MONTHYEARW3F1-2023-0052, Core Operating Limits Report (COLR) - Cycle 26, Revision O2023-11-0707 November 2023 Core Operating Limits Report (COLR) - Cycle 26, Revision O ML22123A3322022-05-0303 May 2022 Core Operating Limits Report (COLR) - Cycle 25, Revision 0 W3F1-2020-0066, Core Operating Limits Report (COLR) - Cycle 24, Revision 22020-11-11011 November 2020 Core Operating Limits Report (COLR) - Cycle 24, Revision 2 W3F1-2020-0064, Core Operating Limits Report (COLR) - Cycle 24, Revision 12020-10-27027 October 2020 Core Operating Limits Report (COLR) - Cycle 24, Revision 1 W3F1-2020-0058, Core Operating Limits Report (COLR) - Cycle 24, Revision 02020-10-15015 October 2020 Core Operating Limits Report (COLR) - Cycle 24, Revision 0 W3F1-2019-0015, Core Operating Limits Report (COLR) - Cycle 23, Revision 12019-03-13013 March 2019 Core Operating Limits Report (COLR) - Cycle 23, Revision 1 W3F1-2019-0014, Core Operating Limits Report-Cycle 23 Revision 02019-02-14014 February 2019 Core Operating Limits Report-Cycle 23 Revision 0 W3F1-2017-0045, Core Operating Limits Report - Cycle 22 Revision 02017-05-0909 May 2017 Core Operating Limits Report - Cycle 22 Revision 0 W3F1-2017-0034, Submittal of Core Operating Report for Cycle 21, Rev. 12017-04-0505 April 2017 Submittal of Core Operating Report for Cycle 21, Rev. 1 W3F1-2015-0088, Submits Core Operating Limits Report - Cycle 21 Revision 02015-11-18018 November 2015 Submits Core Operating Limits Report - Cycle 21 Revision 0 W3F1-2014-0047, Core Operating Limits Report - Cycle 20, Revision 12014-07-29029 July 2014 Core Operating Limits Report - Cycle 20, Revision 1 W3F1-2014-0033, Core Operating Limits Report Cycle 20 Revision 0, Waterford Steam Electric Station, Unit 32014-05-12012 May 2014 Core Operating Limits Report Cycle 20 Revision 0, Waterford Steam Electric Station, Unit 3 W3F1-2013-0074, Core Operating Limits Report - Cycle 19 Revision 22013-12-18018 December 2013 Core Operating Limits Report - Cycle 19 Revision 2 W3F1-2013-0026, Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 18 / Refuel 182013-04-18018 April 2013 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 18 / Refuel 18 W3F1-2012-0103, Core Operating Limits Report - Cycle 19 Revision 02012-12-14014 December 2012 Core Operating Limits Report - Cycle 19 Revision 0 W3F1-2011-0084, Core Operating Limits Report - Cycle 18 Revision 02011-11-23023 November 2011 Core Operating Limits Report - Cycle 18 Revision 0 ML11229A0262011-08-10010 August 2011 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 17 / Refuel 17 W3F1-2009-0030, Response to Amendment Request NPF-38-276, Core Protection Calculator Power Calibration Adjustment Limit2009-06-30030 June 2009 Response to Amendment Request NPF-38-276, Core Protection Calculator Power Calibration Adjustment Limit W3F1-2008-0057, Startup Power Escalation Report for Cycle 162008-08-25025 August 2008 Startup Power Escalation Report for Cycle 16 W3F1-2008-0041, Core Operating Limits Report - Cycle 16 Revision 02008-05-20020 May 2008 Core Operating Limits Report - Cycle 16 Revision 0 W3F1-2006-0068, Core Operating Limits Report - Cycle 15 Revision 02006-12-14014 December 2006 Core Operating Limits Report - Cycle 15 Revision 0 W3F1-2006-0063, 10 CFR 50.46 Thirty-Day Report for Changes to the Plant Emergency Core Cooling System Performance Analysis2006-12-0606 December 2006 10 CFR 50.46 Thirty-Day Report for Changes to the Plant Emergency Core Cooling System Performance Analysis ML0513902172005-05-17017 May 2005 Core Operating Limits Report for Cycle 14, Revision 0 W3F1-2004-0022, Core Operating Limits Report - Cycle 13 Revision 1, Change 22004-04-19019 April 2004 Core Operating Limits Report - Cycle 13 Revision 1, Change 2 W3F1-2003-0097, Core Operating Limits Report, Cycle 13, Revision 1, Change 12003-11-20020 November 2003 Core Operating Limits Report, Cycle 13, Revision 1, Change 1 W3F1-2003-0094, Core Operating Limits Report, Cycle 13, Revision 12003-11-17017 November 2003 Core Operating Limits Report, Cycle 13, Revision 1 W3F1-2003-0086, Core Operating Limits Report - Cycle 13, Revision 02003-11-0505 November 2003 Core Operating Limits Report - Cycle 13, Revision 0 W3F1-2002-0064, Ses Startup and Power Escalation Report for Cycle 122002-07-12012 July 2002 Ses Startup and Power Escalation Report for Cycle 12 W3F1-2002-0034, Ses Core Operating Limits Report for Cycle 122002-04-0404 April 2002 Ses Core Operating Limits Report for Cycle 12 2023-11-07
[Table view] Category:Letter type:W
