Letter Sequence Request |
---|
EPID:L-2019-LLA-0036, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange (Open) |
|
|
|
---|
Category:Letter type:ET
MONTHYEARET 23-0006, CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components2023-05-17017 May 2023 CFR 50.55a Request Number CI3R-01 for the Third Containment Inservice Inspection Program Interval for Proposed Alternative Frequency to Containment Unbonded Post-Tensioning System Components ET 23-0005, 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peen2023-03-16016 March 2023 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened ET 23-0003, License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications2023-03-0101 March 2023 License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ET 23-0002, Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2023-02-0707 February 2023 Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 23-0004, Response to Requests for Additional Information (RAI) Regarding License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements2023-01-26026 January 2023 Response to Requests for Additional Information (RAI) Regarding License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ET 22-0006, Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2022-12-0101 December 2022 Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 22-0010, License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements2022-08-0202 August 2022 License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ET 22-0012, Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-07-12012 July 2022 Supplement to License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 22-0011, Withdrawal of 10 CFR 50.55a Request I4R-08, Relief for Extension of Follow-up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened Surface2022-05-31031 May 2022 Withdrawal of 10 CFR 50.55a Request I4R-08, Relief for Extension of Follow-up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head Penetration Nozzles with Mitigated Alloy 600/82/182 Peened Surface ET 22-0005, Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2022-04-13013 April 2022 Response to Request for Additional Information Regarding License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 22-0003, CFR 50.55a Request I4R-09 for the Fourth Inservice Inspection Program Interval, Relief from Examination of Reactor Vessel Flange Threads2022-04-0606 April 2022 CFR 50.55a Request I4R-09 for the Fourth Inservice Inspection Program Interval, Relief from Examination of Reactor Vessel Flange Threads ET 22-0002, Operating Corp 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head .2022-04-0404 April 2022 Operating Corp 10 CFR 50.55a Request Number I4R-08 for the Fourth Inservice Inspection Program Interval, Relief for Extension of Follow Up Examination and Visual Examination Requirements for Reactor Pressure Vessel Head . ET 22-0004, Operating Corp - Response to Request for Confirmation of Information (RCI) Regarding Steam Generator Tube Inspection Report2022-03-15015 March 2022 Operating Corp - Response to Request for Confirmation of Information (RCI) Regarding Steam Generator Tube Inspection Report ET 22-0001, Removal of the Table of Contents from the Technical Specifications2022-01-12012 January 2022 Removal of the Table of Contents from the Technical Specifications ET 21-0017, Response to Request for Additional Information Regarding License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2021-12-22022 December 2021 Response to Request for Additional Information Regarding License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ET 21-0009, Results of the Steam Generator Tube Inservice Inspection During the 24th Refueling Outage2021-11-0101 November 2021 Results of the Steam Generator Tube Inservice Inspection During the 24th Refueling Outage ET 21-0015, Withdrawal of License Amendment Request for a Risk-Informed Resolution to GSI-1912021-10-20020 October 2021 Withdrawal of License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 21-0012, Supplement to License Amendment Request for a Risk-Informed Resolution to GSI-1912021-10-11011 October 2021 Supplement to License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 21-0004, License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2021-09-29029 September 2021 License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 21-0010, License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2021-09-29029 September 2021 License Amendment Request - Revision to Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ET 21-0005, Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-1912021-08-12012 August 2021 Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-191 ET 20-0013, Response to Request for Additional Information Re Application for Technical Specification Change Re Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program (TSTF-415)2020-10-26026 October 2020 Response to Request for Additional Information Re Application for Technical Specification Change Re Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program (TSTF-415) ET 20-0011, Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2020-10-0101 October 2020 Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI ET 20-0007, License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers2020-06-0808 June 2020 License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers ET 20-0008, Operating Corporation Update for Full Implementation of Open Phase Detection System2020-05-20020 May 2020 Operating Corporation Update for Full Implementation of Open Phase Detection System ET 20-0004, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425)2020-04-27027 April 2020 Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) ET 20-0002, Response to Request for Additional Information Regarding Utilizing Code Case N-666-1, Weld Overlay of Class 1, 2, and 3 Socket Welded Connections, Section XI, Division 12020-01-29029 January 2020 Response to Request for Additional Information Regarding Utilizing Code Case N-666-1, Weld Overlay of Class 1, 2, and 3 Socket Welded Connections, Section XI, Division 1 ET 19-0021, Errata for Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-12-0909 December 2019 Errata for Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0020, Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation2019-11-13013 November 2019 