MONTHYEAR1CAN109906, Forwards Framatome Technologies,Inc non-proprietary TR BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheet of Once-Through Sgs, Rev 11999-10-19019 October 1999 Forwards Framatome Technologies,Inc non-proprietary TR BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheet of Once-Through Sgs, Rev 1 ML20217J4971999-10-18018 October 1999 Requests Addl Info Re Results of Util Most Recent Steam Generator Insp at ANO-2 & Util Methodology Used to Predict Future Performance of SG Tubes ML20217J3871999-10-15015 October 1999 Informs That Topical Rept BAW-10235P, Management Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through SG, Rev 0 Marked as Proprietary Will Be Withheld from Public Disclosure 2CAN109902, Submits Withdrawal of Code Case N-593 for ANO-2 Replacement SGs1999-10-15015 October 1999 Submits Withdrawal of Code Case N-593 for ANO-2 Replacement SGs ML20217J3601999-10-15015 October 1999 Informs That Topical Rept BAW-10235P, Management Program for Volumetric Outer Diameter Integranular Attack in Tubesheets of Once-Through SG, Rev 1 Marked as Proprietary Will Be Withheld from Public Disclosure 2CAN109903, Forwards Response to RAI Re Proposed Tech Specs Change for Special SG Insp1999-10-14014 October 1999 Forwards Response to RAI Re Proposed Tech Specs Change for Special SG Insp ML20217D1721999-10-0808 October 1999 Forwards RAI Re 990729 Request for Amend to TSs Allowing Special SG Insp for Plant,Unit 2.Questions Re Proposed Insp Scope for Axial Cracking Degradation in Eggcrate Support Region Submitted.Response Requested by 991015 1CAN109905, Discusses Insp of Once Through SG Tubing Surveillance Performed During 1R15 Scheduled RFO on 990910.Category C-3 Results,Included1999-10-0404 October 1999 Discusses Insp of Once Through SG Tubing Surveillance Performed During 1R15 Scheduled RFO on 990910.Category C-3 Results,Included ML20212L0621999-10-0101 October 1999 Forwards Safety Evaluation & Exemption from Certain Requirements of 10CFR50,App R,Section III.G.2, Fire Protection of Safe Shutdown Capability 1CAN099908, Withdraws 990919 Exigent TS Change Request to Allow Continued Installation of re-rolls for One Cycle of Operation Through End of Cycle 16 in Conjunction with Addl Insp Criteria1999-09-30030 September 1999 Withdraws 990919 Exigent TS Change Request to Allow Continued Installation of re-rolls for One Cycle of Operation Through End of Cycle 16 in Conjunction with Addl Insp Criteria 2CAN099902, Requests That NRC Assign CENPD-132,Suppl 4-P, Calculative Methods for Abb Cenp Large Break LOCA Evaluation Model, Review Priority So That Approval Will Be Granted No Later than Oct 31,20001999-09-29029 September 1999 Requests That NRC Assign CENPD-132,Suppl 4-P, Calculative Methods for Abb Cenp Large Break LOCA Evaluation Model, Review Priority So That Approval Will Be Granted No Later than Oct 31,2000 1CAN099903, Forwards Rev 0 to COLR for ANO-1 Cycle 16, IAW TS 6.12.31999-09-27027 September 1999 Forwards Rev 0 to COLR for ANO-1 Cycle 16, IAW TS 6.12.3 1CAN099907, Requests That Alternative Be Allowed in Accordance with 10CFR50.55a(a)(3)(i) & (II) as Discussed in Encl 1.Encl 2 & 3 Stress Analysis & Flaw Evaluation Summaries Ref in Encl Alternative1999-09-26026 September 1999 Requests That Alternative Be Allowed in Accordance with 10CFR50.55a(a)(3)(i) & (II) as Discussed in Encl 1.Encl 2 & 3 Stress Analysis & Flaw Evaluation Summaries Ref in Encl Alternative 1CAN099906, Forwards 1R15 Growth Data Obtained & Analyzed Through 990922 & Includes Plus Point Voltages,Axial Extent & Circumferential Extent Patches,As Well as Preliminary Growth Conclusions Based on Analysis of Data1999-09-24024 September 1999 Forwards 1R15 Growth Data Obtained & Analyzed Through 990922 & Includes Plus Point Voltages,Axial Extent & Circumferential Extent Patches,As Well as Preliminary Growth Conclusions Based on Analysis of Data 2CAN099901, Informs That G Kendrick,License SOP-43658,no Longer Has Need to Maintain Operating License on Ano,Unit 2.Entergy Requests That License for Individual Be Withdrawn,Due to Resignation, Effective 9908271999-09-24024 September 1999 Informs That G Kendrick,License SOP-43658,no Longer Has Need to Maintain Operating License on Ano,Unit 2.Entergy Requests That License for Individual Be Withdrawn,Due to Resignation, Effective 990827 2CAN099904, Forwards Ano,Unit 2 10CFR50.59 Rept for Time Period Ending 990225.Rept Contains Brief Description of Changes in Procedures & in Facility as Described in Sar,Tests & Experiments Conducted & Other Changes to SAR1999-09-23023 September 1999 Forwards Ano,Unit 2 10CFR50.59 Rept for Time Period Ending 990225.Rept Contains Brief Description of Changes in Procedures & in Facility as Described in Sar,Tests & Experiments Conducted & Other Changes to SAR ML20212F5031999-09-22022 September 1999 Forwards SER Granting Relief Requests 1-98-001 & 1-98-002 Which Would Require Design Mods to Comply with Code Requirements,Which Would Impose Significant Burden Pursuant to 10CFR50.55a(g)(6)(i) 1CAN099905, Submits Supplemental Info in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria.Proposed TS Rev & Info Related to Use of Alternate Repair Discussed in