|
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARML20046C0661993-07-30030 July 1993 LER 92-009-01:on 920910,deficiencies Discovered During Dynamic Testing of Motor Operated Valves in Response to Generic Ltr 89-10.MOVs W/Deficiencies Modified or Repaired. W/930730 Ltr ML20046B6011993-07-26026 July 1993 LER 93-004-00:on 930428,plant Entered Mode 2 W/Afw Pump Turbine Main Steam Line Crossover Check Valve MS735 in Open Position.Caused by Inappropriate Use of Engineering Judgement.Valve MS735 closed.W/930726 Ltr ML20046A4871993-07-23023 July 1993 LER 93-001-00:on 930607,determined RCP Uv & Underfrequency Portion of Rt Sys,& TDAFP Autostart Signal from RCP Bus Uv Contained Design Deviation Due to Personnel Error. Procedural Guidance enhanced.W/930723 Ltr ML20045D2451993-06-17017 June 1993 LER 93-003-00:on 930520,plant Experienced Trip from Approx & Continuity Between Fuse & Fuseholder Lost,Resulting in Loss of Selected RCS Average Temp Input to Ics.Faulty Fuse Cap & Fuse replaced.W/930617 Ltr ML20044D1331993-05-11011 May 1993 LER 91-007-01:on 910629,two Neutral Overcurrent Relays on Unit 1B Auxiliary Transformer Actuated,Resulting in Generator Trip & Reactor Trip.Caused by Electrical Fault. Loose Strand Removed from conductor.W/930511 Ltr ML20024G7191991-04-23023 April 1991 LER 91-001-00:on 910401,reactor Trip Occurred When Rod Dropped in Core.Caused by Defective Circuit Card in Rod Control Sys.Suspect Circuit Cards Replaced & Sent to Westinghouse for evaluation.W/910423 Ltr ML20044B1681990-07-10010 July 1990 LER 90-002-01:on 900126,reactor Coolant Pump Current Monitor Inputs to Sfrcs ACH1 & Reactor Pressure Sys Channel 1 Experienced Reactor Trip.Probably Caused by Inadequate Test Switches & Isolation plug.W/900710 Ltr ML20043H3201990-06-18018 June 1990 LER 90-010-00:on 900518,station Experienced Inadvertent Safety Features Actuation Signal Level 1-4 Actuation W/Injection of 1,000 Gallons of Borated Water.Caused by Loss of 120-volt Ac Bus Y3.W/900618 Ltr ML20043F1681990-06-0808 June 1990 LER 90-001-00:on 900512,reactor Tripped Due to lo-lo Water Level in Steam Generator 2A.Caused by Procedural Inadequacy. Procedure FNP-2-STP-151 Revised to Provide Addl Initial Conditions to Prevent Subj event.W/900608 Ltr ML20043B8051990-05-25025 May 1990 LER 90-009-00:on 900426,source-check of Station Vent Radiation Monitors Not Performed Per Tech Spec 3.3.3.10. Caused by Use of Outmoded Light Emitting Dioide as Check Source.Source Check Procedures revised.W/900525 Ltr ML20043B5711990-05-25025 May 1990 LER 90-008-00:on 900425,safety Features Actuation Sys Level 1 Actuation Occurred,Resulting in Trip of Containment Radiation Monitors.Caused by High Radiation Fields While Lifting Core Support Assembly.Mod initiated.W/900525 Ltr ML20042F2811990-05-0303 May 1990 LER 90-007-00:on 900403,inadvertent,inconsequential Safety Features Actuation Signal Occured While Defueled.Caused by Incidental Contact W/Monitor in Containment.Temporary Barriers Built Around monitors.W/900503 Ltr ML20042F2791990-05-0303 May 1990 LER 90-006-00:on 900403,station Experienced Safety Features Actuation Sys Levels 1 Through 5 Actuation.Caused by Contact W/Breaker Switch HAAE2 in High Voltage Switchgear Room 2. Meetings Held W/Craft personnel.W/900503 Ltr ML20042E4891990-04-16016 April 1990 LER 90-005-00:on 900314,determined That Some Class 1E Circuits That Pass Through Containment Electrical Penetrations Do Not Have Adequate Backup Fault Protection. Caused by Inadequate Design control.W/900416 Ltr ML20012D9591990-03-20020 March 1990 LER 90-002-00:on 900222,two Cases Found Where Surveillance Testing Procedures Did Not Perform All Tests Required by Tech Specs.Caused by Inadequate Procedural Guidance. Procedures revised.W/900320 Ltr ML20012D0341990-03-19019 March 1990 LER 90-004-00:on 900217,fuel Assembly Moved in Spent Fuel Pool While Emergency Ventilation Inoperable.Caused by Personnel Error.Personnel Involved Counseled & Subj LER Part of Required reading.W/900319 Ltr ML20012C7151990-03-14014 March 1990 LER 90-003-00:on 900212,station Entered Mode 6,refueling,w/o Operable Audible Source Range Indication.Caused by Personnel Error.Individual counseled.W/900314 Ltr ML20012C3031990-03-13013 March 1990 LER 90-001-00:on 900213,fire Watch Not Established within Required Time Period Due to Personnel Error.Administrative Procedure FNP-0-SOP-0.4 Revised & Personnel Retrained on requirements.W/900313 Ltr ML20012B4851990-03-0606 March 1990 LER 83-039/03X-2:on 830726,discovered That Handwheel for Inner Door of Personnel Airlock in Shut Position & Partially Opened.Caused by Excessive Use of Door During Outages.Door Repaired & Returned to Operable status.W/900306 Ltr ML20011F3831990-02-26026 February 1990 LER 90-002-00:on 900126,reactor