Supplemental Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation ET 19-0019, Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-09-10010 September 2019 Response to Request for Additional Information Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ET 19-0018, Supplement to License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-08-22022 August 2019 Supplement to License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ET 19-0014, lnserv1ce Inspection (ISI) Program Relief Request Number 14R-07, to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, D1v1s1on 12019-08-15015 August 2019 lnserv1ce Inspection (ISI) Program Relief Request Number 14R-07, to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, D1v1s1on 1 ET 19-0002, License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-03-18018 March 2019 License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ET 19-0008, Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption.2019-03-0505 March 2019 Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption. ET 19-0003, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange2019-02-25025 February 2019 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange ET 19-0001, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-01-23023 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 ET 18-0032, Operating Corporation Change of Date for Full Implementation of Open Phase Detection System2018-12-0707 December 2018 Operating Corporation Change of Date for Full Implementation of Open Phase Detection System ET 18-0035, Operating Corp., Supplemental Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-12-0606 December 2018 Operating Corp., Supplemental Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0029, (WCGS) - Results of the Twenty First Steam Generator Tube Inservice Inspection2018-10-31031 October 2018 (WCGS) - Results of the Twenty First Steam Generator Tube Inservice Inspection ET 18-0018, Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-06-19019 June 2018 Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0016, Response to Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools Request for Supplemental Information2018-05-29029 May 2018 Response to Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools Request for Supplemental Information ET 18-0014, Response to Request for Additional Information Regarding the License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System.2018-05-29029 May 2018 Response to Request for Additional Information Regarding the License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System. ET 18-0013, Relief Request Number I4R-06, Request for Relief from ASME Code Case N-729-4 for Reactor Vessel Head Penetration Nozzle Weld2018-05-0202 May 2018 Relief Request Number I4R-06, Request for Relief from ASME Code Case N-729-4 for Reactor Vessel Head Penetration Nozzle Weld ET 18-0011, (WCGS) - Guarantee of Payment of Deferred Premiums2018-04-30030 April 2018 (WCGS) - Guarantee of Payment of Deferred Premiums ET 18-0012, Operating Corp., Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-04-19019 April 2018 Operating Corp., Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 18-0010, Financial Protection Levels2018-03-29029 March 2018 Financial Protection Levels ET 18-0007, Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System.2018-02-15015 February 2018 Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System. ET 18-0005, Withdrawal of License Amendment Request for Revision to the Emergency Plan2018-02-0505 February 2018 Withdrawal of License Amendment Request for Revision to the Emergency Plan ET 18-0004, Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-01-29029 January 2018 Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ET 17-0025, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term2017-11-14014 November 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term 2023-05-17
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARML24018A2482024-01-18018 January 2024 License Amendment Request to Modify the Implementation Date of License Amendment No. 238 ML23331A4972023-11-27027 November 2023 Supplement to License Amendment Request to Modify the 90-Day Implementation of License Amendment No. 237 ML23320A2772023-11-16016 November 2023 License Amendment Request to Revise Ventilation Filter Testing Program Criteria in Technical Specification 5.5.11.b and Administrative Correction of Absorber in Technical Specification 5.5.11 ML23171B1312023-06-20020 June 2023 Additional Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 23-0003, License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications2023-03-0101 March 2023 License Amendment Request (LAR) for Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML23045A1952023-02-14014 February 2023 Transmittal of the National Pollution Discharge Elimination System Permit Renewal Application for Wolf Creek Generating Station I-NE07-PO02 ET 23-0002, Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2023-02-0707 February 2023 Supplement to License Amendment Request to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22353A5552022-12-15015 December 2022 Application to Revise Technical Specifications to Adopt TSTF-554-A, Revision 1, Revise Reactor Coolant Leakage Requirements ET 22-0006, Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections2022-12-0101 December 2022 Operating Corp. - Application to Revise Technical Specifications to Adopt TSTF-577-A, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ET 22-0010, License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements2022-08-0202 August 2022 License Amendment Request (LAR) for Deviation from Fire Protection Program Requirements ET 22-0001, Removal of the Table of Contents from the Technical Specifications2022-01-12012 January 2022 Removal of the Table of Contents from the Technical Specifications ET 21-0004, License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating2021-09-29029 September 2021 License Amendment Request - Diesel Generator Completion Time Extension for Technical Specification 3.8.1, AC Sources - Operating ET 21-0005, Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-1912021-08-12012 August 2021 Operating Corp., License Amendment Request for a Risk-Informed Resolution to GSI-191 WO 21-0015, License Amendment Request (LAR) for Revision to the Emergency Plan2021-05-25025 May 2021 License