MONTHYEARIR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 ML23354A2902024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0028 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 ML23286A2602023-11-0808 November 2023 Issuance of Amendment Nos. 260 and 245 to Renewed Facility Operating Licenses Relocation of Pressure and Temperature Limit Curves to the Pressure Temperature Report IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212A9012023-08-0303 August 2023 Regulatory Audit Report to Support the Review of the Amendments to Relocation of the Pressure Temperature Limit Curves to the Pressure and Temperature Limits Report IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 ML23208A3182023-07-27027 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-07-24024 July 2023 Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis ML23192A5272023-07-12012 July 2023 NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 ML23186A2062023-07-0606 July 2023 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000374/2023010 ML23181A1502023-06-30030 June 2023 Combined Response to Request for Additional Information and Supplemental Information in Support of LAR to Relocate Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167A0352023-06-16016 June 2023 Registration of Use of Cask to Store Spent Fuel ML23171A9562023-06-12012 June 2023 Post Exam Ltr RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 ML23123A2202023-05-0303 May 2023 Relief Request I4R-14 for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23121A1612023-05-0101 May 2023 Information Meeting (Open House) with a Question-and-Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of LaSalle County Station, Units 1 and 2 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23107A1822023-04-18018 April 2023 Operator Licensing Examination Approval Lasalle County Station, May 2023 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23073A2182023-03-22022 March 2023 Issuance of Amendment No. 258 to Renewed Facility Operating Licenses Exigent Amendment to Revise Design Basis Related to Seismic Requirements RS-23-048, Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements2023-03-0707 March 2023 Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-037, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station2023-02-22022 February 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station ML23024A1372023-02-0303 February 2023 Request for Withholding Information from Public Disclosure for LaSalle County Station, Unit Nos. 1 and 2 ML23031A1972023-01-31031 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information, Inspection Report Nos. 05000373/2023011 and 05000374/2023011 IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 2024-01-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23360A6082023-12-27027 December 2023 County Station Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000373/2024010 and 05000374/2024010 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23208A3182023-07-27027 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI ML23153A1562023-06-0202 June 2023 NRR E-mail Capture - RAI LaSalle pressure-temperature Limits Report (PTLR) Amendment Request ML23150A2482023-05-25025 May 2023 NRR E-mail Capture - RAI Re LaSalle Downcomer Analysis Amendment Request ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22361A0792022-12-27027 December 2022 Notification of NRC Baseline Inspection and Request for Information (05000374/2023001) ML22256A0112022-09-12012 September 2022 NRR E-mail Capture - Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage ML22138A4112022-05-18018 May 2022 NRR E-mail Capture - Lasalle 1 and 2 - (RAI) License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Changes to TS Sections 4.3.1 and 5.6.5 (EPID-L-2021-LLA-0124) ML22126A0392022-05-0606 May 2022 NRR E-mail Capture - Lasalle 1 and 2 Draft (RAI) License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Proposed Changes to TS Sections 4.3.1 and 5.6.5 ML22097A0832022-04-0707 April 2022 County Station Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000373/2022403 and 05000374/2022403 ML22062B0232022-03-0303 March 2022 NRR E-mail Capture - EPID-L-2022-LLR-0028, LaSalle Unit 1, Request for Additional Information (Rai), LaSalle Unit 1, Relief Request I4R-13 Relief from Code Examinations for 1B33-F060A and 1B33-F060B Repairs ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21292A1782021-10-19019 October 2021 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000373/2022010 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21207A0072021-07-26026 July 2021 NRR E-mail Capture - La Salle Units 1 and 2 - Request for Additional Information (RAI) License Amendment Request to Incorporate Licensing Topical Report NEDE-33885P-A, Revision 1, GNF CRDA Application Methodology(EPID-L-2021-LLA-0016) ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21187A2972021-07-0707 July 2021 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21119A2282021-04-29029 April 2021 NRR E-mail Capture - Request for Additional Information (RAI) - LaSalle, EPID-L-2020-LLA-0018, License Amendment Request (LAR) TSTF-505 ML21077A1902021-03-18018 March 2021 NRR E-mail Capture - Lasalle Units 1 and 2 - Request for Additional Information (RAI) Request for License Amendment Regarding Ultimate Heat Sink, (EPID-L-2020-LLA-0165) ML21068A2762021-03-0909 March 2021 NRR E-mail Capture - La Salle Units 1 and 2 - Request for Additional Information (RAI) Relief Request I4R-12 Relief from Code