MONTHYEARIR 05000237/20230042024-02-0202 February 2024 Integrated Inspection Report 05000237/2023004 and 05000249/2023004 IR 05000010/20230012024-01-17017 January 2024 NRC Inspection Report 05000010/2023001 (Drss) IR 05000237/20230032023-11-13013 November 2023 Integrated Inspection Report 05000237/2023003 and 05000249/2023003 and Exercise of Enforcement Discretion IR 05000237/20230112023-09-0606 September 2023 Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 IR 05000237/20234022023-08-29029 August 2023 Security Baseline Inspection Report 05000237/2023402 and 05000249/2023402 IR 05000237/20230022023-08-0808 August 2023 Integrated Inspection Report 05000237/2023002 and 05000249/2023002 IR 05000237/20233012023-05-30030 May 2023 NRC Initial License Examination Report 05000237/2023301; 05000249/2023301 IR 05000237/20230012023-05-0404 May 2023 Integrated Inspection Report 05000237/2023001 and 05000249/2023001 IR 05000237/20234012023-04-26026 April 2023 Cyber Security Inspection Report 05000237/2023401 and 05000249/2023401 IR 05000237/20235012023-04-21021 April 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000237/2023501 and 05000249/2023501 IR 05000237/20230102023-03-0909 March 2023 Biennial Problem Identification and Resolution Inspection Report 05000237/2023010 and 05000249/2023010 IR 05000237/20220062023-03-0101 March 2023 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2022006 and 05000249/2022006) IR 05000237/20220042023-02-10010 February 2023 Integrated Inspection Report 05000237/2022004, 05000249/2022004 and 07200037/2022002 IR 05000237/20224022023-01-0505 January 2023 Security Baseline Inspection Report 05000237/2022402 and 05000249/2022402 IR 05000237/20224012022-11-30030 November 2022 Security Baseline Inspection Report 05000237/2022401 and 05000249/2022401 (Cover Letter Only) IR 05000237/20220032022-10-31031 October 2022 Integrated Inspection Report 05000237/2022003 and 05000249/2022003 ML22270A1032022-09-27027 September 2022 Notification of NRC Baseline Inspection and Request for Information (05000249/2022004) IR 05000237/20220122022-09-0606 September 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000237/2022012 and 05000249/2022012 IR 05000237/20220052022-08-22022 August 2022 Updated Inspection Plan for Dresden Nuclear Power Station (Report 05000237/2022005; 05000249/2022005) IR 05000010/20220012022-08-0808 August 2022 NRC Inspection Report No. 05000010/2022001(DNMS) - Dresden Nuclear Power Station, Unit 1 IR 05000237/20220022022-08-0808 August 2022 Integrated Inspection Report 05000237/2022002; 05000249/2022002 and 07200037/2022002 and Exercise of Enforcement Discretion ML22180A2512022-06-30030 June 2022 2022 Dresden Cover Letter IR 05000237/20220012022-04-20020 April 2022 Integrated Inspection Report 05000237/2022001 and 05000249/2022001 IR 05000237/20220112022-04-12012 April 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000237/2022011 and 05000249/2022011 IR 05000237/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000237/2021006 and 05000249/2021006) IR 05000237/20210042022-02-0707 February 2022 Integrated Inspection Report 05000237/2021004 and 05000249/2021004 IR 05000237/20214032022-01-26026 January 2022 Security Baseline Inspection Report 05000237/2021403 and 05000249/2021403 IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 IR 05000237/20220102021-12-21021 December 2021 Notification of NRC DBAI (Programs) and Initial RFI Inspection Report 05000237/2022010 05000249/2022010 IR 05000010/20210012021-11-0909 November 2021 NRC Inspection Report No. 05000010/2021001(DNMS) - Dresden Nuclear Power Station, Unit 1 IR 05000237/20210032021-11-0101 November 2021 Integrated Inspection Report 05000237/2021003 and 05000249/2021003 IR 05000237/20210112021-09-30030 September 2021 Triennial Fire Protection Inspection Report 05000237/2021011 and 05000249/2021011 IR 05000237/20210052021-09-0101 September 2021 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3, Report 05000237/2021005 and 05000249/2021005 IR 05000237/20215012021-08-25025 August 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000237/2021501 and 05000249/2021501 IR 05000237/20210022021-08-0909 August 2021 Integrated Inspection Report 05000237/2021002 and 05000249/2021002 IR 05000237/20214042021-08-0909 August 2021 Security Baseline Inspection Report 05000237/2021404 and 05000249/2021404 IR 05000237/20213012021-06-17017 June 2021 NRC Initial License Examination Report 05000237/2021301; 05000249/2021301 IR 05000237/20214012021-05-21021 May 2021 Cyber Security Inspection Report 05000237/2021401 and 05000249/2021401 IR 