Attachments1999-09-17017 September 1999 Submits Supplemental Info in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria.Proposed TS Rev & Info Related to Use of Alternate Repair Discussed in Attachments ML20212D9961999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of Arkansas Nuclear One.Nrc Plan to Conduct Core Insps at Facility Over Next 7 Months.Details of Insp Plan Through March 2000 Encl 1CAN099902, Forwards Proprietary Rev 1 to Topical Rept BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs, in Response to 990831 Rai.Proprietary Encl Withheld1999-09-15015 September 1999 Forwards Proprietary Rev 1 to Topical Rept BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs, in Response to 990831 Rai.Proprietary Encl Withheld 2CAN099905, Informs That Jk Caery,License OP-42589 & as Bates,License OP-42506,no Longer Need to Maintain Operating License at Ano,Unit 2.Withdrawal of Licenses Is Requested1999-09-0909 September 1999 Informs That Jk Caery,License OP-42589 & as Bates,License OP-42506,no Longer Need to Maintain Operating License at Ano,Unit 2.Withdrawal of Licenses Is Requested 1CAN099901, Forwards Responses to 990831 RAI Containing follow-up Questions Discussed on 990823-26,in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria. Revs to Proposed TSs Included in Attachments1999-09-0707 September 1999 Forwards Responses to 990831 RAI Containing follow-up Questions Discussed on 990823-26,in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria. Revs to Proposed TSs Included in Attachments ML20211P4121999-09-0707 September 1999 Requests NRC Staff Review & Approval of Integrated Nuclear Security Plan (Insp) & Integrated Security Training & Qualification Plan (Ist&Q), for Use by All Entergy Operations,Inc.Encl Withheld,Per 10CFR2.790(d) 0CAN099906, Forwards Comments on Ano,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid,Version 2,in Response to NRC 990708 & 0715 Ltrs1999-09-0101 September 1999 Forwards Comments on Ano,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid,Version 2,in Response to NRC 990708 & 0715 Ltrs ML20211L4901999-09-0101 September 1999 Forwards Insp Repts 50-313/99-12 & 50-368/99-12 on 990711- 0821.No Violations Noted ML20211J2351999-08-31031 August 1999 Forwards Request for Addl Info Re SG Outer Diameter Intergranular Attack Alternate Repair Criteria for Plant, Unit 1 ML20211E6161999-08-25025 August 1999 Forwards Amend 15 to ANO Unit 2,USAR,per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of 10CFR50.59 Evaluations Associated with Amend 15 of ANO Unit 2 SAR Will Be Provided Under Separate Cover Ltr with 30 Days 0CAN089905, Forwards Arkansas Nuclear One Units 1 & 2 FFD Program Performance Data for Period Jan-June 19991999-08-25025 August 1999 Forwards Arkansas Nuclear One Units 1 & 2 FFD Program Performance Data for Period Jan-June 1999 ML20211F4181999-08-25025 August 1999 Forwards SE Accepting Licensee 980603 & 990517 Requests for Approval of risk-informed Alternative to 1992 Edition of ASME BPV Code Section Xi,Insp Requirements for Class 1, Category B-J Piping Welds ML20211G0731999-08-19019 August 1999 Forwards Applications for Renewal of Operating License for Kw Canitz & Aj South.Without Encls 1CAN089904, Forwards Addl Info in Support of SG Tube End Cracking Alternate Repair Criteria,In Response to NRC 990728 Rai. Proposed TS Changes Encl1999-08-19019 August 1999 Forwards Addl Info in Support of SG Tube End Cracking Alternate Repair Criteria,In Response to NRC 990728 Rai. Proposed TS Changes Encl ML20211C5101999-08-19019 August 1999 Forwards Certified Copies of Liability Insurance Policy Endorsements Issued in First Half of 1999 for Each Entergy Operations,Inc Nuclear Unit,Per 10CFR140.15 ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl 0CAN089903, Submits Addl Response to NRC Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Gate Valves1999-08-12012 August 1999 Submits Addl Response to NRC Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Gate Valves IR 05000368/19990111999-08-12012 August 1999 Forwards Insp Repts 50-313//99-11 & 50-368/99-11 on 990719-23.No Violations Noted.Insp Focused on Review of Licensed Operator Requalification Program & Observation of Requalification Exam Activities at Unit 1 2CAN089901, Forwards Description of Planned Scope & Expansion Criteria for Special SG Tube Insp,In Support of Proposed ANO-2 TS Amend for 2P99 Special SG Insp Submitted on 9907291999-08-0606 August 1999 Forwards Description of Planned Scope & Expansion Criteria for Special SG Tube Insp,In Support of Proposed ANO-2 TS Amend for 2P99 Special SG Insp Submitted on 990729 1CAN089902, Requests NRC Input on Encl Proposed Draft Format for ANO-1 License Renewal Application,Which Will Provide Option to Continue Operating Plant for Addl Twenty Years Beyond End of Current Operating License1999-08-0505 August 1999 Requests NRC Input on Encl Proposed Draft Format for ANO-1 License Renewal Application,Which Will Provide Option to Continue Operating Plant for Addl Twenty Years Beyond End of Current Operating License 2CAN089902, Informs That Tl Russell,License SOP-43587-1 & Jk Fancher, License OP-42300-1,no Longer Have Need to Maintain Operating License at