JAFP-18-0050, Report of Full Compliance with Phase 1 & Phase 2 of 06/06/2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)

From kanterella
(Redirected from ML18240A002)
Jump to navigation Jump to search

Report of Full Compliance with Phase 1 & Phase 2 of 06/06/2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)
ML18240A002
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 08/28/2018
From: Jim Barstow
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-13-109, JAFP-18-0050, RS-18-066
Download: ML18240A002 (77)


Text

Exelon Generation .

JAFP-18-0050 Order No. EA-13-109 RS-18-066 August 28, 2018 U.S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, DC 20555-0001 James A. FitzPatrick Nuclear Power Plant Renewed Facility Operating License No. DPR-59 NRG Docket No. 50-333

Subject:

Report of Full Compliance with Phase 1 and Phase 2 of June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109)

References:

1. NRG Order Number EA-13-109, "Issuance of Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," dated June 6, 2013
2. NRG Interim Staff Guidance JLD-ISG-2015-01, "Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," Revision 0, dated April 2015
3. NEI 13-02, "Industry Guidance for Compliance With Order EA-13-109, BWR Mark I & II Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions", Revision 1, dated April 2015
4. James A. FitzPatrick Nuclear Power Plant Phase 1 Overall Integrated Plan per Order EA-13-109 Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions, dated June 30, 2014 (JAFP-14-0075)
5. James A. FitzPatrick Nuclear Power Plant First Six-Month Status Report Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated December 19, 2014 (JAFP-14-0146)
6. James A. FitzPatrick Nuclear Power Plant Second Six-Month Status Report Phase 1 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 30, 2015 (JAFP-15-0080)

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 2

7. James A. FitzPatrick Nuclear Power Plant Third Six-Month Status Report Phase 1 (Updated) and Phase 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA 109), dated December 15, 2015 (JAFP-15-0148)
8. James A. FitzPatrick Nuclear Power Plant Fourth Six-Month Status Report For Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 30, 2016 (JAFP-16-0111)
9. James A. FitzPatrick Nuclear Power Plant Fifth Six-Month Status Report For Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated December 22, 2016 (JAFP-16-0192) 1O. James A. FitzPatrick Nuclear Power Plant Sixth Six-Month Status Report For Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated June 29, 2017 (JAFP-17-0063)
11. James A. FitzPatrick Nuclear Power Plant Seventh Six-Month Status Report For Phases 1 and 2 Overall Integrated Plan in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109), dated December 15, 2017 (JAFP-17-0116)
12. NRC letter to James A. FitzPatrick Nuclear Power Plant - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 1 of Order EA-13-109 (Severe Accident Capable Hardened Vents), dated February 12, 2015
13. NRC letter to James A. FitzPatrick Nuclear Power Plant - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 2 of Order EA-13-109 (Severe Accident Capable Hardened Vents), dated December 16, 2016
14. NRC letter to Exelon Generation Company, LLC, James A. FitzPatrick Nuclear Power Plant - Report for the Audit of Licensee Responses to Interim Staff Evaluation Open Items Related to NRC Order EA-13-109 to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions, dated June 21, 2018 On June 6, 2013, the Nuclear Regulatory Commission ("NRC" or "Commission") issued Order EA-13-109, "Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," (Reference 1) to James A.

FitzPatrick Nuclear Power Plant (JAF). Reference 1 was immediately effective and directs JAF to take certain actions to ensure that JAF has a hardened containment vent system (HCVS) to remove decay heat from the containment, and maintain control of containment pressure within acceptable limits following events that result in loss of active containment heat removal capability while maintaining the capability to operate under severe accident (SA) conditions resulting from an Extended Loss of AC Power (ELAP). Specific requirements are outlined in of Reference 1.

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 3 Reference 2 provided the NRG interim staff guidance on methodologies for compliance with Phases 1 and 2 of Reference 1 and endorsed industry guidance document NEI 13-02, Revision 1 (Reference 3) with clarifications and exceptions. Reference 4 provided the JAF Phase 1 Overall Integrated Plan (OIP), which was replaced with the Phase 1 (Updated) and Phase 2 OIP (Reference 7). References 12 and 13 provided the NRG review of the Phase 1 and Phase 2 OIP, respectively, in an Interim Staff Evaluation (ISE).

Reference 1 required submission of a status report at six-month intervals following submittal of the OIP. References 5, 6, 7, 8, 9, 1O, and 11 provided the first, second, third, fourth, fifth, sixth, and seventh six-month status reports, respectively, pursuant to Section IV, Condition D.3, of Reference 1 for JAF.

The purpose of this letter is to provide the report of full compliance with Phase 1 and Phase 2 of the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order Number EA-13-109) (Reference 1) pursuant to Section IV, Condition D.4 of the Order for JAF.

JAF has designed and installed a venting system that provides venting capability from the wetwell during severe accident conditions in response to Phase 1 of NRG Order EA-13-109.

JAF has implemented a reliable containment venting strategy that makes it unlikely that the plant would need to vent from the containment drywell before alternative reliable containment heat removal and pressure control is reestablished in response to Phase 2 of NRG Order EA-13-109.

JAF Phase 2 OIP Open Items have been addressed and closed as documented in Reference 11 and are considered complete per Reference 14. There were no Phase 1 01 P Open Items. The information provided herein documents full compliance for JAF with NRG Order EA-13-109.

JAF's response to the NRG Interim Staff Evaluation (ISE) Phase 1 Open Items identified in Reference 12 have been addressed and closed as documented in Reference 11, and below, and are considered complete per Reference 14. The following table provides completion references for each OIP and ISE Phase 1 Open Item.

Reference 14 provided the results of the audit of ISE Open Item closure information provided in Reference 11, and below. All Phase 1 and Phase 2 ISE Open Items are statused as closed in Reference 14.

ISE Phase 1 Open Item No. 1 Closed per Reference 11 Make available for NRC staff audit analyses demonstrating that HCVS has the capacity to vent the steam/energy equivalent of one (1) percent of licensed/rated thermal power (unless a lower value is justified), and that the suppression pool and the HCVS together are able to absorb and reject decay heat, such that following a reactor shutdown from full power containment pressure is restored and then maintained below the primary containment

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 4 design pressure and the primary containment pressure limit.

ISE Phase 1 Open Item No. 2 Closed per Reference 11 Make available for NRC staff audit the seismic and tornado missile final design criteria for the HCVS stack.

ISE Phase 1 Open Item No. 3 Closed per Reference 11 Make available for NRC staff audit the final sizing evaluation for HCVS batteries/battery charger including incorporation into FLEX DG loading calculation.

ISE Phase 1 Open Item No. 4 Closed per Reference 11 Make available for NRC staff audit documentation of the HCVS nitrogen pneumatic system design including sizing and location.

ISE Phase 1 Open Item No. 5 Closed per Reference 11 Provide a description of the final design of the HCVS to address hydrogen detonation and deflagration.

ISE Phase 1 Open Item No. 6 Closed per Reference 11 Provide a description of the strategies for hydrogen control that minimizes the potential for hydrogen gas migration and ingress into the reactor building or other buildings.

ISE Phase 1 Open Item No. 7 The required instrumentation and controls (existing and new) are Make available for NRC staff audit descriptions of all identified as part of the JAF OIP, Part instrumentation and controls (existing and planned) 2. Plant instrumentation for HCVS that necessary to implement this order including is qualified to RG 1.97 or equivalent is qualification methods. considered qualified for the sustained operating period without further evaluation. The following plant instruments and controls are qualified to RG 1.97:

  • Torus Valve Limit Switches:

27PNS-117-1, 27PNS-117-2, 27PNS-118-1, 27PNS-118-2 The following additional

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 5 instrumentation and controls performing a HCVS function is considered for temperature and radiation effects:

  • HCVS Control Valve Limit Switches
  • HCVS Temperature Instrument
  • HCVS Radiation Instrument
  • HCVS Battery Charger
  • HCVS Indicators The environmental qualification of the existing and new HCVS specific equipment has been summarized in Attachment 6.009 to EC 52721 along with the referenced reports and Topic Notes sections.

Temperature Temperatures within the Reactor Building are calculated in JAF-CALC-15-00025. Temperatures within the Administration Building and Battery Room are evaluated in Topic Notes Section 3.1.11.2 based on FLEX heatup calculation JAF-CALC 000025.

Radiation Specific HCVS dose values are calculated in calculation JAF-CALC-14-00029.

These documents have been provided in the eportal.

ISE Phase 1 Open Item No. B The existing equipment supporting HCVS is seismically qualified. The new Make available for NRC staff audit documentation of a seismic qualification evaluation of HCVS HCVS equipment is seismically robust components. as discussed in Topic Notes Sections 3.1 .5.1 and 3.1.6.2, which is supported by the following reports I calculations:

  • JAF-RPT-17-00029 "Hardened Containment Vent System Equipment Seismic Evaluations"

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 6 Control Valve, 27 AOV-142, 1O" 150 Tricentric with Bettis Op Design I Seismic Report, Weak Link Analysis, Maximum Torque Calculation"

Actuator/Limit Switch Qualification Reports"

Instrumentation and Battery System Seismic Qualification" These documents have been provided in the eportal.

ISE Phase 1 Open Item No. 9 The requ ired instrumentation and controls (existing and new) are Make available for NRC staff audit the descriptions identified as part of the JAF OIP, Part of local conditions (temperature, radiation and 2. The environmental qualification of humidity) anticipated during ELAP and severe the existing and new HCVS specific accident for the components (valves , equipment has been summarized in instrumentation , sensors, transmitters, indicators , Attachment 6.009 to EC 52721 along electronics , control devices, etc.) required for HCVS with the referenced reports and Topic venting including confirmation that the components Notes sections. See additional are capable of performing their functions during discussion in ISE Open Item 7.

ELAP and severe accident conditions.

These documents have been provided in the eportal.

ISE Phase 1 Open Item No. 1O Closed per Reference 11 Make available for NRC staff audit documentation of an evaluation verifying the existing containment isolation valves, relied upon for the HCVS, will open under the maximum expected differential pressure during BDBEE and severe accident wetwell venting.

ISE Phase 1 Open Item No. 11 Closed per Reference 11 Make available for NRC staff audit documentation that demonstrates adequate communication between the remote HCVS operation locations and HCVS decision makers during ELAP and severe accident conditions.

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 7 ISE Phase 1 Open Item No. 12 Closed per Reference 11 Make available for NRC staff audit an evaluation of temperature and radiological conditions to ensure that operating personnel can safely access and operate controls and support equipment.

JAF's response to the NRG Interim Staff Evaluation (ISE) Phase 2 Open Items identified in Reference 13 have been addressed and closed as documented in Reference 11 and are considered complete per Reference 14. The following table provides completion references for each OIP and ISE Phase 2 Open Item.

OIP Phase 2 Open Item No. 1 Closed per Reference 11 Complete hydraulic analysis of diesel fire pump for SAWA I SAWM flowrates .

OIP Phase 2 Open Item No. 2 Closed per Reference 11 Identify and evaluate severe accident conditions for Phase 2 manual actions.

OIP Phase 2 Open Item No. 3 Closed per Reference 11 The FLEX Engineering Change (EC 52736) has not been completed; therefore, any reference to this information is considered unverified.

ISE Phase 2 Open Item No. 1 Closed per Reference 11 utilizing BWROG generic response template.

Licensee to evaluate the SAWA equipment and controls, as well as the ingress and egress paths for the expected severe accident conditions (temperature, humidity, radiation) for the sustained operating period.

ISE Phase 2 Open Item No. 2 Closed per Reference 11 utilizing BWROG generic response template.

Licensee to demonstrate how instrumentation and equipment being used for SAWA and supporting equipment is capable to perform for the sustained operating period under the expected temperature and radiological conditions.

ISE Phase 2 Open Item No. 3 Closed per Reference 11 utilizing BWROG generic response template.

Licensee to demonstrate that containment failure as a result of overpressure can be prevented without a drywell vent during severe accident conditions.

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August 28, 2018 Page 8 ISE Phase 2 Open Item No. 4 Closed per Reference 11 utilizing BWROG generic response template.

Licensee to demonstrate that there is adequate communication between the primary HCVS operating station and the operator at the FLEX supply hose splitter valve during severe accident conditions.

ISE Phase 2 Open Item No. 5 Closed per Reference 11 utilizing BWROG generic response template.

Licensee to demonstrate the SAW A/SAWM flow instrumentation qualification for the expected environmental conditions.

MILESTONE SCHEDULE - ITEMS COMPLETE JAF - Phase 1 Specific Milestone Schedule Milestone Completion Date Hold preliminary/conceptual design meeting January 2014 Submit Overall Integrated Implementation Plan June 2014 Submit 6 Month Status Report December 2014 Submit 6 Month Status Report June 2015 Submit 6 Month Status Report December 2015 Design Engineering Complete December 2015 Submit 6 Month Status Report June 2016 Submit 6 Month Status Report December 2016 Submit 6 Month Status Report June 2017 Submit 6 Month Status Report December 2017 Operations and Maintenance Procedure Changes June 2018 Developed, Training Complete Walk-Through Demonstration/Functional Test June 2018 HCVS Phase 1 Complete June 29, 2018 Submit Completion Report Complete with this submittal

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 9 JAF - Phase 2 Specific Milestone Schedule Milestone Completion Date Hold preliminary/conceptual design meeting October 2015 Submit Overall Integrated Implementation Plan December 2015 Submit 6 Month Status Report June 2016 Submit 6 Month Status Report December 2016 Submit 6 Month Status Report June 2017 Design Engineering Complete October 2017 Submit 6 Month Status Report December 2017 Maintenance and Operations Procedure Changes Developed, June 2018 Training Complete Implementation June 2018 Walk-Through Demonstration/Functional Test June 2018 HCVS Phase 2 Complete June 29, 2018 Submit Completion Report Complete with this submittal ORDER EA-13-109 COMPLIANCE ELEMENTS

SUMMARY

The elements identified below for JAF, as well as the Phase 1 (Updated) and Phase 2 OIP response submittal (Reference 7), and the 6-Month Status Reports (References 5, 6, 7, 8, 9, 1O, and 11 ), demonstrate compliance with NRG Order EA-13-109. The JAF Final Integrated Plan for reliable hardened containment vent Phase 1 and Phase 2 strategies is provided in the enclosure to this letter.

HCVS PHASE 1 AND PHASE 2 FUNCTIONAL REQUIREMENTS AND DESIGN FEATURES-COMPLETE The JAF Phase 1 HCVS provides a vent path from the wetwell to remove decay heat, vent the containment atmosphere, and control containment pressure within acceptable limits. The Phase 1 HCVS will function for those accident conditions for which containment venting is relied upon to reduce the probability of containment failure, including accident sequences that result in the loss of active containment heat removal capability during an extended loss of alternating current power.

The JAF Phase 2 HCVS provides a reliable containment venting strategy that makes it unlikely that the plant would need to vent from the containment drywall before alternative reliable containment heat removal and pressure control is reestablished. The JAF Phase 2 HCVS strategies implement Severe Accident Water Addition (SAWA) with Severe Accident Water Management (SAWM) as an alternative venting strategy. This

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 10 strategy consists of the use of the Phase 1 wetwell vent and SAWA hardware to implement a water management strategy that will preserve the wetwell vent path until alternate reliable containment heat removal can be established.

The JAF Phase 1 and Phase 2 HCVS strategies are in compliance with Order EA-13-109. The modifications required to support the HCVS strategies for JAF have been fully implemented in accordance with the station processes.

