July 10, 2019
Mr. Robert Craven
Site Director
NextEra Energy Point Beach, LLC
6610 Nuclear Road
Two Rivers, WI 54241-9516
SUBJECT: POINT BEACH NUCLEAR PLANT UNITS 1 AND 2NOTIFICATION OF
NRC REQUEST FOR INFORMATION FOR POST-APPROVAL SITE
INSPECTION FOR LICENSE RENEWALPHASE IV; INSPECTION
REPORT 05000266/2019010; 05000301/2019010
Dear Mr. Craven:
On September 16, 2019, the U.S. Nuclear Regulatory Commission (NRC) will begin an
inspection in accordance with Inspection Procedure 71003 Section 02.02.d. (Phase IV). This
onsite inspection is scheduled to be performed September 16, 2019, thru September 20, 2019.
The purpose of the inspection is to review the implementation of The Aging Management
Program (AMP) elements during the Period of Extended Operation. The inspection team will
select for review a sample of the sites AMPs.
This Request for Information is separated into three Sections (A, B and C). Section A
information will be used to facilitate the AMP sample selections. The team leader will make
AMP selections and inform the licensee. Based on these selections, the licensee will provide
the additional information requested under Section B. This information will be used as part of
the inspection preparation and implementation. Requests under Section C should be available
to the inspectors during the on-site week of inspection. See the table below for specific dates:
Requested Action: Expected Date:
Licensee provides Section A Information July 29, 2019
Team Leader communicates selection to the licensee August 9, 2019
Licensee provides Section B Information August 23, 2019
Licensee provides Section C Information September 16, 2019
Experience has shown that this inspection is resource intensive both for the NRC inspector and
your staff. In order to minimize the impact to your onsite resources, and to ensure a productive
inspection for both sides, we have enclosed a request for documents needed for this inspection.
It is important that all of these documents are up-to-date, and complete, in order to minimize the
number of additional documents requested during the preparation and/or the onsite portion of
the inspection.
R. Craven -2-
We have discussed the schedule for inspection activities with your staff and understand that our
regulatory contact for this inspection will be Brenda Scherwinski of your organization. If there
are any questions about this inspection or the material requested, please contact the lead
inspector John V. Bozga at 630-829-9613.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,
Exemptions, Requests for Withholding.
Sincerely,
/RA/
John V. Bozga, Senior Reactor Inspector
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-266, 50-301
Enclosure:
Document Request for License Renewal
Phase IV Inspection
cc: Distribution via LISTSERV
R. Craven -3-
Letter to Robert Craven from John V. Bozga dated July 10, 2019.
SUBJECT: POINT BEACH NUCLEAR PLANT UNITS 1 AND 2NOTIFICATION OF
NRC REQUEST FOR INFORMATION FOR POST-APPROVAL SITE
INSPECTION FOR LICENSE RENEWALPHASE IV; INSPECTION
REPORT 05000266/2019010; 05000301/2019010
DISTRIBUTION:
RidsNrrDorlLpl3
RidsNrrPMPointBeach
RidsNrrDirsIrib Resource
DRPIII
DRSIII
ADAMS Accession Number: ML19191A079
OFFICE RIII
NAME JBozga:cl
DATE 07/10/19
OFFICIAL RECORD COPY
DOCUMENT REQUEST FOR LICENSE RENEWAL PHASE IV INSPECTION
Inspection Report: 05000266/2019010; 05000301/2019010
Inspection Dates: September 9-13, 2019 (In-Office Prep)
September 16-20, 2019 (Onsite)
Inspection Procedures: 71003, Post-Approval Site Inspection for License Renewal
(Phase IV)
Lead Inspectors: John V. Bozga, Senior Reactor Inspector
Please provide the information requested below to the U.S. Nuclear Regulatory Commission
Region III Office in care of the lead inspector. The information can be provided in hard copy
or electronic format; however, electronic format is preferred, via digital data storage device
(i.e. DVDs/CDs).
A. Information Requested to Facilitate Aging Management Program Sample Selection
(1) Provide copies of corporate and/or site-specific program document/procedure
related to overall Aging Management Program (AMP).
(2) Provide a list of all site AMPs.
(3) Provide list of AMPs that were new or enhanced in the License Renewal
Application.
(4) Provide list of AMPs that had commitment changes since entering the Period of
Extended Operation (PEO).
