MONTHYEARML24032A2752024-02-0707 February 2024 Pre-Pre-Submittal Meeting for Proposed License Amendment Regarding Hydrologic Analysis Updates (Slides) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML24019A1512024-01-22022 January 2024 Slides - Modification of Browns Ferry Technical Specifications to Eliminate LCO 3.3.2.1 Actions C.2.1.1 and C.2.1.2 for Rod Worth ML23317A2032023-12-13013 December 2023 Pre-Submittal Meeting: Tech Spec Amendment Request for HPCI Flow Switch Setpoint Change ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23262B2602023-09-19019 September 2023 Slides - Constellation - Pre-Application EP 9/25/2023 Meeting Handout ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23174A0012023-06-23023 June 2023 Pre-submittal Meeting Slides Regarding Update to the FitzPatrick Fuel Handling Accident Analysis with Impacts to Technical Specifications, June 26, 2023 ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23150A1382023-06-0101 June 2023 Pre Submittal Meeting: Containment Inservice Inspection (Cisi) Relief Request, June 1, 2023 ML23150A1372023-06-0101 June 2023 Pre-Submittal Meeting: Diesel Generator Fuel Oil Storage Tank Cleaning/Inspection, June 1, 2023 ML23130A0912023-05-11011 May 2023 TVA Browns Ferry Nuclear Plant Safety Pre-Application Public Meeting Slides 05/11/2023 ML23130A0922023-05-11011 May 2023 NRC Browns Ferry Nuclear Plant, Units 1, 2, and 3, Subsequent License Renewal Application, Public Meeting Slides ML23128A2882023-05-0808 May 2023 TVA Nuclear Plants -2022 EOC Media Slides ML23025A0472023-01-25025 January 2023 Pre-Submittal Meeting for Proposed License Amendment Request Regarding Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves - January 25, 2023 ML22285A1902022-10-13013 October 2022 October 13, 2022 Public Meeting on 5th Interval Alternative Planned Requests - Licensee Slides ML22279A8992022-10-0606 October 2022 Subsequent License Renewal Application - SAMA Pre-Application Meeting October 6, 2022-TVA Slides ML22277A6562022-10-0606 October 2022 Subsequent License Renewal Application - SAMA Pre-Application Meeting October, 2022 (TVA Slides) ML22264A2332022-09-22022 September 2022 Slides for Pre-Submittal Meeting for Request to Use a Later Edition of the ASME OM Code for the Fifth Inservice Testing (IST) 10-Year Interval ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22216A0062022-08-31031 August 2022 ECCS Strainer LAR Pre-Submittal Presentation Material ML22187A0652022-06-0808 June 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - NRC Presentation Slides ML22091A1332022-04-0101 April 2022 Bru Har Combined 2021 Assessment Meeting Slides ML22080A1662022-03-21021 March 2022 TVA Nuclear Plants -2021 EOC Media Loop Slides for Automatic Play ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21281A2282021-10-13013 October 2021 Tennessee Valley Authority Fleet Pre-Submittal Meeting for License Amendment Request to Change Emergency Action Level Scheme Presentation - October 13, 2021 (EPID L-2021-LRM-0096) (Slides) ML21270A0322021-09-27027 September 2021 Presentation Slides for Browns Ferry Pre-submittal Public Meeting September 27, 2021 ML21265A0422021-09-21021 September 2021 Presentation Slides for Browns Ferry Pre-submittal Public Meeting 09/22/2021 ML21250A3012021-09-0707 September 2021 TVA Slides for September 7, 2021, Presubmittal Meeting to Discuss Planned Browns Ferry TSTF-505 License Amendment Request ML21183A1072021-07-0202 July 2021 2020 Fermi Power Plant End-of-Cycle Meeting Presentation ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21152A1872021-06-0101 June 2021 TVA Slides for June 1, 2021, Presubmittal Meeting to Discuss Planned Control Bay Chiller Cross-Tie License Amendment Request ML21125A0372021-05-0606 May 2021 May 6, 2021 Public Meeting (Observation) Slides for RAP Back Program Presentation to Industry(003) ML21041A4532021-02-17017 February 2021 Brunswick/Nrc Pre-submittal Meeting: LAR to Adopt TSTF-505, Rev. 2 (Risk-Informed Completion Times) Presentation ML21011A0822021-01-12012 January 2021 Pre-Submittal Meeting January 12, 2021, Revision to VRR-01, Full Stroke Testing of Safety/Relief Valves - Presentation Material ML24019A1322020-11-0909 November 2020 ANP-3874NP, Revision 1, Browns Ferry Atrium 11 Control Rod Drop Accident Analysis with the AURORA-B CRDA ML20269A3452020-09-28028 September 2020 Pre-submittal Meeting for Request for One-Time Exemption from 10 CFR Part 50, Appendix E, Biennial EP Exercise (Offsite) Due to COVID-19- Entergy Presentation Slides ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20241A1672020-08-28028 August 2020 2019 Fermi Unit 2 EOC Virtual Meeting Presentation ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20175A0552020-06-23023 June 2020 TVA Slides for June 23, 2020, Emergency Plan Change Presubmittal Meeting ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20156A2812020-06-0808 June 2020 TVA Slides for June 8, 2020, ATRIUM-11 Presubmittal Meeting ML20100G6342020-04-0909 April 2020 Revised- Bru 2019 Annual Assessment Meeting Slides ML20092F5742020-04-0202 April 2020 TVA Slides for Browns Ferry 50.69 License Amendment Request Presubmittal Meeting ML20080M1582020-02-21021 February 2020 PFHA-2020-3B-3-Vossmar_Stafford-2019_CNS_FCS_Flooding ADAMS Version ML20049G1822020-02-18018 February 2020 February 20, 2020 - Pre-submittal Meeting Presentation - Transition to Westinghouse Fuel 2024-02-07
[Table view] |
Text
PUBLIC MEETING WITH BOILING WATER REACTOR OWNERS GROUP Target Rock Safety Relief Valve Setpoint Drift Issue for Boiling Water Reactors September 12, 2018 1
Agenda
- Technical Specification (TS) Compliance
- Industry Actions Considered in Past
- Boiling Water Reactor Owners Group (BWROG)
Feedback 2
Background
Purpose:
To discuss Target Rock 2-stage SRV setpoint drift issue for boiling water reactors (BWRs).
