Letter Sequence Withholding Request Acceptance |
---|
EPID:L-2017-LLA-0414, Resolution of Commitments Related to Review Request for the Aging Management Program and Inspection Plan for the McGuire Nuclear Station Units 1 and 2 Reactor Vessel Internals to Implement MRP-227-A (Open) |
|
MONTHYEARML18023B0192018-01-23023 January 2018 NRR E-mail Capture - McGuire Nuclear Station, Units 1 and 2 - Acceptance of Requested Licensing Action Approval of Reactor Vessel Internals Inspection Plan Based on MRP-227-A Project stage: Acceptance Review ML18030B0722018-02-0909 February 2018 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML18135A0872018-04-30030 April 2018, 9 May 2018 Resolution of Commitments Related to Review Request for the Aging Management Program and Inspection Plan for the McGuire Nuclear Station Units 1 and 2 Reactor Vessel Internals to Implement MRP-227-A Project stage: Request ML18352A8052018-12-18018 December 2018 NRR E-mail Capture - Request for Additional Information - McGuire Nuclear Station, Units 1 and 2 - MRP-227 Review Project stage: RAI ML19036A6192019-02-15015 February 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19058A4162019-03-0808 March 2019 Staff Evaluation Related to Reactor Vessel Internals Inspection Plan Based on MRP-227-A Project stage: Other 2018-02-09
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000369/20230042024-01-31031 January 2024 Integrated Inspection Report 05000369/2023004 and 05000370/2023004 ML24019A1392024-01-25025 January 2024 TSTF 505 and 50.69 Audit Summary ML24019A2002024-01-24024 January 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000369/20234022023-12-14014 December 2023 Material Control and Accounting Program Inspection Report 05000369/2023402 and 05000370/2023402 ML23317A2272023-11-17017 November 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Transmittal of Dam Inspection Report - Non-Proprietary ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230032023-10-24024 October 2023 Integrated Inspection Report 05000369/2023003 and 05000370/2023003; and Inspection Report 07200038/2023001 IR 05000369/20240102023-10-13013 October 2023 Notification of McGuire Nuclear Station Comprehensive Engineering Team Inspection U.S. Nuclear Regulatory Commission Inspection Report 05000369, 370/2024010 IR 05000369/20230102023-10-13013 October 2023 Age Related Degradation Inspection Report 05000369/2023010 and 05000370/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds IR 05000369/20233012023-09-20020 September 2023 William B. McGuire Nuclear Station - NRC Examination Report 05000369/2023301 and 05000370/2023301 ML23230A0652023-08-31031 August 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Relief Request Use of Later Edition of ASME Code ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230052023-08-25025 August 2023 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 (Report 05000369/2023005 and 05000370/2023005) IR 05000369/20230022023-07-28028 July 2023 Integrated Inspection Report 05000369/2023002 and 05000370/2023002 IR 05000369/20234202023-07-24024 July 2023 Security Baseline Inspection Report 050003692023420 and 050003702023420 ML23206A0092023-07-24024 July 2023 William B. McGuire Nuclear Station Operator Licensing Written Examination Approval 05000369/2023301 and 05000370/2023301 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23159A2712023-06-20020 June 2023 William B. McGuire Nuclear Station, Unit 1 - Relief Request Impractical Reactor System Welds ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000369/20230012023-05-0101 May 2023 Integrated Inspection Report 05000369/2023001 and 05000370/2023001 ML23115A2122023-05-0101 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23094A1832023-04-18018 April 2023 Audit Plan TSTF-505, Rev. 2, RITSTF Initiative 4B & 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors (EPIDs L-2023-LLA-0021 & L-2023-LLA-0022) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000369/20220062023-03-0101 March 2023 Annual Assessment Letter for McGuire Nuclear Station Units 1 and 2 (NRC Inspection Report 05000369/2022006 and 05000370 2022006) IR 05000369/20220042023-01-30030 January 2023 Mcguire Nuclear Station - Integrated Inspection Report 05000369/2022004 and 05000370/2022004 IR 05000369/20224202023-01-11011 January 2023 Security Baseline Inspection Report 05000369/2022420 and 05000370/2022420 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22347A1512022-12-13013 December 2022 William B. Mcguire Nuclear Station Notification of Licensed Operator Initial Examination 05000369/2023301 and 05000370/2023301 ML22340A6662022-12-0808 December 