Tripped from 73% Power. Caused by Spurious Reactor Coolant Pump Monitor Signal Indicating Only One Pump Running in Each Loop.Pump Seal to Be Replaced During Sixth Refueling outage.W/900226 Ltr ML20006E6861990-02-20020 February 1990 LER 90-001-00:on 900118,reactor Protection Sys Channel 2 Bypassed Temporarily During Performance of DB-MI-03207. Caused by Inadequate Procedure Re Inoperable Channel Removal.Procedure SP1105.02 revised.W/900220 Ltr ML20011E2251990-01-30030 January 1990 LER 86-032-01:on 860802,inadvertent Start of High Pressure Injection Pump 1-2 Occurred.Caused by Open Relay Coil. Failed Relay Replaced & Procedure Change Initiated. W/900130 Ltr ML19354E3341990-01-23023 January 1990 LER 89-016-00:on 891228,discovered That Required Surveillance for Plant Vent Stack Radioactive Gas Monitor Not Performed.Caused by Personnel Improperly Scheduling Surveillance for Time Later than Due date.W/900123 Ltr ML20005G1091990-01-0909 January 1990 LER 89-015-01:on 891026,concluded That Transmitter Was Out of Tolerance When Reactor Protection Sys Channel 2 Returned to Operable Status on 890924.Caused by leak-by in Instrument Manifold.Transmitter Recalibr successfully.W/900109 Ltr ML20042D4011990-01-0202 January 1990 LER 89-010-01:on 890612,control Room Ventilation Sys Declared Inoperable Due to Compressor High Pressure Trips. Caused by Tripping of Refrigerant Pressure Switch on High Pressure.Switch Reset & Sys retested.W/900102 Ltr ML19354D7361989-12-22022 December 1989 LER 89-018-00:on 891123,hydrogen Dilution Blower 1-1 Casing Drain Line Broke Off at Casing,Declaring Blower Inoperable. Caused by Drain Line Being Accidentally Stepped On.Drain Removed & Pipe Plug installed.W/891222 Ltr ML20011D5611989-12-18018 December 1989 LER 89-015-00:on 891118,reactor Tripped Due to Turbine Trip. Caused by Voltage Transient in Power Circuit to Digital electro-hydraulic Control Sys & Inverter Failure.Inverter Repaired & Returned to svc.W/891218 Ltr ML19332F8951989-12-13013 December 1989 LER 89-017-00:on 891113,containment Spray Pump 1-1 Inadvertently Started During Monthly Functional Test in Safety Features Actuation Sys (Sfas) Channel 1.Caused by Failed Relay in Sfas Channel 3.Relay replaced.W/891213 Ltr ML19332F9061989-12-13013 December 1989 LER 89-008-00:on 891113,containment Integrity Not Maintained for Approx 30 S.Caused by Personnel in That Inner Door Was Left Blocked Open.Personnel Counseled & Interim Administrative Controls established.W/891213 Ltr ML19351A4571989-12-12012 December 1989 LER 89-014-00:from 891115-16,Tech Spec 3.0.3 Entered Voluntarily to Repair Leaking Containment Purge Isolation Dampers.Caused by Need to Repair Dampers.Dampers Closed & Automatic Isolation Feature restored.W/891212 Ltr ML19332F6761989-12-12012 December 1989 LER 89-007-00:on 891112,both Motor Driven Auxiliary Feedwater Pumps Failed to Start Manually by Operator.Caused by Cognitive Personnel Error Re Design Change.Wiring Discrepancy Corrected & Pump Returned to svc.W/891212 Ltr ML19332F0851989-12-0707 December 1989 LER 89-006-00:on 891112,safety Injection & Reactor Trip Initiated Due to Low Steam Line Pressure.Caused by Personnel Error Involving Misconfiguration of Circuit Valve.Personnel Involved counseled.W/891207 Ltr ML19332E7521989-12-0404 December 1989 LER 89-016-00:on 890917,unplanned Release of Radioactive Resin to Onsite Settling Basin Occurred.Caused by Personnel Error.Standing Order 89-051 Generated on 890920 to Direct Use of Working Copy of procedures.W/891204 Ltr ML19332D3111989-11-27027 November 1989 LER 89-015-00:on 890924,RCS Flow Transmitter Out of Tolerance When Reactor Protection Sys Channel 2 Returned to Operable Status.Caused by leak-by in Instrument Manifold Seen as Zero Shift.Transmitter recalibr.W/891127 Ltr ML19327C2671989-11-14014 November 1989 LER 89-013-00:on 891019,reactor Tripped Due to lo-lo Level in Steam Generator 2C.Caused by Operator Incorrectly Transferring Steam Generator Level Control to Main Feedwater.Involved Personnel counseled.W/891114 Ltr ML19327C2621989-11-14014 November 1989 LER 89-012-00:on 891018,reactor Tripped Due to lo-lo Steam Generator Level Due to Closure of Governor Valves.Caused by Design Error in Digital electro-hydraulic Control Sys.Valve Position Limiter Feature removed.W/891114 Ltr ML19324C2081989-11-10010 November 1989 LER 89-014-00:on 891011,plastic Sheeting Blocked Off Fire Detectors in Auxiliary Feedwater Pump 1-1 Room & High Voltage Switchgear Room B,Making Fire Detectors Inoperable. Caused by Personnel Oversight.Event reviewed.W/891110 Ltr ML19354D4691989-11-0101 November 1989 LER 89-005-00:on 890930 & 1001,core Alterations Performed W/O Establishing Containment Refueling Integrity.Caused by Cognitive Personnel Error.Personnel Involved