HCVS PHASE 1 AND PHASE 2 QUALITY STANDARDS - COMPLETE The design and operational considerations of the Phase 1 and Phase 2 HCVS installed at JAF complies with the requirements specified in the Order and described in NEI 13-02, Revision 1, "Industry Guidance for Compliance with Order EA-13-109". The Phase 1 and Phase 2 HCVS has been installed in accordance with the station design control process.

The Phase 1 and Phase 2 HCVS components including piping, piping supports, containment isolation valves, containment isolation valve actuators and containment isolation valve position indication have been designed consistent with the design basis of the plant. All other Phase 1 and Phase 2 HCVS components including electrical power supply, valve actuator pneumatic supply and instrumentation have been designed for reliable and rugged performance that is capable of ensuring Phase 1 and Phase 2 HCVS functionality following a seismic event.

HCVS PHASE 1 AND PHASE 2 PROGRAMMATIC FEATURES - COMPLETE Storage of portable equipment for JAF Phase 1 and Phase 2 HCVS use provides adequate protection from applicable site hazards, and identified paths and deployment areas will be accessible during all modes of operation and during severe accidents, as recommended in NEI 13-02, Revision 1, Section 6.1.2.

Training in the use of the Phase 1 and Phase 2 HCVS for JAF has been completed in accordance with an accepted training process as recommended in NEI 13-02, Revision 1, Section 6.1.3.

Operating and maintenance procedures for JAF have been developed and integrated with existing procedures to ensure safe operation of the Phase 1 and Phase 2 HCVS.

Procedures have been verified and are available for use in accordance with the site procedure control program.

Site processes have been established to ensure the Phase 1 and Phase 2 HCVS is tested and maintained as recommended in NEI 13-02, Revision 1, Sections 5.4 and 6.2.

JAF has completed validation in accordance with industry developed guidance to assure required tasks, manual actions and decisions for HCVS strategies are feasible and may be executed within the constraints identified in the HCVS Phases 1 and 2 OIP for Order EA-13-109 (Reference 7).

U.S. Nuclear Regulatory Commission Report of Full Compliance with Order EA-13-109 August28,2018 Page 11 JAF has completed evaluations to confirm accessibility, habitability, staffing sufficiency, and communication capability in accordance with NEI 13-02, Revision 1, Sections 4.2.2 and 4.2.3.

This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David J. Distel at 610-765-5517.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 281h day of August 2018.

Respectfully submitted, James Barstow Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

James A. FitzPatrick Nuclear Power Plant Final Integrated Plan Document -

Hardened Containment Vent System NRC Order EA-13-109 cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region I NRC Senior Resident Inspector- James A. FitzPatrick Nuclear Power Plant NRC Project Manager, NRR - James A. FitzPatrick Nuclear Power Plant Mr. Peter J. Bamford, NRR/JLD/JOMB, NRC Mr. Brian E. Lee, NRR/JLD/JCBB, NRC Mr. Rajender Auluck, NRR/JLD/JCBB, NRC NYSPSC NYSERDA

Enclosure James A. FitzPatrick Nuclear Power Plant Final Integrated Plan Document- Hardened Containment Vent System NRG Order EA-13-109 (62 pages)

Final Integrated Plan HCVS Order EA-13-109 for James A. FitzPatrick Nuclear Power Plant August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Table of Contents Section I: Introduction ............................................................................................................... 1 Section I.A: Summary of Compliance .................................................................................... 3 Section I.A.1: Summary of Phase 1 Compliance ................................................................ 3 Section I.A.2: Summary of Phase 2 Compliance ................................................................ 3 Section II: List of Acronyms ....................................................................................................... 5 Section III: Phase 1 Final Integrated Plan Details ....................................................................... 8 Section III.A: HCVS Phase 1 Compliance Overview............................................................... 8 Section III.A.1: Generic Letter 89-16 Vent System ............................................................. 8 Section III.A.2: EA-13-109 Hardened Containment Vent System (HCVS) .......................... 8 Section III.B: HCVS Phase 1 Evaluation Against Requirements: ...........................................11

1. HCVS Functional Requirements .................................................................................12
2. HCVS Quality Standards:............................................................................................26 Section IV: HCVS Phase 2 Final Integrated Plan ......................................................................27 Section IV.A: The requirements of EA-13-109, Attachment 2, Section B for Phase 2............27
1. HCVS Drywell Vent Functional Requirements .............................................................28
2. Containment Venting Strategy Requirements .............................................................28 Section IV.B: HCVS Existing System ....................................................................................28 Section IV.C: HCVS Phase 2 SAWA System and SAWM Strategy .......................................29 Section IV.C.1: Detailed SAWA Flow Path Description ......................................................29 Section IV.C.2: Severe Accident Assessment of Flow Path ...............................................30 Section IV.C.3: Severe Accident Assessment of Safety-Relief Valves................................31 Section IV.C.4: Available Freeboard Use ...........................................................................31 Section IV.C.5: Upper range of Torus level indication ........................................................31 Section IV.C.6: Torus vent service time .............................................................................31 Section IV.C.7: Strategy time line ......................................................................................32 Section IV.C.8: SAWA Flow Control ..................................................................................32 Section IV.C.9: SAWA/SAWM Element Assessment .........................................................32 Section IV.C.10: SAWA/SAWM Instrumentation ...............................................................34 Section IV.C.11: SAWA/SAWM Severe Accident Considerations .....................................36 Section V: HCVS Programmatic Requirements.........................................................................38 Section V.A: HCVS Procedure Requirements.......................................................................38 Section V.B: HCVS Out of Service Requirements .................................................................40 Section V.C: HCVS Training Requirements ..........................................................................41 Section V.D: Demonstration with other Post Fukushima Measures ......................................41 Revision 0 Page ii August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section VI: References .........................................................................................................43 : Phase 2 Freeboard diagram ..............................................................................47 : One Line Diagram of HCVS Vent Path ..............................................................48 : One Line Diagram of HCVS Electrical Power Supply ........................................49 : One Line Diagram of SAWA Flow Path .............................................................50 A: One Line Diagram of (FLEX) Electrical Power Supply .....................................51 B: One Line Diagram of (FLEX) Electrical Power Supply .....................................52 : Plant Layout Showing Operator Action Locations ..............................................53 A: Reactor Building Elevation 272 Manual Action Locations ................................54 B: Reactor Building Elevation 344 / 369-6 HCVS / FLEX Manual Actions ..........55 C: FLEX Hose Connection for RPV Injection (Screenwell Elevation 260) ............56 Table 1: List of HCVS Component, Control and Instrument Qualifications ...............................57 Table 2: Operator Actions Evaluation .......................................................................................59 Revision 0 Page iii August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section I: Introduction In 1989, the NRC issued Generic Letter 89-16, Installation of a Hardened Wetwell Vent, (Reference 1) to all licensees of BWRs with Mark I containments to encourage licensees to voluntarily install a hardened wetwell vent. In response, licensees installed a hardened vent pipe from the wetwell to some point outside the secondary containment envelope (usually outside the reactor building). Some licensees also installed a hardened vent branch line from the drywell.

On March 19, 2013, the Nuclear Regulatory Commission (NRC) Commissioners directed the staff per Staff Requirements Memorandum (SRM) for SECY-12-0157, Consideration of Additional Requirements for Containment Venting Systems for Boiling Water Reactors with Mark I and Mark II Containments (References 2 and 3) to require licensees with Mark I and Mark II containments to "upgrade or replace the reliable hardened vents required by Order EA-12-050, Order to Modify Licenses with Regard to Reliable Hardened Containment Vents (Reference 4) with a containment venting system designed and installed to remain functional during severe accident conditions." In response, the NRC issued Order EA-13-109, Issuance of Order to Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accidents, June 6, 2013 (Reference 5). The Order (EA-13-109) requires that licensees of BWR facilities with Mark I and Mark II containment designs ensure that these facilities have a reliable hardened vent to remove decay heat from the containment, and to maintain control of containment pressure within acceptable limits following events that result in the loss of active containment heat removal capability while maintaining the capability to operate under severe accident (SA) conditions resulting from an Extended Loss of AC Power (ELAP).

James A. FitzPatrick Nuclear Power Plant (JAF) is required by NRC Order EA-13-109 to have a reliable, severe accident capable hardened containment venting system (HCVS).

Order EA-13-109 allows implementation of the HCVS Order in two phases.

  • Phase 1 upgraded the venting capabilities from the containment wetwell to provide reliable, severe accident capable hardened vent to assist in preventing core damage and, if necessary, to provide venting capability during severe accident conditions. JAF achieved Phase 1 compliance in June 2018.
  • Phase 2 provided additional protections for severe accident conditions through the development of a reliable containment venting strategy that makes it unlikely that JAF would need to vent from the containment drywell during severe accident conditions.

JAF achieved Phase 2 compliance in June 2018.

NEI developed guidance for complying with NRC Order EA-13-109 in NEI 13-02, Industry Guidance for Compliance with Order EA-13-109, BWR Mark I & II Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions, Revision 0 (Reference 6) with significant interaction with the NRC and Licensees. NEI issued Revision 1 to NEI 13-02 in April 2015 (Reference 7) which contained guidance for Revision 0 Page 1 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 compliance with both Phase 1 and Phase 2 of the order. NEI 13-02, Revision 1 also includes HCVS- Frequently Asked Questions (FAQs) 01 through 09 and reference to white papers (HCVS-WP-01 through 03 (References 8 through 10)). The NRC endorsed NEI 13-02 Revision 0 as an acceptable approach for complying with Order EA-13-109 through Interim Staff Guidance JLD-ISG-2013-02, Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions, issued in November 2013 (Reference 12) and JLD-ISG-2015-01, Compliance with Order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions issued in April 2015 (Reference 13) for NEI 13-02 Revision 1 with some clarifications and exceptions. NEI 13-02 Revision 1 provides an acceptable method of compliance for both Phases of Order EA-13-109.

In addition to the endorsed guidance in NEI 13-02, the NRC staff endorsed several other documents that provide guidance for specific areas. HCVS-FAQs 10 through 13 (References 14 through 17) were endorsed by the NRC after NEI 13-02 Revision 1 on October 8, 2015. NRC staff also endorsed four White Papers, HCVS-WP-01 through 04 (References 8 through 11), which cover broader or more complex topics than the FAQs.

As required by the order, JAF submitted a phase 1 Overall Integrated Plan (OIP) in June of 2014 (Reference 18) and subsequently submitted a Phase 2 OIP in December 2015 (Reference 19). These OIPs followed the guidance NEI 13-02 Revision 0 and 1 respectively, Compliance with Order EA-13-109, Severe Accident Reliable Hardened Containment Vents. The NRC staff used the methods described in the ISGs to evaluate licensee compliance as presented in the Order EA-13-109 OIPs. While the Phase 1 and combined Phase 1 and 2 OIPs where written to different revisions of NEI 13-02, JAF conformed to NEI 13-02 Revision 1 for both Phases of Order EA-13-109.

The NRC performed a review of each OIP submittal and provided JAF with Interim Staff Evaluations (ISEs) (References 20 and 21) assessing the sites compliance methods.

In the ISEs the NRC identified open items which the site needed to address before that phase of compliance was reached. Six-month progress reports (References 22 through

28) were provided consistent with the requirements of Order EA-13-109. These status reports were used to close many of the ISE open items. In addition, the site participated in NRC ISE Open Item audit calls where the information provided in the six-month updates and on the E-Portal were used by the NRC staff to determine whether the ISE Open Item appeared to be addressed.

By submittal of this Final Integrated Plan JAF has addressed all the elements of NRC Order EA-13-109 utilizing the endorsed guidance in NEI 13-02, Revision 1 and the related HCVS-FAQs and HCVS-WPs documents. In addition, the site has addressed the NRC Phase 1 and Phase 2 ISE Open Items as documented in previous six-month updates.

Section III contains the JAF Final Integrated Plan details for Phase 1 of the Order. Section IV contains the Final Integrated Plan details for Phase 2 of the Order. Section V details Revision 0 Page 2 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 the programmatic elements of compliance.

Section I.A: Summary of Compliance Section I.A.1: Summary of Phase 1 Compliance The plant venting actions for the EA-13-109, Phase 1, severe accident capable venting scenario can be summarized by the following:

The HCVS is initiated via manual action from the Remote Operating Station (ROS) at the appropriate time based on procedural guidance in response to plant conditions from observed or derived symptoms.

  • The vent utilizes containment parameters of pressure and level from the MCR instrumentation to monitor effectiveness of the venting actions.
  • The vent operation is monitored by HCVS valve position, temperature and effluent radiation levels.
  • The HCVS motive force is monitored and has the capacity to operate for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> with installed equipment. Replenishment of the motive force will be by use of portable equipment once the installed motive force is exhausted.
  • Venting actions are capable of being maintained for a sustained period of at least 7 days.

The operation of the HCVS is designed to minimize the reliance on operator actions in response to external hazards. The screened in external hazards for JAF are seismic, external flooding, high winds, extreme high temperature, and extreme cold (including ice and snow). Initial operator actions are completed by plant personnel and include the capability for remote-manual initiation from the HCVS control station. Depending on the plant status at the time of the accident, actions may be required within the Reactor Building to align specific valves to the closed position. Monitoring of the containment is from the Main Control Room (MCR). The ROS at JAF is the only location for operation and monitoring of the HCVS System with communication to the MCR. Attachment 2 contains a one-line diagram of the HCVS vent flowpath.

Section I.A.2: Summary of Phase 2 Compliance The Phase 2 actions can be summarized as follows:

  • Utilization of Severe Accident Water Management (SAWM) to control injection and Suppression Pool level to ensure the HCVS Phase 1 Torus vent will remain functional for the removal of heat from the containment.

Revision 0 Page 3 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109

  • Heat can be removed from the containment for at least seven (7) days using the HCVS or until alternate means of heat removal are established that make it unlikely the drywell vent will be required for containment pressure control.
  • The SAWA and SAWM actions can be manually activated and controlled from areas that are accessible during severe accident conditions.
  • Parameters measured are drywell pressure, Torus level, SAWA flowrate and the HCVS Phase 1 vent path parameters.

The locations of the SAWA equipment and controls, as well as ingress and egress paths have been evaluated for the expected severe accident conditions (temperature, humidity, radiation) for the Sustained Operating period. Equipment has been evaluated to remain operational throughout the Sustained Operating period. Personnel radiological exposure, temperature and humidity conditions for operation of SAWA equipment will not exceed the limits for ERO dose or plant safety guidelines for temperature and humidity.

The FLEX primary and secondary injection flow paths were switched as the secondary pathway offered the advantage of reduced operator dose exposure and burden. As a result, the primary FLEX pathway and SAWA injection pathway are the same. To support this change, (a) new permanent plant piping connections were installed for ease of connection, (b) permanent platforms installed for operation of manual isolation valves in the Screenwell / Reactor Building, and (c) portable throttling valve manifolds installed (including the FLEX/SAWA flow meter) were provided to support the range of FLEX and SAWA flow rates. The new carts are located within the basement of the Screenwell local to the Fire Protection and Residual Heat Removal Service Water (RHRSW) pipeline connections. This modified flow path has been evaluated and found to be acceptable in calculation JAF-CALC-17-00104 (Reference 36).

The FLEX primary (SAWA) pump is the permanently installed Diesel Driven Fire Pump (DDFP) 76P-4 which takes suction from Lake Ontario. A new permanent plant hose quick connection at the discharge of pump 76P-4 is connected via portable hose and quick connections to the new throttling valve cart where SAWA flow indication and control is provided. The outlet of the new throttling valve cart is connected via portable hose to new permanent fire hose quick connections downstream of the RHRSW pump strainer. To complete the flowpath, valves are then modulated as follows:

  • 76FPS-807 (Manually closed via permanent platform)

(Note: 10MOV-27B is normally open)

Revision 0 Page 4 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Backflow prevention is provided by installed containment isolation check valve 10AOV-68B. Cross flow into other portions of the RHR system is prevented using normally closed valves. Communication will be established between the MCR and the SAWA flow control location in the Screenwell. Attachment 4 contains a one-line diagram of the SAWA flowpath.

