MONTHYEARRBG-47824, License Amendment Request to Correct a Non-Conservative Technical Specification Figure 3.4.11-1 Minimum Temperature Required Vs. RCS Pressure by Replacing with 54 Effective Full Power Years (EFPY) Curves2018-04-0202 April 2018 License Amendment Request to Correct a Non-Conservative Technical Specification Figure 3.4.11-1 Minimum Temperature Required Vs. RCS Pressure by Replacing with 54 Effective Full Power Years (EFPY) Curves Project stage: Request RBG-47890, Supplemental Information Related to License Renewal Application NRC Request for Additional Information Set 10 (4.2.1-1, 4.7.3-1 and 4.7.3-2)2018-08-13013 August 2018 Supplemental Information Related to License Renewal Application NRC Request for Additional Information Set 10 (4.2.1-1, 4.7.3-1 and 4.7.3-2) Project stage: Supplement RBG-47903, Response to Request for Additional Information License Amendment Request to Correct a Non-Conservative Technical Specification Figure 3.4,11 -1 Minimum Temperature Required Vs, RCS Pressure by Replacing with 54 Effective Full Power2018-10-0404 October 2018 Response to Request for Additional Information License Amendment Request to Correct a Non-Conservative Technical Specification Figure 3.4,11 -1 Minimum Temperature Required Vs, RCS Pressure by Replacing with 54 Effective Full Power Project stage: Response to RAI ML18348A3412019-01-0202 January 2019 Request for Withholding Information from Public Disclosure, Two Affidavits Dated November 10 and November 17, 2017, by GE-Hitachi Nuclear Energy Americas LLC and Electric Power Research Company Project stage: Withholding Request Acceptance ML18360A0252019-01-17017 January 2019 Redacted Version - Issuance of Amendment No. 195 Correction of a Non-Conservative Technical Specification for Pressure-Temperature Limits Project stage: Approval 2018-08-13
[Table View] |
|
---|
Category:Letter type:RBG
MONTHYEARRBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk RBG-48267, Reply to a Notice of Violation, NRC Inspection Report 05000458/20230032023-12-0707 December 2023 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 RBG-48264, Core Operating Limits Report (COLR) - Cycle 23, Revision 12023-11-0606 November 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 1 RBG-48260, Notification of Readiness for Supplemental Inspection2023-10-12012 October 2023 Notification of Readiness for Supplemental Inspection RBG-48258, Notification of Readiness for Supplemental Inspection2023-10-0505 October 2023 Notification of Readiness for Supplemental Inspection RBG-48259, Revision to Reply to Notice of Violation; EA-23-0552023-10-0303 October 2023 Revision to Reply to Notice of Violation; EA-23-055 RBG-48254, Report of Changes and Errors to 10CFR50.462023-09-21021 September 2023 Report of Changes and Errors to 10CFR50.46 RBG-48249, Reply to a Notice of Violation, EA-23-0712023-09-14014 September 2023 Reply to a Notice of Violation, EA-23-071 RBG-48253, Submittal of Owner'S Activity Report Form for Cycle 222023-09-12012 September 2023 Submittal of Owner'S Activity Report Form for Cycle 22 RBG-48247, Reply to Notice of Violation; EA-23-0552023-08-21021 August 2023 Reply to Notice of Violation; EA-23-055 RBG-48226, Core Operating Limits Report (COLR) - Cycle 23, Revision 02023-05-31031 May 2023 Core Operating Limits Report (COLR) - Cycle 23, Revision 0 RBG-48237, Response to NRC Integrated Inspection Report 05000458/20230012023-05-25025 May 2023 Response to NRC Integrated Inspection Report 05000458/2023001 RBG-48220, Submittal of 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report RBG-48221, 2022 Annual Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Radiological Environmental Operating Report RBG-48142, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSFT-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-02-27027 February 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSFT-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RBG-48143, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-02-27027 February 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors RBG-48198, Report of Changes and Errors to 10CFR50.462022-09-22022 September 2022 Report of Changes and Errors to 10CFR50.46 RBG-48187, Notification of Spent Fuel Cask Use2022-08-15015 August 2022 Notification of Spent Fuel Cask Use RBG-48184, Notification of Spent Fuel Cask Use2022-07-18018 July 2022 Notification of Spent Fuel Cask Use RBG-48178, Notification of Spent Fuel Cask Use2022-06-29029 June 2022 Notification of Spent Fuel Cask Use RBG-48166, Supplement to Special Report for Tritium Discovered Onsite2022-05-12012 May 2022 Supplement to Special Report for Tritium Discovered Onsite RBG-48149, 2021 Annual Radioactive