ANO-2.Withdrawal of Licenses Requested1999-08-0404 August 1999 Informs That Tl Russell,License SOP-43587-1 & Jk Fancher, License OP-42300-1,no Longer Have Need to Maintain Operating License at ANO-2.Withdrawal of Licenses Requested ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams 0CAN089902, Submits 60 Day Response to GL 99-02, Laboratory Testing of Nuclear Grade Activated Charcoal. Proposed Actions That Will Be Taken on ANO Unit 1 RB Purge Filtration Sys & Unit 2 Containment Purge & Exhaust Sys,Clarified1999-08-0202 August 1999 Submits 60 Day Response to GL 99-02, Laboratory Testing of Nuclear Grade Activated Charcoal. Proposed Actions That Will Be Taken on ANO Unit 1 RB Purge Filtration Sys & Unit 2 Containment Purge & Exhaust Sys,Clarified 0CAN089901, Forwards Info Re Estimate of licensee-originated Licensing Actions for ANO-1 & ANO-2,in Response to Administrative Ltr 99-02,dtd 9906031999-08-0202 August 1999 Forwards Info Re Estimate of licensee-originated Licensing Actions for ANO-1 & ANO-2,in Response to Administrative Ltr 99-02,dtd 990603 ML20210L3581999-07-29029 July 1999 Ltr Contract,Task Order 43, Arkansas Nuclear One Safety System Engineering Insp (Ssei), Under Contract NRC-03-98-021 1CAN079903, Forwards non-proprietary Addendum to Rev 0 of Topical Rept BAW-2346P,in Support of Proposed TS Changes Revising SG Tubing Surveillance Requirements to Provide Alternate Repair Criteria for Tube End Cracks1999-07-29029 July 1999 Forwards non-proprietary Addendum to Rev 0 of Topical Rept BAW-2346P,in Support of Proposed TS Changes Revising SG Tubing Surveillance Requirements to Provide Alternate Repair Criteria for Tube End Cracks ML20216D8131999-07-28028 July 1999 Forwards Request for Addl Info Re SG Tube End Cracking Alternate Repair Criteria for Plant,Unit 1 ML20216D3561999-07-23023 July 1999 Discusses non-cited Violation Identified in Insp Rept 50-313/98-21,involving Failure to Have Acceptable Alternative Shutdown Capability for ANO-1 ML20210C2191999-07-21021 July 1999 Forwards Insp Repts 50-313/99-08 & 50-368/99-08 on 990530-0710 at Arkansas Nuclear One,Units 1 & 2,reactor Facility.No Violations Noted.Conduct of Activities at Plant Generally Characterized by safety-conscious Operations ML20209H5251999-07-15015 July 1999 Informs That as Result of NRC Review of Licensee 980701 & 990311 Responses to GL 92-01,rev 1 & Suppl 1 & Suppl 1 RAI, Staff Revised Info in Reactor Vessel Integrity Database & Releasing Database as Rvid Version 2 1CAN079901, Forwards Proposed Changes to Current Util 990409 Submittal Re Rev to RB Structural Integrity Requirements Contained in Plant Ts.Proposed Revs Affect ACs & Applicable Bases Re ISI Reporting for Containment Structures,Tendons & Anchorages1999-07-14014 July 1999 Forwards Proposed Changes to Current Util 990409 Submittal Re Rev to RB Structural Integrity Requirements Contained in Plant Ts.Proposed Revs Affect ACs & Applicable Bases Re ISI Reporting for Containment Structures,Tendons & Anchorages 0CAN079902, Responds to NRC Telcon RAI Re Proposed Administrative Controls TS Changes.Revised TS Pages Which Replaces Pages Previously Provided in 981124 Submittal,Encl1999-07-14014 July 1999 Responds to NRC Telcon RAI Re Proposed Administrative Controls TS Changes.Revised TS Pages Which Replaces Pages Previously Provided in 981124 Submittal,Encl ML20209E5551999-07-0808 July 1999 Informs That as Result of NRC Review of Util Responses to GL 92-01,rev 1,suppl 1,staff Revised Info in Rv Integrity Database & Releasing Database as Rvid Version 2 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEAR1CAN109906, Forwards Framatome Technologies,Inc non-proprietary TR BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheet of Once-Through Sgs, Rev 11999-10-19019 October 1999 Forwards Framatome Technologies,Inc non-proprietary TR BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheet of Once-Through Sgs, Rev 1 2CAN109902, Submits Withdrawal of Code Case N-593 for ANO-2 Replacement SGs1999-10-15015 October 1999 Submits Withdrawal of Code Case N-593 for ANO-2 Replacement SGs 2CAN109903, Forwards Response to RAI Re Proposed Tech Specs Change for Special SG Insp1999-10-14014 October 1999 Forwards Response to RAI Re Proposed Tech Specs Change for Special SG Insp 1CAN109905, Discusses Insp of Once Through SG Tubing Surveillance Performed During 1R15 Scheduled RFO on 990910.Category C-3 Results,Included1999-10-0404 October 1999 Discusses Insp of Once Through SG Tubing Surveillance Performed During 1R15 Scheduled RFO on 990910.Category C-3 Results,Included 1CAN099908, Withdraws 990919 Exigent TS Change Request to Allow Continued Installation of re-rolls for One Cycle of Operation Through End of Cycle 16 in Conjunction with Addl Insp Criteria1999-09-30030 September 1999 Withdraws 990919 Exigent TS Change Request to Allow Continued Installation of re-rolls for One Cycle of Operation Through End of Cycle 16 in Conjunction with Addl Insp Criteria 2CAN099902, Requests That NRC Assign CENPD-132,Suppl 4-P, Calculative Methods for Abb Cenp Large Break LOCA Evaluation Model, Review Priority So That Approval Will Be Granted No Later than Oct 31,20001999-09-29029 September 1999 Requests That NRC