The SAWA electrical loads are included in the FLEX DG loading calculation reviewed for EA-12-049 compliance. The Screenwell is located north of the RB and the FLEX DGs are located north of the Screenwell. The FLEX DG location is a significant distance and on the opposite side of the RB from the HCVS discharge. See Attachment 6 for applicable locations. Refueling of the FLEX DG is accomplished from the EDG fuel oil storage tanks located to the West of the Screenwell as described in the EA-12-049 FIP (Reference 37).

Evaluations for projected SA conditions (radiation / temperature) indicate that personnel can complete the initial and support activities without exceeding the ERO-allowable dose for equipment operation or site safety standards.

Electrical equipment and instrumentation is powered from the existing station batteries, and from AC distribution systems that are powered from the FLEX generator(s). The battery chargers are also powered from the FLEX generator(s) to maintain the battery capacities during the Sustained Operating period.

Section II: List of Acronyms AC Alternating Current AOV Air Operated Valve BDBEE Beyond Design Basis External Event BWROG Boiling Water Reactor Owners Group CAD Containment Atmosphere Dilution CAP Containment Accident Pressure DC Direct Current ECCS Emergency Core Cooling Systems ELAP Extended Loss of AC Power EOP Emergency Operating Procedure EPG/SAG Emergency Procedure and Severe Accident Guidelines Revision 0 Page 5 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 EPRI Electric Power Research Institute ERO Emergency Response Organization FAQ Frequently Asked Question FIP Final Integrated Plan FLEX Diverse & Flexible Coping Strategy FSB FLEX Storage Building GPM Gallons per minute HCVS Hardened Containment Vent System ISE Interim Staff Evaluation ISG Interim Staff Guidance JAF James A. FitzPatrick Nuclear Power Plant JLD Japan Lessons Learned Project Directorate MCR Main Control Room N2 Nitrogen NEI Nuclear Energy Institute NPSH Net Positive Suction Head NRC Nuclear Regulatory Commission NSRC National SAFER Response Center OIP Overall Integrated Plan PCIV Primary Containment Isolation Valve PCPL Primary Containment Pressure Limit RM Radiation Monitor ROS Remote Operating Station Revision 0 Page 6 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 RPV Reactor Pressure Vessel SA Severe Accident SAMG Severe Accident Management Guidelines SAOG Severe Accident Operating Guidelines SAWA Severe Accident Water Addition SAWM Severe Accident Water Management SGTS Standby Gas Treatment System SRV Safety-Relief Valve UFSAR Updated Final Safety Analysis Report VAC Voltage AC VDC Voltage DC Revision 0 Page 7 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section III: Phase 1 Final Integrated Plan Details Section III.A: HCVS Phase 1 Compliance Overview JAF modified the existing hardened wetwell vent path installed in response to NRC Generic Letter 89-16 to comply with NRC Order EA-13-109.

Section III.A.1: Generic Letter 89-16 Vent System JAF, in response to GL 89-16, successfully justified to the NRC that the existing vent pathway to the Standby Gas Treatment System (SGTS) meets the required criterion (or the intent) for a hardened vent (Reference 38). The existing JAF Torus (wetwell) vent path originates at Torus Penetration X-205 and terminates at the inlet to SGTS. The pathway consists of large bore piping (12+) inboard and outboard Torus Primary Containment Isolation Valves (PCIVs) (27AOV-117 and 27AOV-118), parallel SGTS motor operated isolation valves (27MOV-120 and 27MOV-121), and SGTS filter isolation valves (01-125MOV-14A / B). The hardened vent terminates in the SGTS room, located adjacent to the Reactor Building, which contains sheet metal ductwork and filters. The ductwork and filters are only rated for a few pounds and are presumed to fail under most venting scenarios. After ductwork failure, high pressure venting will pressurize the SGTS room until failure of the access doors to the outside. These are double doors that normally open to the environment thereby providing a large release path for the steam mixture.

Inadvertent actuation of the existing system is prevented through emergency operating procedures, physical separation of the valve controls from the MCR, and the likely requirement for manual operation of some venting valves due to a loss of power.

Radiation monitoring is provided using existing containment high range monitor (CHRM) and post-accident sampling system (PASS).

Section III.A.2: EA-13-109 Hardened Containment Vent System (HCVS)

The EA-13-109 compliant HCVS system utilizes portions of the GL-89-16 wetwell vent system. Similar to the existing GL 89-16 hardened vent, the EA-13-109 vent path originates at the Torus Penetration X-205, passes through existing Containment Atmosphere Dilution (CAD) inboard and outboard PCIVs (27AOV-117 and -118) and combines with the Drywell piping into a common 30 header. Installed between the PCIVs and the Standby Gas Treatment System intermediate isolation valves (27MOV-120 and 27MOV-121) is a new 8 / 10 branch pipeline (10-N-152-108, 8-N-152-109, 10-N-152-110) with a HCVS air-operated control valve (27AOV-142) to bypass the SGTS. The new HCVS pipeline and HCVS isolation valve starts above RB elevation of 344, routes through a stairwell, and up the inside the Southwest side of the Refuel Floor to discharge a minimum of 3 feet above the RB parapet. The HCVS control valve and piping is designed and fabricated as a secondary containment barrier and for anticipated severe accident conditions. The pipeline above the Refuel Floor meets the reasonable protection requirements of HCVS-WP-04 for tornado missiles. Attachment 2 shows the HCVS vent flow path Revision 0 Page 8 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Valves 27MOV-120 and 27MOV-121 serve to isolate the HCVS from the SGTS. 27MOV-121 is the only valve that could be procedurally opened prior to a severe accident event; therefore, a permanent platform is provided for manual operation of this valve.

Monitoring of existing plant instrumentation is within the MCR. Operation and additional monitoring and operation of the HCVS is from a dedicated HCVS Remote Operating Station located two floors below the MCR in the Administration Building Corridor (El.

272). Both locations are protected from adverse natural phenomena and are sufficiently shielded. Table 2 contains the evaluation of the acceptability of the ROS with respect to severe accident conditions.

The HCVS requires electrical power only for monitoring of HCVS parameters. All electrical power required for monitoring of HCVS components is provided by a dedicated HCVS battery charger and battery located in the DC A Equipment Room (Administration Building El. 272). The HCVS battery has a minimum capacity capable of providing power for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> without recharging. The HCVS battery charger provided requires a 120 VAC supply. The battery charger is repowered via portable cables from 71ACUPS-2 that will be repowered by a diesel generator as part of the FLEX response. Actions to replenish the electrical supply include refueling the DG.

For the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> following the event, the motive supply for the AOVs will be nitrogen gas bottles that have been pre-installed at the ROS. Calculation JAF-CALC-15-00013 (Reference 45) determined the required amount of nitrogen needed for the required number of vent cycles in a 24-hour period. These bottles were sized such that they can provide motive force for at least 8 cycles of a vent path, which includes two (2) openings for each of the two PCIVs (27AOV-117 and 27AOV-118) and at least eight (8) openings of the HCVS control valve, 27AOV-142.

The HCVS design includes a nitrogen purge system connected just downstream of the HCVS isolation valve 27AOV-142. It is designed to prevent hydrogen detonation downstream of that valve. However, the nitrogen purge system is required to be used only if the ELAP progresses to severe accident conditions which result in the creation of combustible gases. The nitrogen purge system has a manual supply control valve at the ROS to allow opening the purge for the designated time. Calculation JAF-CALC 00038 (Reference 46) determined the required amount of nitrogen for 8 purges within the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of the ELAP. The design allows for nitrogen bottle replacement for continued operation past 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

The following table describes the existing drywell pressure and Torus level indication and associated transmitters/switches that are used for supporting decision making for operation of the HCVS. Operation of the HCVS will be based on guidance in the EOPs and SAOGs and will follow the primary containment pressure limit (PCPL) curves contained in these procedures. The PCPL curve uses Torus pressure vs. primary containment water level parameters to determine when to vent containment. Since Torus Pressure instrumentation is not repowered for use during this event, EPC Issue 1614 is implemented for evaluating Primary Containment Pressure Limit (PCPL) using existing Drywell Pressure instrumentation.

Revision 0 Page 9 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Table 3-1: Existing Containment Instrumentation Indicating Component Assoc. Indication Classification Component Location Drywell Pressure Safety Related /

27PI-115A2* 27PT-115A2 MCR / Relay Environmentally 27PI-115B2 27PT-115B2 Room Qualified Torus Water Level Safety Related /

23LI-202A* 23LT-202A MCR / Relay Environmentally 23LI-202B 23LT-202B Room Qualified

  • Credited via backup from the Primary FLEX Diesel Generator; others defense-in-depth Torus level indication is needed to determine that the Torus vent path is preserved.

Both of the instruments interface with the Torus up to elevation 257-6 (27.5 ft). The inlet to the HCVS vent pipe is at elevation 260-6. Therefore, water level will have to be maintained below 257-6 in order to ensure that the vent inlet does not get covered with water (see Attachment 1). Engineering Change 620605 Attachment 6.004 demonstrates that the Torus water level will remain below the maximum indicated level of 257-6 with approximately 50,000 gallons of margin.

The pressure and level indicators and related transmitters are all Safety Related, Regulatory Guide 1.97 compliant components (Reference 34). They are also environmentally qualified for accident conditions. Division A (125 VDC Battery Bus 71BCB-2A) is the primary FLEX Phase 2 diesel power backed loop, and Division 2 (125 VDC Battery Bus 71BCB-2B) can be powered as an alternate strategy.

The Remote Operating Station displays the following parameters:

  • HCVS Control Valve Position Indication
  • HCVS Vent Pipe Temperature
  • HCVS Vent Pipe Radiation
  • HCVS Valve Motive Force and Purge System Supply Pressure
  • HCVS Battery Voltage
  • HCVS Battery Current Table 1 contains a complete list of instruments available to the operators for operating and monitoring the HCVS. contains a one-line diagram of the HCVS electrical distribution system.

The Torus vent up to, and including, the second containment isolation barrier is designed consistent with the design basis of the plant. These items include piping, piping supports, containment isolation valves, containment isolation valve actuators and containment isolation valve position indication components. The Torus vent downstream of the second containment isolation barrier is designed for the containment design pressure of 56 psig and ambient temperature (100°F). The design conditions of Revision 0 Page 10 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 the existing and new portions of the HCVS System (downstream of the second containment isolation barrier) remain consistent with these conditions. However, the EA-13-109 Order requires this portion of the system to be capable of operation at the higher of the PCPL or containment design pressure. NEI 13-02 suggests a 350°F value for HCVS design temperature based on the highest Primary Containment Pressure Limit (PCPL) among the Mark I and II plants but it is also acceptable to assume saturation conditions in containment (2.4.3.1). Therefore, the existing and new HCVS downstream of the second containment isolation barrier downstream of the containment boundary is evaluated for a pressure consistent with the containment design pressure of 62 psig and a corresponding saturation temperature of 309°F. The system is acceptable for these conditions as shown in pipe stress analyses JAF-CALC-14-00016 (Reference 39) and the associated support calculations.

There is one interfacing mechanical system on the HCVS flow path (in the Standby Gas Treatment System). The boundary valves between the two systems are 27MOV-120 and 27MOV-121. Valve 27MOV-120 remains closed for plant modes 1-3; therefore, it could not be in the open position prior to a BDBEE when the HCVS is required to be functional.

A new permanent access platform is used to access 27MOV-121 should it be open prior to the BDBEE. Per the guidance given in NEI 13-02, leak rate testing is suggested for the HCVS system boundary valves (27MOV-120 and 27MOV-121). Per FAQ-05, HCVS Control and Boundary Valves the allowable leakage was set equal to the allowable leakage for the PCIV of the valve pair associated with the HCVS containment penetrations which exhibits the highest accepted leakage rate during a 10CFR50, Appendix J testing cycle. In this way, expectations set for boundary valves will not be set higher than those for the existing safety related PCIVs.

HCVS features to prevent inadvertent actuation include locked closed manual valves and a normally open vent valve at the ROS which is an acceptable method of preventing inadvertent actuation per NEI 13-02.

The HCVS radiation monitor with an ion chamber detector is qualified for the ELAP and external event conditions. In addition to the RM, a temperature element is installed on the vent line to allow the operators to monitor operation of the HCVS. Electrical and controls components are seismically qualified and include the ability to handle harsh environmental conditions (although they are not considered part of the site Environmental Qualification (EQ) program).

Section III.B: HCVS Phase 1 Evaluation Against Requirements:

The functional requirements of Phase 1 of NRC Order EA-13-109 are outlined below along with an evaluation of the JAF response to maintain compliance with the Order and guidance from JLD-ISG-2015-01. Due to the difference between NEI 13-02, Revision 0 and Revision 1, only Revision 1 will be evaluated. Per JLD-ISG-2015-01, this is acceptable as Revision 1 provides acceptable guidance for compliance with Phase 1 and Phase 2 of the Order.

Revision 0 Page 11 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109

1. HCVS Functional Requirements 1.1 The design of the HCVS shall consider the following performance objectives:

1.1.1 The HCVS shall be designed to minimize the reliance on operator actions.

Evaluation:

The operation of the HCVS was designed to minimize the reliance on operator actions in response to hazards identified in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide (Reference 32), which are applicable to the plant site. Operator actions to initiate the HCVS vent path can be completed by plant personnel and include the capability for remote-manual initiation from the HCVS control station. A list of the remote manual actions performed by plant personnel to open the HCVS vent path is in the following table:

Table 3-2: HCVS Operator Actions Primary Location/

Primary Action Notes Component

1. Open RB doors / Reactor Building Complete in less than 5 exhaust duct and the RB-369-1 hours.

Track Bay door RB-369-2 RB-272-1 RB-272-2

2. Close SGTS Reactor Building Complete in less than 7 Isolation Valve, hours.

27MOV-121 Valve may be closed at start of event; use permanent access platform, if needed

3. Prepare nitrogen Remote Operating Station in Admin supply system Building Corridor valves for use 27CAD-314 - Unlock and close 27CAD-309 - Unlock and open 27CAD-310 - Unlock 27CAD-311 - Unlock 27CAD-313 - Unlock 27CAD-317 - Open Revision 0 Page 12 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Primary Location/

Primary Action Notes Component

4. Open Torus Inboard Remote Operating Station in Admin Primary Building Corridor Containment 27CAD-310 - Change Position to Isolation Valve supply nitrogen (27AOV-117)
5. Open Torus Remote Operating Station in Admin Outboard Primary Building Corridor Containment 27CAD-311 - Change Position to Isolation Valve supply nitrogen (27AOV-118)
6. Open HCVS Control Remote Operating Station in Admin After closing, initiate Valve (27AOV-142) Building Corridor purge system by opening 27CAD-313 - Change Position to valve 27CAD-319.

supply nitrogen

7. Connect back-up Administration Building (Battery Prior to depletion of the power to HCVS Charger located in DC A Equipment dedicated HCVS power battery charger Room) supply batteries (connect using the extension prior to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> from cord from initiation of ELAP).

71ACUPS-2

8. Replenish Nitrogen Administration Building Corridor Prior to depletion of the bottles (stored in pneumatic/purge supply FSBs) and/or (no less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> portable air from initiation of ELAP).

compressor stored in FSB.