MONTHYEARW3F1-2023-0056, Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242023-12-19019 December 2023 Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2023-0055, Reply to a Notice of Violation2023-12-14014 December 2023 Reply to a Notice of Violation W3F1-2023-0052, Core Operating Limits Report (COLR) - Cycle 26, Revision O2023-11-0707 November 2023 Core Operating Limits Report (COLR) - Cycle 26, Revision O W3F1-2023-0049, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal2023-09-28028 September 2023 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal W3F1-2023-0048, Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-09-25025 September 2023 Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0035, Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program2023-07-26026 July 2023 Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program W3F1-2023-0036, Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-05-0404 May 2023 Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0032, Annual Radioactive Effluent Release Report (ARERR) 20222023-04-27027 April 2023 Annual Radioactive Effluent Release Report (ARERR) 2022 W3F1-2023-0033, Submittal of Annual Radiological Environmental Operating Report - 20222023-04-27027 April 2023 Submittal of Annual Radiological Environmental Operating Report - 2022 W3F1-2023-0025, Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.22062023-04-11011 April 2023 Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.2206 W3F1-2023-0018, Updated Final Supplemental Response to NRC Generic Letter 2004-022023-03-30030 March 2023 Updated Final Supplemental Response to NRC Generic Letter 2004-02 W3F1-2023-0022, Registration of Dry Fuel Storage Cask Use2023-03-22022 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0021, Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days2023-03-17017 March 2023 Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0016, Registration of Dry Fuel Storage Cask Use2023-03-0303 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0014, Reply to a Notice of Violation; EA-22-1192023-02-20020 February 2023 Reply to a Notice of Violation; EA-22-119 W3F1-2023-0013, Notification of Readiness for Supplemental Inspection2023-02-15015 February 2023 Notification of Readiness for Supplemental Inspection W3F1-2023-0007, Registration of Dry Fuel Storage Cask Use2023-02-0606 February 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0010, Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days2023-01-25025 January 2023 Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0002, SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days2023-01-0505 January 2023 SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days W3F1-2022-0067, Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-022022-12-20020 December 2022 Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-02 W3F1-2022-0054, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability2022-11-0101 November 2022 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability W3F1-2022-0063, Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 372022-10-27027 October 2022 Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 37 W3F1-2022-0059, Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-5052022-10-13013 October 2022 Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-505 W3F1-2022-0058, Reply to a Notice of Violation; EA-22-0332022-10-12012 October 2022 Reply to a Notice of Violation; EA-22-033 W3F1-2022-0049, Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-5052022-08-19019 August 2022 Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 W3F1-2022-0037, Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242022-08-0808 August 2022 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2022-0044, SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-07-0606 July 2022 SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0042, SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-06-27027 June 2022 SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0015, Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf.2022-05-16016 May 2022 Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf. W3F1-2022-0026, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20222022-04-28028 April 2022 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2022 W3F1-2022-0028, Annual Radiological Environmental Operating Report - 20212022-04-26026 April 2022 Annual Radiological Environmental Operating Report - 2021 W3F1-2022-0029, Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.22062022-04-26026 April 2022 Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.2206 W3F1-2022-0009, Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2022-04-25025 April 2022 Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors W3F1-2022-0031, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-2842022-04-25025 April 2022 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-284 W3F1-2022-0020, Review of Preliminary Accident Sequence Precursor Report2022-04-11011 April 2022 Review of Preliminary Accident Sequence Precursor Report W3F1-2022-0017, Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 