in Event Counseled.Containment Procedure strengthened.W/891101 Ltr ML19327B5451989-10-25025 October 1989 LER 89-011-00:on 890925,discovered That Tech Spec 4.6.3.1.a Surveillance Requirement Re Containment Air Lock Outer Door Not Done.Caused by Personnel Error.Individuals Involved Counseled Re Importance of Subj requirements.W/891025 Ltr ML19325D4941989-10-17017 October 1989 LER 89-004-00:on 890616,determined That Calculations Were Not Available to Demonstrate That Svc Water Sys Capable of Supplying Design Flow to safety-related Loads Under Scenario of Seismic event.W/891017 Ltr ML19325D4671989-10-16016 October 1989 LER 89-004-01:on 890411,determined That Circulating Water Line Break Would Result in Loss of Svc Water as Result of Concerns Raised on 890206.Cause Unknown.Standing Order 89-026 in Place to Plug Floor drains.W/891016 Ltr ML19325C8531989-10-13013 October 1989 LER 89-013-00:on 890913,hourly Fire Watch Patrol Exceeded Allowed Interval,Violating Tech Spec 3.7.10,Action a.2. Caused by Personnel Error.Individual Counseled & Event Info Distributed to Fire Watch personnel.W/891013 Ltr ML19325D2461989-10-12012 October 1989 LER 89-010-00:on 890920,reactor Tripped Manually Following Loss of Operating Steam Generator Feed Pump.Caused by Inadvertent Opening of Overspeed Trip Test Valve.Individual Involved in Event Counseled to Be More aware.W/891012 Ltr ML19325C7481989-10-10010 October 1989 LER 89-009-00:on 890525,determined That Power Range Nuclear Instrumentation Channels Reading Approx 7% Low.Equalizing Valves on Two of Three Instruments Were Leaking.Valves Repaired & Power Range Instruments adjusted.W/891010 Ltr ML20024F6781983-08-31031 August 1983 LER 83-042/03L-0:on 830802,post-LOCA Hydrogen Recombiner 1A Declared Inoperable.Caused by Failure of Temp Indicator.New Indicator Installed & Declared Operable ML20024F6841983-08-31031 August 1983 LER 83-031/03L-0:on 830806,during Testing,Instrumentation Channel Associated W/Level Transmitter LT-474 Declared Inoperable.Caused by Setpoint Drift of Comparator Card.Card Adjusted & Instrumentation Channel Declared Operable ML20024E2591983-08-0101 August 1983 LER 83-033/03L-0:on 830620,fire Detection Zone Reactor Coolant Pump 1-2,containment Level 603 Ft Alarmed & Could Not Be Reset.Caused by Faulty Detector String.Zone Will Be Restored During Next Refueling outage.W/830801 Ltr ML20024D0871983-07-26026 July 1983 LER 83-038/03L-0:on 830627,during Turbine Driven Auxiliary Feedwater Pump Inservice Test,Pump Failed to Start from Train a Steam Supply & Declared Inoperable.Caused by Valve HV-3226 Failing to Stroke properly.W/830726 Ltr ML20024B8351983-07-0101 July 1983 LER 83-028/03L-0:on 830603 & 17,fuel Handling Area Radiation Monitors RE8446 & 7 Found Deenergized.Caused by Blown Radiation Monitoring Cabinet Fuse.Fuse replaced.W/830701 Ltr ML20024C1251983-06-30030 June 1983 LER 83-027/03L-0:on 830607,during Performance of FNP-1-STP-43.0,train a Penetration Room Filtration Sys Declared Inoperable When Exhaust Fan Damper 3357A Would Not Open.Caused by Comparator Card failure.W/830630 Ltr 1993-07-30
[Table view] Category:RO)
MONTHYEARML20046C0661993-07-30030 July 1993 LER 92-009-01:on 920910,deficiencies Discovered During Dynamic Testing of Motor Operated Valves in Response to Generic Ltr 89-10.MOVs W/Deficiencies Modified or Repaired. W/930730 Ltr ML20046B6011993-07-26026 July 1993 LER 93-004-00:on 930428,plant Entered Mode 2 W/Afw Pump Turbine Main Steam Line Crossover Check Valve MS735 in Open Position.Caused by Inappropriate Use of Engineering Judgement.Valve MS735 closed.W/930726 Ltr ML20046A4871993-07-23023 July 1993 LER 93-001-00:on 930607,determined RCP Uv & Underfrequency Portion of Rt Sys,& TDAFP Autostart Signal from RCP Bus Uv Contained Design Deviation Due to Personnel Error. Procedural Guidance enhanced.W/930723 Ltr ML20045D2451993-06-17017 June 1993 LER 93-003-00:on 930520,plant Experienced Trip from Approx & Continuity Between Fuse & Fuseholder Lost,Resulting in Loss of Selected RCS Average Temp Input to Ics.Faulty Fuse Cap & Fuse replaced.W/930617 Ltr ML20044D1331993-05-11011 May 1993 LER 91-007-01:on 910629,two Neutral Overcurrent Relays on Unit 1B Auxiliary Transformer Actuated,Resulting in Generator Trip & Reactor Trip.Caused by Electrical Fault. Loose Strand Removed from conductor.W/930511 Ltr ML20024G7191991-04-23023 April 1991 LER 91-001-00:on 910401,reactor Trip Occurred When Rod Dropped in Core.Caused by Defective Circuit Card in Rod Control Sys.Suspect Circuit Cards Replaced & Sent to Westinghouse for evaluation.W/910423 Ltr ML20044B1681990-07-10010 July 1990 LER 90-002-01:on 900126,reactor Coolant Pump Current Monitor Inputs to Sfrcs ACH1 & Reactor Pressure Sys Channel 1 Experienced Reactor Trip.Probably Caused