Surface Examinations for 2B33-F060B Valve Repair (EPID-L-2020-LLA-0016) ML21067A6752021-03-0808 March 2021 NRR E-mail Capture - La Salle Units 1 and 2 - Request for Additional Information (RAI) UHS Amendment Request (EPID-L-2020-LLA-0165) ML21060B4352021-03-0101 March 2021 NRR E-mail Capture - Second Round - Request for Additional Information (Rais) EPID-L-2020-LLA-0018, LaSalle License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2 ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21053A0252021-02-20020 February 2021 NRR E-mail Capture - Request for Additional Information (Rais) - LaSalle Request for Exemption from Pre-Access Drug and Alcohol Testing ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21048A0432021-02-16016 February 2021 County Station - Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information - Inspection Report 05000373/2021011 and 05000374/2021011 ML20364A2452020-12-29029 December 2020 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000373/2021002; 05000374/2021002 ML20346A1042020-12-11011 December 2020 NRR E-mail Capture - LaSalle County Station, Units 1 and 2 - Request for Additional Information Regarding the License Amendment Request to Adopt 10 CFR 50.69 ML20330A1892020-11-25025 November 2020 Request for Information for an NRC Post-Approval Site Inspection for License Renewal; Inspection Report 05000374/2021010 ML20321A0852020-11-16016 November 2020 Notification of NRC Baseline Inspection and Request for Information (05000374/2021001) ML20247J4082020-09-29029 September 2020 Apla Request for Additional Information LAR 50.69 and TSTF-505 (Epids L-2020-LLA-0017) and ML20253A3422020-09-17017 September 2020 Correction to Request for Additional Information Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors (EPID-2020-LLA-0017) ML20253A2272020-09-16016 September 2020 Correction to Request for Additional Information Application to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML20240A2182020-09-0303 September 2020 Request for Additional Information Regarding Amendment Request for Amendments to Renewed Facility Operating Licenses to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Co ML20239A7262020-08-27027 August 2020 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Request for a License Amendment to Technical Specification 3.7.3, Ultimate Heat Sink ML20239A7982020-08-25025 August 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet License Amendment Request to Adopt TSTF-568, Revision 2 ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML19120A2302019-04-29029 April 2019 Ltr. 04/29/19 LaSalle County Station, Units 1 and 2 - Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000373/2019012; 05000374/2019012 (DRS-M.Jones) ML19087A2682019-03-28028 March 2019 NRR E-mail Capture - Request for Additional Information (RAI) - LaSalle 1 and 2, EPID-L-2018-LLA-0162, LAR Removal of Operating Mode Restrictions for Performing Surveillance Testing of the Div 3 Battery and HPCS DG ML19065A0902019-03-0505 March 2019 NRR E-mail Capture - LaSalle 1 and 2, EPID-L-2018-LLR-0162, LAR Removal of Operating Mode Restrictions for Performing Surveillance Testing of the Div 3 Battery and HPCS DG, Additional Draft Request for Additional Information (RAI) ML19058A2392019-02-27027 February 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspection at LaSalle County Station, Units 1 and 2 ML19036A6562019-02-0505 February 2019 NRR E-mail Capture - LaSalle 1 and 2, EPID-L-2018-LLR-0123, Relief Request I3R-15, Third Inservice Inspection Interval, Request for Additional Information (RAI) ML19022A2552019-01-22022 January 2019 NRR E-mail Capture - LaSalle Units 1 and 2, EPID-L-2018-LLA-0035, Amendment Request to Adopt TSTF-334-A, Status of Revised Draft RAIs Sent to You on December 13, 2018 ML19050A0042019-01-22022 January 2019 NRR E-mail Capture - LaSalle 1 and 2, EPID-L-2018-LLR-0162, LAR Removal of Operating Mode Restrictions for Performing Surveillance Testing of the Div 3 Battery and HPCS DG, Draft Request for Additional Information (RAI) ML19022A0292018-12-13013 December 2018 NRR E-mail Capture - Draft Request for Additional Information for LaSalle License Amendment Request to Adopt TSTF-334-A, Revision 2 2023-09-21
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, ILLINOIS 60532-4352 February 27, 2019 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
INFORMATION REQUEST TO SUPPORT UPCOMING PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION AT LASALLE COUNTY STATION, UNITS 1 AND 2
Dear Mr. Hanson:
This letter is to request information to support our scheduled Problem Identification and Resolution (PI&R) inspection beginning April 8, 2019, at the LaSalle County Station, Units 1 and 2. This inspection will be performed in accordance with the NRC baseline Inspection Procedure 71152.
Experience has shown that these inspections are extremely resource intensive both for the NRC inspectors and the utility staff. In order to minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a list of documents required for the inspection.
The documents requested are copies of condition reports and lists of information necessary to ensure the inspection team is adequately prepared for the inspection. The information requested prior to the inspection may be provided in either CD-ROM/DVD (preferred) or hard copy format and should be ready for NRC review by March 22, 2019. Mr. Nirodh Shah, the Lead Inspector, will contact your staff to determine the best method of providing the requested information.