Permanently installed electrical power and pneumatic supplies are available to support operation and monitoring of the HCVS for a minimum of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. No portable equipment is required in the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

After 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, available personnel will be able to connect supplemental electric power and pneumatic supplies for sustained operation of the HCVS for a minimum of 7 days. The FLEX generators, spare nitrogen bottles provide this operation and monitoring. In all likelihood, these actions will be completed in less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. However, the HCVS can be operated for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> without any supplementation.

The above set of actions conform to the guidance in NEI 13-02 Revision 1 Section 4.2.6 for minimizing reliance on Operator actions and are acceptable for compliance with Order element A.1.1.1. These were identified in the OIP and subsequent NRC ISE.

Revision 0 Page 13 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Table 3-3 below provides a list of functional failure modes and the corresponding mitigating actions.

Table 3-3: Failure Evaluation Failure with Alternate Action Impact Functional on Containment Failure Mode Failure Cause Alternate Action Venting?

Fail to Vent (Open) Valves fail to open/close Open valves from No on Demand due to loss of normal Remote Operating AC power Station (dedicated nitrogen supply)

Fail to Vent (Open) Valves fail to open/close Open valves from No on Demand / due to loss of normal Remote Operating Spurious Closure pneumatic air supply Station (dedicated nitrogen supply)

Fail to Vent (Open) Valves fail to open/close Replace bottles as No on Demand / due to loss of backup needed and/or Spurious Closure pneumatic air supply recharge with (long term) portable air compressors.

Fail to stop venting Not credible as there is N/A No (Close) on demand not a common mode failure that would prevent the closure of at least 1 of the 3 valves needed for venting.

Spurious Opening Not credible - two N/A No locked closed nitrogen isolation valves and a locked open nitrogen vent valve in series prevent pneumatic supply to the PCIVs.

1.1.2 The HCVS shall be designed to minimize plant operators exposure to occupational hazards, such as extreme heat stress, while operating the HCVS system.

Evaluation:

Primary control of the HCVS is accomplished from the Remote Operating Station two floors below the Control Room in the Administration Building (located adjacent to the Reactor Building). FLEX actions that will maintain the MCR and ROS habitable were implemented in response to NRC Order EA-12-049 (Reference 33). These include:

Revision 0 Page 14 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109

1. Restoring MCR ventilation via the NSRC DG, if required.

Temperatures may increase beyond 110°F late in the mission time of 168 hours0.00194 days <br />0.0467 hours <br />2.777778e-4 weeks <br />6.3924e-5 months <br /> requiring this action. Without action to restore MCR ventilation, MCR temperature will remain <120°F for the duration of the 7 days of Sustained Operation.

2. While not specifically credited, opening of the MCR doors can also be implemented to reduce the MCR temperature.
3. Opening doors in the RB to establish natural circulation air flow in the RB (Reference 30).

Table 2 contains a thermal evaluation of all the operator actions that may be required to support HCVS operation. The relevant ventilation calculations / evaluations (References 30, 31, 43, 50, 51, 52) demonstrate that the final design meets the order requirements to minimize the plant operators exposure to occupational hazards.

1.1.3 The HCVS shall also be designed to minimize radiological consequences that would impede personnel actions needed for event response.

Evaluation:

Monitoring of the drywell pressure and Torus level is accomplished from the Main Control Room. Under the postulated scenarios of order EA 109 the control room is adequately protected from excessive radiation dose and no further evaluation of its use is required. (Ref. 7)

HCVS control and monitoring is accomplished from the ROS (primary).

Table 2 contains a radiological evaluation of the operator actions that may be required to support HCVS operation in a severe accident. There are no abnormal radiological conditions present for HCVS operation without core damage. The HCVS PCIVs (27AOV-117 and 27AOV-118) are located within the Reactor Building adjacent to the Administration Building Corridor; however, shielding from the Reactor Building (secondary containment) exterior concrete wall as well as interior Administration Building walls provides shielding from the HCVS. Peak maximum dose rates and a 7-day total integrated dose have been calculated for the ROS in Calculation JAF-CALC-14-00029 (Reference 40). The radiation dose to personnel occupying this location is predicted to be 5 rem whole body over a period of 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> (using a conservative drywell source term). Since action times at the ROS are short during the 7 days of sustained operation for BDBEE, the predicted radiological conditions will be acceptable for the operators to gain access to the ROS for HCVS operation.

If venting operations create the potential for airborne contamination in the Revision 0 Page 15 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 MCR or at the ROS, the ERO will provide personal protective equipment to minimize any operator exposure.

1.1.4 The HCVS controls and indications shall be accessible and functional under a range of plant conditions, including severe accident conditions, extended loss of AC power, and inadequate containment cooling.

Evaluation:

Monitoring of the drywell pressure and Torus level is accomplished from the Main Control Room. Under the postulated scenarios of order EA 109 the control room is adequately protected from excessive radiation dose and no further evaluation of its use is required (Reference HCVS-FAQ-06)

HCVS control and monitoring is accomplished from the ROS (primary).

Table 2 contains a radiological evaluation of the operator actions that may be required to support HCVS operation in a severe accident. There are no abnormal radiological conditions present for HCVS operation without core damage. The HCVS PCIVs (27AOV-117 and 27AOV-118) are located within the Reactor Building adjacent to the Administration Building Corridor; however, shielding from the Reactor Building (secondary containment) exterior concrete wall as well as interior Administration Building walls provides shielding from the HCVS. Peak maximum dose rates and a 7-day total integrated dose have been calculated for the ROS in Calculation JAF-CALC-14-00029 (Reference 40). The radiation dose to personnel occupying this location is predicted to be 5 rem whole body over a period of 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> (using a conservative drywell source term). Since action times at the ROS are short during the 7 days of sustained operation for BDBEE, the predicted radiological conditions will be acceptable for the operators to gain access to the ROS for HCVS operation.

For ELAP with injection, the HCVS Torus vent will be opened to protect the containment from overpressure. The operator actions and timing of those actions to perform this function under ELAP conditions were evaluated as part of JAFs response to NRC Order EA-12-049 as stated in the FLEX SER (Reference 37).

Table 1 contains an evaluation of the controls and indications that are or may be required to operate the HCVS during a severe accident. The evaluation demonstrates that the controls and indications are accessible and functional during a severe accident with a loss of AC power and inadequate containment cooling.

Table 2 contains a thermal and radiological evaluation of all the operator actions that may be required to support HCVS operation during a severe accident. The relevant ventilation evaluations (Reference 43) demonstrate Revision 0 Page 16 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 that the final design meets the order requirements to minimize the plant operators exposure to occupational and radiological hazards.

1.2 The HCVS shall include the following design features:

1.2.1 The HCVS shall have the capacity to vent the steam/energy equivalent of 1 percent of licensed /rated thermal power (unless a lower value is justified by analysis) and be able to maintain containment pressure below the primary containment design pressure.

Evaluation Calculation JAF-CALC-14-00015 (Reference 41) contains the verification of 1% power flow capacity at the lesser of the containment design pressure and PCPL (56 psig). This is a flow rate of approximately 95,500 lbm/hr. The analysis was performed by a RELAP5 model created for the HCVS piping and fittings. The current design has been evaluated considering pipe diameter, length, and geometry as well as vendor provided valve Cvs. Calculation JAF-CALC-14-00015 concludes that the design provides margin to the minimum required flow rate; therefore, the vent is capable of preventing containment pressure from increasing above the containment design pressure. Calculation JAF-CALC-15-00026 (Reference 42) contains the verification that the Torus is sufficient to absorb the decay heat generated during at least the first 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

The decay heat absorbing capacity of the Torus and the selection of venting pressure were made such that the HCVS will have sufficient capacity to maintain containment pressure at or below the lower of the containment design pressure (56 psig) or the PCPL (62 psig).

1.2.2 The HCVS shall discharge the effluent to a release point above main plant structures.

Evaluation The HCVS vent pipe release point to the outside atmosphere is at an elevation that is higher than the adjacent power block structures. The vent exits the Torus through the existing Containment Atmosphere Dilution piping (penetration X-205), through the Torus inboard and outboard PCIVs (27AOV-117 and 27AOV-118), and finally the HCVS Control Valve (27AOV-142). Downstream of the HCVS Control Valve, the vent pipe is routed through the southwest Refuel Floor stairwell and up the interior of the Reactor Building before penetrating the roof. The discharge point was extended approximately three feet above the Reactor Building parapet wall (435-0). The release point is on the far southwest side of the RB and a minimum of 25 from the Reactor Building and Turbine Building HVAC Revision 0 Page 17 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 exhaust ductwork. Since the effluent release velocity of the vent exceeds 8000 fpm, it is assured that the effluent plume will not be entrained into the recirculation zone of the Turbine Building, Reactor Building, emergency response facilities or ventilation system intakes, and open doors used for natural circulation in the BDBEE response.

Part of the HCVS-FAQ-04 guidance is designed to ensure that vented fluids are not drawn immediately back into any emergency ventilation intakes. Such ventilation intakes should be below a level of the pipe by 1 foot for every 5 horizontal feet. The MCR emergency intake in the ELAP event is at the 322 ft. elevation which is approximately 113 feet below the HVCS pipe outlet. This intake is approximately 180 feet from the vent pipe which would require the intake to be approximately 36 feet below the vent pipe. Therefore, the vent pipe is appropriately placed relative to this air intake.

The vent pipe extends approximately 3 feet above the parapet wall of the RB roof. This satisfies the guidance for height from HCVS-FAQ-04.

EC 9000052721 Topic Notes (Reference 43) was provided for EA-13-109 compliance and contains an evaluation of vent pipe for protection from external events based on HCVS-WP-04 criteria to demonstrate robustness of the HCVS pipe. JAF meets all the requirements of this white paper. This evaluation documents that the HCVS pipe is adequately protected from all external events and no further protection is required.

JAF evaluated the vent pipe robustness with respect to wind-borne missiles against the requirements contained in HCVS-WP-04. This evaluation demonstrated that the pipe was robust with respect to external missiles per HCVS-WP-04 in that:

1. The JAF HCVS piping is contained within the RB and first exits a tornado missile protected area at elevation 369-6 (Refuel Floor). This is nearly 100 feet above the site grade at 272-0; there is no HCVS piping at JAF exposed to wind missile hazards below 30 feet above grade that is applicable to this assumption.
2. The exposed piping greater than 30 feet above grade has the following characteristics:
a. The total vent pipe exposed area is 255 square feet which is less than the 300 square feet.
b. The pipe is made of schedule 40 carbon steel and is not plastic and the pipe components have no small tubing susceptible to missiles Revision 0 Page 18 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109

c. There are no obvious potential missiles or unrestrained material lay down areas in close proximity to the HCVS components because all components, except upper portions of the HCVS large bore piping and the radiation monitor, are located within the protected structure below the Refuel Floor. The radiation monitor, located adjacent to the vent pipe on El. 369-6, is qualified seismically and is enclosed with a robust vendor supplied lead shield. Under the unlikely occurrence that a tornado missile strikes this component, the device within the lead shield may not remain functional; however, alternate, protected devices are available to serve the function of the radiation monitor, which is to provide an indication of vent line status (i.e., vent line open or isolated). Alternate indicators include HCVS vent line temperature and valve position indication.

In addition, temporary storage of material in the area is controlled through work management procedures.

3. JAF will maintain the existing GL 89-16 Torus vent capability as a contingency vent path should the HCVS vent path above 30 feet become damaged such that it restricts flow to an unacceptable level.
4. Hurricanes are not screened for JAF.

Based on the above description of the vent pipe design, the JAF HCVS vent pipe design meets the order requirement to be robust with respect to all external hazards including wind-borne missiles.

1.2.3 The HCVS shall include design features to minimize unintended cross flow of vented fluids within a unit and between units on the site.

Evaluation There is one interfacing mechanical system on the HCVS flow path for which there could be unintended cross flow of vented fluids:

  • Standby Gas Treatment System - the boundary valves between the two systems are 27MOV-120 and 27MOV-121. Valve 27MOV-120 remains closed for plant modes 1-3; therefore, it could not be in the open position prior to a BDBEE when the HCVS is required to be functional. A new permanent access platform is used to access 27MOV-121 should it be open prior to the BDBEE. Per the guidance given in NEI 13-02, leak rate testing is suggested for the HCVS system boundary valves (27MOV-120 and 27MOV-121). Per HCVS-FAQ-05, HCVS Control and Boundary Valves the allowable leakage was set equal to the allowable leakage for the PCIV of the valve pair associated with the HCVS containment penetrations which exhibits the highest accepted leakage rate during a 10CFR50, Appendix J testing cycle. In this way, expectations set for boundary valves will not Revision 0 Page 19 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 be set higher than those for the existing safety related PCIVs.

The miscellaneous vent, drain, and test connections have a normally closed valve and are end-capped. The process instrumentation lines are isolated by a manual valve or the instrument. These pathways adequately minimize the potential for cross flow or combustible migration into the RB or other systems.

Based on the above description, the JAF design meets the requirements to minimize unintended cross-flow of vented fluids within a unit and between units on site.

1.2.4 The HCVS shall be designed to be manually operated during sustained operations from a control panel located in the MCR or a remote but readily accessible location.

Evaluation Monitoring of the containment parameters is within the MCR. Operation and monitoring of the HCVS is from a control panel located in the Administration Building Corridor. This location is two floors below the Main Control Room and accessible via a local stairway making the Remote Operating Station readily accessible. The ROS location has a direct travel path to the MCR and is protected by intervening structures. Table 2 contains a list and evaluation of the HCVS required actions ensuring access during a severe accident. Attachment 6 shows the location relative to the Main Control Room.

Refer to the sketch provided in Attachment 6 for the HCVS site layout. The controls available at the ROS location are accessible and functional under a range of plant conditions, including severe accident conditions with due consideration to source term and dose impact on operator exposure, extended loss of AC power (ELAP), inadequate containment cooling, and loss of reactor building ventilation. Table 1 contains an evaluation of all the required controls and instruments that are required for severe accident response and demonstrates that all these controls and instruments will be functional during a loss of AC power and severe accident. Table 2 contains a thermal and radiological evaluation of all the operator actions that may be required to support HCVS operation during a loss of AC power and severe accident and demonstrates that these actions will be possible without undue hazard to the operators. These evaluations demonstrate that the design meets the requirement to be manually operated from a remote but readily accessible location during sustained operation.

Revision 0 Page 20 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 1.2.5 The HCVS shall be capable of manual operation (e.g., reach-rod with hand wheel or manual operation of pneumatic supply valves from a shielded location), which is accessible to plant operators during sustained operations.

Evaluation Manual operation of the HCVS is completed at the Remote Operating Station as described in Order Item 1.2.4 above. The ROS contains manually operated valves that supply pneumatics to the HCVS flow path valve actuators so that these valves may be opened without power to the valve actuator solenoids and regardless of any containment isolation signals that may be actuated.

1.2.6 The HCVS shall be capable of operating with dedicated and permanently installed equipment for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> following the loss of normal power or loss of normal pneumatic supplies to air operated components during an extended loss of AC power.

Evaluation HCVS-WP-01 (Reference 8) contains clarification on the definition of dedicated and permanently installed with respect to the order. In summary, it is acceptable to use plant equipment that is used for other functions, but it is not acceptable to credit portable equipment that must be moved and connected for the first 24-hour period of the ELAP.