by Inadequate Test Switches & Isolation plug.W/900710 Ltr ML20043H3201990-06-18018 June 1990 LER 90-010-00:on 900518,station Experienced Inadvertent Safety Features Actuation Signal Level 1-4 Actuation W/Injection of 1,000 Gallons of Borated Water.Caused by Loss of 120-volt Ac Bus Y3.W/900618 Ltr ML20043F1681990-06-0808 June 1990 LER 90-001-00:on 900512,reactor Tripped Due to lo-lo Water Level in Steam Generator 2A.Caused by Procedural Inadequacy. Procedure FNP-2-STP-151 Revised to Provide Addl Initial Conditions to Prevent Subj event.W/900608 Ltr ML20043B8051990-05-25025 May 1990 LER 90-009-00:on 900426,source-check of Station Vent Radiation Monitors Not Performed Per Tech Spec 3.3.3.10. Caused by Use of Outmoded Light Emitting Dioide as Check Source.Source Check Procedures revised.W/900525 Ltr ML20043B5711990-05-25025 May 1990 LER 90-008-00:on 900425,safety Features Actuation Sys Level 1 Actuation Occurred,Resulting in Trip of Containment Radiation Monitors.Caused by High Radiation Fields While Lifting Core Support Assembly.Mod initiated.W/900525 Ltr ML20042F2811990-05-0303 May 1990 LER 90-007-00:on 900403,inadvertent,inconsequential Safety Features Actuation Signal Occured While Defueled.Caused by Incidental Contact W/Monitor in Containment.Temporary Barriers Built Around monitors.W/900503 Ltr ML20042F2791990-05-0303 May 1990 LER 90-006-00:on 900403,station Experienced Safety Features Actuation Sys Levels 1 Through 5 Actuation.Caused by Contact W/Breaker Switch HAAE2 in High Voltage Switchgear Room 2. Meetings Held W/Craft personnel.W/900503 Ltr ML20042E4891990-04-16016 April 1990 LER 90-005-00:on 900314,determined That Some Class 1E Circuits That Pass Through Containment Electrical Penetrations Do Not Have Adequate Backup Fault Protection. Caused by Inadequate Design control.W/900416 Ltr ML20012D9591990-03-20020 March 1990 LER 90-002-00:on 900222,two Cases Found Where Surveillance Testing Procedures Did Not Perform All Tests Required by Tech Specs.Caused by Inadequate Procedural Guidance. Procedures revised.W/900320 Ltr ML20012D0341990-03-19019 March 1990 LER 90-004-00:on 900217,fuel Assembly Moved in Spent Fuel Pool While Emergency Ventilation Inoperable.Caused by Personnel Error.Personnel Involved Counseled & Subj LER Part of Required reading.W/900319 Ltr ML20012C7151990-03-14014 March 1990 LER 90-003-00:on 900212,station Entered Mode 6,refueling,w/o Operable Audible Source Range Indication.Caused by Personnel Error.Individual counseled.W/900314 Ltr ML20012C3031990-03-13013 March 1990 LER 90-001-00:on 900213,fire Watch Not Established within Required Time Period Due to Personnel Error.Administrative Procedure FNP-0-SOP-0.4 Revised & Personnel Retrained on requirements.W/900313 Ltr ML20012B4851990-03-0606 March 1990 LER 83-039/03X-2:on 830726,discovered That Handwheel for Inner Door of Personnel Airlock in Shut Position & Partially Opened.Caused by Excessive Use of Door During Outages.Door Repaired & Returned to Operable status.W/900306 Ltr ML20011F3831990-02-26026 February 1990 LER 90-002-00:on 900126,reactor Tripped from 73% Power. Caused by Spurious Reactor Coolant Pump Monitor Signal Indicating Only One Pump Running in Each Loop.Pump Seal to Be Replaced During Sixth Refueling outage.W/900226 Ltr ML20006E6861990-02-20020 February 1990 LER 90-001-00:on 900118,reactor Protection Sys Channel 2 Bypassed Temporarily During Performance of DB-MI-03207. Caused by Inadequate Procedure Re Inoperable Channel Removal.Procedure SP1105.02 revised.W/900220 Ltr ML20011E2251990-01-30030 January 1990 LER 86-032-01:on 860802,inadvertent Start of High Pressure Injection Pump 1-2 Occurred.Caused by Open Relay Coil. Failed Relay Replaced & Procedure Change Initiated. W/900130 Ltr ML19354E3341990-01-23023 January 1990 LER 89-016-00:on 891228,discovered That Required Surveillance for Plant Vent Stack Radioactive Gas Monitor Not Performed.Caused by Personnel Improperly Scheduling Surveillance for Time Later than Due date.W/900123 Ltr ML20005G1091990-01-0909 January 1990 LER 89-015-01:on 891026,concluded That Transmitter Was Out of Tolerance When Reactor Protection Sys Channel 2 Returned to Operable Status on 890924.Caused by leak-by in Instrument Manifold.Transmitter Recalibr successfully.W/900109 Ltr ML20042D4011990-01-0202 January 1990 LER 89-010-01:on 890612,control Room Ventilation Sys Declared Inoperable Due to Compressor High Pressure Trips. Caused by Tripping of Refrigerant Pressure Switch on High Pressure.Switch Reset & Sys retested.W/900102 Ltr ML19354D7361989-12-22022 December 1989 LER 89-018-00:on 891123,hydrogen Dilution Blower 1-1 Casing Drain Line Broke Off at Casing,Declaring Blower Inoperable. Caused by Drain Line Being Accidentally Stepped On.Drain Removed & Pipe Plug