Effluent Release Report2022-04-27027 April 2022 2021 Annual Radioactive Effluent Release Report RBG-48148, 2021 Annual Radiological Environmental Operating Report2022-04-27027 April 2022 2021 Annual Radiological Environmental Operating Report RBG-48134, Inservice Testing Program Relief Request VRR-RBS-2021-1 Pressure Isolation Valve Testing Frequency2021-11-29029 November 2021 Inservice Testing Program Relief Request VRR-RBS-2021-1 Pressure Isolation Valve Testing Frequency RBG-48136, Additional Information for the 2020 Annual Radioactive Effluent Release Report2021-11-12012 November 2021 Additional Information for the 2020 Annual Radioactive Effluent Release Report RBG-48137, Additional Information for the 2019 Annual Radioactive Effluent Release Report2021-11-12012 November 2021 Additional Information for the 2019 Annual Radioactive Effluent Release Report RBG-48128, Reply to a Notice of Violation; EA-21-017, 030 and 0502021-10-29029 October 2021 Reply to a Notice of Violation; EA-21-017, 030 and 050 RBG-48129, Payment of a Civil Penalty2021-10-21021 October 2021 Payment of a Civil Penalty RBG-48112, Report of Changes and Errors to 10CFR50.462021-09-16016 September 2021 Report of Changes and Errors to 10CFR50.46 RBG-48110, Core Operating Limits Report (COLR) - Cycle 22, Revision 12021-08-19019 August 2021 Core Operating Limits Report (COLR) - Cycle 22, Revision 1 RBG-48104, Fitness for Duty Blind Quality Assurance Specimen Testing Error2021-06-30030 June 2021 Fitness for Duty Blind Quality Assurance Specimen Testing Error RBG-48099, Submittal of Owner'S Activity Report Form for Cycle 212021-06-16016 June 2021 Submittal of Owner'S Activity Report Form for Cycle 21 RBG-48083, Application to Add License Condition Concerning Receipt, Possession, and Use of Byproduct Materials2021-06-15015 June 2021 Application to Add License Condition Concerning Receipt, Possession, and Use of Byproduct Materials RBG-48093, Corrected 2020 Annual Radiological Environmental Operating Report2021-05-20020 May 2021 Corrected 2020 Annual Radiological Environmental Operating Report RBG-48082, 2020 Annual Radiological Environmental Operating Report2021-04-20020 April 2021 2020 Annual Radiological Environmental Operating Report RBG-48081, 2020 Annual Radioactive Effluent Release Report2021-04-20020 April 2021 2020 Annual Radioactive Effluent Release Report RBG-48078, Core Operating Limits Report (COLR) - Cycle 22, Revision 02021-03-14014 March 2021 Core Operating Limits Report (COLR) - Cycle 22, Revision 0 RBG-48075, Notification of Deviation from BWRVIP Guidelines2021-02-24024 February 2021 Notification of Deviation from BWRVIP Guidelines RBG-48074, Spent Fuel Storage Radioactive Effluent Release Report for 20202021-02-22022 February 2021 Spent Fuel Storage Radioactive Effluent Release Report for 2020 RBG-48061, One-Time Schedular Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency2020-12-0303 December 2020 One-Time Schedular Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency RBG-48054, Application to Adopt GL 86-10 Standard License Condition for Fire Protection Program2020-11-0202 November 2020 Application to Adopt GL 86-10 Standard License Condition for Fire Protection Program RBG-48049, Reply to a Notice of Violation; EA-20-0582020-10-26026 October 2020 Reply to a Notice of Violation; EA-20-058 RBG-48038, Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Offsite Exercise Requirements Due to Covid 19 Pandemic2020-10-0606 October 2020 Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Offsite Exercise Requirements Due to Covid 19 Pandemic RBG-48042, Submittal of Rev. 48 to Emergency Plan2020-09-22022 September 2020 Submittal of Rev. 48 to Emergency Plan RBG-48039, Report of Changes and Errors to 10CFR50.462020-09-16016 September 2020 Report of Changes and Errors to 10CFR50.46 RBG-48033, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2020-09-0404 September 2020 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements RBG-48023, Submittal of Revs. 46 and 47 to Emergency Plan and Revised Emergency Implementing Procedures2020-06-0909 June 2020 Submittal of Revs. 46 and 47 to Emergency Plan and Revised Emergency Implementing Procedures RBG-48019, 2019 Annual Radioactive Effluent Release Report2020-04-30030 April 2020 2019 Annual Radioactive Effluent Release Report RBG-48020, Annual Radiological Environmental Operating Report2020-04-30030 April 2020 Annual Radiological Environmental Operating Report RBG-48018, Withdrawal of License Amendment Request to Extend the RBS Emergency Plan Implementation Date2020-04-24024 April 2020 Withdrawal of License Amendment Request to Extend the RBS Emergency Plan Implementation Date 2024-01-12
[Table view] |
Text
.~.