Amendment Request (LAR) for Revision to the Emergency Plan WM 21-0005, Supplement to License Amendment Request for Change to Owner Licensee Names2021-05-24024 May 2021 Supplement to License Amendment Request for Change to Owner Licensee Names ML21070A0582021-03-11011 March 2021 Changes to Technical Specification Bases - Revisions 82, 83, 84, and 85 WO 20-0050, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange2020-11-10010 November 2020 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Allow Use of a Blind Flange WM 20-0006, (WCGS) - License Amendment Request for Change to Owner Licensee Names2020-11-0404 November 2020 (WCGS) - License Amendment Request for Change to Owner Licensee Names ET 20-0007, License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers2020-06-0808 June 2020 License Amendment Request for Replacement of Engineered Safety Features Transformers with New Transformers That Have Active Automatic Load Tap Changers ET 20-0004, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425)2020-04-27027 April 2020 Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (TSTF-425) WO 20-0029, License Amendment Request to Revise Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2020-04-20020 April 2020 License Amendment Request to Revise Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies WO 19-0033, License Amendment Request for Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System2019-08-29029 August 2019 License Amendment Request for Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System WO 19-0031, Supplement 1 to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-08-0808 August 2019 Supplement 1 to Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 ML19052A5462019-04-0101 April 2019 Issuance of Amendment No. 220 Revision to the Emergency Plan ET 19-0002, License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation.2019-03-18018 March 2019 License Amendment Request to Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation. ET 19-0003, License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange2019-02-25025 February 2019 License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to Remove Use of a Blind Flange ET 19-0001, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 42019-01-23023 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4 WO 18-0044, Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-11-15015 November 2018 Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term WO 18-0034, Operating Corp., Additional Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-08-0909 August 2018 Operating Corp., Additional Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term ML18135A1462018-05-0909 May 2018 Attachments I to V: Evaluation of Proposed Changes, Emergency Plan Change Summary, ERO Position Matrix, Summary of Shift Staffing and Letter of Consultation and Concurrence from Off-Site Response Organizations Ack of Opportunity WO 18-0016, License Amendment Request for Revision to the Emergency Plan2018-05-0909 May 2018 License Amendment Request for Revision to the Emergency Plan ET 18-0007, Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System.2018-02-15015 February 2018 Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System. ML17363A1422017-12-19019 December 2017 License Amendment Request (LAR) for Revision to the Emergency Plan (Attachments and Enclosures) WM 17-0021, Updated Request for Consent to Indirect Transfer of Control2017-09-0505 September 2017 Updated Request for Consent to Indirect Transfer of Control WO 17-0026, Errata for License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses2017-03-22022 March 2017 Errata for License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses ML17054C2232017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Proposed COLR Changes ET 17-0001, License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses, Enclosure 10 - CAW-16-45002017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses, Enclosure 10 - CAW-16-4500 ML17054C2272017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Alternative Source Term, Rev 1 ML17054C2362017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses, Enclosure 9 - CAW-16-4499 ML17054C2192017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Evaluation ML17054C2352017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - WOG-93-066 ML17054C2302017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - A-3788, Technical Report, Appendix a, Fission Product Removal Effectiveness of Chemical Additives in PWR Containment Sprays ML17054C2332017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - CAW-92-287 ML17054C2202017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Proposed Technical Specification Changes ML17054C2262017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - WCAP-18083-NP, Rev 0, Westinghouse Revised Thermal Design Procedure Uncertainty Calculations. ML17054C2222017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Proposed Technical Specification Bases Changes ML17054C2322017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - OG-92-25, Steam Generator Tube Uncovery Issue ML17054C2212017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Revised Technical Specification Pages ML17054C2292017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Responses to NRC RAIs on August 2013 Methodology Transition LAR Submittal NEI 99-01, Wolf Creek Nuclear Operating Corporation Request to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors2016-09-30030 September 2016 Wolf Creek Nuclear Operating Corporation Request to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors 2024-01-18
[Table view] |
Text
W$LFCREEK
, 'NUCLEAR OPERATING CORPORATION February 25, 2019 Stephen L Smith Vice President Engineering ET 19-0003 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
Subject:
Docket No. 50-482: License Amendment Request to Revise Technical Specification 3.6.3 and Surveillance Requirement 3.6.3.1 to remove use of a blind flange To Whom It May Concern:
Pursuant to 10 CFR 50.90, "Application for amendment of license, construction permit, or early site permit," Wolf Creek Nuclear Operating Corporation (WCNOC) hereby requests an amendment to Renewed Facility Operating License Number NPF-42 for the Wolf Creek Generating Station (WCGS). The license amendment request (LAR) proposes to revise Technical Specification (TS) 3.6.3.