If there are any questions about the material requested or the inspection in general, please contact Mr. Nirodh Shah at 630-829-9821 or Nirodh.Shah@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011.
B. Hanson The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Kenneth Riemer, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18
Enclosure:
Requested Information to Support PI&R Inspection cc: Distribution via LISTSERV
B. Hanson Letter to Bryan Hanson from Kenneth Riemer dated February 27, 2019
SUBJECT:
INFORMATION REQUEST TO SUPPORT UPCOMING PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION AT LASALLE COUNTY STATION, UNITS 1 AND 2 DISTRIBUTION:
Michael McCoppin RidsNrrDorlLpl3 RidsNrrPMLaSalle RidsNrrDirsIrib Resource Darrell Roberts John Giessner Jamnes Cameron Allan Barker DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML19058A239 OFFICE RIII RIII NAME NShah:lg KRiemer DATE 2/27/2019 2/27/2019 OFFICIAL RECORD COPY
Requested Information to Support Problem Identification and Resolution Inspection Please provide the information on a compact disc (one for each of four team members), if possible. Unless otherwise specified, the time frame for requested information is for the period of September 1, 2017, through the time the data request is answered. Please label any electronic files with file content information. In the case of list of condition reports requested, the list should be sortable electronically.
In addition, inspectors will require computer access to the corrective action program (CAP) database while on site.
PROGRAM DOCUMENTS
- 1. Copies of current administrative procedures associated with the corrective action program. This should include procedures related to: (1) corrective action process (including procedures on how to perform root and apparent cause evaluations);
(2) operating experience program; (3) self-assessment program; (4) maintenance rule program; (5) operability determination process; (6) degraded/non-conforming condition process (e.g., IMC 0326); (7) system health process or equivalent equipment reliability improvement programs; and (8) operational decision making (ODMI) process.
- 2. A current copy of the Employee Concerns Program/Ombudsman administrative procedure.
- 3. Description of any substantive changes made to the CAP since the last Problem Identification and Resolution (PI&R) Inspection (September 2017). Please include the effective date with each listed change.
ASSESSMENTS
- 4. A copy of Quality Assurance (QA) audits of the corrective action program for the last two years.
- 5. A copy of self-assessments and associated condition reports generated in preparation for this PI&R inspection.
- 6. A list of all other QA audits completed in the last two years.
- 7. The schedule of future QA audits.
- 8. A copy of completed CAP self-assessments for the last two years and the plan/schedule for future CAP self-assessments.
- 9. A chronological list of department and site self-assessments completed in the last two years (include date completed).
- 10. A list of condition reports (CRs) written for findings or concerns identified in self-assessments and audits. Include a short description/title of the finding, its status, and include a cross-reference to the audit or self-assessment number.
Enclosure
CORRECTIVE ACTION DOCUMENTS
- 11. A copy of completed root cause evaluations generated since September 2017. Provide status of any actions developed as part of the evaluations. Include a reference, if not part of the root cause package, to the documents and/or CRs directing and tracking the actions.
- 12. A list of completed apparent cause evaluations generated since September 2017.
Provide status of any actions developed as part of the evaluations. Include a reference, if not part of the apparent cause package, to the documents and/or CRs directing and tracking the actions.
- 13. A list of completed common cause evaluations generated since September 2017.
Provide status of any actions developed as part of the evaluations. Include a reference, if not part of the common cause package, to the documents and/or CRs directing and tracking the actions.
- 14. A list of all open condition reports sorted by significance level. Include CR number, the date initiated, a brief description/title, system affected if any, significance level, and anticipated completion date, if available.
- 15. A list of closed CRs since September 2017 sorted by significance level and then initiation date. Include CR number, a brief description/title, the date initiated and closed, assigned organization, system affected and whether there was an associated operability evaluation.
- 16. A list of open corrective actions, sorted by significance/priority level, with a brief description/title, initiating date and due date. The list should include the number of due date extensions and be grouped by the responsible department.
- 17. A list of CRs generated by the corporate office September 2017 that involve or affect plant operation, sorted by significance level. Include the date initiated, a brief description/title, site(s) affected, system affected, assigned organization, and status (if closed include date closed; if open, include scheduled date to be closed).
- 18. A list of effectiveness reviews completed since September 2017 with a brief description of the results. Include a cross-reference to the CRs for which the effectiveness review was conducted and, if applicable, CR numbers documenting any additional follow-up actions.
