MONTHYEARIR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 IR 05000313/20234052023-12-12012 December 2023 Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230102023-09-20020 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000313/2023010 and 05000368/2023010 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20243012023-08-14014 August 2023 Notification of NRC Initial Operator Licensing Examination 05000313/2024301 IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 IR 05000313/20234032023-06-28028 June 2023 Security Baseline Inspection Report 05000313/2023403 and 05000368/2023403 IR 05000313/20234012023-06-13013 June 2023 Cyber Security Inspection Report 05000313/2023401 and 05000368/2023401 IR 05000313/20230012023-05-0909 May 2023 Integrated Inspection Report 05000313/2023001 and 05000368/2023001 IR 05000368/20233012023-05-0101 May 2023 NRC Examination Report 05000368/2023301 IR 05000313/20220062023-03-0101 March 2023 Annual Assessment Letter for Arkansas Nuclear One Units 1 and 2 (Report 05000313/2022006 and 05000368/2022006) IR 05000313/20220042023-01-26026 January 2023 Integrated Inspection Report 05000313/2022004 and 05000368/2022004 - 4th Quarter IR 05000313/20220032022-11-0909 November 2022 Integrated Inspection Report 05000313/2022003 and 05000368/2022003 and Exercise of Enforcement Discretion IR 05000313/20220112022-11-0909 November 2022 Notice of Violation NRC Inspection Report 05000313/2022011 and 05000368/2022011 ML22301A1532022-11-0909 November 2022 Notice of Violation NRC Inspection Report 05000313/2022011 and 05000368/2022011 ML22308A1912022-11-0606 November 2022 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000313/2023401 and 05000368/2023401 IR 05000313/20224012022-10-20020 October 2022 Security Baseline Inspection Report 05000313/2022401 and 05000368/2022401 IR 05000313/20220502022-09-26026 September 2022 Special Inspection Reactive Report 05000313 2022050 and 05000368 2022050 Cover Letter Only ML22208A1282022-08-0404 August 2022 (2nd Quarter) Inspection Report 2022 002 IR 05000313/20224032022-06-23023 June 2022 Security Baseline Inspection Report 05000313/2022403 and 05000368/2022403 IR 05000313/20223012022-06-15015 June 2022 NRC Examination Report 05000313/2022301 IR 05000313/20210132022-05-17017 May 2022 License Renewal Phase 4 Inspection Report 05000313/2021013 IR 05000313/20220012022-05-10010 May 2022 Integrated Inspection Report 05000313/2022001 and 05000368/2022001 IR 05000313/20220102022-03-14014 March 2022 Triennial Fire Protection Inspection Report 05000313/2022010 and 05000368/2022010 IR 05000313/20210062022-03-0202 March 2022 Annual Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Report 05000313/2021006 and 05000368/2021006) ML22047A2702022-02-23023 February 2022 Security Baseline Inspection Report 05000313/2022403 and 05000368/2022403 IR 05000313/20210042022-02-0404 February 2022 Integrated Inspection Report 05000313/2021004 and 05000368/2021004 ML22011A0992022-01-14014 January 2022 IR 2021012 EOI CO3 IR 05000313/20210102022-01-13013 January 2022 Biennial Problem Identification and Resolution Inspection Report 05000313/2021010 and 05000368/2021010 IR 05000313/20210032021-11-0505 November 2021 Integrated Inspection Report 05000313/2021003 and 05000368/2021003 IR 05000313/20210112021-09-23023 September 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000313/2021011 and 05000368/2021011 IR 05000313/20214012021-08-10010 August 2021 Security Baseline Inspection Report 05000313/2021401 and 05000368/2021401 IR 05000313/20210022021-08-0909 August 2021 Integrated Inspection Report 05000313/2021002 and 05000368/2021002 IR 05000368/20213012021-05-17017 May 2021 NRC Examination Report 05000368/2021301 IR 05000313/20210012021-05-0606 May 2021 Integrated Inspection Report 05000313/2021001 and 05000368/2021001 ML21095A3162021-04-13013 April 2021 ANO 2021402-Non SGI Rcl IR 05000313/20200062021-03-0303 March 2021 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2020006 and 05000368/2020006) IR 05000313/20200042021-02-0303 February 2021 Integrated Inspection Report 05000313/2020004 and 05000368/2020004 IR 05000313/20200032020-11-0909 November 2020 Integrated Inspection Report 05000313/2020003 and 05000368/2020003 and Independent Spent Fuel Storage Installation Aging Management Inspection Report 07200013/2020001 IR 05000313/20204112020-10-22022 October 2020 Security Baseline Inspection Report 05000313/2020411 and 05000368/2020411 IR 05000313/20204042020-09-23023 September 2020 Notice of Violation; NRC Inspection Report 05000313/2020404 and 05000368/2020404 and NRC Investigation Report 4-2019-009 IR 05000313/20204102020-09-14014 September 2020 Security Baseline Inspection Report 05000313/2020410 and 05000368/2020410 IR 05000313/20200052020-09-0101 September 2020 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Reports 05000313/2020005 and 05000368/2020005) IR 05000313/20200022020-08-0505 August 2020 Integrated Inspection Report 05000313/2020002 and 05000368/2020002 IR 05000313/20204032020-07-30030 July 2020 Material Control and Accounting Inspection Report 05000313/2020403 and 05000368/2020403 2024-01-02
[Table view] |
Text
June 28, 2019 ANO Site Vice President Arkansas Nuclear One Entergy Operations, Inc.
