EPID:L-2017-FPR-0006, Package: Environmental Assessment and Finding of No Significant Impact for First Energy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Beaver Valley ISFSI (Approved, Closed) EPID:L-2017-FPR-0019, Package: Environmental Assessment and Finding of No Significant Impact for First Energy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Beaver Valley ISFSI (Approved, Closed) EPID:L-2017-FPR-0053, Package: Environmental Assessment and Finding of No Significant Impact for First Energy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Beaver Valley ISFSI (Approved, Closed) |
|
MONTHYEARML19162A0312019-06-0707 June 2019 Enclosufinal Safety Evaluation (Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Perry ISFSI Project stage: Approval ML19162A0292019-06-0707 June 2019 Package: Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Perry ISFSI Project stage: Request ML19162A0302019-06-0707 June 2019 Memorandum to File Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Perry ISFSI Project stage: Other ML19162A0102019-06-0707 June 2019 Memorandum to File Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Davis Besse ISFSI Project stage: Other ML19162A0082019-06-0707 June 2019 Package: Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Davis Besse ISFSI Project stage: Request ML19162A0092019-06-0707 June 2019 Enclosufinal Environmental Assessment (Memorandum to File Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) an Project stage: Other ML19161A3302019-06-0707 June 2019 Memo to File Environmental Assessment and Finding of No Significant Impact for First Energy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Beaver Valley ISFSI Project stage: Other ML19161A3282019-06-0707 June 2019 Package: Environmental Assessment and Finding of No Significant Impact for First Energy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Beaver Valley ISFSI Project stage: Request ML19161A3292019-06-0707 June 2019 Enclosufinal Environmental Assessment (Memo to File Environmental Assessment and Finding of No Significant Impact for First Energy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72. Project stage: Other ML19219A6072019-08-0808 August 2019 LTR to G. Halnon Nrc'S Analysis of Firstenergy Nuclear Operating Company'S Initial and Updated Decommissioning Funding Plans for Davis-Besse Nuclear Power Station Unit 1,Perry Nuclear Power Plant Unit 1, and Beaver Valley Power Station Unit Project stage: Other 2019-06-07
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000346/20234012023-09-13013 September 2023 Security Baseline Inspection Report 05000346/2023401 (Public) L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000346/20230112023-08-30030 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000346/2023011 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000346/20230052023-08-24024 August 2023 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2023005) L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000346/20230502023-08-0303 August 2023 Special Inspection Report 05000346/2023050 L-23-175, Submittal of Fifth Ten Year Inservice Testing Program2023-08-0101 August 2023 Submittal of Fifth Ten Year Inservice Testing Program IR 05000346/20230902023-08-0101 August 2023 EA-23-002 Davis-Besse Nuclear Power Station - NRC Inspection Report No. 05000346/2023090 (Public) ML23178A2742023-08-0101 August 2023 Letter to the Honorable Marcy Kaptur from Chair Hanson Responds to Letter Regarding the License Transfer Application for the Davis-Besse Nuclear Power Station IR 05000346/20230022023-07-27027 July 2023 Integrated Inspection Report 05000346/2023002 ML23193A7842023-07-13013 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000346/2023402 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000346/20235012023-06-13013 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000346/2023501 ML23160A2342023-06-13013 June 2023 Confirmation of Initial License Examination L-23-034, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-13013 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-135, Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-31031 May 2023 Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) ML23131A2732023-05-15015 May 2023 Notification of NRC Supplemental Inspection 95001 and Request for Information L-23-131, Readiness for Resumption of NRC Supplemental Inspection2023-05-12012 May 2023 Readiness for Resumption of NRC Supplemental Inspection L-23-101, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station - 20222023-05-12012 May 2023 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station - 2022 IR 05000346/20230102023-05-0909 May 2023 Commercial Grade Dedication Inspection Report 05000346/2023010 ML23123A1272023-05-0303 May 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Davis-Besse Nuclear Power Station IR 05000346/20230012023-05-0101 May 2023 Integrated Inspection Report 05000346/2023001 and 07200014/2022001 L-23-092, Occupational Radiation Exposure Report for Year 20222023-04-27027 April 2023 Occupational Radiation Exposure Report for Year 2022 ML23111A1972023-04-26026 April 2023 Information Meeting with Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Davis-Besse Nuclear Power Plant Station ML23114A1062023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23096A1382023-04-11011 April 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-037, and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments2023-03-29029 March 2023 and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments L-23-066, Annual Notification of Property Insurance Coverage2023-03-21021 March 2023 Annual Notification of Property Insurance Coverage ML23066A2592023-03-14014 March 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2, Davis Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 2024-02-02
[Table view] |
Text
August 8, 2019 Gregory H. Halnon Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company 76 South Main Street Akron, Ohio 44308
SUBJECT:
NUCLEAR REGULATORY COMMISSIONS ANALYSIS OF FIRSTENERGY NUCLEAR OPERATING COMPANYS INITIAL AND UPDATED DECOMMISSIONING FUNDING PLANS FOR DAVIS-BESSE NUCLEAR POWER STATION UNIT NO. 1, PERRY NUCLEAR POWER PLANT UNIT NO.