installed.W/891222 Ltr ML20011D5611989-12-18018 December 1989 LER 89-015-00:on 891118,reactor Tripped Due to Turbine Trip. Caused by Voltage Transient in Power Circuit to Digital electro-hydraulic Control Sys & Inverter Failure.Inverter Repaired & Returned to svc.W/891218 Ltr ML19332F8951989-12-13013 December 1989 LER 89-017-00:on 891113,containment Spray Pump 1-1 Inadvertently Started During Monthly Functional Test in Safety Features Actuation Sys (Sfas) Channel 1.Caused by Failed Relay in Sfas Channel 3.Relay replaced.W/891213 Ltr ML19332F9061989-12-13013 December 1989 LER 89-008-00:on 891113,containment Integrity Not Maintained for Approx 30 S.Caused by Personnel in That Inner Door Was Left Blocked Open.Personnel Counseled & Interim Administrative Controls established.W/891213 Ltr ML19351A4571989-12-12012 December 1989 LER 89-014-00:from 891115-16,Tech Spec 3.0.3 Entered Voluntarily to Repair Leaking Containment Purge Isolation Dampers.Caused by Need to Repair Dampers.Dampers Closed & Automatic Isolation Feature restored.W/891212 Ltr ML19332F6761989-12-12012 December 1989 LER 89-007-00:on 891112,both Motor Driven Auxiliary Feedwater Pumps Failed to Start Manually by Operator.Caused by Cognitive Personnel Error Re Design Change.Wiring Discrepancy Corrected & Pump Returned to svc.W/891212 Ltr ML19332F0851989-12-0707 December 1989 LER 89-006-00:on 891112,safety Injection & Reactor Trip Initiated Due to Low Steam Line Pressure.Caused by Personnel Error Involving Misconfiguration of Circuit Valve.Personnel Involved counseled.W/891207 Ltr ML19332E7521989-12-0404 December 1989 LER 89-016-00:on 890917,unplanned Release of Radioactive Resin to Onsite Settling Basin Occurred.Caused by Personnel Error.Standing Order 89-051 Generated on 890920 to Direct Use of Working Copy of procedures.W/891204 Ltr ML19332D3111989-11-27027 November 1989 LER 89-015-00:on 890924,RCS Flow Transmitter Out of Tolerance When Reactor Protection Sys Channel 2 Returned to Operable Status.Caused by leak-by in Instrument Manifold Seen as Zero Shift.Transmitter recalibr.W/891127 Ltr ML19327C2671989-11-14014 November 1989 LER 89-013-00:on 891019,reactor Tripped Due to lo-lo Level in Steam Generator 2C.Caused by Operator Incorrectly Transferring Steam Generator Level Control to Main Feedwater.Involved Personnel counseled.W/891114 Ltr ML19327C2621989-11-14014 November 1989 LER 89-012-00:on 891018,reactor Tripped Due to lo-lo Steam Generator Level Due to Closure of Governor Valves.Caused by Design Error in Digital electro-hydraulic Control Sys.Valve Position Limiter Feature removed.W/891114 Ltr ML19324C2081989-11-10010 November 1989 LER 89-014-00:on 891011,plastic Sheeting Blocked Off Fire Detectors in Auxiliary Feedwater Pump 1-1 Room & High Voltage Switchgear Room B,Making Fire Detectors Inoperable. Caused by Personnel Oversight.Event reviewed.W/891110 Ltr ML19354D4691989-11-0101 November 1989 LER 89-005-00:on 890930 & 1001,core Alterations Performed W/O Establishing Containment Refueling Integrity.Caused by Cognitive Personnel Error.Personnel Involved in Event Counseled.Containment Procedure strengthened.W/891101 Ltr ML19327B5451989-10-25025 October 1989 LER 89-011-00:on 890925,discovered That Tech Spec 4.6.3.1.a Surveillance Requirement Re Containment Air Lock Outer Door Not Done.Caused by Personnel Error.Individuals Involved Counseled Re Importance of Subj requirements.W/891025 Ltr ML19325D4941989-10-17017 October 1989 LER 89-004-00:on 890616,determined That Calculations Were Not Available to Demonstrate That Svc Water Sys Capable of Supplying Design Flow to safety-related Loads Under Scenario of Seismic event.W/891017 Ltr ML19325D4671989-10-16016 October 1989 LER 89-004-01:on 890411,determined That Circulating Water Line Break Would Result in Loss of Svc Water as Result of Concerns Raised on 890206.Cause Unknown.Standing Order 89-026 in Place to Plug Floor drains.W/891016 Ltr ML19325C8531989-10-13013 October 1989 LER 89-013-00:on 890913,hourly Fire Watch Patrol Exceeded Allowed Interval,Violating Tech Spec 3.7.10,Action a.2. Caused by Personnel Error.Individual Counseled & Event Info Distributed to Fire Watch personnel.W/891013 Ltr ML19325D2461989-10-12012 October 1989 LER 89-010-00:on 890920,reactor Tripped Manually Following Loss of Operating Steam Generator Feed Pump.Caused by Inadvertent Opening of Overspeed Trip Test Valve.Individual Involved in Event Counseled to Be More aware.W/891012 Ltr ML19325C7481989-10-10010 October 1989 LER 89-009-00:on 890525,determined That Power Range Nuclear Instrumentation Channels Reading Approx 7% Low.Equalizing Valves on Two of Three Instruments Were Leaking.Valves Repaired & Power Range Instruments adjusted.W/891010 Ltr ML20024F6781983-08-31031 August 1983 LER 83-042/03L-0:on 