MONTHYEARML24032A2752024-02-0707 February 2024 Pre-Pre-Submittal Meeting for Proposed License Amendment Regarding Hydrologic Analysis Updates (Slides) ML24019A1512024-01-22022 January 2024 Slides - Modification of Browns Ferry Technical Specifications to Eliminate LCO 3.3.2.1 Actions C.2.1.1 and C.2.1.2 for Rod Worth ML23130A0912023-05-11011 May 2023 TVA Browns Ferry Nuclear Plant Safety Pre-Application Public Meeting Slides 05/11/2023 ML23130A0922023-05-11011 May 2023 NRC Browns Ferry Nuclear Plant, Units 1, 2, and 3, Subsequent License Renewal Application, Public Meeting Slides ML23128A2882023-05-0808 May 2023 TVA Nuclear Plants -2022 EOC Media Slides ML23025A0472023-01-25025 January 2023 Pre-Submittal Meeting for Proposed License Amendment Request Regarding Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves - January 25, 2023 ML22285A1902022-10-13013 October 2022 October 13, 2022 Public Meeting on 5th Interval Alternative Planned Requests - Licensee Slides ML22279A8992022-10-0606 October 2022 Subsequent License Renewal Application - SAMA Pre-Application Meeting October 6, 2022-TVA Slides ML22277A6562022-10-0606 October 2022 Subsequent License Renewal Application - SAMA Pre-Application Meeting October, 2022 (TVA Slides) ML22264A2332022-09-22022 September 2022 Slides for Pre-Submittal Meeting for Request to Use a Later Edition of the ASME OM Code for the Fifth Inservice Testing (IST) 10-Year Interval ML22080A1662022-03-21021 March 2022 TVA Nuclear Plants -2021 EOC Media Loop Slides for Automatic Play ML21281A2282021-10-13013 October 2021 Tennessee Valley Authority Fleet Pre-Submittal Meeting for License Amendment Request to Change Emergency Action Level Scheme Presentation - October 13, 2021 (EPID L-2021-LRM-0096) (Slides) ML21270A0322021-09-27027 September 2021 Presentation Slides for Browns Ferry Pre-submittal Public Meeting September 27, 2021 ML21265A0422021-09-21021 September 2021 Presentation Slides for Browns Ferry Pre-submittal Public Meeting 09/22/2021 ML21250A3012021-09-0707 September 2021 TVA Slides for September 7, 2021, Presubmittal Meeting to Discuss Planned Browns Ferry TSTF-505 License Amendment Request ML21152A1872021-06-0101 June 2021 TVA Slides for June 1, 2021, Presubmittal Meeting to Discuss Planned Control Bay Chiller Cross-Tie License Amendment Request ML24019A1322020-11-0909 November 2020 ANP-3874NP, Revision 1, Browns Ferry Atrium 11 Control Rod Drop Accident Analysis with the AURORA-B CRDA ML20175A0552020-06-23023 June 2020 TVA Slides for June 23, 2020, Emergency Plan Change Presubmittal Meeting ML20156A2812020-06-0808 June 2020 TVA Slides for June 8, 2020, ATRIUM-11 Presubmittal Meeting ML20092F5742020-04-0202 April 2020 TVA Slides for Browns Ferry 50.69 License Amendment Request Presubmittal Meeting ML20049G1822020-02-18018 February 2020 February 20, 2020 - Pre-submittal Meeting Presentation - Transition to Westinghouse Fuel ML20022A0262020-01-22022 January 2020 NEI Presentation Status Update for Ropte Short Term Action Plan: Removed Planned Unavailability for Mitigating Systems Performance Index ML24019A1482019-01-28028 January 2019 Surveillance Procedure 2-SR-3.1.6.1, BPWS Compliance Verification, Revision 006 ML18255A0142018-09-12012 September 2018 BWROG Presentation Slides for Public Meeting Sept 12 2018 ML18255A0102018-09-12012 September 2018 NRC Slides for Target Rock Public Meeting ML18239A2522018-08-27027 August 2018 Proposed Changes to NFPA 805 License Conditions ML18158A2862018-06-0707 June 2018 May 30, 2018 Summary of Public Meeting with Browns Ferry Nuclear Plant, Docket No. 50-259, 50-260, and 50-296 ML17271A0162017-09-28028 September 2017 Meeting Slide for Tennessee Valley Authority (TVA) Hydrology Precipitation Model Topical Report Review Status ML17212A8432017-08-0101 August 2017 Meeting Slides for Pre-submittal Meeting with Tennessee Valley Authority on Unbalanced Voltage License Amendment Request for TVA Nuclear Plants ML17034A3322017-02-0303 February 2017 Presentation Slides for Public Meeting Regarding Browns Ferry Extended Power Uprate License Amendment Request Transmission System Update Supplements ML16356A0342017-01-0404 January 2017 Pre-app Meeting Mellla+ LAR Final ML16341A7422017-01-0404 January 2017 Presentation Slides for Browns Ferry Pre-application Meeting Regarding Mellla+ ML16350A2962016-12-14014 December 2016 Enclosure 3- Reactor Oversight Process Task Force FAQ Log- November 16, 2016 ML16279A2332016-10-0505 October 2016 Summary of Closed Pre-Decisional Enforcement Conference with Tennessee Valley Authority Regarding Browns Ferry Nuclear Plant ML16200A2592016-07-19019 July 2016 July 19, 2016: NRC Public Meeting on Browns Ferry Nuclear Plant Extended Power Uprate License Amendment Request ML16189A3482016-07-19019 July 2016 Presentation Slides for July 19, 2016, Public Meeting ML16028A0962016-02-0101 February 2016 Emergency Core Cooling System Preferred Pump Logic, Common Accident Signal Logic, and Unit Priority Re-Trip Logic License Amendment Request ML15308A1002015-11-10010 November 2015 Public Meeting