Assign CENPD-132,Suppl 4-P, Calculative Methods for Abb Cenp Large Break LOCA Evaluation Model, Review Priority So That Approval Will Be Granted No Later than Oct 31,2000 1CAN099903, Forwards Rev 0 to COLR for ANO-1 Cycle 16, IAW TS 6.12.31999-09-27027 September 1999 Forwards Rev 0 to COLR for ANO-1 Cycle 16, IAW TS 6.12.3 1CAN099907, Requests That Alternative Be Allowed in Accordance with 10CFR50.55a(a)(3)(i) & (II) as Discussed in Encl 1.Encl 2 & 3 Stress Analysis & Flaw Evaluation Summaries Ref in Encl Alternative1999-09-26026 September 1999 Requests That Alternative Be Allowed in Accordance with 10CFR50.55a(a)(3)(i) & (II) as Discussed in Encl 1.Encl 2 & 3 Stress Analysis & Flaw Evaluation Summaries Ref in Encl Alternative 2CAN099901, Informs That G Kendrick,License SOP-43658,no Longer Has Need to Maintain Operating License on Ano,Unit 2.Entergy Requests That License for Individual Be Withdrawn,Due to Resignation, Effective 9908271999-09-24024 September 1999 Informs That G Kendrick,License SOP-43658,no Longer Has Need to Maintain Operating License on Ano,Unit 2.Entergy Requests That License for Individual Be Withdrawn,Due to Resignation, Effective 990827 1CAN099906, Forwards 1R15 Growth Data Obtained & Analyzed Through 990922 & Includes Plus Point Voltages,Axial Extent & Circumferential Extent Patches,As Well as Preliminary Growth Conclusions Based on Analysis of Data1999-09-24024 September 1999 Forwards 1R15 Growth Data Obtained & Analyzed Through 990922 & Includes Plus Point Voltages,Axial Extent & Circumferential Extent Patches,As Well as Preliminary Growth Conclusions Based on Analysis of Data 2CAN099904, Forwards Ano,Unit 2 10CFR50.59 Rept for Time Period Ending 990225.Rept Contains Brief Description of Changes in Procedures & in Facility as Described in Sar,Tests & Experiments Conducted & Other Changes to SAR1999-09-23023 September 1999 Forwards Ano,Unit 2 10CFR50.59 Rept for Time Period Ending 990225.Rept Contains Brief Description of Changes in Procedures & in Facility as Described in Sar,Tests & Experiments Conducted & Other Changes to SAR 1CAN099905, Submits Supplemental Info in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria.Proposed TS Rev & Info Related to Use of Alternate Repair Discussed in Attachments1999-09-17017 September 1999 Submits Supplemental Info in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria.Proposed TS Rev & Info Related to Use of Alternate Repair Discussed in Attachments 1CAN099902, Forwards Proprietary Rev 1 to Topical Rept BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs, in Response to 990831 Rai.Proprietary Encl Withheld1999-09-15015 September 1999 Forwards Proprietary Rev 1 to Topical Rept BAW-10235P, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs, in Response to 990831 Rai.Proprietary Encl Withheld 2CAN099905, Informs That Jk Caery,License OP-42589 & as Bates,License OP-42506,no Longer Need to Maintain Operating License at Ano,Unit 2.Withdrawal of Licenses Is Requested1999-09-0909 September 1999 Informs That Jk Caery,License OP-42589 & as Bates,License OP-42506,no Longer Need to Maintain Operating License at Ano,Unit 2.Withdrawal of Licenses Is Requested ML20211P4121999-09-0707 September 1999 Requests NRC Staff Review & Approval of Integrated Nuclear Security Plan (Insp) & Integrated Security Training & Qualification Plan (Ist&Q), for Use by All Entergy Operations,Inc.Encl Withheld,Per 10CFR2.790(d) 1CAN099901, Forwards Responses to 990831 RAI Containing follow-up Questions Discussed on 990823-26,in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria. Revs to Proposed TSs Included in Attachments1999-09-0707 September 1999 Forwards Responses to 990831 RAI Containing follow-up Questions Discussed on 990823-26,in Support of SG Outer Diameter Intergranular Attack Alternate Repair Criteria. Revs to Proposed TSs Included in Attachments 0CAN099906, Forwards Comments on Ano,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid,Version 2,in Response to NRC 990708 & 0715 Ltrs1999-09-0101 September 1999 Forwards Comments on Ano,Units 1 & 2 Specific Reactor Vessel Info Contained in Rvid,Version 2,in Response to NRC 990708 & 0715 Ltrs ML20211E6161999-08-25025 August 1999 Forwards Amend 15 to ANO Unit 2,USAR,per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of 10CFR50.59 Evaluations Associated with Amend 15 of ANO Unit 2 SAR Will Be Provided Under Separate Cover Ltr with 30 Days 0CAN089905, Forwards Arkansas Nuclear One Units 1 & 2 FFD Program Performance Data for Period Jan-June 19991999-08-25025 August 1999 Forwards Arkansas Nuclear One Units 1 & 2 FFD Program Performance Data for Period Jan-June 1999 ML20211G0731999-08-19019 August 1999 Forwards Applications for Renewal of Operating License for Kw Canitz & Aj South.Without Encls 1CAN089904, Forwards Addl Info in Support of SG Tube End Cracking Alternate Repair Criteria,In Response to NRC 990728 Rai. Proposed TS Changes Encl1999-08-19019 August 1999 Forwards Addl Info in Support of SG Tube End Cracking Alternate Repair Criteria,In Response to NRC 990728 Rai. Proposed TS Changes Encl ML20211C5101999-08-19019 August 1999 Forwards Certified Copies of Liability Insurance Policy Endorsements