2022 Summary of November 30, 2022, Public Meeting with Duke Energy Carolinas, LLC for McGuire Nuclear Station, Units 1 & 2 Proposed LAR to Adopt TSTF-505, Rev. 2 and 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems ML22290A1012022-11-29029 November 2022 Issuance of Amendment Nos. 326 and 305, Regarding Changes to Technical Specification 3.4.3, Reactor Coolant System Pressure Temperature Limits ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000369/20220032022-10-27027 October 2022 Integrated Inspection Report 05000369/2022003 and 05000370/2022003 IR 05000369/20220112022-09-29029 September 2022 Biennial Problem Identification and Resolution Inspection Report 05000369/2022011 and 05000370/2022011 ML22266A0782022-09-26026 September 2022 William B. Mcguire Nuclear Station, Unit 2 Pressurizer Power Operated Relief Valve Relief Request ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports IR 07200038/20220012022-09-12012 September 2022 Operation of an Independent Spent Fuel Storage Installation Report 07200038/2022001 ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22230B6132022-09-0101 September 2022 Review of the Draft Environmental Assessment and Finding of No Significant Impact for Brunswick Steam Electric Plant and McGuire Nuclear Station Independent Spent Fuel Storage Installations Decommissioning Funding Plans IR 05000369/20220052022-08-29029 August 2022 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 NRC Inspection Report 05000369/2022005 and 05000370/2022005 IR 05000369/20220022022-07-26026 July 2022 Integrated Inspection Report 05000369/2022002 and 05000370/2022002 ML22215A2502022-07-25025 July 2022 EN 55960 - Update - Curtiss Wright ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22175A0162022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22111A3112022-05-16016 May 2022 Letter Issuing Exemption to McGuire IR 05000369/20224012022-05-12012 May 2022 Cyber Security Inspection Report 05000369/2022401 and 05000370/2022401 2024-01-31
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 15, 2019 Mr. Thomas D. Ray Vice President McGuire Nuclear Station Duke Energy Carolinas, LLC 12700 Hagers Ferry Road Huntersville, NC 28078-8985
SUBJECT:
MCGUIRE NUCLEAR STATION, UNITS 1 AND 2 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (EPID L-2017-LLA-0414)
Dear Mr. Ray:
By letter dated January 30, 2019 Agencywide Documents Access and Management System (ADAMS) Accession No. and ML19032A094, respectively), you submitted an affidavit dated January 22, 2019, executed by Philip A. Opsal, Manager, Product Licensing of Framatone Inc.
(formally known as AREVA, Inc.), requesting that the information contained in the following documents be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
- Attachment 3 - "Response to Requests for Additional Information for Aging Management Program and Inspection Plan for the McGuire Units 1 and 2 Reactor Vessels Internals to Implement MRP-227-A Technical Report; ANP-3750P Revision O" The affidavits stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(a) The information reveals details of Framatones lnc.'s research and development plans and programs or their results.
(b) Use of the information by a competitor would permit the competitor to significantly reduce its expenditures, in time or resources, to design, produce, or market a similar product or service.
(c) The information includes test data or analytical techniques concerning a process, methodology, or component, the application of which results in a competitive advantage for Framatone, Inc.
(d) The information reveals certain distinguishing aspects of a process, methodology, or component, the exclusive use of which provides a competitive advantage for Framatone Inc. in product optimization or marketability.
T. Ray (e) The information is vital to a competitive advantage held by Framatone, Inc., would be helpful to competitors to Framatone, Inc., and would likely cause substantial harm to the competitive position of Framatone Inc.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the documents listed above, marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the Nuclear Regulatory Commission (NRC). You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at by phone at 301-415-3867 or by email at Michael.Mahoney@nrc.gov.
Michael Mahoney, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-369 and 50-370 cc: Listserv
ML19036A619 OFFICE NRR/DORULPL2-1 /PM NRR/DORULPL2-1/LA NRR/DMLR/MVIB/BC NAME MMahoney KGoldstein SRuffin DATE 02/13/19 02/11/19 02/13/19 OFFICE NRR/DORULPL2-1 /BC NRR/DORULPL2-1 /PM NAME MMarkley MMahoney DATE 02/15/19 02/15/19