Electrical power required for operation of HCVS components in the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> will come from a dedicated 24 VDC HCVS battery and charger. The HCVS battery and charger are permanently installed in the DC A Equipment Room in the Administration Building where they are protected from screened in hazards and have sufficient capacity to provide this power without recharging. Engineering Change 9000052721 Attachment 6.003 (Reference 43) demonstrated that the 24 VDC battery capacity is sufficient to supply HCVS Torus venting components for a minimum of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

At 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, FLEX generators can be credited to repower the station instrument buses and/or the battery charger to supply HCVS loads while recharging the 24VDC batteries per the response to EA-12-049. The HCVS battery charger provided requires a 120 VAC supply. The battery charger is repowered via portable cables from 71ACUPS-2 that will be repowered by a portable diesel generator as part of the response to EA 049. Engineering Change 9000052721 Topic Notes Section 3.1.4 (Reference 43) confirms that the battery charger is capable of supplying the continuous HCVS loads while recharging the batteries within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

Revision 0 Page 21 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Calculation JAF-CALC-15-00031 (Reference 44) included the 24VDC battery charger in the FLEX DG loading calculation, so there is no additional load on the FLEX DG and they are capable of carrying HCVS Torus venting components electrical loads. 24 VDC battery voltage and current status will be indicated on panel 27CAD-PNL-1 so that operators will be able to monitor the status of the 24 VDC batteries. Attachment 3 contains a diagram of the HCVS electrical distribution system.

A permanent access platform is available to access the valve 27MOV-121 handwheel should it require closure prior to operation of the HCVS. This eliminates the need for portable equipment such as ladders, portable platforms, scaffolding, etc.

The pneumatic motive force is provided by two nitrogen bottles in the Administration Building Corridor. The designed capacity of the pneumatic system is required to perform a minimum of 8 vent cycles. Valve 27AOV-142 is cycled for venting operation while valves 27AOV-117 and 27AOV-118 will remain open once venting process is initiated. Per JAF-CALC 00013 (Reference 45), the nitrogen system is sized to open Torus PCIVs 27AOV-117 and 27AOV-118 twice and to perform up to twelve (12) open and close cycles of HCVS Control Valve 27AOV-142 over a 24-hour period.

1.2.7 The HCVS shall include a means to prevent inadvertent actuation.

Evaluation Emergency operating procedures provide clear guidance that the HCVS is not to be used to defeat containment integrity during any design basis transients and accidents. In addition, the HCVS was designed to provide features to prevent inadvertent actuation due to equipment malfunction or operator error. Also, these protections are designed such that any credited containment accident pressure (CAP) that would provide net positive suction head (NPSH) to the emergency core cooling system (ECCS) pumps will be available (inclusive of a design basis loss-of-coolant accident). However, the ECCS pumps will not have normal power available because of the ELAP.

The Torus PCIVs must be open to permit vent flow. The physical features that prevent inadvertent actuation are locked close manual nitrogen supply valves and normally open vent valves at the Remote Operating Station. This design feature meets the requirement to prevent inadvertent actuation of HCVS.

Revision 0 Page 22 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 1.2.8 The HCVS shall include a means to monitor the status of the vent system (e.g., valve position indication) from the control panel required by 1.2.4. The monitoring system shall be designed for sustained operation during an extended loss of AC power.

Evaluation The HCVS includes indications for HCVS valve position, vent pipe temperature and effluent radiation levels at the ROS, as well as information on the status of supporting systems which are 24 VDC battery voltage, battery current and backup nitrogen pressure.

This monitoring instrumentation provides the indication from a remote but readily accessible location per Requirement 1.2.4. Containment instrumentation will be supplied by emergency busses repowered by the FLEX DGs. The Torus HCVS will be supplied by the HCVS 24VDC batteries and designed for sustained operation during an ELAP event using the FLEX equipment.

HCVS instrumentation performance (e.g., accuracy and range) need not exceed that of similar plant installed equipment. Additionally, radiation monitoring instrumentation accuracy and range is sufficient to confirm flow of radionuclides through the HCVS.

The HCVS instruments, including valve position indication, vent pipe temperature, radiation monitoring, and support system monitoring, are seismically qualified as indicated on Table 1 and they include the ability to handle harsh environmental conditions (although they may not be considered part of the site Environmental Qualification (EQ) program).

1.2.9 The HCVS shall include a means to monitor the effluent discharge for radioactivity that may be released from operation of the HCVS. The monitoring system shall provide indication from the control panel required by 1.2.4 and shall be designed for sustained operation during an extended loss of AC power.

Evaluation The HCVS radiation monitoring system consists of an ion chamber detector (27RE-106) which is coupled to a process and control module and located adjacent to the HCVS pipeline on the Refuel Floor (RB El.

369-6). The process and control module is mounted in panel 27CAD-PNL-2 in the Administration Building Corridor. The RM detector is fully qualified for the expected environment at the vent pipe during accident conditions, and the process and control module is qualified for the mild environment in the Administration Building Corridor. Both components are Revision 0 Page 23 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 qualified for the seismic requirements. Table 1 includes a description and qualification information on the radiation monitor.

1.2.10 The HCVS shall be designed to withstand and remain functional during severe accident conditions, including containment pressure, temperature, and radiation while venting steam, hydrogen, and other non-condensable gases and aerosols. The design is not required to exceed the current capability of the limiting containment components.

Evaluation The Torus vent up to, and including, the second containment isolation valve is designed consistent with the design basis of the plant. These items include piping, piping supports, containment isolation valves, containment isolation valve actuators and containment isolation valve position indication components.

The existing hardened vent piping between the Torus and the containment isolation boundary is designed to 56 psig at 220ºF. The existing Torus PCIVs, 27AOV-117 and 27AOV-118, meet these design conditions for the containment boundary. Torus vent piping and components installed downstream of the containment isolation boundary are designed or have been reevaluated for beyond design basis conditions.

HCVS piping and components have been analyzed and shown to perform under severe accident conditions using the guidance provided in HCVS-FAQ-08 and HCVS-WP-02. Refer to EA-13-109, requirement 1.2.11 for a discussion on designing for combustible gas.

1.2.11 The HCVS shall be designed and operated to ensure the flammability limits of gases passing through the system are not reached; otherwise, the system shall be designed to withstand dynamic loading resulting from hydrogen deflagration and detonation.

Evaluation In order to prevent a detonable mixture from developing in the pipe, a purge system is installed to purge hydrogen from the pipe with nitrogen after a period of venting. The nitrogen purge system is charged by opening manual valve 27CAD-317 and initiated by opening manual valve 27CAD-319 to inject into the HCVS pipeline downstream of the HCVS Control Valve 27AOV-142. Calculation JAF-CALC-15-00038 (Reference

46) has determined that a 31-second purge time is required to purge the combustibles after a vent cycle. The use of this purge system meets the requirement to ensure the flammability limits of gases passing through the vent pipe will not be reached.

Revision 0 Page 24 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 1.2.12 The HCVS shall be designed to minimize the potential for hydrogen gas migration and ingress into the reactor building or other buildings.

Evaluation The response under Order element 1.2.3 explains how the potential for hydrogen migration into other systems, the reactor building, or other buildings is minimized.

1.2.13 The HCVS shall include features and provisions for the operation, testing, inspection and maintenance adequate to ensure that reliable function and capability are maintained.

Evaluation:

As endorsed in the ISG, sections 5.4 and 6.2 of NEI 13-02 provide acceptable method(s) for satisfying the requirements for operation, testing, inspection, and maintenance of the HCVS.

Primary and secondary containment required leakage testing is covered under existing design basis testing programs. The HCVS outboard the containment boundary shall be tested to ensure that vent flow is released to the outside with minimal leakage, if any, through the interfacing boundaries with other systems or units.

JAF has implemented the following operation, testing and inspection requirements for the HCVS to ensure reliable operation of the system.

These are from NEI 13-02, Table 6.1. The implementing modification packages contain these as well as additional testing required for post-modification testing.

Revision 0 Page 25 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Table 3-4: Testing and Inspection Requirements Description Frequency Cycle the HCVS valves and the1 Once per every2 operating cycle.

interfacing system valves not used to maintain containment integrity during operations.

Cycle the HCVS check valves not Once per every other4 operating used to maintain containment cycle.

integrity during unit operations. 3 Perform visual inspections and a Once per operating cycle walk down of HCVS components Functionally test the HCVS Once per operating cycle radiation monitors.

Leak test the HCVS. (1) Prior to first declaring the system functional; (2) Once every three operating cycles thereafter; and (3) After restoration of any breach of system boundary within the buildings Validate the HCVS operating Once per every other operating procedures by conducting an cycle open/close test of the HCVS control logic from its control panel (primary and alternate) and ensuring that all interfacing system boundary5 valves move to their proper (intended) positions.

2. HCVS Quality Standards:

2.1. The HCVS vent path up to and including the second containment isolation barrier shall be designed consistent with the design basis of the plant. Items in this path include piping, piping supports, containment isolation valves, containment isolation 1

Not required for HCVS check valves.

2 After two consecutive successful performances, the test frequency may be reduced to a maximum of once per every other operating cycle.

3 Not required if integrity of check function (open and closed) is demonstrated by other plant testing requirements.

4 After two consecutive successful performances, the test frequency may be reduced by one operating cycle to a maximum of once per every fourth operating cycle.

5 Interfacing system boundary valves that are normally closed and fail closed under ELAP conditions (loss of power and/or air) do not require control function testing under this section. Performing existing plant design basis function testing or system operation that reposition the valve(s) to the HCVS required position will meet this requirement without the need for additional testing.

Revision 0 Page 26 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 valve actuators, and containment isolation valve position indication components.

Evaluation:

The HCVS upstream of and including the second containment isolation valve 27AOV-118 and penetrations are not being modified for order compliance so that they continue to be designed consistent with the design basis of primary containment including pressure, temperature, radiation, and seismic loads.

2.2. All other HCVS components shall be designed for reliable and rugged performance that is capable of ensuring HCVS functionality following a seismic event. These items include electrical power supply, valve actuator pneumatic supply, and instrumentation (local and remote) components.

Evaluation:

The HCVS components downstream of the outboard containment isolation valve and components that interface with the HCVS are routed in seismically qualified structures or supported from a seismically qualified structure.

The HCVS downstream of the outboard containment isolation valve, including piping and supports, electrical power supply, valve actuator pneumatic supply, and instrumentation (local and remote) components, have been designed and analyzed to conform to the requirements consistent with the applicable design codes for the plant and to ensure functionality following a design basis earthquake. This includes environmental qualification consistent with expected conditions at the equipment location.

Table 1 contains a list of components, controls and instruments required to operate HCVS, their qualification and evaluation against the expected conditions. All instruments are fully qualified for the expected seismic conditions so that they will remain functional following a seismic event.

Section IV: HCVS Phase 2 Final Integrated Plan Section IV.A: The requirements of EA-13-109, Attachment 2, Section B for Phase 2

Licensees with BWRs Mark 1 and Mark II containments shall either:

(1) Design and install a HCVS, using a vent path from the containment drywell, that meets the requirements in section B.1 below, or (2) Develop and implement a reliable containment venting strategy that makes it unlikely that a licensee would need to vent from the containment drywell before alternate reliable containment heat removal and pressure control is reestablished and meets the requirements in Section B.2 below.

Revision 0 Page 27 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109

1. HCVS Drywell Vent Functional Requirements 1.1 The drywell venting system shall be designed to vent the containment atmosphere (including steam, hydrogen, non-condensable gases, aerosols, and fission products), and control containment pressure within acceptable limits during severe accident conditions.

1.2 The same functional requirements (reflecting accident conditions in the drywell),

quality requirements, and programmatic requirements defined in Section A of this Attachment for the wetwell venting system shall also apply to the drywell venting system.

2. Containment Venting Strategy Requirements Licensees choosing to develop and implement a reliable containment venting strategy that does not require a reliable, severe accident capable drywell venting system shall meet the following requirements:

2.1 The strategy making it unlikely that a licensee would need to vent from the containment drywell during severe accident conditions shall be part of the overall accident management plan for Mark I and Mark II containments.

2.2 The licensee shall provide supporting documentation demonstrating that containment failure as a result of overpressure can be prevented without a drywell vent during severe accident conditions.

2.3 Implementation of the strategy shall include licensees preparing the necessary procedures, defining and fulfilling functional requirements for installed or portable equipment (e.g., pumps and valves), and installing needed instrumentation.

Because the order contains just three requirements for the containment venting strategy, the compliance elements are in NEI 13-02, Revision 1. NEI 13-02, Revision 1, endorsed by NRC in JLD-ISG-2015-01, provides the guidance for the containment venting strategy (B.2) of the order. NEI 13-02, Revision 1, provides SAWA in conjunction with Severe Accident Water Management (SAWM), which is designed to maintain the Torus vent in service until alternate reliable containment heat removal and pressure control are established, as the means for compliance with part B of the order.

JAF has implemented Containment Venting Strategy (B.2), as the compliance method for Phase 2 of the Order and conforms to the associated guidance in NEI 13-02 Revision 1 for this compliance method.

Section IV.B: HCVS Existing System There previously was neither a hardened drywell vent nor a strategy at JAF that complied with Phase 2 of the order.

Revision 0 Page 28 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section IV.C: HCVS Phase 2 SAWA System and SAWM Strategy The HCVS Phase 2 SAWA system and SAWM strategy utilize the FLEX mitigation equipment and strategies to the extent practical. This approach is reasonable because the external hazards and the event initiator (ELAP) are the same for both FLEX mitigation strategies and HCVS. For SAWA, it is assumed that the initial FLEX response actions are unsuccessful in providing core cooling such that core damage contributes to significant radiological impacts that may impede the deployment, connection and use of FLEX equipment. These radiological impacts, including dose from containment and HCVS vent line shine were evaluated and modifications made as necessary to mitigate the radiological impacts such that the actions needed to implement SAWA and SAWM are feasible in the timeframes necessary to protect the containment from overpressure related failure. To the extent practical, the SAWA equipment, connection points, deployment locations and access routes are the same as the FLEX primary strategies so that a Unit that initially implements FLEX actions that later degrades to severe accident conditions can readily transition between FLEX and SAWA strategies. This approach further enhances the feasibility of SAWA under a variety of event sequences including timing.

JAF has implemented the containment venting strategy utilizing SAWA and SAWM. The SAWA system consists of a FLEX (SAWA) pump injecting into the Reactor Pressure Vessel (RPV) and SAWM consists of flow control at the FLEX (SAWA) pump along with instrumentation and procedures to ensure that the Torus vent is not submerged (SAWM). Procedures have been issued to implement this strategy including revision 3 to the Severe Accident Management Guidelines (SAMG). This strategy has been shown via Modular Accident Analysis Program (MAAP) analysis to protect containment without requiring a drywell vent for at least seven days which is the guidance from NEI 13-02 for the period of sustained operation.

Section IV.C.1: Detailed SAWA Flow Path Description As part of implementing SAWA, the FLEX primary and secondary injection flow paths were switched as the secondary pathway offered the advantage of reduced operator dose exposure and burden. As a result of this change, the primary FLEX pathway and SAWA injection pathway are the same. To support this change, (a) new permanent plant piping connections were installed for ease of connection, (b) platforms installed for operation of manual isolation valves in the Screenwell /

Reactor Building, and (c) portable throttling valve manifolds installed (including the FLEX/SAWA flow meter) were provided to support the range of FLEX and SAWA flow rates. The new carts are located within the basement of the Screenwell local to the Fire Protection and Residual Heat Removal Service Water (RHRSW) pipeline connections. This modified flow path has been evaluated and found to be acceptable in calculation JAF-CALC-17-00104 (Reference 36). The SAWA system, shown on Attachment 4, consists of a FLEX pump (existing Diesel Driven Fire Pump) injecting into the Reactor Pressure Vessel (RPV) and SAWM consists of Revision 0 Page 29 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 flow control at the valve manifold cart along with Torus level indication to ensure that the Torus vent is not submerged. The FLEX primary (SAWA) pump is the permanently installed Diesel Driven Fire Pump (DDFP) 76P-4 which takes suction from Lake Ontario. A new permanent plant hose quick connection at the discharge of pump 76P-4 is connected via portable hose and quick connections to the new throttling valve cart where SAWA flow indication and control is provided. The outlet of the new throttling valve cart is connected via portable hose to new permanent fire hose quick connections downstream of the RHRSW B strainer. This connection to RHRSW provides a hard pipe connection to the Reactor Pressure Vessel (RPV).