- 19. A list of CRs initiated since September 2017 for inadequate or ineffective corrective actions. Include the date initiated, a brief description/title, significance/priority level, system affected, assigned organization, and status (if closed include date closed; if open, include scheduled date to be closed). Include a cross-reference to the CR or evaluation that generated the original corrective action.
- 20. A copy of any performance reports or indicators used to track CAP effectiveness. The end-of-quarter data will suffice; monthly reports are not required.
- 21. A data table (or similar format) showing the total number of CRs generated per year since 2014 sortable by department (i.e. operations, engineering, security etc.).
5
- 22. A data table showing the number of issues identified externally (NRC, INPO, other etc.)
per year as compared to internally since 2014.
TRENDS
- 23. A list of CRs initiated since September 2017 for trends. Include the date initiated, a brief description/title, significance/priority level, and status (if closed include date closed; if open, include scheduled date to be closed).
- 24. Copies of any completed trend reports for CRs. Quarterly trend reports are acceptable; copies of all monthly reports are not required.
- 25. Copies of all apparent, common and/or root cause evaluations regarding adverse human performance trends.
OPERATING EXPERIENCE
- 26. A copy of the most recent operating experience program effectiveness review.
- 27. A list of CRs initiated since September 2017 to evaluate industry and NRC operating experience, and NRC generic communications (e.g. bulletins, information notices, generic letters, etc.). Include date the CR was initiated, a brief description/title, and the status (if closed include date closed; if open, include scheduled date to be closed).
SYSTEMS AND COMPONENTS
- 28. A list of the top ten risk significant systems and top ten risk significant components.
- 29. A list of operability determinations/evaluations that were opened and evaluated since September 1, 2017. Include a brief description/title, date initiated, date closed or date scheduled to be closed. Also include any open operability evaluations that were initiated prior to September 2017.
- 30. Cause analysis, corrective actions documents, health reports, and trend analysis for systems and components considered Maintenance Rule (a)(1). Provide this information starting one year earlier from when the system or component entered (a)(1) status.
Include dates when system/components entered (a)(1) status and, if applicable, returned to (a)(2) status. For recurring reports, quarterly reports are sufficient; monthly reports are not required.
- 31. A list of temporary modifications that were installed since September 2017, with a brief description/title, installation date, and current status. Include any in-place temporary modifications that were installed prior to September 2017.
SCWE
- 32. Results of completed safety culture/safety conscious work environment surveys or self-assessments. Include reference to associated CRs and status of the CRs actions.
Also include schedule/plans for future surveys.
6
REGULATORY ISSUES
- 33. A copy of CRs for issues (findings, violations, etc.) documented in NRC inspection reports since September 2017. Include the CR number, brief description/title, date initiated and the status (if closed include date closed; if open, include scheduled date to be closed).
- 34. A list of CRs for licensee identified violations that have been documented in NRC inspection reports. Include the CR number, brief description/title, date initiated and the status (if closed include date closed; if open, include scheduled date to be closed).
- 35. A list and status of all corrective actions that are associated with greater than green findings that are still open.
- 36. A list of CRs associated with NRC identified issues. Include the CR number, brief description/title, date initiated and the status (if closed include date closed; if open, include scheduled date to be closed).
- 37. A list of degraded/non-conforming conditions. Include the CR number, brief description/title, date initiated and date closed or projected closeout date. Include open issues that were identified prior to September 11, 2017.
- 38. A list of current control room deficiencies and operator work-arounds, sortable by priority, with a brief description/title and corresponding CR and/or work order number.
5-YEAR REVIEW
- 39. A list of CRs and WOs regarding the safety-related switchgear ventilation (VX) system that have been generated since September 11, 2014. Include the CR number, brief description/title, level of evaluation (i.e. root cause, apparent cause, common cause etc.), date initiated, and the status (if closed include date closed; if open, include scheduled date to be closed).
ADMIN
- 40. A copy of the latest plant organizational chart and phone listing.
- 41. Scheduled dates, times, and location for all meetings associated with implementing the CAP (e.g. CR screening meetings, corrective action review board meetings). Include work order screening/assessment meetings.
Documents Requested to be Available On-Site during the Inspection:
- a. Updated Safety Analysis Report.
- b. Technical Specifications.
- c. Procedures and procedure index.
- d. A copy of the QA manual.
7
- e. A list of issues brought to the ECP/ombudsman and the actions taken for resolution.
- f. A list of the codes used in the CAP.
- g. A copy of the latest independent/offsite organization review of safety culture/safety conscious work environment and internal equivalent assessments if not provided as part of the requested data package.
Other:
On the first day of the inspection, or early on the second day, please provide the inspection team a briefing of your corrective action program. Include your expectations for personnel using the program and how the work order system fits into the overall scheme for addressing identified issues. Also please demonstrate how to use a computer to access CAP data.