(5) Provide list of AMPs that have incorporated newly identified systems, structures,
and components (SSCs) since entering the PEO. List or describe which SSCs
were incorporated.
(6) Provide list of AMPs that have incorporated components from One-Time
Inspection activities since entering the PEO.
(7) Provide any self-assessments and/or audits related to license renewal program
implementation and/or AMP effectiveness.
(8) Provide a list of corrective action documents that were initiated as result of
license renewal activities, self-assessments, and/or audits. (since entering
the PEO)
(9) Electronic copies of Updated Final Safety Analysis Report, Technical
Specifications, Technical Specifications Bases, Technical Requirements Manual,
and Individual Plant Examination of External Events if available.
Enclosure
DOCUMENT REQUEST FOR LICENSE RENEWAL PHASE IV INSPECTION
(10) Site-specific responses and/or evaluations for U.S. Nuclear Regulatory
Commission generic communications associated with license renewal that were
issued after entering the PEO.
(11) Risk-ranking of top 250 basic events from your internal and external (if available)
events site specific probabilistic safety analysis sorted by Birnbaum Importance,
Risk-Reduction Worth, Risk-Achievement Worth, and Fussell-Veseley (as
applicable) (Provide in Excel format). Include basic event names/description.
(12) Provide a list of the top 10 risk important systems for the internal events model
(and external, if available).
B. Information Requested for each Aging Management Program Selected for Review
(As Applicable)
(1) Program basis documents and administrative procedures describing key program
attributes such as program objectives, scope, detection and monitoring methods,
administrative controls, acceptance criteria, corrective actions, and scope
expansion requirements.
(2) Provide a summary document listing which implementing procedures are
included in the selected AMP and what are their required performance frequency.
(3) Copies of implementing procedures for program activities (e.g., visual
examination procedures, ultrasonic examination procedures, maintenance
procedures, system walkdowns, etc.).
(4) Completed Work Orders for the most recent aging management activities
performed, including associated inspection and testing reports, as applicable.
This request is limited to the last two completed activities (per procedure). If this
request becomes too onerous based on the number of work order reach out to
the lead inspector for additional scope clarification.
(5) Copies of aging related corrective actions documents associated with the
selected AMP, and SSCs under its purview (for the last three years). A search
of corrective actions documents should include keywords such as: aging, age
management, degradation, wear, delamination, peeling, crazing,
chipping, leak, crack, corrosion, rust, leaching, embrittlement,
fatigue, blister, spalling, oxidation, loss of function, failed acceptance
criteria, flow-accelerated, or other site specific terms/codes used in aging
monitoring as appropriate.
(6) Updated license renewal scoping drawings showing the SSCs within the scope of
the AMP.
(7) Gap analyses performed (if any) to assess the differences between the current
AMP and the recommendations in the latest revision of NUREG-1801, Generic
Aging Lessons Learned (GALL), and subsequent Interim Staff Guidance.
2
DOCUMENT REQUEST FOR LICENSE RENEWAL PHASE IV INSPECTION
(8) Copy of evaluations performed for applicable external and internal operating
experience issues associated with license renewal. This request is limited to
operating experience items issued after entering the PEO.
(9) Description of instances where examination scope expansion was required
based on the examination of a SSC in accordance with the AMP. Please
describe the logic to select the scope expansion, and any resulting changes to
the AMP. (This request is limited to work performed in the PEO)
(10) Description of instances where AMP examinations/inspections were eliminated or
deferred. (This request is limited to work performed in the PEO)
(11) Description of instances where examination/inspection scope changes were
required based on limitations encountered during the examination. (This request
is limited to work performed in the PEO)
C. Information Requested to be available during the onsite week of inspection
(1) Provide a brief presentation (informal) to the inspection team regarding aging
management at the site. Topics to be covered:
a. How are aging related issue identified, documented and evaluated within the
corrective action program and/or other aging tracking software/program.
b. Describe which individuals and/or organizations are responsible for
identifying and evaluating aging related issues.
c. Describe the responsibilities regarding age management, if any, of the
following:
i. System Engineers
ii. AMP Owners
iii. Corporate office
Ideally, this should be presented Monday or Tuesday of the inspection week.
Coordinate with the team leader for further detail.
(2) Copy of simplified system drawings (a.k.a., Horse Notes or Training Notes).
(3) A computer with network access to the sites Corrective Action Program.
3