To complete the flowpath, valves are then modulated as follows:

  • 76FPS-807 (Manually closed via permanent platform)

(Note: 10MOV-27B is normally open)

Backflow prevention is provided by installed containment isolation check valve 10AOV-68V. Cross flow into other portions of the RHR system is prevented using normally closed valves. Communication will be established between the MCR and the SAWA flow control location in the Screenwell.

BWROG generic assessment, BWROG-TP-15-008, provides the principles of Severe Accident Water Addition to ensure protection of containment. This SAWA injection path is qualified for the all the screened in hazards (Section III) in addition to severe accident conditions.

Section IV.C.2: Severe Accident Assessment of Flow Path The actions inside the RB where there could be a high radiation field due to a severe accident will be to open valves 10MOV-148B and 10MOV-149B. The action to open valves inside the RB can be performed before the dose is unacceptable (7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />) after the loss of RPV injection. This time was validated as part of the Time Sensitive Action validation for EA-13-109. The FSGs direct early accomplishment of actions that must be done early in the severe accident event where there is a loss of all AC power and a loss of all high-pressure injection to the core. In this event, core damage is not expected for at least one hour so that there will be no excessive radiation levels or heat related concerns in the RB when the valves are operated. The other SAWA actions all take place outside the RB at the MCR, Screenwell (and adjacent outdoor locations), FSB, and the deployment pathways.

Since these locations are outside the RB, they are shielded from the severe accident radiation by the thick concrete walls of the RB. Once SAWA is initiated, the operators will monitor the response of containment from the MCR to determine that venting and SAWA are operating satisfactorily, maintaining containment Revision 0 Page 30 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 pressure low to avoid containment failure. Stable or slowly rising trend in Torus level with SAWA at the minimum flow rate indicates water on the drywell floor up to the vent pipe or downcomer openings. After some period of time, as decay heat levels decrease, the operators will be able to reduce SAWA flow to keep the core debris cool while avoiding overfill of the Torus to the point where the Torus vent is submerged.

Section IV.C.3: Severe Accident Assessment of Safety-Relief Valves JAF has methods available to extend the operational capability of manual pressure control using SRVs as provided in the plant specific order EA-12-049 submittal.

Assessment of manual SRV pressure control capability for use of SAWA during the Order defined accident is unnecessary because RPV depressurization is directed by the EPGs in all cases prior to entry into the SAGs.

Section IV.C.4: Available Freeboard Use The freeboard between 243-9 and 257-6 (27.5 above the bottom of the Torus) elevation in the Torus provides approximately 813,012 gallons of water volume before the level instrument would be off scale high. An additional 51,586 gallons is available prior to reaching the elevation of the Torus vent penetration. BWROG generic assessment BWROG-TP-15-011, provides the principles of Severe Accident Water Management to preserve the Torus vent for a minimum of seven days. After containment parameters are stabilized with SAWA flow, SAWA flow will be reduced to a point where containment pressure will remain low while Torus level is stable or very slowly rising. As shown in EC 620605 Attachment 6.004 (Reference 47), the Torus level will not reach the Torus vent for at least seven days. A diagram of the available freeboard is shown on Attachment 1.

Section IV.C.5: Upper range of Torus level indication The upper range of Torus level indication provided for SAWA/SAWM is 257-6 elevation. This defines the upper limit of Torus volume that will preserve the Torus vent function as shown in Attachment 1.

Section IV.C.6: Torus vent service time Reference 27 in NEI 13-02, Revision 1 (Reference 7) and BWROG-TP-15-011 demonstrates that throttling SAWA flow after containment parameters have stabilized, in conjunction with venting containment through the Torus vent will result in a stable or slowly rising Torus level. The references demonstrate that, for the scenario analyzed, Torus level will remain below the Torus vent pipe for greater than the seven days of sustained operation allowing significant time for restoration of alternate containment pressure control and heat removal.

Revision 0 Page 31 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section IV.C.7: Strategy time line The overall accident management plan for JAF is developed from the BWR Owners Group Emergency Procedure Guidelines and Severe Accident Guidelines (EPG/SAG). As such, the SAWA/SAWM implementing procedures are integrated into the JAF SAOGs. In particular, EPG/SAG Revision 3, when implemented with Emergency Procedures Committee Generic Issue 1314, allows throttling of SAWA in order to protect containment while maintaining the Torus vent in service. The SAOG flow charts direct use of the hardened vent as well as SAWA/SAWM when the appropriate plant conditions have been reached.

Using NEI 12-06 Appendix E, JAF has validated that the SAWA pump can be deployed and commence injection in less than 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. The studies referenced in NEI 13-02 demonstrated that establishing flow within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> will protect containment. The initial SAWA flow rate will be about 361 gpm. After a period of time, estimated to be about 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, in which the maximum flow rate is maintained, the SAWA flow will be reduced. The reduction in flow rate and the timing of the reduction will be based on stabilization of the containment parameters of drywell pressure and Torus level.

NEI 13-02 generic analysis per Reference 27 of NEI 13-02 demonstrated that, SAWA flow could be reduced to 71 gpm after four hours of initial SAWA flow rate and containment would be protected. At some point Torus level will begin to rise indicating that the SAWA flow is greater than the steaming rate due to containment heat load such that flow can be reduced. While this is expected to be 4-6 hours, no time is specified in the procedures because the SAOGs are symptom-based guidelines.

Section IV.C.8: SAWA Flow Control JAF will accomplish SAWA flow control by the use of throttle valves on the FLEX /

SAWA valve cart. The operators at the FLEX / SAWA valve cart will be in communication with the MCR via radios or runners and the exact time to throttle flow is not critical since there is a large margin between normal Torus level and the level at which the Torus vent will be submerged. The communications capabilities that will be used for communication between the MCR and the SAWA flow control location are the same as that evaluated and found acceptable for FLEX strategies.

The communications capabilities have been tested to ensure functionality at the SAWA flow control and monitoring locations.

Section IV.C.9: SAWA/SAWM Element Assessment Section IV.C.9.1: SAWA Pump JAF uses one primary and one alternate Diesel Driven Fire Pump pump for FLEX and SAWA (existing and permanently installed). Each pump is capable of a minimum of 361 gpm at the pressures required for RPV injection during an ELAP.

Revision 0 Page 32 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Each of these pumps has been shown to be capable of supplying the required pressure and flow rate to the RPV for FLEX and for SAWA scenarios (Reference 36). The pumps are permanently installed in the Screenwell where they are protected from all screened-in hazards and will be available to function after a seismic event.

Section IV.C.9.2: SAWA analysis of flow rates and timing The JAF SAWA flow rate is 361 gpm which is the site-specific flow rate when the sites rated thermal power (2536 MWth) is compared to the reference power level of NEI 13-02. The initial SAWA flow will be injecting to the RPV within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of the loss of injection. The reference power level is 3514 MWth, equivalent to the reference plant rated thermal power level used in NUREG-1935, State of the Art Reactor Consequence Analysis (SOARCA). NUREG 1935 is Reference 9 of NEI 13-02 Revision 1.

Section IV.C.9.3: SAWA Pump Hydraulic Analysis Calculation JAF-CALC-17-00104 (Reference 36) analyzed the FLEX pumps and the lineup for RPV injection that would be used for SAWA. This calculation showed that the pumps have adequate capacity to meet the SAWA flow rate required to protect containment.

Section IV.C.9.4: SAWA Method of backflow prevention NEI 13-02, Rev. 1 (Reference 7), Section 4.1.4.2 requires a means of backflow prevention for the SAWA/SAWM flow path into containment in order to prevent unintended cross flow and migration from containment into other areas within the plant. Existing safety related check valve 10AOV-68B provides a means of backflow prevention. Therefore, this order requirement is satisfied. These valves are tested as a part of the Inservice Testing (IST) program; therefore, additional testing is not required in accordance with HCVS-FAQ-05 and NEI 13-02 Section 6.2.3.3.

Section IV.C.9.5: SAWA Water Source JAF is located on the southeastern shore of Lake Ontario, which is the ultimate heat sink for the plant and the normal supply to the permanently installed Diesel Driven Fire Pump. This provides an unlimited water source throughout the ELAP/Severe Accident event. This long-term strategy of water supply was qualified for order EA-12-049 response and is available during a severe accident. Therefore, there will be sufficient water for injection to protect containment during the period of sustained operation.

Revision 0 Page 33 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section IV.C.9.6: SAWA/SAWM Motive Force Section IV.C.9.6.1: SAWA Pump Power Source The SAWA pumps are permanently installed in the Screenwell where they are protected from all screened-in hazards. The SAWA pumps are commercial fire pumps rated for long-term use in emergency scenarios. The pumps are diesel-driven by an engine mounted on the skid with the pump. The pumps will be refueled by the FLEX refueling equipment that has been qualified for long-term refueling operations per EA-12-049. The action to refuel the SAWA pumps was evaluated under severe accident conditions in Table 2 and demonstrated to be acceptable. Since the pumps are stored in a protected structure, are qualified for the environment in which they will be used, and will be refueled by a qualified refueling strategy, they will perform their function to maintain SAWA flow needed to protect primary containment per EA-13-109.

Section IV.C.9.6.2: DG loading calculation for SAWA/SAWM equipment Table 1 shows the electrical power source for the SAWA/SAWM instruments. For the HCVS instruments powered by the HCVS 24 VDC batteries, EC 9000052721 Attachment 6.003 demonstrates that the HCVS batteries can provide power until the FLEX generator restores power to the battery charger.

The FLEX load on the FLEX DG per EA-12-049 was evaluated in calculation JAF-CALC-15-00031 (Reference 44). This calculation demonstrated 29 kW of margin to full load. There are no additional loads on the FLEX DGs for SAWA and SAWM.

The FLEX generator is qualified to carry the rest of the FLEX loads as part of Order EA-12-049 compliance.

The existing safety-related (seismic) Low Pressure Coolant Injection inverter battery (71BAT-3B) is capable of opening RHR injection valve 10MOV-25B as evaluated in EC 620605 Attachment 6.002 (Reference 47); therefore, opening the LPCI injection valve 10MOV-25B does not require support from the FLEX DG.

Section IV.C.10: SAWA/SAWM Instrumentation

1) Section III.A.2 provides a complete listing of the specific instruments credited for SAWA.
2) The FLEX electromagnetic flow meter is used to provide a means of confirming the desired flow rate. The flow meter is installed on the FLEX (SAWA) valve cart stored in the Screenwell RHRSW Pump Room B. Since the flow meter is installed on the same cart that will be used for FLEX an N+1 FLEX cart with a flow meter is also stored in the Screenwell RHRSW Pump Room A although a backup flow meter is not required by EA-13-109.

Revision 0 Page 34 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109

3) The flow meter is designed for the expected flow rate, temperature, pressure and radiation for SAWA over the period of sustained operation. The flow range for the model selected for JAF is approximately 12 to 1000 GPM. This model is acceptable, because it bounds the JAF SAWA/SAWM flow rates of 71 to 361 gpm. The flow meter is rated for 150 psi which exceeds the 148 psi maximum expected pressure. The 10 to 130°F rated temperature range bounds the 11 to 110°F expected ambient/fluid temperature the meter will be exposed to (Reference 47 Topic Notes Section 3.1.9.5). The dose rate at the operating location of the flow meter cart (inside the Screenwell RHRSW Pump Room B) is <1 mR/hr (Reference 40). The total dose over the 7-day period is less than 1 rem, which is well below the generally accepted maximum for digital equipment, 1000 rem. The flow meter is commercial equipment and does not have a published radiation dose limit. The flow meter is generally rugged, is stored within a Class I Structure in an area protected from non-seismic equipment that could fall on the cart and the cart has its wheels chocked to prevent movement.

These measures are consistent with HCVS-OGP-011 to ensure availability following a seismic event (Reference 48).

4) The flow meter is self-powered from internal batteries with a life of 2.5 years.
5) Containment pressure and Torus level instrumentation will be repowered through their respective electrical buses using the FLEX diesel generator.

Section IV.C.10.1: SAWA/SAWM instruments Table 1 contains a listing of all the instruments needed for SAWA and SAWM implementation. This table also contains the expected environmental parameters for each instrument, its qualifications, and its power supply for sustained operation.

Section IV.C.10.2: Describe SAWA instruments and guidance The drywell pressure and Torus level instruments, used to monitor the condition of containment, are pressure and differential pressure detectors that are safety-related and qualified for post-accident use. These instruments are referenced in Severe Accident Guidelines for control of SAWA flow to maintain the Torus vent in service while maintaining containment protection. These instruments are powered by batteries for at least 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br /> (Ref. 53) and will be re-powered by FLEX generator systems for the sustained operating period. These instruments are on buses included in the FLEX generator loading calculations for EA-12-049 (Reference 44). Note that other indications of these parameters may be available depending on the exact scenario.

The SAWA flow meter is a portable digital based electromagnetic flow meter installed on the FLEX (SAWA) valve manifold cart and self-powered by internal batteries.

No containment temperature instrumentation is required for compliance with HCVS Revision 0 Page 35 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Phase 2. However, most FLEX electrical strategies repower other containment instruments that include drywell temperature, which may provide information for the operations staff to evaluate plant conditions under a severe accident and to provide confirmation for adjusting SAWA flow rates. SAOG strategies will evaluate and use drywell temperature indication if available consistent with the symptom-based approach. NEI 13-02 Revision 1 Section C.8.3 discusses installed drywell temperature indication.

Section IV.C.10.3: Qualification of SAWA/SAWM instruments The drywell pressure and Torus level instruments are pressure and differential pressure detectors that are safety-related and qualified for post-accident use.

These instruments are qualified per RG-1.97 Revision 2 (Reference 34) which is the JAF committed version per UFSAR Table 7.19-1 as post-accident instruments and are therefore qualified for EA-13-109 events.

The SAWA flow meter is rated for continuous use under the expected ambient conditions and so will be available for the entire period of sustained operation.

Furthermore, since the valve cart is located in the basement of the Screenwell, and on the opposite side of the RB from the vent pipe, there is no concern for any effects of radiation exposure to the flow instrument.

Section IV.C.10.4: Instrument Power Supply through Sustained Operation JAF FLEX strategies will restore the containment instruments, containment pressure and Torus level, necessary to successfully implement SAWA. The strategy will be to use the FLEX generator to re-power battery chargers before the batteries supplying the instruments are depleted. Since the FLEX generators are refueled per FLEX strategies for a sustained period of operation, the instruments will be powered for the sustained operating period.

Section IV.C.11: SAWA/SAWM Severe Accident Considerations Thermal and radiological impacts will not impact equipment (installed and portable), instrument functionality, or operators performing necessary actions for the SAWA/SAWM strategy. Key locations are MCR, ROS, Screenwell, and FLEX DG refueling locations. The most important Severe Accident consideration is the radiological dose as a result of the accident and operation of the HCVS. JAF-CALC-14-00029 (Reference 40) analyzed dose at different locations and times where operator actions will take place during FLEX/SAWA/SAWM activities. FSG-001 and FSG-ELAP provide guidance for ventilation strategies at various locations to mitigate high temperature conditions. JAF-CALC-17-00105 (Reference 49) determines the minimum temperature expected in the RHRSW Pump Rooms during an ELAP to ensure equipment remains operational. The other locations for personnel occupancy or equipment operation including the Reactor Building, Diesel Fire Pump Rooms, Switchgear Rooms, Battery Rooms, and MCR were evaluated as part of FLEX and those evaluations remain bounding for SAWA.

