ML18284A182

From kanterella
Jump to navigation Jump to search
Gfes Results, September 2018
ML18284A182
Person / Time
Site: Palisades Entergy icon.png
Issue date: 09/27/2018
From: Robert Orlikowski
Operations Branch III
To: Nelson W
Entergy Nuclear Operations
Orlikowski, R
References
Download: ML18284A182 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, ILLINOIS 60532-4352 September 27, 2018 Mr. Walter Nelson Training Manager Palisades Nuclear Plant Entergy Nuclear Operations, Inc.

27780 Blue Star Memorial Highway Covert, MI 49043

SUBJECT:

SEPTEMBER 5, 2018, NRC GENERIC FUNDAMENTALS EXAMINATION RESULTS FOR PALISADES NUCLEAR PLANT (COVER LETTER ONLY)

Dear Mr. Nelson:

On September 5, 2018, the U.S. Nuclear Regulatory Commission (NRC) administered the generic fundamentals examination (GFE) section of the written operator licensing examination to employees at your facility. Enclosed with this letter are copies of both forms of the examination, including answer keys, the grading results for your facility, and copies of the individual answer sheets for each of your employees. Please forward the results to the individuals along with the copies of their respective answer sheets. A P in the RESULTS column indicates that the individual achieved a passing grade of 80 percent or better on the GFE, while an F indicates that the individual failed the exam.

If you have any questions concerning this examination, please contact Mr. Eric Cushing at 301-415-1064.

Sincerely, Digitally signed by Robert J. Orlikowski Robert J. Orlikowski DN: c=US, o=U.S. Government, ou=U.S. Nuclear Regulatory Commission, ou=NRC-PIV, cn=Robert J.

Orlikowski, 0.9.2342.19200300.100.1.1=200005622 Date: 2018.09.27 16:53:22 -05'00' Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket No. 50-255 Enclosures (Non-Public):

1. PWR Examination Forms A and B with answers
2. Examination Results Summary for Palisades Nuclear Plant
3. Individual Answer Sheets

W. Nelson 2

SUBJECT:

SEPTEMBER 5, 2018, NRC GENERIC FUNDAMENTALS EXAMINATION RESULTS FOR PALISADES NUCLEAR PLANT (COVER LETTER ONLY DOCUMENT NAME:

P:\Client Server Applications OL Downloads\GFE test results\GFE test results - Sept 2018\Palisades Sept 2018 GFE Results.docx TEMPLATE#: NRR -117 OFFICE RIII/DRS/OB:OLA RIII/DRS/OB:BC NAME CSchmidt CS ROrlikowski RJO DATE 09/27/18 09/ 27 /18 OFFICIAL RECORD COPY