Presentation Slides Extended Power Uprate License Amendment Request NRC Public Meeting ML15195A1252015-07-14014 July 2015 July 14, 2015 - Public Meeting Slides on Browns Ferry Seismic Risk Insights ML15293A4582015-07-14014 July 2015 Slides for July 14, 2015 Public Meeting on Browns Ferry Seismic Risk Evaluations (MF3764 Through MF3766) CNL-15-122, Presentation Slides for Closed Meeting Extended Power Uprate (EPU) License Amendment Request2015-07-0808 July 2015 Presentation Slides for Closed Meeting Extended Power Uprate (EPU) License Amendment Request ML15146A2792015-05-21021 May 2015 Bf EOC Meeting Summary 2015 ML15099A2912015-04-22022 April 2015 4/22/2015, Enclosure 2, Slides for TVA Presentation to the NRC in Support of Steam Dryer Replacement ML14147A3222014-05-27027 May 2014 Public Meeting Summary 05/21/2014 to Present Annual Assessment ML14101A1522014-04-11011 April 2014 Summary of Public and Closed Meeting for Tennessee Valley Authority 2013 Synergy Safety Culture Survey Results ML14090A4582014-03-31031 March 2014 Public Meeting Summary TVA Synergy Safety Culture Survey Results ML14036A3872014-02-0505 February 2014 Summary of Meeting with Public to Discuss the Results of the Follow-up Inspection of the Items Identified in Confirmatory Action Letter (ML13232A105) of August 22, 2013, and the Status of Nrc'S Performance Assessment of Browns Ferry Unit 1 IR 05000260/20132012013-07-30030 July 2013 07/24/2013 Summary of Public Conference Meeting With Tennessee Valley Authority to Discuss Safety Significance of One Preliminary Greater Than Green Finding Associated with One Apparent Violation Documented in NRC Inspection Report 05000260 ML13212A0842013-07-30030 July 2013 Summary of Public Conference Meeting with Tennessee Valley Authority to Discuss Safety Significance of One Preliminary Greater than Green Finding Associated with One Apparent Violation Documented in NRC Inspection Report 05000260/20132012 ML13199A4522013-07-17017 July 2013 Summary of Meeting with Browns Ferry 2024-02-07
[Table view] |
Text
Browns Ferry Nuclear Plant Units 1, 2, and 3 Proposed Changes to NFPA 805 License Conditions August 28, 2018
Proposed Changes to NFPA 805 License Condition TVA proposes to submit a LAR that will request NRC approval to make the following changes to the BFN NFPA 805 Program:
Extend due dates for Modifications 102 and 106 by 4 months and 6 months, respectively Eliminate Modification 85 - CO2 Pneumatic Alarm and Time Delay from LAR Table S-2 and revise Table B-1 as appropriate Revise Operating Licenses Changes to NFPA 805 License Conditions l August 28, 2018 l 2
Current Status of NFPA 805 Modifications at BFN There are a total of fifty-seven (57) modifications items listed in the S-2 Table 42 of the items are completed 15 items remain to be completed Currently all modifications are scheduled to be completed by the end of the BFN Unit 2, Refueling Outage 20 scheduled for the Spring of 2019 Changes to NFPA 805 License Conditions l August 28, 2018 l 3
MODIFICATION 102 o Status o Modification is in progress with all stages in plant schedule o 10 separate stages o Current commitment due date Spring 2019 (U2R20 Outage) o More Time Needed o Risk of work being delayed o Weather o Plant conditions restricting work in the switchyard o Extend due date to four months following the end of the outage i.e., August 14, 2019 Changes to NFPA 805 License Conditions l July 24, 2018 l 4
MODIFICATION 106 o New intake station dedicated to bearing lube water.
o Fire Pump currently needed to support Cooling Tower lift pumps o Status o Major construction project o Engineering, procurement and construction contract being put in place o Current commitment due date is Spring 2019 (U2R20 Outage) o More Time Needed o Schedule is aggressive and more time may be needed if problems arise o Extend due date to six months following then end of the outage i.e., October 14, 2019 Changes to NFPA 805 License Conditions l August 28, 2018 l 5
MODIFICATION 85 o Difficulty developing a design compatible with old CARDOX CO2 system o 300 psig Liquid CO2 will require custom design o Maintaining UL and Seismic qualification o 20 separate control stations impacted o Uncertainties in the scope of vendor qualification effort o Justification o No impact on Operator fire event response o No impact on Fire suppression o No impact on plant risk o Existing electrical pre-discharge alarm meets the code of record - NFPA 12-1966 Changes to NFPA 805 License Conditions l August 28, 2018 l 6
NFPA 805 LAR Submittal This NFPA 805 LAR follows the guidance provided by NEI for making changes to the NFPA 805 program (Option A)
(Refer to NEI Letter to NRC, Recommended content for License Amendment Requests that Seek Changes to License Conditions That Were Established in Amendments to Adopt National Fire Protection Association Standard 805 but Have Yet to be Fully Implemented, dated March 2, 2016 (ML16015A416))
Changes to NFPA 805 License Conditions l August 28, 2018 l 7
Questions Changes to NFPA 805 License Conditions l August 28, 2018 l 8