N-TSB-58 1448 S.R. 333 Russellville, AR 72802
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT 2 - REVIEW OF THE FALL 2018 STEAM GENERATOR TUBE INSPECTION REPORT (EPID L-2019-LRO-0012)
Dear Sir or Madam:
By letter dated February 28, 2019 (Agencywide Documents Access and Management System Accession No. ML19059A440), Entergy Operations, Inc. (the licensee) submitted information summarizing the results of the fall 2018 steam generator (SG) tube inspections at Arkansas Nuclear One, Unit 2 (ANO-2). The inspections were performed during Refueling Outage 26 (2R26). The SG tube inspection report was submitted in accordance with Technical Specification (TS) 6.6.7, Steam Generator Tube Inspection Report.
The U.S. Nuclear Regulatory Commission (NRC) staff has completed its review of the submittal and concludes that the licensee provided the information required by ANO-2 TS 6.6.7. In addition, the NRC staff concludes that there are no technical issues that warrant followup actions at this time. Enclosed is the NRC staffs review of the ANO-2, SG tube inspection report.
If you have any questions, please contact me at (301) 415-4037 or by e-mail at Thomas.Wengert@nrc.gov.
Sincerely,
/RA/
Thomas J. Wengert, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-368
Enclosure:
Review of SG Tube Inspection Report cc: Listserv
ML19175A292 *by memorandum OFFICE NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA NRR/DMLR/MCCB/BC*
NAME TWengert PBlechman SBloom DATE 06/28/19 06/25/19 06/17/19 OFFICE NRR/DORL/LPL4/BC NRR/DORL/LPL4/PM NAME RPascarelli TWengert DATE 06/28/19 06/28/19 STAFF REVIEW OF RESULTS OF FALL 2018 STEAM GENERATOR TUBE INSERVICE INSPECTIONS PERFORMED DURING REFUELING OUTAGE 26 ARKANSAS NUCLEAR ONE, UNIT 2 ENTERGY OPERATIONS, INC.
DOCKET NO. 50-368 By letter dated February 28, 2019 (Agencywide Documents Access and Management System Accession No. ML19059A440), Entergy Operations, Inc. (the licensee) submitted information summarizing the results of the fall 2018 steam generator (SG) tube inspections at Arkansas Nuclear One, Unit 2 (ANO-2). These inspections were performed during Refueling Outage 26 (2R26).
The SG tube inspection report was submitted in accordance with Technical Specification (TS) 6.6.7, Steam Generator Tube Inspection Report.
ANO-2 has two Westinghouse model Delta 109 SGs, each containing 10,637 thermally-treated Alloy 690 tubes. The tubes each have a nominal outside diameter of 0.688 inches and a nominal wall thickness of 0.040 inches. The tubes are hydraulically expanded through the tubesheet thickness and are supported by eight broached-hole tube support plates (TSPs) in the vertical region of the tube bundle. In the U-bend region, the tubes are supported by five sets of staggered Type 405 stainless steel anti-vibration bars (AVBs).
In the letter dated February 28, 2019, the licensee provided the scope, extent, methods, and results of its SG tube inspections. In addition, the licensee described corrective actions it has taken, such as tube plugging, in response to the inspection findings.
After reviewing the information provided by the licensee, the U.S. Nuclear Regulatory Commission (NRC) staff has the following comments or observations:
- In the licensees report, the three-letter codes TBP and PTP are used for to be plugged and preventive tube plug, respectively.
- Service induced indications were reported from wear with anti-vibration bars, tube support plates, and loose parts; however, the loose part indications were all historical and no new loose parts were reported.
Based on a review of the information provided, the NRC staff concludes that the licensee provided the information required by ANO-2 TS 6.6.7. In addition, the staff concludes that there are no technical issues that warrant followup action at this time because the inspections appear to be consistent with the objective of detecting potential tube degradation and the inspection results appear to be consistent with industry operating experience at similarly designed and operated units.
Enclosure