- Licensees continue to experience a large number of surveillance test failures with 2-stage Target Rock SRVs.
- Typically TSs allow only one SRV failure.
- TS operability allowance for setpoint drift for most plants is +/-3 percent.
- As found setpoint drift for a number of BWRs ranges between +3 to +10 percent.
- Most significant instance being a setpoint drift of +18.5 percent.
3
Background (cont.)
- Originally, the issue was addressed by Generic Safety Issue (GSI) B-55, Improved Reliability of Target Rock Safety Relief Valves.
- GSI B-55 concluded the following:
- Safety significance is low.
- Industry was already pursuing actions to correct the setpoint drift.
- Staff was satisfied with industry actions to resolve issue.
- Regulations already require licensees to correct the setpoint drift (no new regulatory requirements are needed).
- Therefore, GSI B-55 was closed in December 1999.
4
SRV Design Function
- The SRVs are part of the nuclear pressure relief system and, in part, prevent overpressurization of the nuclear process barrier.
- A select number of SRVs are used by the automatic depressurization system (ADS) to rapidly decrease reactor pressure during specific small-break loss-of-coolant accidents during loss of high-pressure injection scenarios.
- The setpoint drift issue does not affect the ADS function.
5
Safety Significance The NRC staff reviewed the licensee event reports (LERs) considering the following design aspects for determining the safety significance for SRVs that do not open at their expected setpoints:
- ASME Code pressure/service limits on the primary system.
- Hydrodynamic loads on SRV discharge piping.
- Performance of high-pressure injection systems.
6
Safety Significance (cont.)
Based on the review of LERs, the NRC staff determined the safety significance associated with Target Rock 2-stage setpoint drift to be low.
7
TS Compliance
- In the Standard Technical Specifications for General Electric BWR plants, Limiting Condition for Operation (LCO) 3.4.3 states: The safety function of [11] S/RVs shall be OPERABLE.
- SR 3.4.3.1 states: Verify the safety function lift setpoints of the [required] S/RVs are within a specified range.
- Surveillance Requirement 3.0.1 states that [f]ailure to meet a Surveillance, whether such failure is experienced during the performance of the Surveillance or between performances of the Surveillance, shall be failure to meet the LCO.
8
TS Compliance (cont.)
& Functionality Assessments for Conditions Adverse to Quality or Safety, if there is not a reasonable expectation of operability, the SRVs should not be considered operable.
- NRC staff considers the repeated failure of Target Rock SRVs a challenge to a reasonable expectation of operability. This could lead to determination of inoperability and non-compliance with TSs.
9
Past Industry Actions Industry has identified corrosion-induced oxide bonding to be the cause of the current setpoint drift issue for 2-stage Target Rock SRVs. The licensees have tried the following options since the closure of GSI B-55, but with limited success:
- Application of platinum coatings to SRV pilot valve discs.
- Enhanced SRV insulation to reduce corrosion and improve reliability.
- Return to modified Target Rock 3-stage SRV (subject to downward setpoint drift concerns).
10
Next Steps
- Based on the history of Target Rock SRV setpoint drift, the NRC staff has determined that this potential TS non-compliance issue needs to be addressed in a timely fashion.
- NRC staff will coordinate with licensees as they work to determine a path towards restoring reasonable assurance of operability for this low safety significance issue.
- The NRC staff is considering enforcement discretion guidance, among other options, for resolution of the issue in a reasonable time frame.
11
BWROG Feedback
- The NRC staff would like the BWROG to address potential corrective actions being considered for a timely resolution.
- Based on the past history of repeated failures, what is the confidence level that corrections actions being considered are likely to succeed and why?
- What is the expected time frame for the industry to demonstrate reasonable assurance of operability and TS compliance?