830802,post-LOCA Hydrogen Recombiner 1A Declared Inoperable.Caused by Failure of Temp Indicator.New Indicator Installed & Declared Operable ML20024F6841983-08-31031 August 1983 LER 83-031/03L-0:on 830806,during Testing,Instrumentation Channel Associated W/Level Transmitter LT-474 Declared Inoperable.Caused by Setpoint Drift of Comparator Card.Card Adjusted & Instrumentation Channel Declared Operable ML20024E2591983-08-0101 August 1983 LER 83-033/03L-0:on 830620,fire Detection Zone Reactor Coolant Pump 1-2,containment Level 603 Ft Alarmed & Could Not Be Reset.Caused by Faulty Detector String.Zone Will Be Restored During Next Refueling outage.W/830801 Ltr ML20024D0871983-07-26026 July 1983 LER 83-038/03L-0:on 830627,during Turbine Driven Auxiliary Feedwater Pump Inservice Test,Pump Failed to Start from Train a Steam Supply & Declared Inoperable.Caused by Valve HV-3226 Failing to Stroke properly.W/830726 Ltr ML20024B8351983-07-0101 July 1983 LER 83-028/03L-0:on 830603 & 17,fuel Handling Area Radiation Monitors RE8446 & 7 Found Deenergized.Caused by Blown Radiation Monitoring Cabinet Fuse.Fuse replaced.W/830701 Ltr ML20024C1251983-06-30030 June 1983 LER 83-027/03L-0:on 830607,during Performance of FNP-1-STP-43.0,train a Penetration Room Filtration Sys Declared Inoperable When Exhaust Fan Damper 3357A Would Not Open.Caused by Comparator Card failure.W/830630 Ltr 1993-07-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217K1231999-10-14014 October 1999 Revised Positions for DBNPS & Pnpp QA Program ML20217P0761999-10-0606 October 1999 Non-proprietary, Farley Units 1 & 2 LBB Calculation Results Due to SG Replacement & SG Snubber Elimination Programs ML20217D5441999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Davis-Besse Nuclear Power Station.With ML20217G0361999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20211R0811999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20216E4941999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Jmfnp.With ML20212E7451999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Hcgs,Unit 1.With Summary of Changes,Tests & Experiments Implemented During Aug 1999.With ML20211B0271999-08-13013 August 1999 SER Accepting Second 10-year Interval Inservice Insp Requests for Relief RR-A16,RR-A17 & RR-B9 for Plant, Unit 1 ML20210T2161999-08-0606 August 1999 Draft SE Supporting Proposed Conversion of Current TS to ITS for Plant ML20211B2011999-08-0404 August 1999 Informs Commission About Results of NRC Staff Review of Kaowool Fire Barriers at Farley Nuclear Plant,Units 1 & 2 & Staff Plans to Address Technical Issues with Kaowool & FP-60 Barriers ML20210R6031999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20210Q8541999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20209G0661999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With L-99-267, Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20209E6231999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20196J3791999-06-30030 June 1999 Safety Evaluation of TR WCAP-14750, RCS Flow Verification Using Elbow Taps at Westinghouse 3-Loop Pwrs. Rept Acceptable ML20195K2871999-06-16016 June 1999 Safety Evaluation Accepting Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20195F4871999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Davis-Besse Nuclear Power Station,Unit 1.With L-99-023, Monthly Operating Repts for May 1999 for Jfnp Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Jfnp Units 1 & 2. with ML20207E8011999-05-19019 May 1999 Non-proprietary Rev 2 to HI-981933, Design & Licensing Rept DBNPS Unit 1 Cask Pit Rack Installation Project ML20207F4351999-05-0404 May 1999 Rev 1 to DBNPS Emergency Preparedness Evaluated Exercise Manual 990504 ML20206G7471999-05-0404 May 1999 Safety Evaluation Accepting Corrective Actions Taken by SNC to Ensure That Valves Perform Intended Safety Functions & Concluding That SNC Adequately Addressed Requested Actions in GL 95-07 L-99-020, Monthly Operating Repts for Apr 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20206M6341999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Davis-Besse Nuclear Station,Unit 1.With ML20206C9461999-04-30030 April 1999 1:Final Cycle 16 Freespan ODSCC Operational Assessment L-99-161, Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20205M2931999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Davis-Besse Nuclear Power Station.With ML20205N0961999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20204D7271999-03-15015 March 1999 ISI Refueling 15,Interval 2,Period 3,Outage 3 for Jm Farley Nuclear Generating Plant,Unit 1 ML20207J1461999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Davis-Besse Nuclear Power Station,Unit 1.With ML20207M6421999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20203A2651999-01-31031 