20212022-04-0707 April 2022 Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 2021 W3F1-2022-0019, WAT-2022-02 Post Exam Analysis2022-03-0909 March 2022 WAT-2022-02 Post Exam Analysis W3F1-2022-0011, Special Report SR-22-002-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-02-0808 February 2022 Special Report SR-22-002-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0008, SR-22-001-00, Waterford Steam Electric Station, Unit 3, Radiation Monitors Inoperable Greater than 7 Days2022-02-0101 February 2022 SR-22-001-00, Waterford Steam Electric Station, Unit 3, Radiation Monitors Inoperable Greater than 7 Days W3F1-2021-0074, Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-022021-12-16016 December 2021 Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-02 W3F1-2021-0064, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Relocation of Capsules 104 and 2842021-11-30030 November 2021 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Relocation of Capsules 104 and 284 W3F1-2021-0061, Supplement to License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual2021-10-14014 October 2021 Supplement to License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual W3F1-2021-0063, Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Exercise Requirements Due to Severe Storm Recovery2021-10-12012 October 2021 Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Exercise Requirements Due to Severe Storm Recovery W3F1-2021-0050, Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request to Adopt2021-10-0101 October 2021 Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request to Adopt W3F1-2021-0060, Response to Request for Additional Information Regarding License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual2021-09-30030 September 2021 Response to Request for Additional Information Regarding License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual W3F1-2021-0039, Application for Technical Specification Change to Revise Pressure/Temperature and Low Temperature Overpressure Protection for 55 Effective Full Power Years2021-08-25025 August 2021 Application for Technical Specification Change to Revise Pressure/Temperature and Low Temperature Overpressure Protection for 55 Effective Full Power Years W3F1-2021-0055, Supplement to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual2021-08-20020 August 2021 Supplement to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual W3F1-2021-0057, (Waterford 3) - Emergency Plan Revision 0522021-08-18018 August 2021 (Waterford 3) - Emergency Plan Revision 052 W3F1-2021-0054, License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator (CPC) System and Control Element Assembly Calculator (Ceac) System, Dated July 23, 20202021-07-29029 July 2021 License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator (CPC) System and Control Element Assembly Calculator (Ceac) System, Dated July 23, 2020 W3F1-2021-0051, Revised Licensing Technical Report for the Common Q Core Protection Calculator System - License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator System and Control Element Assembly Calculator2021-07-19019 July 2021 Revised Licensing Technical Report for the Common Q Core Protection Calculator System - License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator System and Control Element Assembly Calculator 2023-09-28
[Table view] |
Text
W3F1-2019-0014 Page 2 cc: Mr. Scott Morris Regional Administrator U. S. Nuclear Regulatory Commission Region IV RidsRgn4MailCenter@nrc.gov NRC Senior Resident Inspector Waterford Steam Electric Station Unit 3 Frances.Ramirez@nrc.gov Chris.Speer@nrc.gov NRC/NRR Project Manager for Waterford 3 April.Pulvirenti@ nrc.gov
Attachment to W3F1-2019-0014 Waterford 3 Core Operating Limits Report Cycle 23 Revision 0 (Attachment contains 17 pages)
ENTERGY OPERATIONS WATERFORD 3 CORE OPERATING LIMITS REPORT FOR CYCLE 23 MODES 5 AND 6 ONLY REVISION 0
WATERFORD 3 CORE OPERATING LIMITS REPORT CYCLE 23 MODES 5 AND 6 ONLY REVISION 0 INDEX PAGE I. INTRODUCTION 5 II. AFFECTED TECHNICAL SPECIFICATIONS 6 3.1.1.1 Shutdown Margin - Any CEA Withdrawn COLR 3/4 1-1 3.1.1.2 Shutdown Margin - All CEAs Fully Inserted COLR 3/4 1-3 3.1.2.9 Boron Dilution COLR 3/4 1-15 3.9.1 Boron Concentration COLR 3/4 9-1 III. METHODOLOGIES 17 LIST OF EFFECTIVE PAGES Revision 0 Pages 1-6, COLR 3/4 1-1, 1-3, 1-15, 9-1, and Page 17 WATERFORD 3 Page 2 CYCLE 23 REVISION 0
LIST OF FIGURES PAGE COLR Figure 1 Shutdown Margin Versus Cold Leg Temperature COLR 3/4 1-3A LIST OF EFFECTIVE FIGURE PAGES Revision 0 COLR 3/4 1-3A WATERFORD 3 Page 3 CYCLE 23 REVISION 0
LIST OF TABLES PAGE COLR Table 1 Required Monitoring Frequencies for Backup COLR 3/4 1-15A Boron Dilution Detection as a Function of Operating Charging Pumps and Plant Operational Modes for Keff Greater Than 0.98.
