Letter to K. Cimorelli Request for Additional Information Regarding Susquehanna Nuclear, Llc'S Decommissioning Funding Plan Update for Susquehanna Steam Electric Station Independent Spent Fuel Storage Installation
ML18352B184
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 12/13/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Cimorelli K
Susquehanna
Longmire P
Shared Package
ML18352B182 List:
References
CAC 001028, EPID L-2017-FPR-0067
Download: ML18352B184 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 13, 2018 Mr. Kevin Cimorelli Site Vice President Susquehanna Nuclear, LLC 769 Salem Boulevard Berwick, PA 18603

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING SUSQUEHANNA NUCLEAR, LLCS DECOMMISSIONING FUNDING PLAN UPDATE FOR SUSQUEHANNA STEAM ELECTRIC STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Mr. Cimorelli:

By letter dated December 16, 2015, Susquehanna Nuclear, LLCs (Susquehanna) and Allegheny Electric Cooperative, Inc.s (Allegheny) submitted for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at Susquehanna Steam Electric Station (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML15350A071 and ML16032A339). The NRC staff reviewed Susquehannas and Alleghenys DFP update for the ISFSI and believes Susquehannas and Alleghenys submittal is not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.

The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working days of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response due date occurred on December 12, 2018. The conversation record and e-mail exchange are available in ADAMS (Accession Nos.

ML18347A272 and ML18347A328, respectively).

K. Cimorelli The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov.

Sincerely,

/RA/

Pamela Longmire, Ph.D.

Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-28 CAC No.: 001028 EPID No.: L-2017-FPR-0067

Enclosure:

Request for Additional Information

K. Cimorelli 3

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING SUSQUEHANNA NUCLEAR, LLCS DECOMMISSIONING FUNDING PLAN UPDATE FOR SUSQUEHANNA STEAM ELECTRIC STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: December 13, 2018 DISTRIBUTION:

SFM R/F JMcKirgan, NMSS ABowers, NRR SHarwell, NRR KLois, NRR MHenderson, NRR THood, NRR Letter: G:\SFST\72.30 Decommissioning Funding Plans\RAIs\Susquehanna\Susquehanna-RAI.docx

Enclosure:

G:\SFST\72.30 Decommissioning Funding Plans\RAIs\Susquehanna\Susquehanna-Enclosure.docx ADAMS Package No.: ML18352B182 Letter: ML18352B184 Encl.: ML18352B183 C = COVER E = COVER & ENCLOSURE N = NO COPY OFFICE NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley JMcKirgan DATE 12/6/18 12/11/18 12/13/18 OFFICIAL RECORD COPY