January 1999 Monthly Operating Repts for Jan 1999 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20199H5931999-01-20020 January 1999 Safety Evaluation Accepting Thermo-Lag Re Ampacity Derating Issues for Plant ML20199D8611999-01-12012 January 1999 SER Accepting Relief Request for Inservice Insp Program for Plant,Units 1 & 2 ML20199E6591998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20204J6751998-12-31031 December 1998 1998 Annual Rept for Dbnps,Unit 1,PNPP,Unit 1 & BVPS Units 1 & 2 ML20205K5781998-12-31031 December 1998 Waterhammer Phenomena in Containment Air Cooler Swss ML20199E2501998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Davis-Besse Nuclear Power Station,Unit 1.With ML20206C8081998-12-31031 December 1998 Alabama Power 1998 Annual Rept ML20206B0101998-12-31031 December 1998 1998 Annual Rept for Firstenergy Corp, for Perry Nuclear Power Plant & Davis-Besse Nuclear Power Station.Form 10-K Annual Rept to Us Securities & Exchange Commission for Fiscal Yr Ending 981231,encl ML20198K4091998-12-18018 December 1998 COLR for Jm Farley,Unit 1 Cycle 16 ML20198B2561998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20197J3441998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Davis-Besse Nuclear Power Station,Unit 1.With ML20195E2281998-11-16016 November 1998 Safety Evaluation Authorizing Relief Request for Second 10-year ISI Program Relief Request 56 for Plant,Unit 1 ML20195C9681998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Jm Farley Nuclear Plant,Units 1 & 2.With ML20195D0001998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Davis-Besse Nuclear Power Station,Unit 1.With ML20155E0271998-10-29029 October 1998 SER Approving & Denying in Part Inservice Testing Program Relief Requests for Plant.Relief Requests Q1P16-RR-V-3 & Q2P16-RR-V Denied Since Requests Do Not Meet Size Requirement of GL 89-04 ML20155B6781998-10-28028 October 1998 Safety Evaluation Accepting Proposed Reduction in Commitment Changes in QA Program Matl Receipt Insp Process ML20154B6121998-10-0101 October 1998 Safety Evaluation Granting Second 10-year ISI Requests for Relief RR-13 & RR-49 Through RR-55 for Jm Farley NPP Unit 1 ML20151V8341998-09-30030 September 1998 Non-proprietary Rev 2 to NSA-SSO-96-525, Jm Farley Nuclear Plant Safety Analysis IR Neutron Flux Reactor Trip Setpoint Change 1999-09-30
[Table view] |
Text
-- __ - . _ _
1$
- h. ~
- , ', ,3 'd l- K .;
f -(h gg,, !
EDISON PLAZA e
300 MADISON AVENUE -
T ' "' # "" # '
6 990 5
Log No.: BB90-00144 NP33-83-045, Rev 2 L
Docket No. 50-346 License No'.NPF-3 r
i b United States Nuclear Regulatory Commission Document Control Desk Vashington, D. C. 20555 Gentlemen:
LER 83-039, Revision 2 Davis-Desse Nuclear Power Station, Unit No. 1 '
Date of Occurrence - July 26, 1983 Enclosed please find revision 2 to Licensee Event Report 83-039. This revision eliminated FCR 85-0178 as an intended corrective action. The revisions are indicated by a revision-bar in the left-hand margin. Please discard or. mark superseded any previous copies of this LER.
Yours truly ,
l @ *Q r Louis F. Storz Plant Manager Davis-Besse~ Nuclear Pover Station LFS/plf' Enclosure cc: Mr. A. Bert Davis Regional Administrator USNRC Region III Hr. Paul Byron DB-1 NRC Sr. Resident Inspector l'@
- 883 1888R 8888j k S
M m J.77) -
CJ~ ,
b LICENSEE EVENT REPORT H -3 C)NTROL BLOCK: l - l
-1 l l l l lh-6 (PLEASE PRINT CR TYPE ALL REEUIRED INFORMATION)
M l 8'9 J,
0 l H l LICENSEE D l BCODE l S l 114l@l16 0 lo l lo lo lo l Ol ol -l 0l 0 l@l LICENSE NUMBER 26 426l 1 LICENSE l 1 l 1TYPE l 1JOl@l67 l CAT l 68 @
CON'T lTITI 3[n] l L l@l 0 l 5 l 0DOCK l 0ETl0NUMBER l 3l 4 l 6 l@l 68 0 l 7 EVENT l 2 l DATE 6 l 8 l 374l@l7b0 l 3REPORT l 0 lDATE6l 9 l 080 l@ ,
' ?- 8 60 61 69 i EVENT DESCRIPTION AND PROBABLE CONSEQUENCES h L 0 2 l (NP-33-83-45) on 7/26/83 at 0710 hours0.00822 days <br />0.197 hours <br />0.00117 weeks <br />2.70155e-4 months <br />, two personnel were exiting the containment I g l-building by way of'the personnel hatch. While in the tunnel, it was discovered l' i o i4 g' l that with the hand whcc1 for the inner door in the shut position, the inner door l go,3p[ was partially open. The hatch was declared inoperable, invoking the criteria of l 1016 l l Technical Specification 3.6.1.3. There was no danger to the health and safety of l
. ya;7i ; the public or station personnel. The outer door was verified shut with the l
- , , , , , g exception of the exiting of the two personnel involved. l 80 7 89 DE CODE S 8C E COMPONENT CODE SU8 CODE 5 E 1019I 7 8 1 z l z l@ in_J@ Lz_1@ I P l r I N It IT in l@ W@ W @
9 10 11 12 13 18 19 20
,,, SE QUE NTI AL OCCURRENCE REPORT REVISION LE R/RO EVENT YE AR REPORT NO. CODE TYPE NO.