05000237/20210012021-04-13013 April 2021 Integrated Inspection Report 05000237/2021001 and 05000249/2021001 IR 05000237/20214022021-03-16016 March 2021 Security Baseline Inspection Report 05000237/2021402 and 05000249/2021402 IR 05000237/20200062021-03-0404 March 2021 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020006 and 05000249/2020006) IR 05000237/20210102021-02-23023 February 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000237/2021010 and 05000249/2021010 IR 05000237/20200042021-02-10010 February 2021 Integrated Inspection Report 05000237/2020004 and 05000249/2020004 IR 05000237/20200902020-12-17017 December 2020 Reissue Dresden Nuclear Power Station, Units 2 and 3 - NRC Inspection Report 05000237/2020090 and 05000249/2020090 IR 05000237/20204032020-12-16016 December 2020 Security Baseline Inspection Report 05000237/2020403 and 05000249/2020403 ML20342A2832020-12-0707 December 2020 NRC Inspection Report 05000237/2020090 and 05000249/2020090 IR 05000237/20200032020-11-10010 November 2020 Integrated Inspection Report 05000237/2020003 and 05000249/2020003 ML20307A4832020-11-0202 November 2020 NRC Inspection Report No. 05000010/20200001 (DNMS) - Dresden Nuclear Power Station, Unit 1 IR 05000237/20200052020-09-0101 September 2020 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020005 and 05000249/2020005) IR 05000237/20203012020-08-27027 August 2020 NRC Initial License Examination Report 05000237/2020301; 05000249/2020301 2024-02-02
[Table view] Category:Letter
MONTHYEARIR 05000237/20230042024-02-0202 February 2024 Integrated Inspection Report 05000237/2023004 and 05000249/2023004 IR 05000010/20230012024-01-17017 January 2024 NRC Inspection Report 05000010/2023001 (Drss) ML23354A2812024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0031 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 RS-23-121, Sixth Ten-Year Interval Inservice Testing Program2023-11-30030 November 2023 Sixth Ten-Year Interval Inservice Testing Program SVPLTR 23-0037, Core Operating Limits Report for Cycle 292023-11-29029 November 2023 Core Operating Limits Report for Cycle 29 RS-23-119, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-107, Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-11-0808 November 2023 Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-102, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23279A0712023-10-0606 October 2023 Response to NRC Dresden Nuclear Power Station, Units 2 and 3 - Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 ML23269A0662023-09-28028 September 2023 Proposed Alternative Request RV-23H Associated with the Sixth 10-Year Inservice Testing Interval ML23265A1322023-09-27027 September 2023 Proposed Alternative Request RV-03 Associated with the Sixth 10-Year Inservice Testing Interval ML23205A1362023-09-20020 September 2023 Proposed Alternative Request RV-02D Associated with the Sixth IST Interval IR 05000237/20230112023-09-0606 September 2023 Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 RS-23-071, Application to Adopt TSTF-564, Safety Limit MCPR2023-08-30030 August 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs IR 05000237/20234022023-08-29029 August 2023 Security Baseline Inspection Report 05000237/2023402 and 05000249/2023402 IR 05000237/20230022023-08-0808 August 2023 Integrated Inspection Report 05000237/2023002 and 05000249/2023002 ML23212A9892023-08-0303 August 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23174A1502023-08-0303 August 2023 Issuance of Amendment Nos. 282 and 275 Control Rod Scram Times ML23193A0052023-07-28028 July 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23192A6292023-07-11011 July 2023 Correction Letter - Issuance of Amendment Nos. 281 and 274 Regarding Transition to GNF3 Fuel (EPID L-2022-LLA-0121) (Non-Proprietary) ML23144A3142023-07-0606 July 2023 Issuance of Amendment Nos. 281 and 274 Transition to GNF3 Fuel (EPID L-2022-LLA-0121) - Nonproprietary ML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III SVPLTR 23-0021, Registration of Use of Casks to Store Spent Fuel2023-06-20020 June 2023 Registration of Use of Casks to Store Spent Fuel RS-23-078, Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times2023-06-16016 June 2023 Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20233012023-05-30030 May 2023 NRC Initial License Examination Report 05000237/2023301; 05000249/2023301 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23132A0932023-05-17017 May 2023 Information Meeting (Public Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Dresden Power Station, Units 2 and 3 RS-23-070, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-05-16016 