Issued in First Half of 1999 for Each Entergy Operations,Inc Nuclear Unit,Per 10CFR140.15 0CAN089903, Submits Addl Response to NRC Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Gate Valves1999-08-12012 August 1999 Submits Addl Response to NRC Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Gate Valves 2CAN089901, Forwards Description of Planned Scope & Expansion Criteria for Special SG Tube Insp,In Support of Proposed ANO-2 TS Amend for 2P99 Special SG Insp Submitted on 9907291999-08-0606 August 1999 Forwards Description of Planned Scope & Expansion Criteria for Special SG Tube Insp,In Support of Proposed ANO-2 TS Amend for 2P99 Special SG Insp Submitted on 990729 1CAN089902, Requests NRC Input on Encl Proposed Draft Format for ANO-1 License Renewal Application,Which Will Provide Option to Continue Operating Plant for Addl Twenty Years Beyond End of Current Operating License1999-08-0505 August 1999 Requests NRC Input on Encl Proposed Draft Format for ANO-1 License Renewal Application,Which Will Provide Option to Continue Operating Plant for Addl Twenty Years Beyond End of Current Operating License 2CAN089902, Informs That Tl Russell,License SOP-43587-1 & Jk Fancher, License OP-42300-1,no Longer Have Need to Maintain Operating License at ANO-2.Withdrawal of Licenses Requested1999-08-0404 August 1999 Informs That Tl Russell,License SOP-43587-1 & Jk Fancher, License OP-42300-1,no Longer Have Need to Maintain Operating License at ANO-2.Withdrawal of Licenses Requested 0CAN089901, Forwards Info Re Estimate of licensee-originated Licensing Actions for ANO-1 & ANO-2,in Response to Administrative Ltr 99-02,dtd 9906031999-08-0202 August 1999 Forwards Info Re Estimate of licensee-originated Licensing Actions for ANO-1 & ANO-2,in Response to Administrative Ltr 99-02,dtd 990603 0CAN089902, Submits 60 Day Response to GL 99-02, Laboratory Testing of Nuclear Grade Activated Charcoal. Proposed Actions That Will Be Taken on ANO Unit 1 RB Purge Filtration Sys & Unit 2 Containment Purge & Exhaust Sys,Clarified1999-08-0202 August 1999 Submits 60 Day Response to GL 99-02, Laboratory Testing of Nuclear Grade Activated Charcoal. Proposed Actions That Will Be Taken on ANO Unit 1 RB Purge Filtration Sys & Unit 2 Containment Purge & Exhaust Sys,Clarified 1CAN079903, Forwards non-proprietary Addendum to Rev 0 of Topical Rept BAW-2346P,in Support of Proposed TS Changes Revising SG Tubing Surveillance Requirements to Provide Alternate Repair Criteria for Tube End Cracks1999-07-29029 July 1999 Forwards non-proprietary Addendum to Rev 0 of Topical Rept BAW-2346P,in Support of Proposed TS Changes Revising SG Tubing Surveillance Requirements to Provide Alternate Repair Criteria for Tube End Cracks ML20216D3561999-07-23023 July 1999 Discusses non-cited Violation Identified in Insp Rept 50-313/98-21,involving Failure to Have Acceptable Alternative Shutdown Capability for ANO-1 1CAN079901, Forwards Proposed Changes to Current Util 990409 Submittal Re Rev to RB Structural Integrity Requirements Contained in Plant Ts.Proposed Revs Affect ACs & Applicable Bases Re ISI Reporting for Containment Structures,Tendons & Anchorages1999-07-14014 July 1999 Forwards Proposed Changes to Current Util 990409 Submittal Re Rev to RB Structural Integrity Requirements Contained in Plant Ts.Proposed Revs Affect ACs & Applicable Bases Re ISI Reporting for Containment Structures,Tendons & Anchorages 0CAN079902, Responds to NRC Telcon RAI Re Proposed Administrative Controls TS Changes.Revised TS Pages Which Replaces Pages Previously Provided in 981124 Submittal,Encl1999-07-14014 July 1999 Responds to NRC Telcon RAI Re Proposed Administrative Controls TS Changes.Revised TS Pages Which Replaces Pages Previously Provided in 981124 Submittal,Encl ML20210K1621999-07-0707 July 1999 Informs That Licensee in Process of Preparing Scope of Service Delineation for Environ Assessment to Be Performed for New Airport Located Near Russellville,Ar,To Identify Anticipated Environ Impacts from Various Agencies 1CAN079902, Documents ANO-1 Position Discussed on 990705,with Members of NRC Staff & Formally Requests Enforcement Discretion from Requirements of TS 3.7.2.C to Allow Continued Power of Operation1999-07-0606 July 1999 Documents ANO-1 Position Discussed on 990705,with Members of NRC Staff & Formally Requests Enforcement Discretion from Requirements of TS 3.7.2.C to Allow Continued Power of Operation ML20209B6081999-06-30030 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Disclosure Encl 0CAN069906, Forwards Corrected Pages to 1997 & 1998 Annual Radiological Environ Operating Repts, Issued 980430 (0CAN049804) & 990506 (0CAN059902).Ltr Number & Page Number Are at Top of of Corrected Pages to Replace Originally Pages1999-06-30030 June 1999 Forwards Corrected Pages to 1997 & 1998 Annual Radiological Environ Operating Repts, Issued 980430 (0CAN049804) & 990506 (0CAN059902).Ltr Number & Page Number Are at Top of of Corrected Pages to Replace Originally Pages 1CAN069905, Forwards non-proprietary Version of Rev 0 to TR BAW-10235, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs1999-06-17017 June 1999 Forwards non-proprietary Version of Rev 0 to TR