h ,RE l8l3l [---J l0 l3 l9 l l/l lOl3l lX l 30
[---J l2l 32 21 22 23 24 26 27 28 29 al KEN AC O L NT HOURS 22 #$B$1T S N FOR$1 B. SUPPLih MANUF CTURER
[F,,Jg]34Z l@ l35 Z lg l0l0l0l0l lYl@ W@ lNl@ lCl3l1l0lg:
33 lJ6Zl@ 31 40 di 42 43 44 47 CAUSE DESCRIPTION AND CORRECTIVE ACTION 3 h
-11 l 0 l l The cause was excessive use during outages which caused excessive wear. With this l gil3l l wear, it can rebound open while the latching mechanism continues to close. Under l
,,,,,; MWO 83-4009, the personnel lock was returned to operable. During the 1984 Refueling l g g 3, y Outage, a thorough inspection was conducted by the vendor. Under MWO 1-84-2947-01, l the noted problems were corrected. ;
, ,, g 7 8 9 80 ST S % POWER OTHER STATUS IS O RY DISCOVERY DESCRIPTION I115 l lD l@ l 0 l 0 l 0 l@l N/A l lAl@l-Operatorobservation l A TIVITY CO TENT 5
RELEASED OF RELEASE AMOUNT OF ACTIVITY LOCATION OF RELEASE I1 l6' l'[7d h l 'Z l@l N/A l [ N/A l PERSONNE$ EXPOS ES NUMBER TYPE DESCRIPTION l1 l 7 l l0 l0 l0 l@lZ l@] N/A l PE RSONN E L INJU IES NUMBER DESCRIPTION l
It IR8 I9lo 10 l0 l@l12 N/A 7 11 80 LOSS OF OR DAMAGE TO FACILITY l 3 l 9 l lYlgl N7I l 7 8 9 10 80 ISSUE l N/A D_[OJ [z_j@ DESCRIPTION I 68 69 llllIIlIIllllI 80 5
-7 .8=9- 10 o
, Jan C. Stotz (419) 321-7544
f I '
TOLEDO EDISON COMPANY
[ DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 F SUPPLEMENTAL INFORMATION FOR'LER'NP-33-83-45, REVISION 2
?
p DATE OF EVENT: July 26,- 1983 FACILITY ' Davis-Besse, Unit No. 1 IDENTIFICATION OF OCCURRENCE: The Unit was in Mode 3, with Power (MVt) = 0 and Load (Gross MVe) = 0 conditions Prior to occurrence: At 0710 hours0.00822 days <br />0.197 hours <br />0.00117 weeks <br />2.70155e-4 months <br /> on July 26, 1983, two personnel
% vere exiting the_ containment building by vay of the personnel hatch. While in the tunnel, it was found that the hand wheel for the inner door was all the way in the shut position while the inner door was still partially _open. The
' outer door.vould open and both personnel exited the personnel hatch tunnel and reshut the outer door. The Shift Supervisor declared the personnel hatch inoperable, and the Unit entered the action statement of Technical Specification 3.6.1.3. ,
i Designation of Apparent Cause of Occurrence .The cause was excessive use !
which caused wear of the roller cam bearings. Vith this vear, the door can rebound open while the latching mechanism continues to close. In late May-1983, the personnel hatch manufacturer, Chicago Bridge and Iron, advised Toledo Edison that this is a potential malfunction for their air locks fabricated and installed between 1464 and 1973.- During the 1984 Refueling Outage, the vendor representative inspected the lock and suggested modifications to strengthen areas to reduce wear on the bearings..
Analysis of Occurrences i i
There was'no danger to the health and safety of the public or station !
personnel. The plant was in Mode 3 in the process of shutting down.for the {
1983 Refueling Outage. The outer door was verified shut with the exception of -!
the exiting of the two personnel involved. j 1
Corrective Action: j j
Under MVO 83-4009, the personnel lock was repaired and returned to operable !
status. A more indepth preventive maintenance program (PM-0745) has been l implemented. j-During the 1984 Refueling Outage, some suggested refurbishments by Chicago !
Bridge and Iron (CB&I) vere implemented under MVO 1-84-2947-01. Additional !
' modifications were considered for implementation during subsequent outages. !
However, due to the very successful use of temporary doors in the personnel-- !
hatch during outages, vear and tear on the permanent doors has been .
significantly reduced. Therefore, no additional modifications vill be made. !
Failure Date Previous similar occurrences involving containment personnel !
air lock door failing to latch were reported in Licensee Event Reports NP-33-77-18 (77-018), NP-33-80-92 (80-073), and NP-33-81-80 (81-167).
LER No.83-039 1, i