The proposed amendment would modify TS 3.6.3 "Containment Isolation Valves," Condition D, to remove use of a blind flange for Required Action D.1. In addition, a change to Surveillance Requirement (SR) 3.6.3.1 is proposed to remove use of a blind flange.
It has been determined that this amendment application does not involve a significant hazard consideration as determined per 10 CFR 50.92, "Issuance of amendment." Pursuant to 10 CFR 51.22(b), "Criterion for categorical exclusion; identification of licensing and regulatory actions eligible for categorical exclusion or otherwise not requiring environmental review," no environmental impact statement or environmental assessment needs to be prepared in connection with the issuance of this amendment. The amendment application was reviewed by the WCNOC Plant Safety Review Committee.
In accordance with 10 CFR 50.91, "Notice for public comment; State consultation," a copy of this amendment application is being provided to the designated Kansas State official.
P.O. Box 411 / Burlington, KS 66839 / Phone: (620) 364-8831 An Equal Opportunity Employer M/F/HCNET
" ET 19-0003
- , Page 2 of 3 Attachment I provides an Evaluation of Prop*osed Changes. Attachment II provides the Proposed Technical Specification Changes (Mark-Up) Pages. Attachment Ill provides the Retyped Technical Specification Pages. Attachment IV provides the Proposed Technical Specification Bases Changes (Mark-Up) (for information only). Final TS Bases changes will be implemented pursuant to TS 5.5.14, "Technical Specifications (TS} Bases Control Program," at the time the amendment is implemented.
WCNOC requests approval of this proposed license amendment by March 5, 2020. The changes proposed are not required to address an immediate safety concern. It is anticipated that the license amendment, as approved, will be effective upon issuance, to be implemented within 90 days from the date of issuance.
There are no regulatory commitments contained in this submittal. If you have any questions concerning this matter, please contact me at (620) 364-4093, or Ron Benham at (620) 364-4204.
Sincerely, Stephen L. Smith SLS/rlt Attachments: I Evaluation of Proposed Changes II - Proposed Technical Specification Changes (Mark-Up) Pages Ill - Retyped Technical Specification Pages IV - Proposed Technical Specification Bases Changes (Mark-Up) (for information only) cc: S. A Morris (NRC), w/a B. K. Singal (NRC), w/a K. S. Steves (KDHE}, w/a N. H. Taylor (NRC), w/a Senior Resident Inspector (NRC), w/a
-*" ET 19-0003 Page 3 of 3 STATE OF KANSAS )
) ss COUNTY OF COFFEY )
Stephen L. Smith, of lawful age, being first duly sworn upon oath says that he is Vice President Engineering of Wolf Creek Nuclear Operating Corporation; that he has read the foregoing document and knows the contents thereof; that he has executed the same for and on behalf of said Corporation with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.
By&M Stephen L. Smith Vice President Engineering SUBSCRIBED and sworn to before me this J._5+:/ay of f(lDrt.Ja.r-'{ , 2019.
RHONDA L. TIEMEYER Notary Public Notary Public, State of Kansas My Appointment Expires Expiration DateJ{1A111,{1J)'f J/ 1 J. Od :1.
"\
Attachment I to ET 19-0003 Page 1 of 5 ATTACHMENT I .
. EVALUATION OF PROPOSED CHANGES
- Attachment I to ET 19-0003 Page 2 of 5 EVALUATION OF PROPOSED CHANGES
Subject:
License_ Amendment Request to Revise Technical Specifications TS 3.6.3 "Containment Isolation Valves" to remove use of a blind flange for Required Action D.1 1.0
SUMMARY
DESCRIPTION 2.0 DETAILED DESCRIPTION
3.0 TECHNICAL EVALUATION
4.0 REGULATORY EVALUATION
4.1 No Significant Hazards Consideration Determination ,
5.0 ENVIRONMENTAL CONSIDERATION
Attachment I to ET 19-0003 Page 3 of 5 EVALUATION OF PROPOSED CHANGES 1.0
SUMMARY
DESCRIPTION This evaluation supports a request to amend Renewed Facility Operati~g License Number NPF-42 for the Wolf Creek Generating Station (WCGS).