Revision 0 Page 36 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section IV.C.11.1: Severe Accident Effect on SAWA Pump and Flowpath Since the SAWA pump is permanently installed in the Screenwell and will be operated from outside the RB, on the opposite side of the RB from the vent pipe, there will be no issues with radiation dose rates at the SAWA pump control location and there will be no significant dose to the SAWA pump.

Inside the RB, the SAWA flow path consists of steel pipe which will remain unaffected by the radiation or elevated temperatures inside the RB. All SAWA hoses are contained within the Screenwell and, as noted for the SAWA pump, there will be no significant dose. Therefore, the SAWA flow path will not be affected by radiation or temperature effects due to a severe accident.

Section IV.C.11.2: Severe Accident Effect on SAWA/SAWM instruments The SAWA/SAWM instruments are described in section IV.C.9.3, that section provides severe accident effects Section IV.C.11.3: Severe Accident Effect on personnel actions Section IV.C.2 describes the RB actions within the first 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />. The actions including access routes outside the Reactor Building that will be performed after the first use of the vent during severe accident conditions (assumed to be 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> per HCVS-FAQ-12) are located such that they are either shielded from direct exposure to the vent line or are a significant distance from the vent line so that expected dose is maintained below the ERO exposure guidelines.

As part of the response to Order EA-12-049, JAF performed or referenced existing calculations of the temperature response of the Reactor and Control Buildings during the ELAP event. Since, in the severe accident, the core materials are contained inside the primary containment, the temperature response of the RB and Control Building (CB) is driven by the loss of ventilation and ambient conditions and therefore will not change. Thus, the FLEX calculations are acceptable for severe accident use.

Table 2 provides a list of SAWA/SAWM operator actions as well as an evaluation of each for suitability during a severe accident. Attachment 6 shows the approximate locations of the actions.

After the SAWA pipe is aligned inside the RB, the operators can control SAWA/SAWM as well as observe the necessary instruments from outside the RB.

Up to the first 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> (prior to the HCVS venting), the thick concrete RB walls as well as the distance to the core materials mean that there is no radiological concern with any actions outside the RB. Therefore, all SAWA controls and indications are accessible during severe accident conditions.

The SAWA pump and monitoring equipment can all be operated from the MCR or Revision 0 Page 37 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 from outside the RB below ground level. The JAF FLEX response ensures that the SAWA pump, FLEX generators, and other equipment can all be run for a sustained period by refueling. All the refueling locations are located in shielded or protected areas so that there is no radiation hazard from core material within the containment or from the HCVS vent line during a severe accident. The monitoring instrumentation includes SAWA flow at the pump, and Torus level and containment pressure in the MCR.

Section V: HCVS Programmatic Requirements Section V.A: HCVS Procedure Requirements Licensees shall develop, implement, and maintain procedures necessary for the safe operation of the HCVS. Procedures shall be established for system operations when normal and backup power is available, and during an extended loss of AC power.

Evaluation:

Procedures have been established for system operations when normal and backup power is available, and during ELAP conditions. The implementing design change documents contain instructions for modifying the HCVS specific procedures.

The HCVS and SAWA procedures have been developed and implemented following JAFs process for initiating and/or revising procedures and contain the following details:

  • appropriate conditions and criteria for use of the system
  • when and how to place the system in operation,
  • the location of system components,
  • instrumentation available,
  • normal and backup power supplies,
  • directions for sustained operation, including the storage location of portable equipment,
  • training on operating the portable equipment, and
  • testing portable equipment JAF has implemented the BWROG Emergency Procedures Committee Issue 1314 that implements the Severe Accident Water Management (SAWM) strategy in the Severe Accident Management Guidelines (SAMGs). The Revision 0 Page 38 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 following general cautions, priorities and methods have been evaluated for plant specific applicability and incorporated as appropriate into the plant specific SAMGs using administrative procedures for EPG/SAG change control process and implementation. SAMGs are symptom-based guidelines and therefore address a wide variety of possible plant conditions and capabilities. While these changes are intended to accommodate those specific conditions assumed in Order EA-13-109, the changes were made in a way that maintains the use of SAMGs in a symptom-based mode while at the same time addressing those conditions that may exist under extended loss of AC power (ELAP) conditions with significant core damage including ex-vessel core debris.

Cautions JAF Specific Caution wordings in SAOG-1:

  • Adding water to hot core debris may pressurize the primary containment by rapid steam generation
  • Raising Torus water level above 29.5 ft will result in loss of Torus vent capability Priorities - With significant core damage and RPB breach, SAOGs prioritize the preservation of primary containment integrity while limiting radioactivity releases as follows:
  • Water addition is managed to preserve the Mark I suppression chamber vent paths, thereby retaining the benefits of suppression pool scrubbing and minimizing the likelihood of radioactivity and hydrogen release into the secondary containment (SAWM)

Methods - Identify systems and capabilities to add water to the RPV or drywell, with the following generic guidance:

  • Use controlled injection if possible
  • Inject into the RPV if possible
  • Maintain injection from external sources of water as low as possible to preserve the suppression chamber vent capability Revision 0 Page 39 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section V.B: HCVS Out of Service Requirements Provisions for out-of-service requirements of the HCVS and compensatory measures have been added to CC-JF-118 so that it is with the FLEX out-of-service program.

Programmatic controls have been implemented to document and control the following:

NOTE: Out of service times and required actions noted below are for HCVS and SAWA functions. Equipment that also supports a FLEX function that is found to be non-functional must also be addressed using the out of service times and actions in accordance with the FLEX program.

The provisions for out-of-service requirements for HCVS and SAWA functionality are applicable in Modes 1, 2, and 3 per NEI 13-02, 6.3.

  • If for up to 90 consecutive days, the primary or alternate means of HCVS operation are non-functional, no compensatory actions are necessary.
  • If for up to 30 days, the primary and alternate means of HCVS operation or SAWA are non-functional, no compensatory actions are necessary.
  • If the out of service times projected to exceed 30 or 90 days as described above, the following actions will be performed through the corrective action system to determine:

o The cause(s) of the non-functionality, o The actions to be taken and the schedule for restoring the system to functional status and prevent recurrence, o Initiate action to implement appropriate compensatory actions, and o Restore full HCVS functionality at the earliest opportunity not to exceed one full operating cycle.

The HCVS system is functional when piping, valves, instrumentation and controls including motive force necessary to support system operation are available. Since the system is designed to allow a primary control and monitoring or alternate valve control by Order criteria 1.2.4 or 1.2.5, allowing for a longer out of service time with either of the functional capabilities maintained is justified. A shorter length of time when both primary control and monitoring and alternate valve control are unavailable is needed to restore system functionality in a timely manner while at the same time allowing for component repair or replacement in a time frame consistent with most high priority maintenance scheduling and repair programs, not to exceed 30 days unless compensatory actions are established per NEI 13-02 Revision 0 Page 40 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section 6.3.1.3.3.

SAWA is functional when piping, valves, motive force, instrumentation and controls necessary to support system operation are functional.

The system functionality basis is for coping with beyond design basis events and therefore plant shutdown to address non-functional conditions is not warranted.

However, such conditions should be addressed by the corrective action program and compensatory actions to address the non-functional condition should be established. These compensatory actions may include alternative containment venting strategies or other strategies needed to reduce the likelihood of loss of fission product cladding integrity during design basis and beyond design basis events even though the severe accident capability of the vent system is degraded or non-functional. Compensatory actions may include actions to reduce the likelihood of needing the vent but may not provide redundant vent capability.

Applicability for allowed out of service time for HCVS and SAWA for system functional requirements is limited to startup, power operation and hot shutdown conditions when primary containment is required to be operable and containment integrity may be challenged by decay heat generation.

Section V.C: HCVS Training Requirements Licensee shall train appropriate personnel in the use of the HCVS. The training curricula shall include system operations when normal and backup power is available, and during an extended loss of AC power.

Evaluation:

Personnel expected to perform direct execution of the HCVS have received necessary training in the use of plant procedures for system operations when normal and backup power is available and during ELAP conditions. The training will be refreshed on a periodic basis and as any changes occur to the HCVS. The personnel trained and the frequency of training was determined using a systematic analysis of the tasks to be performed using the Systems Approach to Training (SAT) process.

In addition, per NEI 12-06, any non-trained personnel on-site will be available to supplement trained personnel.

Section V.D: Demonstration with other Post Fukushima Measures JAF will demonstrate use of the HCVS and SAWA systems in drills, tabletops or exercises as follows:

1. Hardened containment vent operation on normal power sources (no ELAP)

Revision 0 Page 41 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109

2. During FLEX demonstrations (as required by EA-12-049: Hardened containment vent operation on backup power and from primary or alternate locations during conditions of ELAP/loss of UHS with no core damage.) System use is for containment heat removal AND containment pressure control.
3. HCVS operation on backup power and from primary or alternate location during conditions of ELAP/loss of UHS with core damage. System use is for containment heat removal AND containment pressure control with potential for combustible gases.

Evaluation NOTE: Items 1 and 2 above are not applicable to SAWA.

The use of the HCVS and SAWA capabilities will be demonstrated during drills, tabletops or exercises consistent with NEI 13-06 and on a frequency consistent with 10 CFR 50.155(e)(4). JAF will perform the first drill demonstrating at least one of the above capabilities by June 30, 2022 which is within four years of compliance with Phase 2 of Order EA-13-109, or consistent with the next FLEX strategy drill or exercise. Subsequent drills, tabletops or exercises will be performed to demonstrate the capabilities of different elements of Items 1, 2 and/or 3 above that is applicable to JAF in subsequent eight year intervals.

Revision 0 Page 42 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Section VI: References Number Rev Title Location6

1. GL-89-16 0 Installation of a Hardened Wetwell Vent ML031140220 (Generic Letter 89-16), dated September 1, 1989.
2. SECY-12-0157 0 Consideration of Additional Requirements for ML12345A030 Containment Venting Systems for Boiling Water Reactors with Mark I and Mark II Containments
3. SRM-SECY 0 Staff Requirements - SECY-12-0157 - ML13078A017 0157 Consideration of Additional Requirements for Containment Venting Systems for Boiling Water Reactors with Mark I and Mark II Containments
4. EA-12-050 0 Order to Modify Licenses with Regard to ML12054A694 Reliable Hardened Containment Vents
5. EA-13-109 0 Order to Modify Licenses with Regard to ML13143A334 Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions
6. NEI 13-02 0 Industry Guidance for Compliance with Order ML13316A853 EA-13-109, BWR Mark I & II Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions
7. NEI 13-027 1 Industry Guidance for Compliance with Order ML15113B318 EA-13-109, BWR Mark I & II Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions
8. HCVS-WP-01 0 Hardened Containment Vent System ML14120A295 Dedicated and Permanently Installed Motive ML14126A374 Force, Revision 0, April 14, 2014
9. HCVS-WP-02 0 Sequences for HCVS Design and Method for ML14358A038 Determining Radiological Dose from HCVS ML14358A040 Piping, Revision 0, October 23, 2014
10. HCVS-WP-03 1 Hydrogen/Carbon Monoxide Control ML14302A066 Measures Revision 1, October 2014 ML15040A038
11. HCVS-WP-04 0 Missile Evaluation for HCVS Components 30 ML15244A923 Feet Above Grade ML15240A072 6

Where two ADAMS accession numbers are listed, the first is the reference document and the second is the NRC endorsement of that document.

7 NEI 13-02 Revision 1 Appendix J contains HCVS-FAQ-01 through HCVS-FAQ-09.

Revision 0 Page 43 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Number Rev Title Location6

12. JLD-ISG-2013- 0 Compliance with Order EA-13-109, Order ML13304B836 02 Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions
13. JLD-ISG-2015- 0 Compliance with Order EA-13-109, Order ML15104A118 01 Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions
14. HCVS-FAQ-10 1 Severe Accident Multiple Unit Response ML15273A141 ML15271A148
15. HCVS-FAQ-11 0 Plant Response During a Severe Accident ML15273A141 ML15271A148
16. HCVS-FAQ-12 0 Radiological Evaluations on Plant Actions ML15273A141 Prior to HCVS Initial Use ML15271A148
17. HCVS-FAQ-13 0 Severe Accident Venting Actions Validation ML15273A141 ML15271A148
18. Phase 1 OIP 0 HCVS Phase 1 Overall Integrated Plan (OIP) ML14181B117
19. Phase 2 OIP 0 HCVS Phase 2 Overall Integrated Plan (OIP) ML15365A593
20. Phase 1 ISE 0 HCVS Phase 1 Interim Staff Evaluation (ISE) ML15007A090
21. Phase 2 ISE 0 HCVS Phase 2 Interim Staff Evaluation (ISE) ML16343B030
22. 1st Update 0 First Six Month Update ML14353A359
23. 2nd Update 0 Second Six Month Update ML15181A261
24. 3rd Update 0 Third Six Month Update ML15363A412
25. 4th Update 0 Fourth Six Month Update ML16182A377
26. 5th Update 0 Fifth Six Month Update ML16357A787
27. 6th Update 0 Sixth Six Month Update ML17180A951
28. 7th Update 0 Seventh Six Month Update ML16238A522
29. Compliance 0 HCVS Phase 1 and Phase 2 Compliance N/A Letter Letter
30. JAF-CALC 0 Reactor Building Heat Up During Extended N/A 00025 Loss of AC Power (ELAP)
31. JAF-CALC- 0 Main Control Room Heat-Up During Extended N/A MISC-04509 Loss of Offsite Power
32. NEI 12-06 4 Diverse and Flexible Coping Strategies ML16354B421 (FLEX) Implementation Guide Revision 0 Page 44 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Number Rev Title Location6

33. EA-12-049 0 Issuance of Order to Modify Licenses With ML12054A735 Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012.
34. JAF-RPT- 0 Updated Regulatory Guide 1.97 Assessment N/A MULTI-03366 for New York Power Authority JAF Nuclear Power Plant
35. TR-1026539 0 EPRI Investigation of Strategies for Mitigating N/A Radiological Releases in Severe Accidents BWR, Mark I and Mark II Studies, October 2012
36. JAF-CALC 0 HCVS Phase 2 SAWA Hydraulic Analysis N/A 00104
37. FLEX/SFPI SER 0 James A. Fitzpatrick Nuclear Power Plant - ML17342A006 Safety Evaluation Regarding Implementation Of Mitigating Strategies And Reliable Spent Fuel Pool Instrumentation Related To Orders EA-12-049 and EA-12-051
38. September 28, Hardened Wetwell Vent Capability at the ML13015A634 1992 Letter James A. FitzPatrick Nuclear Power Plant
39. JAF-CALC 0 Hardened Containment Vent System: N/A 00016 Process Piping Stress Analysis
40. JAF-CALC 0 Hardened Containment Vent System: Dose N/A 00029 Assessment
41. JAF-CALC 0 Hardened Containment Vent Capacity N/A 00015
42. JAF-CALC 0 Containment Heat Up Without Water Addition N/A 00026
43. EC 9000052721 0 Phase 1 Hardened Containment Vent N/A System (Parent EC)
44. JAF-CALC 0 FLEX Strategy - Portable Generator System N/A 00031 Sizing
45. JAF-CALC 0 Hardened Containment Vent System: N2 N/A 00013 Bottle and Venting Capacity
46. JAF-CALC 0 Hardened Containment Vent System: Purge N/A 00038 Bottle Sizing and PCV Setpoint Revision 0 Page 45 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Number Rev Title Location6