May 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel SVPLTR 23-0018, Submittal of 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report IR 05000237/20230012023-05-0404 May 2023 Integrated Inspection Report 05000237/2023001 and 05000249/2023001 SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000237/20234012023-04-26026 April 2023 Cyber Security Inspection Report 05000237/2023401 and 05000249/2023401 ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration IR 05000237/20235012023-04-21021 April 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000237/2023501 and 05000249/2023501 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection RS-23-057, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-04-17017 April 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel SVPLTR 23-0014, Annual Dose Report for 20222023-04-15015 April 2023 Annual Dose Report for 2022 ML23088A2242023-04-0505 April 2023 Regulatory Audit Report Regarding License Amendment Request to Transition to GNF3 Fuel ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 2024-02-02
[Table view] |
See also: IR 05000249/2018004
Text
August 16, 2018
Mr. Bryan C. Hanson
Senior VP, Exelon Generation Co., LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3NOTIFICATION OF
NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION;
INSPECTION REPORT 05000249/2018004
Dear Mr. Hanson:
On October 29, 2018 the U.S. Nuclear Regulatory Commission (NRC) is scheduled to begin
the Baseline Inservice Inspection Procedure 71111.08. This onsite inspection is currently
scheduled to be performed October 29, 2018, through November 3, 2018, but this schedule is
subject to change based on licensee Inservice Inspection activities.
Experience has shown that this inspection is resource intensive both for the NRC inspector and
your staff. In order to minimize the impact to your onsite resources, and to ensure a productive
inspection for both sides, we have enclosed a request for documents needed for this inspection.
These documents have been divided into two groups.
The first group identifies information necessary to ensure that the inspector is adequately
prepared. The second group identifies the information the inspector will need upon arrival at
the site. It is important that all of these documents are up-to-date, and complete, in order to
minimize the number of additional documents requested during the preparation and/or the
onsite portions of the inspection.
We understand that our regulatory contact for this inspection will be Mr. Dean Walker, of your
organization. If there are any questions about this inspection or the material requested, please
contact the lead inspector Mr. Matt Domke at 630-829-9562, or via e-mail at MJD4@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
B. Hanson -2-
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,
Exemptions, Requests for Withholding.
Sincerely,
/RA/
Matt Domke, Reactor Inspector
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-237, 50-249
License Nos. DPR-19; DPR-25
Enclosure:
Document Request for Baseline Inservice
Inspection
cc: Distribution via LISTSERV
B. Hanson -3-
Letter to Bryan C. Hanson from Matt Domke dated August 16, 2018
SUBJECT: DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3NOTIFICATION OF
NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION;
INSPECTION REPORT 05000249/2018004
DISTRIBUTION:
Jeremy Bowen
RidsNrrDorlLpl3
RidsNrrPMDresden Resource
RidsNrrDirsIrib Resource
Steven West
Darrell Roberts
Richard Skokowski
Allan Barker
DRPIII
DRSIII
ADAMS Accession Number ML: 18229A146
OFFICE RIII RIII RIII RIII
NAME MDomke:cl
DATE 08/16/18
OFFICIAL RECORD COPY
DOCUMENT REQUEST FOR BASELINE INSERVICE INSPECTION
Inspection Report: 05000249/2018004
Inspection Dates: October 29, 2018, through November 2, 2018 (tentative dates)
Inspection Procedures: Inspection Procedure 71111-08, Inservice Inspection
Lead Inspector: Matt Domke, DRS
630-829-9562
MJD4@nrc.gov
A. Information for the In-Office Preparation Week
The following information (electronic copy CD ROM if possible) is requested by
October 1, 2018, to facilitate the selection of specific items that will be reviewed during
the onsite inspection week. The inspector will select specific items from the information
requested below and request a list of additional documents needed onsite to your staff.
We request that the specific items selected from the lists be available and ready for
review on the first day of inspection. If you have any questions regarding this
information, please call the inspector as soon as possible.