The proposed change revises Technical Specification (TS) 3.6.3, "Containment Isolation Valves" to remove use of a blind flange to meet Limiting Condition for Operation (LCO) 3.6.3, Required Action D.1. In addition, a change to Surveillance Requirement (SR) 3.6.3.1 is proposed to remove use of a blind flange.
2.0 DETAILED DESCRIPTION Proposed Changes TS 3.6.3, "Containment Isolation Valves" Required Action D.1 currently states, in part:
Isolate the affected penetration flow path by use of at least one closed and de-activated automatic valve, closed manual valve, or blind flange.
TS 3.6.3, Required Action D.1 is revised to state, in part:
Isolate the affected penetration flow path by use of at least one closed and de-activated automatic valve or closed manual valve.
SR 3.6.3.1 currently states, in part:
Verify each containment shutdown purge valve is sealed closed or closed and blind flange installed except for one purge valve in a penetration flow path while in Condition D of this LCO.
SR 3.6.3.1 is revised to state, in part:
Verify each containment shutdown purge valve is sealed closed except for one purge valve in c1 penetration flow path while in Condition D of this LCO.
3.0 TECHNICAL EVALUATION
The Containment Purge and Exhaust System operates to supply outside air into the containment for ventilation and cooling or heating needed for prolonged containment access following a shutdown and during refueling. The system may also be used to reduce the concentration of noble gases within containment prior to and during personnel access. The supply and exhaust lines each contain two isolation valves. Because of their large size, the 36 inch containment purge supply and exhaust valves are not qualified for automatic closure from their open position under OBA conditions. The safety analyses assume that the 36 inch shutdown purge valves are closed at event initiation. Therefore, the 36 inch containment purge supply and exhaust isolation valves are normally sealed closed in MODES 1, 2, 3, and 4 to
1
- Attachment I to ET 19-0003 Page 4 of 5 ensure the containment boundary is maintained. Sealed closed means the valves are closed and deactivated.
TS LCO 3.6.3 requires that while the plant is in MODES 1, 2, 3, and 4, each containment isolation valve shall be OPERABLE. When one or more containment penetration flow paths contain one or more containment purge isolation valves whose leakage is not with allowable limits, Condition D is entered. Required Action D.1 is to isolate the affected penetration flow path by use of at least one closed and de-activated valve, closed manual valve, or blind flange.
Action D.1 has a Completion Time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
The design of the Containment Purge and Exhaust System includes spectacle blind flanges installed on both supply and exhaust lines penetrating containment. However, *these are installed beyond the seismic category I class break on these lines and are non-safety related.
They are normally used for valve leakage testing during refueling outages. Because they are not safety-related, they can not be credited for containment isolation. Therefore, there is no practical way to use a blind flange to isolate the containment penetrations associated with the Containment Purge and Exhaust System.
This license amendment request is proposing to remove the use of a blind flange as a way to satisfy Required Action D.1 for containment purge isolation valves.
4.0 REGULATORY EVALUATION
4.1 No Significant Hazards Consideration Determination Wolf Creek Nuclear Operating Corporation (WCNOC) requests adoption of License Amendment Request to revise Technical Specification (TS) 3.6.3 "Containment Isolation Valves" to remove use of a blind flange to meet Limiting Condition for Operation (LCO) 3.6.3, Required Action D.1, and Surveillance Requirement (SR) 3.6.3.1. WCNOC has evaluated whether or not a significant hazards consideration is involved with the proposed amendments by focusing on the three standards set forth in 10 CFR 50.92, "1$suance of amendment," as discussed below:
- 1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously.evaluated?
Response: No.
The proposed changes to TS LCO 3.6.3 and SR 3.6.3.1 have no effect on the requirement for systems to be OPERABLE and have no effect on the application of TS actions. Since the proposed change does not significantly affect system OPERABILITY the proposed change will have no significant effect on the initiating events for accidents previously evaluated and will have no significant effect on the ability of the systems to mitigate accidents previously evaluated.
Therefore, it is concluded that this change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
I*
Attachment I to ET 19-0003 Page 5 of 5
- 2. Does the proposed change create the possibility of a new or different kind of accident from any accident previously evaluated?
Response: No.
The proposed change to update the TS does not affect the design or function of any plant systems. The proposed change does not change the Operability requirements for plant systems or the actions taken when plant systems are not OPERABLE.