BAW-10235, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs 0CAN069903, Submits Rept of Each Change to or Error Discovered in Acceptable Evaluation Model or in Application of Such Model for ECCS That Affects Peak Cladding Temp,Iaw 10CFR50.46(a) (3)(ii)1999-06-10010 June 1999 Submits Rept of Each Change to or Error Discovered in Acceptable Evaluation Model or in Application of Such Model for ECCS That Affects Peak Cladding Temp,Iaw 10CFR50.46(a) (3)(ii) 2CAN069901, Forwards Probabilistic Operational Assessment of ANO-2 SG Tubing for Cycle 14. Replacement of SGs Planned for Next Refueling Outage (2R14) Scheduled for Fall of 20001999-06-0202 June 1999 Forwards Probabilistic Operational Assessment of ANO-2 SG Tubing for Cycle 14. Replacement of SGs Planned for Next Refueling Outage (2R14) Scheduled for Fall of 2000 1CAN069901, Submits 10CFR50.46 Rept Re Inconsistent Input in SBLOCA Analysis.Rept Submitted in Accordance with Recommendations Stated in Notice1999-06-0202 June 1999 Submits 10CFR50.46 Rept Re Inconsistent Input in SBLOCA Analysis.Rept Submitted in Accordance with Recommendations Stated in Notice 0CAN059906, Forwards Response to NRC 990402 RAI Re GL 96-05, Periodic Verification of Design Basis Capability of Safety-Related Movs1999-05-28028 May 1999 Forwards Response to NRC 990402 RAI Re GL 96-05, Periodic Verification of Design Basis Capability of Safety-Related Movs ML20207E4341999-05-25025 May 1999 Submits 30-day Written Rept on Significant PCT Changes in ECCS Analysis for ANO-1.CRAFT2 Limiting PCT for ANO-1 Was Bounded by 1859 F PCT Calculated at 2568 Mwt for Crystal River 3 Cold Leg Pump Discharge Break Size of 0.125 Ft 1CAN059904, Informs NRC That Wl Franklin No Longer Has Need to Maintain Operating License on Ano,Unit 1.Requests License for Wl Franklin Be Withdrawn1999-05-20020 May 1999 Informs NRC That Wl Franklin No Longer Has Need to Maintain Operating License on Ano,Unit 1.Requests License for Wl Franklin Be Withdrawn 2CAN059906, Informs That ANO-2 UFSAR Will Be Revised to Include Comprehensive Discussions of Each Category of Containment Penetration Overcurrent Protective Devices,Per NRC Review of 980806 TS Change Request Re Relocation of TS Table 3.8-11999-05-18018 May 1999 Informs That ANO-2 UFSAR Will Be Revised to Include Comprehensive Discussions of Each Category of Containment Penetration Overcurrent Protective Devices,Per NRC Review of 980806 TS Change Request Re Relocation of TS Table 3.8-1 1CAN059902, Responds to NRC 990406 RAI Re risk-informed Inservice Insp Pilot Application,Submitted 980603.Approval of Alternative Is Requested Prior to End of July 1999,to Allow Sufficient Time for Util to Revise ANO-1 ISI Program1999-05-17017 May 1999 Responds to NRC 990406 RAI Re risk-informed Inservice Insp Pilot Application,Submitted 980603.Approval of Alternative Is Requested Prior to End of July 1999,to Allow Sufficient Time for Util to Revise ANO-1 ISI Program 2CAN059905, Expresses Appreciation for Staff & Mgt Team Efforts in Aggressively Pursuing Risk Informed ISI Initiative1999-05-14014 May 1999 Expresses Appreciation for Staff & Mgt Team Efforts in Aggressively Pursuing Risk Informed ISI Initiative ML20206P7681999-05-10010 May 1999 Forwards Applications for Renewal of Operating License (Form 398) for MW Little & F Uptagrafft.Without Encl 2CAN059903, Forwards Rev to Footnote Submitted to Provide Clarity to Aforementioned Guidance1999-05-10010 May 1999 Forwards Rev to Footnote Submitted to Provide Clarity to Aforementioned Guidance ML20206N1921999-05-10010 May 1999 Provides Revised Attachment 2 for Alternative Request IWE-02,originally Submitted 990429 Re Bolt Torque or Tension Testing of Class Mc pressure-retaining Bolting as Specified in Item 8.20 of Article IWE-2500,Table IWE-2500-1 ML20206H7121999-05-0606 May 1999 Forwards 1998 Annual Radiological Environ Operating Rept, for Ano.All Radionuclides Detected by Radiological Environ Monitoring Program During 1998 Were Significantly Below Regulatory Limits 1999-09-09
[Table view] |
Text
, ,
Entergy Operations, Inc.
E ENTERGY " * * "'o Ra x W .AR 72601 Tel501 % 48838 Jerry W, Yelverton
%:n hc% lent Lb4$n At()
May 2,1994 OCAN059402 U. S. Nuclear Regulatory Commission Document Control Desk Mail Station Pl-137 Washington, DC 20555 Gentlemen:
Pursuant to the provisions of 10CFR2.201, attached is our response to the Severity Level
!!I problem identified dur'..ig the inspection of activities concerning the failure to recognize that Arkansas Nuclear One (ANO) Unit I, exceeded a Technical Specification required Limiting Condition for Operation for approximately 59 hours6.828704e-4 days <br />0.0164 hours <br />9.755291e-5 weeks <br />2.24495e-5 months <br />. Additionalinformation concerning the violation is contained in Licensee Event Repon 50-313/94-001 transmitted via letter ICAN029403 dated February 25,1994.
Should you have comments or questions please call Mr. Dwight Mims at 501-964-8601.
Very truly yours,
/
d;gyn/
u w/c/du~[
r Attachments To the best of my knowledge and belief, the statements contained in this submittal are true, SUllSCRillED AND SWORN TO before me, a Notary Public in and for b 0%
I County and the State of Arkansas, this 2nd day of May 1994.