COLR Table 2 Required Monitoring Frequencies for Backup COLR 3/4 1-15B Boron Dilution Detection as a Function of Operating Charging Pumps and Plant Operational Modes for Keff Greater Than 0.97 and Less Than or Equal to 0.98.
COLR Table 3 Required Monitoring Frequencies for Backup COLR 3/4 1-15C Boron Dilution Detection as a Function of Operating Charging Pumps and Plant Operational Modes for Keff Greater Than 0.96 and Less Than or Equal to 0.97.
COLR Table 4 Required Monitoring Frequencies for Backup COLR 3/4 1-15D Boron Dilution Detection as a Function of Operating Charging Pumps and Plant Operational Modes for Keff Greater Than 0.95 and Less Than or Equal to 0.96.
COLR Table 5 Required Monitoring Frequencies for Backup COLR 3/4 1-15E Boron Dilution Detection as a Function of Operating Charging Pumps and Plant Operational Modes for Keff Greater Than or Equal to 0.95.
LIST OF EFFECTIVE TABLE PAGES Revision 0 COLR 3/4 1-15A through COLR 3/4 1-15E WATERFORD 3 Page 4 CYCLE 23 REVISION 0
WATERFORD 3 CORE OPERATING LIMITS REPORT CYCLE 23 FOR MODES 5 AND 6 ONLY REVISION 0 I. INTRODUCTION This CORE OPERATING LIMITS REPORT (COLR) has been prepared in accordance with the requirements of Waterford 3 Technical Specification 6.9.1.11 for Technical Specifications 3.1.1.1 and 3.1.1.2, Shutdown Margin, 3.1.2.9, Boron Dilution, and 3.9.1, Boron Concentration only for Waterford 3 Cycle 23. This revision of the COLR is applicable for Modes 5 and 6 only. This document will be revised to address the remaining parameters listed in Technical Specification 6.9.1.11 prior to entering Mode 4. The core operating limits have been developed using the NRC approved methodologies specified in Section III. This is Revision 0 of the Cycle 23 COLR.
There were no major changes between the Cycle 23, Revision 0, COLR and the Cycle 22, Revision 0, COLR. This is the initial issuance of the Cycle 23 COLR. It is applicable to operations in Modes 5 and 6 only. There are no changes to the values for the required Shutdown Margin in Mode 5 from the latest revision to the Cycle 22 COLR. There are no changes to the values for the required RCS boron concentration monitoring frequencies and Charging Pump operation limits in Modes 5 and 6 from the latest revision to the Cycle 22 COLR. There are no changes to the values for the required RCS boron concentration in Mode 6 from the latest revision to the Cycle 22 COLR.
WATERFORD 3 Page 5 CYCLE 23 REVISION 0
II. AFFECTED TECHNICAL SPECIFICATIONS WATERFORD 3 Page 6 CYCLE 23 REVISION 0
CORE OPERATING LIMITS REPORT SHUTDOWN MARGIN - ANY CEA WITHDRAWN 3.1.1.1 The SHUTDOWN MARGIN shall be greater than or equal to 5.15% k/k when Tavg is greater than 200 F or 2.0% k/k when Tavg is less than or equal to 200 F.