47. EC 620605 0 Hardened Containment Vent (HCVS) System N/A Phase 2
48. HCVS-HG-011 0 SAWA Potable Equipment Qualification N/A
49. JAF-CALC 0 Evaluation of JAF RHRSW Pump Rooms N/A 00105 Minimum Temperature during the Extended Loss of AC Power (ELAP)
50. JAF-CALC 0 Temperature Evaluation of Battery Room and N/A 00027 DC Equipment Room During Extended Loss of Offsite Power (FLEX)
51. JAF-CALC 0 Diesel Fire Pump Room Heatup for Extended N/A 00006 Loss of Offsite Power (FLEX)
52. JAF-CALC 0 Steady-State Temperature in El. 272 N/A 00020 Electrical Bays and EL. 272 EDG Switchgear Rooms During Phase 2 of Response to BDBEE
53. JAF-CALC 0 Station Service Batteries A and B Discharge N/A 00045 Capacity during Extended Loss of AC Power Revision 0 Page 46 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 1: Phase 2 Freeboard diagram SAWV El. 259-6 (354)

(Top of Torus)

Drywell Vent Pipe Intersection with Drywell Shell 257-11 Additional Freeboard Height 24 (2-0) Spillover

~51,586 gallons height=2.64 Drywell Floor 256-6 Freeboard Height 13-6 1/4 (162.25) Level Instrument Range (23LI-202A)

~ 813,012 gallons El. 231-7 to El. 257-6 (19 to 330)

Normal Torus Level (NTL)

El. 243-9 (167.75)

Bottom of Torus El. 230-0 (0)

EC 620605 Attachment 6.004 (Reference 47)

Revision 0 Page 47 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 2: One Line Diagram of HCVS Vent Path Revision 0 Page 48 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 3: One Line Diagram of HCVS Electrical Power Supply Revision 0 Page 49 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 4: One Line Diagram of SAWA Flow Path Revision 0 Page 50 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 5A: One Line Diagram of (FLEX) Electrical Power Supply Revision 0 Page 51 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 5B: One Line Diagram of (FLEX) Electrical Power Supply Revision 0 Page 52 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 6: Plant Layout Showing Operator Action Locations Revision 0 Page 53 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 6A: Reactor Building Elevation 272 Manual Action Locations Revision 0 Page 54 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 6B: Reactor Building Elevation 344 / 369-6 HCVS / FLEX Manual Actions Revision 0 Page 55 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Attachment 6C: FLEX Hose Connection for RPV Injection (Screenwell Elevation 260)

Revision 0 Page 56 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Table 1: List of HCVS Component, Control and Instrument Qualifications Local Local Local Qualification Component BDBEE Qualification Qualification Power Equipment ID Range Location BDBEE BDBEE Qualification Radiation Name Radiation Temp Humidity Supply Temp Humidity (TID)

(TID)

Torus Vent Instruments and Components HCVS Effluent 27RTD-115 50-700°F Above 344' RB 309°F 100% 5.3E7 Rad IEEE 323-1974 485°F 95% plus 3.0E8 Rad HCVS 24 Temperature Floor, on 8" pipe IEEE 344-1975 Chemical Spray VDC Batt &

Sensor Batt Charger HCVS Effluent 27RE-106 10E-2 to 369'-6 RB Floor, 309°F 100% 2.1E6 Rad IEEE-323-1974 350°F (max normal 100% 2.0E8 Rad HCVS 24 Radiation 10E4 R/hr adjacent to pipe IEEE 344-1975 operating) VDC Batt &

Detector Batt Charger HCVS Effluent 27RM-106 10E-2 to 27CAD-PNL-2 55-109°F 20-90% 1.2E2 Rad IEEE-323-1974 39-131°F 95% 1E3 Rad HCVS 24 Radiation 10E+4 Remote Operating IEEE 344-1975 VDC Batt &

Monitor Rad/hr Station Batt Charger (AB Corridor, El.

272)

HCVS Effluent 27TT-115 N/A 27CAD-PNL-1 55-109°F 20-90% 1.2E2 Rad IEEE 323-1974 185°F Sealed unit and 1E3 Rad HCVS 24 Temperature Remote Operating IEEE 344-1974 / coated circuit VDC Batt &

Transmitter Station -1987 board - high Batt Charger (AB Corridor, El. level of 272) humidity Circuit Breaker 27BRK-2 Various 27CAD-PNL-1 55-109°F 20-90% 1.2E2 Rad UL489 55-109°F 20-90% 1E3 Rad N/A (instruments) 27BRK-3 Remote Operating (Mild) (Mild) (Mild) IEEE 344- (Minimum**) (Minimum**)

Nitrogen 27BRK-4 Station Various Pressure 27BRK-5 (AB Corridor, El. IEEE 323-1974 Gauges 27BRK -8 272) UL 489 Circuit Breaker 27BRK -9 IEC 947.5.1 (Power Supply) 27PI-152 IEEE C37.90-Power Switch 27PI-149 1989 Valve Position 27BRK-1 Indicator Lights 27-1-SWHCVS Current / 27DC-117A / -117B Voltage / 27DC-118A / -118B Temperature 28DC-142A / -142B Indicator 27AM-1 27VM-1 27TI-115 Battery 27BAT-1 N/A DC Equipment 55-120°F 20-90% 3.3E-2 IEEE 344-1975 55-120°F 20-90% 1E3 Rad N/A Battery Charger 27BC-1 Room A, (Mild) (Mild) Rad UL 1012 (Minimum**) (Minimum**)

Circuit Breaker 27BRK-6 (AB El. 272) (Mild)

(Power Supply) 27BRK-7 Revision 0 Page 57 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Local Local Local Qualification Component BDBEE Qualification Qualification Power Equipment ID Range Location BDBEE BDBEE Qualification Radiation Name Radiation Temp Humidity Supply Temp Humidity (TID)

(TID)

HCVS Control 27PNS-142-1 N/A Reactor Building 309°F 100% 8.1E6 Rad IEEE 323-1974 > 309°F 100% 2.16E8 Rad HCVS 24 Valve (27AOV- 27PNS-142-2 El. 344 IEEE 344-1975 (Ref. EC VDC Batt &

142) Limit 9000052721 Topic Batt Charger Switches Notes Section 3.1.5.1)

HCVS Valve 27AOV-142 (OP) N/A Reactor Building 309°F 100% 8.1E6 Rad IEEE 323-1974 > 309°F 100% 7.8E7 Rad N/A Actuators El. 344 IEEE 344-1987 (Ref. EC 9000052721 Topic Notes Section 3.1.6.2)

Torus Level 23LI-202A 1.7-27.5 MCR* N/A N/A N/A IEEE 323-1974 RG 1.97 RG 1.97 RG 1.97 Backed by Indicator IEEE 344-1975 FLEX DG Torus Level 23LT-202A 1.7-27.5 RB El. 227 N/A N/A N/A IEEE 323-1974 RG 1.97 RG 1.97 RG 1.97 Backed by Transmitter IEEE 344-1975 FLEX DG Drywell 27PI-115A2 0-250 psig MCR* N/A N/A N/A IEEE 323-1974 RG 1.97 RG 1.97 RG 1.97 Backed by Pressure IEEE 344-1975 FLEX DG Indicator Drywell 27PT-115A2 0-250 psig RB El. 344 N/A N/A N/A IEEE 323-1974 RG 1.97 RG 1.97 RG 1.97 Backed by Pressure IEEE 344-1975 FLEX DG Transmitter SAWA Flow N/A 12-1,000 RHR Pump Room 11-110°F 90% <1R N/A 10 - 130°F N/A 1E3 TID Internal Meter gpm B (Screenwell El. Batteries 260)

  • Denotes Control Building where local radiation levels are not applicable. Building has no significant radiation sources.
    • Denotes components with least margin to the expected temperature and humidity conditions Revision 0 Page 58 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Table 2: Operator Actions Evaluation Evaluation Validation Thermal Operator Action Location Radiological Conditions Evaluation Time8 Time conditions 1 Open Reactor 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> 47 minutes Reactor Building El. 272 < 110°F 1.258E-01 rem/hr Acceptable Building Doors (Goal 1 (Track Bay) and 369-6 (Ventilation) hour) [[::JAF-VP-011|JAF-VP-011]] from original FLEX validation 2 Close Valve 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 15 minutes Reactor Building El. 344 < 110°F 1.258E-01 rem/hr Acceptable 27MOV-121, if (Goal 1 30 seconds required (HCVS) hour) [[::JAF-VP-012|JAF-VP-012]] revised for HCVS modifications 3 Open Valves 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Reactor Building El. 272 < 110°F 7.04E+03 mrem/hr Acceptable 10MOV-148B / - (Goal 1 26 minutes (42 minute stay time; 149B (SAWA) hour) validation timing shows [[::JAF-VP-018|JAF-VP-018]] revised for task completed in less HCVS modifications than 15 minutes) 4 Close Valve 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Screenwell El. 260 < 110°F Outside Reactor Building, Acceptable 76FPS-807 26 minutes shielded by intervening Open Valves structures and concrete, [[::JAF-VP-018|JAF-VP-018]] revised for 76FPS-780 / low to no dose. HCVS modifications 10RHR-460 (SAWA) 8 Evaluation timing is from NEI 13-02 to support radiological evaluations.

Revision 0 Page 59 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Evaluation Validation Thermal Operator Action Location Radiological Conditions Evaluation Time8 Time conditions 5 Electrical Load 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 30 minutes (None in RB) < 110°F Outside Reactor Building Acceptable Shed West Elec Bay (272') and shielded by South Emer SWG Room intervening structures and Combination of:

(272') concrete, low to no dose. 1) Most limiting AOP-Relay Room (284') 49 load shed Battery Room (272') individual actions Fan Room (300') documented in [[::JAF-VP-001|JAF-VP-001]] from original FLEX validation (16 min 21 seconds)

2) Most limiting FSG-002 deep load shed individual actions documented in [[::JAF-VP-008|JAF-VP-008]] from original FLEX validation (12 minutes 23 seconds) 6 Stage and Start 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> North of Screenwell Outdoors 4.86E+01 mrem/hr Acceptable FLEX DG 5 minutes (Ambient) Outside Reactor Building, shielded by intervening [[::JAF-VP-015|JAF-VP-015]] from structures and concrete original FLEX validation 102 hour0.00118 days <br />0.0283 hours <br />1.686508e-4 weeks <br />3.8811e-5 months <br /> stay time after (using N+1 equipment) the start of venting.

7 Stage SAWA 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Screenwell El. 260 < 110°F Outside Reactor Building, Acceptable pump / hoses / 26 minutes shielded by intervening cart structures and concrete, [[::JAF-VP-018|JAF-VP-018]] revised for no radiological concern. HCVS modifications 8 Open Fire Pump 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Screenwell El. 260 < 110°F Outside Reactor Building, Acceptable Room Doors (as 26 minutes shielded by intervening required) structures and concrete, [[::JAF-VP-018|JAF-VP-018]] revised for 76FDR-SP-255-5 no radiological concern HCVS modifications 76FDR-SP-255-6 76FDR-SP-255-7 Revision 0 Page 60 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Evaluation Validation Thermal Operator Action Location Radiological Conditions Evaluation Time8 Time conditions 9 Open Valve 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Main Control Room <120°F MCR is removed from the Acceptable 27MOV-25B (Goal 1 26 minutes (Switch using LPCI vent pipes and RP actions (SAWA) hour) Batteries) will provide protection from MCR is a preferred any airborne activity location based on HCVS-FAQ-1.

[[::JAF-VP-018|JAF-VP-018]] revised for HCVS modifications 10 Open HCVS Vent 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 15 minutes Remote Operating < 110°F 6.634E-01 rem/hr Acceptable Valves 27AOV- (approximate 30 seconds Station Protected by intervening 117 / -118 / -142 venting start) (AB Corridor El. 272) structures [[::JAF-VP-012|JAF-VP-012]] revised for 7 hour8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> stay time HCVS modifications 11 Monitor 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> 15 minutes Main Control Room <120°F MCR is removed from the Acceptable Containment (approximate 30 seconds vent pipes and RP actions Pressure and venting start) will provide protection from MCR is a preferred Torus Level any airborne activity location based on HCVS-FAQ-1.

[[::JAF-VP-012|JAF-VP-012]] revised for HCVS modifications 12 Start SAWA Pump 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Screenwell El. 260 < 110°F Shielded by intervening Acceptable and inject at 361 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> 26 minutes structures and concrete, gpm no radiological concern. [[::JAF-VP-018|JAF-VP-018]] revised for HCVS modifications 13 Reduce SAWA 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Screenwell El. 260 < 110°F Shielded by intervening Acceptable Pump injection to 168 hours0.00194 days <br />0.0467 hours <br />2.777778e-4 weeks <br />6.3924e-5 months <br /> 26 minutes structures and concrete, 73 gpm no radiological concern. [[::JAF-VP-018|JAF-VP-018]] revised for HCVS modifications 14 Open Fire Doors 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> 6 minutes DC Equipment and < 110°F Protected by intervening Acceptable (as required in Battery Charger Rooms structures Summer) (AB El. 272) [[::JAF-VP-016|JAF-VP-016]] from 76FDR-HB-272-2 original FLEX validation 76FDR-HB-272-3 76FDR-HB-272-4 76FDR-HB-272-5 76FDR-HD-272-6 Revision 0 Page 61 August 28, 2018

Final Integrated Plan HCVS Order EA-13-109 Evaluation Validation Thermal Operator Action Location Radiological Conditions Evaluation Time8 Time conditions 15 Refuel Diesel 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br /> (1 14.64 hours7.407407e-4 days <br />0.0178 hours <br />1.058201e-4 weeks <br />2.4352e-5 months <br /> West of Screenwell Outdoors < 1 mr/hr - At DDFP Acceptable Driven Fire Pump hour refuel (Ambient) 7.80E+01 mr/hr - At time required) Refuel Skid New JAF-VP-HCVS-001 Shielded by intervening validation structures and concrete.

102 hour0.00118 days <br />0.0283 hours <br />1.686508e-4 weeks <br />3.8811e-5 months <br /> stay time at Refuel Skid after the start of venting.

16 Refuel FLEX 15.4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> 13.55 hours6.365741e-4 days <br />0.0153 hours <br />9.093915e-5 weeks <br />2.09275e-5 months <br /> West of Screenwell Outdoors 4.86E+01- At DG Acceptable Diesel Generator (0.8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> (Ambient) 7.80E+01 mr/hr - At refuel time Refuel Skid New JAF-VP-HCVS-001 required) Shielded by intervening validation structures and concrete.

102 hour0.00118 days <br />0.0283 hours <br />1.686508e-4 weeks <br />3.8811e-5 months <br /> stay time at DG and 64 hours7.407407e-4 days <br />0.0178 hours <br />1.058201e-4 weeks <br />2.4352e-5 months <br /> at Refuel Skid after the start of venting.

17 Repower HCVS 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Administration Building < 110°F Protected by intervening Acceptable Battery Charger 14 minutes DC Equipment Room A structures (Extension Cord to New JAF-VP-HCVS-002 Administration validation 18 Replenish 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Remote Operating < 110°F 6.634E-01 rem/hr Acceptable Nitrogen Bottles 20 minutes Station Protected by intervening (AB Corridor El. 272) structures New JAF-VP-HCVS-003 7 hour8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> stay time after the validation start of venting.

Revision 0 Page 62 August 28, 2018