& &a Qui 20~
NotaryJ4tilie My Commission Expires 494 2(1.4- - - - - -
PA .imG DAVIDSON Notary Publ!C POPE COUNTY, ARXANSAS Comminion Expues 4 24-2002
~
-~ ~
l 9405100100 9tOfC2.- 3 Ol DR ADOCK'0500 ,
' 1
cc: Mr. Leonard J. Callan Regional Administrator U. S: Nuclear Regulatory Commission Region IV .:
611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One - ANO-1 & 2 Number 1, Nuclear Plant Road Russellville, AR'7280l Mr. George Kalman NRR Project Manager Region IV/ANO-l U. S. Nuclear Regulatory Commission NRR Mail Stop 13-11-3 One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mr. Thomas W. Alexion NRR Project Manager, Region IV/ANO-2 U. S. Nuclear Regulatory Commission NRR Mail Stop 13-11-3 One White Flint North 11555 Rockville Pike Rockville, MD 20852
- -,.,, .w ,- -,n. -, -,
4
s s Attachment to OCAN059402 NOTICE OF VIOLATION During an NRC inspection conducted February 2-9,1994, violations of NRC requirements were identified. In accordance with the " General Statement of Policy and Procedure for
.NRC Enforcement Actions, "10CFR Part 2, Appendix C, the violations are listed below:
A. Technical Specification 3.4.1 states, il part, that the reactor shall not be heated above 280 degrees F unless both EFW pumps and their flow paths are operable.
Technical Specification 3.4.5.1 states, in part, that with one EFW flow path inoperable, the unit shall be brought to hot shutdown within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
Contrary to the above, at approximately 12 a.m. on January 28,1994, one EFW flow path became inoperable due to a malfunctioning steam generator level transmitter (which would have affected automatic flow control in one flow path) and the unit was not brought to hot shutdown within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The unit was brought to hot shutdown at approximately 1:55 p.m. on February 1,1994, approximately 74 hours8.564815e-4 days <br />0.0206 hours <br />1.223545e-4 weeks <br />2.8157e-5 months <br /> afler one EFW flow path became inoperable. (01013)
B. Technical Specification 6.8.1.a requires, in part, that written procedures be established, implemented, and maintained covering the applicable procedures recommended in Appendix A of Regulatory Guide 1.33, November 1972.
Regulatory Guide 1.33, Appendix A, Revision 2, November 1972, lists typical safety-related activities that should be covered by written procedures, including:
(1) administrative procedures governing the authorities and responsibilities for safe operation and shutdown, and (2) administrative procedures governing log entries and record retention.
ANO Procedure 1015.003 A, Revision 31, " Unit One Operation Logs," Section 6.5.4 requires, in pan, that operators perform the following actions when an Operability Difference ("Op. DifT.") value is exceeded: declare the alrected instrument channel or indicator inoperable; initiate a condition report; and implement any actions required by Technical Specification Limiting Conditions for Operation.
Procedure 1015.003A, Section 4.4, defines operability difference values as variations between Technical Specification or other NRC required instrumentation channels monitoring the same parameter which, if exceeded, will constitute -
' instrument component inoperability.
e I
a Attachment to -
OCAN059402 Procedure 1015.003 A, Form 1: i5.003 A-7, "CBO Reactor Logsheet," specifies an operability difTerence of 8 inches for instmmentation channels monitoring Steam Generator Low Range Level and, in Footnote 2, requires that if the operability difTerence limits are exceeded, the SS/CRS (shift superintendent / control room supervisor) be immediately notified, a condition report be written, and the afTected instrument'be declared inoperable.
Section 6.5.2 of ANO Procedure 1015.001, Revision 46, " Conduct of Operation,"
requires, in part, that the Control Board Operator (Reactor) monitor parameters associated with plant operations, recording those which are specified on log sheets,
- and notify the SS or CRS of unusual indications or abnormal trends.
Contrary to the above, from January 2< , .,94, until Januarv 31,1994, the indication from Steam Generator Low Range Level Trar.,mitter LT-2622 varied from the other NRC required instrument channel indications monitoring the same part. meter by more than 8 inches, a value in excess of the specified operability difference, and licensed operators did not: (1) immediately notify the SS/CRS that the operability limit was exceeded; (2) decir.re Low Level Transmitter LT-2622 inoperable; (3) initiate a condition report; and (4) implement actions required by the Technical Specifications Limiting Conditions for Operation for an inoperable EFW fVw path (0_1023)
These violations represent a Severity Level III problem (Supplement I) i 6
b 2-e- -- -- __--.__---
-- - . ~.- -- . .-
Attachment to O' OCAN059402 Respnnselp violation 313/9412-01;j68/9412-01 (1) Ikason fpr the violation; .>
On January 22,1994, Once Through Steam Generator (OTSG) Level Indicator LI-2622, the indicator for level transmitter LT-2622_, was noted to be greater than the allowable maximum normal difference between channels during the channel check performed every eight hours as part of the reactor operater (RO) log. To ,
perform the channel check in question, three OTSG level indicators are compared by the RO, the maximum difference between channels is mentally calculated, and'a comparison is made to the values for maximum normal difference and operability difference. These readings are reviewed once per shin by the Control Room Supervisor (CRS), and daily by the Operations Shin Superintendent (SS). The RO '
is procedurally required to initiate a job request if the difference exceeds the maximum normal difference of five inches. If the difference between the channels exceeds the operabilim difference of eight inches, the RO is required to notify the SS/CRS immediately and write a Condition Report.
In this instance the RO logged the reading as being greater than five inches on January 22,1994, circled the reading on the log sheet, and initiated a job request to repair the indicator as required by procedure. Thejob request number was annotated on the back of the log sheet as corrective action for the out of specification reading and subsequent readings were circled referencing the same note. During the midnight shin (2300-0700) on January 28,1994, Ll.-2622 exceeded the operability difference of eight inches; however, this was not recognized by the Control Room Operators.
LI-2622 was identified as being outside ofits operability limits at 2150 on January 31,1994, by the evening shin (1500-2300) RO while walking down the control panel. The RO notified the Shift Superintendent as required and a Condition Report was initiated. The unit entered the Technical Specification action which requires placing the plant in hot shptdown within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> based on the inoperability of one EFW flow path associated with the level control feature of LT-2622 A Notification of Unusual Event (NUE) was declared when shutdown commenced at 0905 on February 1,1994, based on the initiation of a shutdown required by Technical Specifications. Transmitter LT-2622 was replaced while the plant was in hot shutdown and was declared operable along with its associated EFW flow path at 2204 on February 1,1994. The NUE was terminated at this time. The !