1, AND BEAVER VALLEY POWER STATION UNIT NOS. 1 AND 2 INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS
Dear Mr. Halnon:
By letters dated December 17, 2012, and December 8, 2014, FirstEnergy Nuclear Operating Company (FENOC) submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, initial decommissioning funding plans (initial DFPs) for the independent spent fuel storage installations (ISFSIs) at Davis-Besse Nuclear Power Station Unit No. 1, Perry Nuclear Power Plant Unit No. 1, and Beaver Valley Power Station Unit Nos. 1 and 2 (Agencywide Documents Access and Management System (ADAMS) Accession Nos.
ML12352A194 and ML14342A707). By letter dated December 9, 2015, FENOC submitted, also for NRC staff review and approval, updated decommissioning funding plans (updated DFPs) for the ISFSls at Davis-Besse Nuclear Power Station Unit No. 1, Perry Nuclear Power Plant Unit No. 1, and Beaver Valley Power Station Unit Nos. 1 and 2 (ADAMS Accession No. ML15343A350). In accordance with Title 10 of the Code of Federal Regulations (10 CFR),
Sections 72.30(b) and (c), and using NUREG-1757, Vol. 3, Rev. 1, Consolidated Decommissioning Guidance, the NRC staff reviewed the initial and updated DFPs submitted by FENOC, including the initial and updated decommissioning cost estimates (DCEs) and the method of assuring funds for decommissioning.
Pursuant to 10 CFR 72.30(b), each holder of, or applicant for, a license under Part 72 must submit for NRC review and approval a DFP containing information on how reasonable assurance will be provided that funds will be available to decommission its ISFSIs. The DFP must contain a detailed DCE, in an amount reflecting: (1) the cost of an independent contractor to perform all decommissioning activities, (2) an adequate contingency factor, and (3) the cost of meeting the 10 CFR 20.1402 unrestricted use criteria (or the cost of meeting the 10 CFR 20.1403 restricted use criteria, provided the licensee can demonstrate its ability to meet these criteria). The licensees DFP must also identify and justify using the key assumptions contained in the DCE. Further, the DFP must describe the method of assuring funds for ISFSI decommissioning, including means for adjusting cost estimates and associated funding levels periodically over the life of the ISFSI. Additionally, the DFP must specify the volume of onsite subsurface material containing residual radioactivity that will require remediation to meet the
G. Halnon criteria for license termination, and contain a certification that financial assurance for ISFSI decommissioning has been provided in the amount of the DCE.
The NRC staff reviewed and analyzed the information submitted by FENOC in its initial DFPs on how reasonable assurance will be provided that funds will be available to decommission the ISFSIs, including the amount of the DCE and the method of assuring funds for decommissioning.
In the initial DFP, FENOC estimated that the total cost to decommission the ISFSIs at Davis-Besse Nuclear Power Station Unit No. 1, Perry Nuclear Power Plant Unit No. 1, and Beaver Valley Power Station Unit Nos. 1 and 2 for unrestricted use is $4.7 million, $6.0 million, $8.0 million, respectively, in 2012 dollars, except for Beaver Valley, provided in 2014 dollars. Based on its analysis of FENOCs initial DFPs, the NRC staff finds that the submitted DCEs are based on reasonable costs of a third party contractor, include an adequate contingency factor, reflect the cost of meeting the 10 CFR 20.1402 criteria for unrestricted use, and are based on reasonable and documented assumptions. Therefore, the NRC staff finds that the DCEs adequately estimated the cost to carry out required ISFSI decommissioning activities prior to license termination, and that the DCEs are acceptable.