Entergy Operations, Inc.
River Bend Station 5485 U.S. Highway 61 N SI. Francisville. LA 70775 Tel 225-381-4374 William F. Maguire Site Vice President RBG-47890 River Bend Station August 13, 2018 Attn: Document Control Desk U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852-2738
SUBJECT:
Supplemental Information Related to License Renewal Application NRC Request for Additional Information Set 10 (4.2.1-1 , 4.7.3-1 and 4.7.3-2)
River Bend Station , Unit 1 Docket No. 50-458 License No. NPF-47
References:
- 1) Entergy Letter: License Renewal Application (RBG-47735 dated May 25, 2017)
- 2) Entergy Letter: Response to License Renewal Application NRC Request for Additional Information (RAI) Set 10 (RBG-47835 dated March 26, 2018)
Dear Sir or Madam:
In Reference 1, Entergy Operations, Inc. (Entergy) submitted an application for renewal of the operating license for River Bend Station (RBS) for an additional 20 years beyond the current expiration date. In Reference 2, updated fluence values were provided for the license renewal application that were based on GEH calculation 003N2078 Revision 1. The purpose of this letter is to provide notification that an error has been identified in GEH calculation 003N2078 Revision 1. This error has been evaluated using the corrective action program and the values provided in Reference 2 remain applicable and the values in the license renewal application are not changing .
The error was the entering of 2.0861 rather than 2.8061 as the EFPY for combined operating cycles 10 and 11. This is an error of 0.72 EFPY. The calculation for fluence at the end of the period of extended operation included a 10% margin for future operating cycles. This 10%
factor for future operating cycles resulted in an effective margin of 2.866 EFPY in the total fluence projected through the end of the period of extended operation . Because the identified error is less than the available margin, the values provided in the license renewal application remain valid. Therefore, the fluence values in the license renewal application are not changing and no change is necessary for the evaluation of fluence effects on the reactor vessel and the reactor vessel internals.
No new commitments have been identified in this letter.
If you require additional information, please contact Mr. Tim Schenk at (225)-381-4177 or tschenk@entergy.com.
RBG-47890 Page 2 of 3 In accordance with 10 CFR 50.91 (b)(1), Entergy is notifying the State of Louisiana and the State of Texas by transmitting a copy of this letter to the designated State Official.
I declare under penalty of perjury that the foregoing is true and correct. Executed on August 13, 2018.
Sincerely, ~tLvJ....
WFM/RMC/dp
RBG-47890 Page 3 of 3 cc: U. S. Nuclear Regulatory Commission Attn : Emmanuel Sayoc 11555 Rockville Pike Rockville , MD 20852 u.s. Nuclear Regulatory Commission Region IV 1600 E. Lamar Blvd .
Arlington , TX 76011-4511 u.s. Nuclear Regulatory Commission Attn : Ms. Lisa M. Regner, Project Manager 09-0-14 One White Flint North 11555 Rockville Pike Rockville , MD 20852 NRC Senior Resident Inspector Attn : Mr. Jeff Sowa 5485 U.S. Highway 61 , Ste . NRC St. Francisville, LA 70775 Department of Environmental Quality Office of Environmental Compliance Radiolog ical Emergency Planning and Response Section Ji Young Wiley P.O. Box 4312 Baton Rouge , LA 70821-4312 Public Utility Commission of Texas Attn: PUC Filing Clerk 1701 N. Congress Avenue P. O. Box 13326 Austin , TX 78711 -3326 RBF1 0157