ML18275A324

From kanterella
Jump to navigation Jump to search
R. E. Ginna Nuclear Power Plant - Requalification Program Inspection
ML18275A324
Person / Time
Site: Ginna Constellation icon.png
Issue date: 10/02/2018
From: Diane Jackson
Operations Branch I
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
Download: ML18275A324 (3)


Text

D. Curtlan UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 October 2, 2018 Mr. Bryan C. Hanson Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - R. E. GINNA NUCLEAR POWER PLANT

Dear Mr. Hanson:

In a telephone conversation on October 1, 2018, Mr. T. Fish, Senior Operations Engineer, and Mr. L. Mireles, Licensed Operator Requalification Lead Instructor, made arrangements for the U.S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at the Ginna facility. The inspection is planned for the week of November 12, 2018, which coincides with your scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish: (1) an index or summary of condition reports written in the past 2 years in which licensed operator errors were determined to be the root or contributing cause; (2) an index or summary of condition reports written in the past 2 years on simulator performance problems; (3) an index or summary of simulator performance test results in the past 2 years; and 4) the examination schedule, sample plan, and operating test scheduled for the week of the inspection to the NRC by October 29, 2018. Mr. Mireles has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.

B. Hanson 2 The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52),

U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C. 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. T. Fish at (610) 337-5369.

Sincerely,

/RA/

Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 50-244 License No. DPR-18 cc: Distribution via ListServ

B. Hanson 3

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - R. E. GINNA NUCLEAR POWER PLANT DATED OCTOBER 2, 2018 Distribution w/encl: (via E-mail)

DLew, RA (R1ORAMAIL RESOURCE)

RLorson, DRA (R1ORAMAIL RESOURCE)

DPelton, DRP (R1DRPMAIL RESOURCE)

PKrohn, DRP (R1DRPMAIL RESOURCE)

JYerokun, DRS (R1DRSMAIL RESOURCE)

BWelling, DRS (R1DRSMAIL RESOURCE)

CCahill, DRP ARosebrook, DRP SObadina, DRP NPerry, DRP, SRI JSchussler, DRP, RI KTennity, DRP CCook, RI OEDO RidsNrrPMREGinna Resource RidsNrrDorlLpl1 Resource ROPReports Resource DOCUMENT NAME: G:\DRS\Operations Branch\FISH\Requal FY19 - Ginna Nov2018\Ginna Nov 2018 60dayrpi.docx ADAMS NO. ML18275A324 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRS/OB RI/DRS/OB NAME TFish DEJackson DATE 10/1/18 10/2/18 OFFICIAL RECORD COPY