Therefore, it is concluded that this change does not create the possibility of a new or different kind of accident from any accident previously evaluated.
- 3. Does the proposed change involve a significant reduction in a margin of safety?
Response: No.
The proposed change updates TS LCO 3.6.3, Required Action D.1 to remove use of a blind flange. It does not result in changes in plant operation .. The proposed change to SR 3.f;,.3.1 removes the use of a blind flange. As a result, plant safety is either improved or unaffected.
Therefore, iUs concluded that this change does not involve a significant reduction in a margin of safety.
Based on the above, WCNOC concludes that the proposed change presents no significant hazards consideration under the standards set forth in 10 CFR 50.92(c), and, accordingly,. a finding of "no significant hazards consideration" is justified.
5.0 ENVIRONMENTAL CONSIDERATION
The proposed change would change a requirement with respect to instaUation or use of a facility component located within the restricted area, as defined in 10 CFR 20. However, the proposed change does not involve (i) a significant hazards consideration, (ii) a significant change in the types or significant increase in the amounts of any effluents that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure.
Accordingly, the proposed change meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the proposed change.
1 to ET 19-0003 Page 1 of 3 ATTACHMENT II PROPOSED TECHNICAL SPECIFICATION CHANGES (MARK-UP)
PAGES 1 to ET 19-0003 Containment Isolation Valves Page 2 of 3 3.6.3 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME D. One or more D.1 Isolate the affected 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> penetration flow penetration flow path by paths with one or use of at least one closed more containment and de-activated purge valves not automatic valve, or closed within leakage limits. manual valve, or blind flaR§e.
AND D.2 -----------NOTES---------
- 1. Isolation devices in high radiation areas may be verified by use of administrative means.
- 2. Isolation devices that are locked , sealed , or otherwise secured may be verified by administrative means.
Verify the affected Once per 31 days penetration flow path is for isolation isolated . devices outside containment Prior to entering MODE 4 from MODE 5 if not performed within the previous 92 days for isolation devices inside containment (continued)
Wolf Creek - Unit 1 3.6-4 Amendment No. 423, 4-e+
Attachment II to ET 19-0003 Containment Isolation Valves Page 3 of 3 3.6.3 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME D. (continued) D.3 Perform SR 3.6.3.6 or Once per 92 days SR 3.6.3 .7 for the resilient seal purge valves closed to comply with Required Action D.1 .
E. Required Action and E.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met. AND E.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.3.1 Verify each containment shutdown purge valve is Once per 31 days sealed closed or closed and blind flange installed for isolation except for one purge valve in a penetration flow path devices outside while in Condition D of this LCO. containment Prior to entering MODE 4 from MODE 5 if not performed within the previous 92 days for isolation devices inside containment (continued)
Wolf Creek - Unit 1 3.6-5 Amendment No. ~ . 4J4, 4e7 11 to ET 19-0003 Page 1 of 3 ATTACHMENT Ill RETYPED TECHNICAL SPECIFICATION PAGES
Containment Isolation Valves 3.6.3 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME D. One or more D.1 Isolate the affected 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> penetration flow penetration flow path by paths with one or use of at least one closed more containment and de-activated purge valves not automatic valve or closed within leakage limits. manual valve .
AND D.2 -------------NOTES------------
- 1. Isolation devices in high radiation areas may be verified by use of administrative means.
- 2. Isolation devices that are locked , sealed , or otherwise secured may be verified by administrative means.
Verify the affected penetration flow path is Once per 31 days isolated. for isolation devices outside containment AND Prior to entering MODE 4 from MODE 5 if not performed within the previous 92 days for isolation devices inside containment (continued)
Wolf Creek - Unit 1 3.6-4 Amendment No. ~ . 4-7
Containment Isolation Valves 3.6 .3 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME D. (continued) D.3 Perform SR 3.6.3 .6 or Once per 92 days SR 3.6 .3 .7 for the resil ient seal purge valves closed to comply with Required Action D.1.