WATERFORD 3 COLR 3/4 1-1 CYCLE 23 REVISION 0
CORE OPERATING LIMITS REPORT SHUTDOWN MARGIN - ALL CEAs FULLY INSERTED 3.1.1.2 The SHUTDOWN MARGIN shall be maintained within the region of acceptable operation of COLR Figure 1.
WATERFORD 3 COLR 3/4 1-3 CYCLE 23 REVISION 0
Shutdown Margin Versus Cold Leg Temperature (All CEAs Fully Inserted) 6 5
(500 oF, 4.6%)
4 Shutdown Margin (%K/K) 3 Acceptable Operation 2
(400 oF, 1.5%)
1 Unacceptable Operation 0
0 100 200 300 400 500 600 Cold Leg Temperature (oF)
COLR Figure 1 WATERFORD 3 COLR 3/4 1-3A CYCLE 23 REVISION 0
CORE OPERATING LIMITS REPORT BORON DILUTION 3.1.2.9 See COLR Tables 1 through 5 for required RCS boron concentration monitoring frequencies and Charging Pump operation limits.
SURVEILLANCE REQUIREMENTS Each required boron dilution alarm shall be adjusted to less than or equal to 1.75 times (1.75x) the existing neutron flux (cps) at the following frequencies:
- a. No sooner than one half hour after shutdown and no later than 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after shutdown.
- b. At least once per one-half (1/2) hour if the reactor has been shut down > 0.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> but < 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
- c. At least once per hour if the reactor has been shutdown > 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> but < 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />.
- d. At least once per 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> if the reactor has been shut down > 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> but < 25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br />.
- e. At least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> if the reactor has been shut down > 25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br /> but < 21 days.
- f. At least once per 7 days, if the reactor has been shutdown 21 days.
WATERFORD 3 COLR 3/4 1-15 CYCLE 23 REVISION 0
COLR TABLE 1 REQUIRED MONITORING FREQUENCIES FOR BACKUP BORON DILUTION DETECTION AS A FUNCTION OF OPERATING CHARGING PUMPS AND PLANT OPERATIONAL MODES FOR Keff GREATER THAN 0.98 Keff 0.98 OPERATIONAL Number of Operating Charging Pumps
- MODE 0 1 2 3 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Operation not allowed **
RCS filled 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Operation not allowed **
RCS partially drained 6 Operation not allowed **
- Charging pump OPERABILITY for any period of time shall constitute OPERABILITY for the entire monitoring frequency.
- Charging pumps shall be verified to be inoperable by removing power to the required number.
WATERFORD 3 COLR 3/4 1-15A CYCLE 23 REVISION 0
COLR TABLE 2 REQUIRED MONITORING FREQUENCIES FOR BACKUP BORON DILUTION DETECTION AS A FUNCTION OF OPERATING CHARGING PUMPS AND PLANT OPERATIONAL MODES FOR Keff GREATER THAN 0.97 AND LESS THAN OR EQUAL TO 0.98 0.98 Keff 0.97 OPERATIONAL Number of Operating Charging Pumps
- MODE 0 1 2 3 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 0.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> Operation not allowed**
RCS filled 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 0.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> Operation not allowed**
RCS partially drained 6 Operation not allowed**
- Charging pump OPERABILITY for any period of time shall constitute OPERABILITY for the entire monitoring frequency.
- Charging pumps shall be verified to be inoperable by removing power to the required number.
WATERFORD 3 COLR 3/4 1-15B CYCLE 23 REVISION 0
COLR TABLE 3 REQUIRED MONITORING FREQUENCIES FOR BACKUP BORON DILUTION DETECTION AS A FUNCTION OF OPERATING CHARGING PUMPS AND PLANT OPERATIONAL MODES FOR Keff GREATER THAN 0.96 AND LESS THAN OR EQUAL TO 0.97 0.97 Keff 0.96 OPERATIONAL Number of Operating Charging Pumps
- MODE 0 1 2 3 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> Operation not allowed**
RCS filled 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 0.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> Operation not allowed**
RCS partially drained 6 Operation not allowed**
- Charging pump OPERABILITY for any period of time shall constitute OPERABILITY for the entire monitoring frequency.
