job.. description / trdining and:
4 M
qualification 1 program .is definedt ~for- 'ni~ combined j
. radiological / chemistry technicien. This program has , H resulted.'in a dilution'of the, specific skills) required s M for - radiological . technicians. . Changes inlthe ioverall 1 1 program, are -beingl pursued to L, increase .the._overall j effectiveness. These changes include.
.1 , g I
Higher qualification standards to become- a; technician. tj q
- A redefined qual'ification/ apprentice program. in j
& which an individual would specialize in radiation protection or chemistry.
' ]:
y o
< - Additional instructors to -expand the continuing ,l
. training program ,which will( support: the C (4; '
specialization of technicians.-
s i
These changes are subject to union negotiation and; as. a result, an' exact date for completion can not beJset. 7' Nevertthe less, this overall upgrade should-be in effect by December.of 1990.-
.c .B. t Supervisory Training
.\..
The procedures for, management. control and-oversight of 4 m radiologically significant activities:are contained in. , s W
different plant procedures. Specific training 1for the i
,. radiological' . protection management staff will be iY Y, conducted to review the requirements of each .of these l
? ,
procedures. 'In additiori, training- in observation
,m itechniques has. been or w
. ill 'be completed. for' the radiological protection management staff.
First-line radiological protection supervisors will ,
1 attend applicable portions;of the upgraded continuing !
M 'W training program' for radiological protection technicians.
i m
- ) .
l-
! hi