E. Required Action and E.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met. AND E.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.3 .1 Ve rify each containment shutdown purge valve is Once per 31 days sealed closed except for one purge valve in a for isolation penetration flow path while in Condition D of this devices outside LCO . containment Prior to entering MODE 4 from MODE 5 if not performed within the previous 92 days for isolation devices inside containment (continued )
Wolf Creek - Unit 1 3.6-5 Amendment No. 4-2-3, 4-a-+, 4-e-7
Attachment IV to ET 19-0003 Page 1 of 5 ATTACHMENT IV PROPOSED TECHNICAL SPECIFICATION BASES CHANGES (MARK-UP) (FOR INFORMATION ONLY)
Attachment IV to ET 19-0003 Page 2 of 5 Containment Isolation Valves B 3.6.3 BASES BACKGROUND within containment prior to and during personnel access. The supply and (continued) exhaust lines each contain two isolation valves. Because of their large size, the 36 inch containment purge supply and exhaust valves are not qualified for automatic closure from their open position under OBA conditions. Therefore, the 36 inch containment purge supply and exhaust isolation valves are normally maintained closed and blind flange installed ei: sealed closed in MODES 1, 2, 3, and 4 to ensure the containment boundary is maintained.
Mini-Purge System (18 inch purge valves)
The Mini-purge System operates to:
- a. Reduce the concentration of noble gases within containment prior to and during personnel access, and
- b. Equalize containment internal and external pressures .
Since the 18 inch valves used in the Mini-purge System are designed to meet the requirements for automatic containment isolation valves, these valves may be opened as needed , for a limited time as specified in procedures, in MODES 1, 2, 3, and 4.
APPLICABLE The containment isolation valve LCO was derived from the assumptions SAFETY ANALYSES related to minimizing the loss of reactor coolant inventory and establishing the containment boundary during major accidents . As part of the containment boundary, containment isolation valve OPERABILITY supports leak tightness of the containment. Therefore, the safety analyses of any event requiring isolation of containment is applicable to this LCO .
The DBAs that result in a release of radioactive material within containment are a loss of coolant accident (LOCA) and a rod ejection accident (Ref. 1). In the analyses for each of these accidents, it is assumed that containment isolation valves are either closed or function to close within the required isolation time following event initiation. This ensures that potential paths to the environment through containment isolation valves (including containment purge valves) are minimized. The safety analyses assume that the 36 inch shutdown purge valves are closed at event initiation.
The OBA analysis assumes that, within 60 seconds after the accident, isolation of the containment is complete and leakage terminated except for the design leakage rate, La* The containment isolation total response time of 60 seconds includes signal delay, diesel generator startup (for loss of offsite power), and containment isolation valve stroke times.
Wolf Creek - Unit 1 B 3.6.3-2 Revision 0
Attachment IV to ET 19-0003 Page 3 of 5 Containment Isolation Valves B 3.6.3 BASES APPLICABLE The LOCA offsite dose analysis assumes leakage from the containment SAFETY ANALYSES at a maximum leak rate of 0.20 percent of the containment volume per (continued) day for the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and at 0.10 percent of the containment volume per day for the duration of the accident.
The single failure criterion required to be imposed in the conduct of plant safety analyses was considered in the original design of the 18 inch containment mini-purge valves. Two valves in series on each purge line provide assurance that both the supply and exhaust lines could be isolated even if a single failure occurred . The inboard and outboard isolation valves on each line are provided with independent electrical power sources to solenoids that open the pneumatically operated spring closed actuators. The actuators fail closed on the loss of power or air.
This arrangement was designed to preclude common mode failures from disabling both valves on a purge line.
The 36 inch purge valves may be unable to close against the buildup of pressure following a LOCA. Therefore, each of the purge valves is required to remain sealed closed OF slosea amf elim:l f.lange installeel during MODES 1, 2, 3, and 4. The Containment Shutdown Purge System valve design precludes a single failure from compromising the containment boundary as long as the system is operated in accordance with the subject LCO.
The containment isolation valves satisfy Criterion 3 of 10 CFR 50 .36(c)(2)(ii).
LCO Containment isolation valves form a part of the containment boundary.
The containment isolation valves' safety function is related to minimizing the loss of reactor coolant inventory and establishing the containment boundary during a DBA.
The automatic power operated isolation valves are required to have isolation times within limits and to actuate on an automatic isolation signal.
The 36 inch containment purge supply and exhaust valves must be maintained sealed closed OF sloseel ana elina f.lange installeel. The valves covered by this LCO are listed along with their associated stroke times in the USAR (Ref. 2) .
The normally closed containment isolation valves are considered OPERABLE when manual valves are closed , automatic valves are de-activated and secured in their closed position , blind flanges are in place, and closed systems are intact. These passive isolation valves/devices are those listed in Reference 2.