- Charging pumps shall be verified to be inoperable by removing power to the required number.
WATERFORD 3 COLR 3/4 1-15C CYCLE 23 REVISION 0
COLR TABLE 4 REQUIRED MONITORING FREQUENCIES FOR BACKUP BORON DILUTION DETECTION AS A FUNCTION OF OPERATING CHARGING PUMPS AND PLANT OPERATIONAL MODES FOR Keff GREATER THAN 0.95 AND LESS THAN OR EQUAL TO 0.96 0.96 Keff 0.95 OPERATIONAL Number of Operating Charging Pumps
- MODE 0 1 2 3 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 2.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> 0.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> Operation not allowed**
RCS filled 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 2.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> 0.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> Operation not allowed**
RCS partially drained 6 Operation not allowed**
- Charging pump OPERABILITY for any period of time shall constitute OPERABILITY for the entire monitoring frequency.
- Charging pumps shall be verified to be inoperable by removing power to the required number.
WATERFORD 3 COLR 3/4 1-15D CYCLE 23 REVISION 0
COLR TABLE 5 REQUIRED MONITORING FREQUENCIES FOR BACKUP BORON DILUTION DETECTION AS A FUNCTION OF OPERATING CHARGING PUMPS AND PLANT OPERATIONAL MODES FOR Keff LESS THAN OR EQUAL TO 0.95 Keff 0.95 OPERATIONAL Number of Operating Charging Pumps*
MODE 0 1 2 3 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 3.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> 1.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> 0.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> RCS filled 5 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> 0.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> Operation not allowed**
RCS partially drained 6 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 2.25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br /> 0.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> Operation not allowed**
- Charging pump OPERABILITY for any period of time shall constitute OPERABILITY for the entire monitoring frequency.
- Charging pumps shall be verified to be inoperable by removing power to the required number.
WATERFORD 3 COLR 3/4 1-15E CYCLE 23 REVISION 0
CORE OPERATING LIMITS REPORT BORON CONCENTRATION 3.9.1 While in Mode 6, the RCS boron concentration shall be maintained sufficiently to ensure that the more restrictive of the following reactivity conditions is met:
- a. Either Keff of 0.95 or less, or
- b. A boron concentration of greater than or equal to 2050 ppm.
WATERFORD 3 COLR 3/4 9-1 CYCLE 23 REVISION 0
III. METHODOLOGIES The analytical methods used to determine the core operating limits listed above are those previously reviewed and approved by the NRC in:
- 1. Qualification of the PHOENIX-P/ANC Nuclear Design System for Pressurized Water Reactor Cores, WCAP-11596-P-A, June 1988; ANC: A Westinghouse Advanced Nodal Computer Code, WCAP-10965-P-A, September 1986; and ANC: A Westinghouse Advanced Nodal Computer Code: Enhancements to ANC Rod Power Recovery, WCAP-10965-P-A Addendum 1, April 1989. (Methodology for Specifications 3.1.1.1 and 3.1.1.2 for Shutdown Margins, 3.1.1.3 for MTC, 3.1.3.6 for Regulating and Group P CEA Insertion Limits, 3.1.2.9 Boron Dilution (Calculation of CBC and IBW),
and 3.9.1 Boron Concentration).
- 2. Technical Description Manual for the CENTS Code, WCAP-15996-P-A, Revision 1, March 2005. (Methodology for Specification 3.1.1.1 and 3.1.1.2 for Shutdown Margins, 3.1.1.3 for MTC, 3.1.3.1 for Movable Control Assemblies - CEA Position, 3.1.3.6 for Regulating and Group P CEA Insertion Limits, and 3.2.4.b for DNBR Margin)
- 3. Qualification of the Two-Dimensional Transport Code PARAGON, WCAP-16045-P-A, August 2004. (Methodology for Specifications 3.1.1.1 and 3.1.1.2 for Shutdown Margins, 3.1.1.3 for MTC, 3.1.3.6 for Regulating and Group P CEA Insertion Limits, 3.1.2.9 Boron Dilution (Calculation of CBC & IBW),
3.2.4.b for DNBR Margin and 3.9.1 Boron Concentration).
WATERFORD 3 Page 17 CYCLE 23 REVISION 0