1. For the upcoming outage, a detailed schedule and description of:
a. Non-Destructive Examinations (NDEs) planned for Class 1 and 2 Systems
and containment, performed as part of your American Society of Mechanical
Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition
and addenda of Code committed to), and NDEs planned for other systems
performed as part of a Risk-Informed ISI Program, or other augmented
inspection programs commitments, as part of an industry initiative. For each
weld examination, include the weld identification number, description of weld
(component name), category, class, type of exam and procedure number, and
date of examination; and
b. Welding on Code Class 1, 2, or 3 components
2. A copy of the NDE procedures and welding procedures used to perform the activities
identified in A.1 (including NDE calibration and flaw characterization/sizing
procedures and Welding Procedure Qualification Records). For ultrasonic
examination procedures qualified in accordance with Appendix VIII, of Section XI
of the ASME Code, provide documentation supporting the procedure qualification
(e.g., the Electric Power Research Institute performance demonstration qualification
summary sheets).
3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations
identified in A.1.
Enclosure
4. A copy of the 10-year ISI Program showing those required exams scheduled to be
performed this outage, and those which have been completed.
5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye
penetrant), which have identified relevant indications on Code Class 1 and 2 systems
since the beginning of the last refueling outage.
6. List with short description of the welds in Code Class 1 and 2 systems, which have
been fabricated due to component repair/replacement activities since the beginning
of the last refueling outage and identify the system, weld number, and reference
applicable documentation (e.g., NIS-2 forms with definitions of system and
component acronyms).
7. If reactor vessel weld examinations required by the ASME Code are scheduled to
occur during the inspection period, provide a detailed description of the welds to be
examined, and the extent of the planned examination.
8. List with description of ISI-related issues such as piping degradation or damage
(e.g., cracks, wall thinning, wear, microbiologically induced corrosion) or errors
identified in piping examinations that have been entered into your corrective action
system since the beginning of the last refueling outage. Also, include a list of
corrective action records associated with foreign material introduced/identified in
the reactor vessel or reactor coolant system since the beginning of the last refueling
outage.
9. Copy of any Title 10 of the Code of Federal Regulations, Part 21 reports applicable
to your structures, systems, or components within the scope of Section XI of the
ASME Code that have been identified since the beginning of the last refueling
outage.
10. Point of contact information (name and site number) for the Inservice Inspection
Program, Aging Management Programs, Site Welding Engineer, and Reactor
Internals Inspection ProgramsSite and vendor leads.
B. Onsite Information to be provided to inspector on the first day of the inspection
(e.g., following the entrance meeting). Please provide hard copies (e.g., paper
records) of the following documents.
1. For welds selected by the inspector from A.1.b and A.6 above, provide copies of the
following documents:
a. Document of the weld number and location (e.g., system, train, branch);
b. Document with a detail of the weld construction (e.g., drawing);
c. Applicable portions of the Design Specification and applicable Code of
construction for the weldment (e.g., B31.1 or ASME Section III);
d. Applicable Code Edition and Addenda for weld procedure qualification;
e. Applicable weld procedure specifications and completed weld data sheets used
to fabricate the welds;
2
f. Copies of procedure qualification records supporting the weld procedure
specifications;
g. Copies of welders performance qualification records;
h. Copies of mechanical test reports identified in the procedure qualification
records above;
i. Copies of the non-conformance reports for the selected welds;
j. Access to radiographs and equipment to view radiographs of the selected welds;
k. ASME Code Section XI repair replacement plan and reconciliation for
replacement components/materials;
l. Certified Material Test Reports for replacement pressure boundary materials; and
m. Copies of the NDE required by the construction Code and the pre-service
examination records required by the ASME Code Section XI for the selected
welds.
2. For the ISI-related corrective action issues selected by the inspector from Item A.7
above, provide a copy of the corrective actions and supporting documentation.
3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems
selected by the inspector from Item A.4 above, provide a copy of the examination
records and associated corrective action documents.
4. Updated schedules for Item A.1 (including schedule showing contingency repair
plans if available).
5. Fabrication Drawings (D size) of the reactor vessel welds if any are to be examined
during the outage. Also provide any drawings used by NDE vendors to locate these
welds.
6. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory
Commission inspection location for the duration of the inspection:
a. Sections V, IX, and XI of the ASME Code with Editions applicable to the ISI
Program and the Repair/Replacement Program; and
b. Copy of the performance demonstration initiative (PDI) generic procedures with
the latest applicable Revisions that support site qualified ultrasonic examination
of piping welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3,
PDI-UT-10 etc.).
7. Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion) if
required to access the NDE selected by the inspector for observation.
If you have questions regarding the information requested, please contact the lead inspector.
3