Wolf Creek - Unit 1 B 3.6.3-3 Revision 0
Attachment IV to ET 19-0003 Page 4 of 5 Containment Isolation Valves B 3.6.3 BASES ACTIONS C.1 and C.2 (continued)
In the event one containment isolation valve in two or more separate penetration flow paths is inoperable, except for purge valve leakage not within limit, all but one of the affected penetration flow path(s) must be isolated. The method of isolation must include the use of at least one isolation barrier that cannot be adversely affected by a single active failure. Isolation barriers that meet this criterion are a closed and de-activated automatic containment isolation valve, a closed manual valve, a blind flange , and a check valve with flow through the valve secured . For a penetration flow path isolated in accordance with C.1, the device used to isolate the penetration should be the closest available one to containment.
Required Action C.1 must be completed within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. For the penetration flow paths isolated in accordance with Required Action C.1, the affected penetration(s) must be verified to be isolated on a periodic basis per Required Action A.2, which remains in effect. This periodic verification is necessary to assure that the penetrations requiring isolation following an accident are isolated. The 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Completion Time is reasonable, considering the time required to isolate the penetration and the relative importance of supporting Containment OPERABILITY during MODES 1, 2, 3, and 4.
This Condition is applicable when multiple containment isolation valves in separate flow paths are inoperable. For subsequent containment isolation valve inoperabilities, the Required Action and Completion Time continue to apply to each additional containment isolation valve inoperability, with the Completion Time based on each subsequent entry into the Condition consistent with Note 2 to the ACTIONS Table (e.g ., for each entry into the Condition). The containment isolation valve(s) inoperable as a result of that entry shall meet the Required Action and Completion Time.
D.1, D.2, and D.3 In the event one or more containment shutdown or mini-purge valves in one or more penetration flow paths are not within the leakage limits, leakage must be restored to within limits, or the affected penetration flow path must be isolated. The method of isolation must be by the use of at least one isolation barrier that cannot be adversely affected by a single active failure. Isolation barriers that meet this criterion are a closed and de-activated automatic valve, or closed manual valve (this includes power operated valves with power removed) , or blind flange . A containment shutdown purge or mini-purge valve with resilient seals utilized to satisfy Required Action D.1 must have been demonstrated to meet the leakage requirements of SR 3.6.3.6 or SR 3.6.3.7. The specified Completion Time is reasonable , considering that one containment purge valve remains closed so that a gross breach of containment does not exist.
Wolf Creek - Unit 1 B 3.6.3-7 Revision 44
' t'
- I Attachment IV to ET 19-0003 Page 5 of 5 Containment Isolation Valves B 3.6.3 BASES ACTIONS E.1 and E.2 (continued)
If the Required Actions and associated Completion Times are not met, the plant must be brought to a MODE in which the LCO does not apply. To achieve this status, the plant must be brought to at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and to MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The allowed Completion Times are rec3sonable , based on operating experience, to reach the required plant conditions from full power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.6.3.1 REQUIREMENTS Each 36 inch containment shutdown purge supply and exhaust valve is required to be verified sealed closed or sloses ans blins flange installes at 31 day intervals. Each 36 inch containment shutdown purge supply and exhaust valve inside containment must be verified sealed closed or blins flange installes prior to entering MODE 4 from MODE 5, if the surveillance has not been performed in the previous 92 days. This Surveillance is designed to ensure that a gross breach of containment is not caused by an inadvertent or spurious opening of a containment shutdown purge valve. Detailed analysis of these valves failed to conclusively demonstrate their ability to close during a LOCA in time to limit offsite doses. Therefore, these valves are required to be in the sealed closed position or sloses ans blins flange installes during MODES 1, 2, 3, and 4 .
A containment shutdown purge valve that is sealed closed must have motive power to the valve operator removed . This can be accomplished by de-energizing the source of electric power or by removing the air supply to the valve operator. In this application , the term "sealed" has no connotation of leak tightness. The Frequency is a result of an NRC initiative, Multi-Plant Action No. B-24 (Ref. 4), related to containment purge valve use during plant operations. In the event valve leakage requires entry into Condition D, the Surveillance permits opening one purge valve in a penetration flow path to perform repairs.
SR 3.6.3.2 This SR ensures that the mini-purge valves are closed as required or, if open, open for an allowable reason. If a mini-purge valve is open in violation of this SR, the valve is considered inoperable. If the inoperable valve is not otherwise known to have excessive leakage when closed , it is not considered to have leakage outside of limits. The SR is not required to be met when the mini-purge valves are open for the reasons stated.
The valves may be opened for pressure control , ALARA or air quality Wolf Creek - Un it 1 B 3.6.3-9 Revision J&