FENOC relied on parent company guarantees as financial assurance for ISFSI decommissioning, a method authorized by 10 CFR 72.30(e). The NRC staff confirmed that the parent company guarantees and the financial test meet the criteria of 10 CFR Part 30, Appendix A. The NRC staff finds that the aggregate dollar amount of the licensees financial instruments provides adequate financial assurance to cover its cost estimates, and therefore, that these financial instruments are acceptable.
Pursuant to 10 CFR 72.30(c), at the time of license renewal and at intervals not to exceed 3 years, the initial DFP required to be submitted by 10 CFR 72.30(b) must be resubmitted with adjustments as necessary to account for changes in costs and the extent of contamination (updated DFP). The updated DFP must update the information submitted with the original or prior approved plan. In addition, the updated DFP must specifically consider the effect of the following events on decommissioning costs, as required by 10 CFR 72.30(c)(1)-(4): (1) spills of radioactive material producing additional residual radioactivity in onsite subsurface material, (2) facility modifications, (3) changes in authorized possession limits, and (4) actual remediation costs that exceed the previous cost estimate.
In the updated DFP, FENOC estimates that the total cost to decommission the ISFSIs at Davis-Besse Nuclear Power Station Unit No. 1, Perry Nuclear Power Plant Unit No. 1, and Beaver Valley Power Station Unit Nos. 1 and 2 for unrestricted use is $5.5 million, $7.9 million, $8.0 million for each ISFSI, respectively, in 2014 dollars. The updated decommissioning cost estimates (updated DCEs) considered the requirements of 10 CFR 72.30(c)(1)-(4) and the licensee provided a discussion of each requirement. The licensees submittal states, in part, that there have been:
- 1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material;
- 2. No facility modifications;
- 3. No changes in authorized possession limits; and
- 4. No actual remediation costs that exceed the previous cost estimate.
G. Halnon Based on its review of FENOCs submittal, the NRC staff finds that the updated DCEs are based on reasonable costs of a third party contractor, include an adequate contingency factor, reflect the cost of meeting the 10 CFR 20.1402 criteria for unrestricted use, and are based on reasonable and documented assumptions. Therefore, the NRC staff finds that the updated DCEs adequately estimate the cost, at this time, to carry out required ISFSI decommissioning activities prior to license termination, and that the updated DCEs are acceptable.
In the updated DFP, FENOC relied on parent company guarantees as financial assurance for ISFSI decommissioning, a method authorized by 10 CFR 72.30(e). The NRC staff confirmed that the parent company guarantees and the financial test meet the criteria of 10 CFR Part 30, Appendix A. The NRC staff reviewed the licensees updated DFP, and finds that the aggregate dollar amount of the licensees financial instruments provides adequate financial assurance to cover its updated DCEs.
Therefore, based on its review, the NRC staff finds that the initial and updated DFPs contain the information required by 10 CFR 72.30(b) and (c) and FENOC has provided reasonable assurance that funds will be available to decommission the ISFSIs at Davis-Besse Nuclear Power Station Unit No. 1, Perry Nuclear Power Plant Unit No. 1, and Beaver Valley Power Station Unit Nos. 1 and 2. In addition to the NRC staffs review of FENOCs initial and updated DFPs, the NRC staff completed an environmental review. On August 5, 2019, the NRC staff published the results of that review in an environmental assessment and finding of no significant impact in the Federal Register (84 FR 38065; 84 FR 38067; and 84 FR 38071) for Davis-Besse Nuclear Power Station, Unit No. 1; Perry Nuclear Power Plant, Unit No. 1; and Beaver Valley Power Station, Unit Nos. 1 and 2; respectively. The NRC staff determined there were no environmental impacts from the NRC staffs review and approval of FENOCs initial and updated DFPs.
If you have any questions regarding this matter, please contact me at (301) 415-5722 or Pamela Longmire, of my staff, at (301) 415-7465.
Sincerely,
/RA/
John McKirgan, Chief Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket Nos.: 72-14, 72-69, and 72-1043 CAC No.: 001028 EPID Nos.: L-2017-FPR-0019, L-2017-FPR-0053, and L-2017-FPR-0006
ML19219A607 OFFICE NMSS/DSFM NMSS/DSFM OGC NMSS/DSFM NAME PLongmire WWheatley JMaltese via email JMcKirgan DATE 4/17/2019 5/31/2019 03/07/2019 08/08/2019