Unit was returned to power on February 2,1994.
3
. , - . - ~ , -
' Attachment to j OCAN059402 The root cause of the failure to identify LT-2622 being inoperable was determined ' q
. to be inattention to detail on the part of ANO Unit I licensed operators while l taking logs. The operators did not exhibit a questioning attitude as the difTerence l continued to grow and exceed the operating limit. Several factors were identified !
- which contributed to this event. The RO log which contains the channel check I requires a mental calculation to determine the channel difference that is then compared to a specified value. This difference was not procedurally required to be written on the log. This task is performed many times for a single set oflogs and requires attention to detail to avoid error. Additionally, procedural requirements were vague as to the requirements for CRS/SS review of these logs, and Operations management did not provide sufTicient feedback to operators on the seriousness oflog taking errors. Further, a false sense of problem resolution was created as a result of the continued reference on the log sheet to the job request that had been initiated to correct the levelindication discrepancy. This condition obscured the need to take further action when the difference increased beyond the ,
operability limit.
(2) Corrective steps taken and results achieved:
. Transmitter LT-2622 was replaced while the plant was in hot shutdown and was declared operable along with its associated EFW flow path at 2204 on February 1, 1994.
- A dedicated operator was immediately stationed in the Unit 1 Control Room to manually control level in the "A" OTSG if required during the out-of specification and plant shutdown period.
e A review of the January 1994 Control Room logs was completed on February 5, ;
1994, to identify any other errors associated with channel check comparisons. No significant deficiencies were noted.
- The Operations Manager for Unit I conducted a CRS/SS meeting on February 5, ;
1994, to review this event emphasizing Technical Specification requirements, Licensed Operator responsibilities, and management expectations. The ANO Vice President of Operations also attended the Unit 1 CRS/SS meeting to reinforce management expectations.
. Unit 1 Shift Superintendents conducted crew meetings attended by either the Operations Manager or Assistant Operations Manager between February 4-8, 1994, to review this event with their respective operating crews emphasizing ;
Technical Specification requirements, licensed operator responsibilities and management expectations.
)
.t 1
~!
l^
Attachment to OCAN059402
- . Unit 1 Shin St perintendents completed additional crew meetings between February 19 and March 3,1994 During these meetings emphasis was placed on management expectations on log taking, how this event could have been prevented by use of self checking techniques, review oflog taking errors from previous log reviews and lessons learned from this event.
- A Iluman Performance Enhancement System (IIPES) evaluation was perfonned regarding this event on February 10,1994, and several human factor enhancements were identified for implementation.
. involved operators responded to a questionnaire which provided their perspective of the event, acceptance of responsibility and accountability for their actions and provided recommendations for enhancing operator log taking practices.
- Unit 2 operations management reviewed this event with their Shin Superintendents on February 10,1994, to address the generic human performance implications.
. Iluman factor enhancements were added on February 16,1994, to the Unit I operator logs, which had previously required mental calculations / comparisons, so that difference values could be visually compared to a standard. Additionally, Technical Specification log readings were segregated on a separate log form. Until human factors enhancements could be incorporated a Senior Reactor Operator performed an additional daily review oflogs containing Technical Specification requirements
- Procedure 1015.003A, Unit / Operations Logs, was revised on February 16, 1994, to clarify the requirements for CRS/SS end of shifl log reviews.
. The lessons learned from this event regarding performance of routine, repetitive tasks were discussed with Units I and 2 Maintenance, Chemistry, Radiation Protection, and System Engineering personinel between February 14, and March 17,1994.
. An Improving Iluman Performance Operations task force has been formed with the support of Entergy executive management. This task force is comprised of Operations Department personnel from each Entergy nuclear site. The mission of the task force is to defme the characteristics of a culture that achieves and maintains high standards of human performance and to recommend efTective implementation methods for the Entergy Operations plants. The first meeting of the task force was held on April 5-6,1994. The agenda which consisted of presentations and discussions of human performance issues included a presentation on improving Iluman Performance by Dr. Chong Chiu, President of FPI International. The task force will continue to meet periodically to resolve human performance issues.
5
1
~. .
Attr4chment to -
'- 0CAN059402
- The following operations related job request priority system enhancements for Unit I were completed on May 1,1994:
Log deficiencies are tracked in the same manner as control room deficiencies.
The Planning and Scheduling Operations Liaist>n Desk Guide was revised to require periodic audits of operations log notes, operations control room status boards and disabled control room annunciators to help ensure items requiring maintenance action are properly prioritized.
(3) Corrt .1;ve steps that will be taken to prevent titrther violations:
- Computerized log taking is being evaluated for anaptation to both Unit I and Unit 2 Control Room logs. This evaluation is scheduled for completion by June 1, 1994.
- As a step toward future enhancements in human performance, Unit i Operations ,
will evaluate feedback mechanisms used in addressing log taking errors by June 1, 1994.
. Unit 1 Log taking errors are currently being addressed with a log discrepancy form that is generated, if needed, by the SS as a result of the final review of the daily logs. An evaluation is currently being performed, and will be completed by June 1, 1994, to determine if enhancements to the method of annotating out-of-specification conditions on operator logs are required.
- An evaluation is currently being performed, and will be completed by June 1,1994, to determine if enhancements to the methods of addressing Unit 2 log taking errors and annotating out-of-specification conditions on operator logs are required.
(4) Datc3Aen full compliance will be achieved:
Full compliance was achieved when the out-of specification condition was corrected i
l 6
-1