Amer MISSOURI en Callaway Plant August 9,2018 U LNRC-06449 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 10 CFR 50.55a Ladies and Gentlemen:

DOCKET NUMBER 50-483 CALLA WAY PLANT UNIT I UNION ELECTRIC CO.

RENEWED FACILITY OPERATING LICENSE NPF-30 SUPPLEMENT TO OWNERS ACTIVITY REPORT (OAR-i FORM)

FOR CYCLE/REFUEL 22

Reference:

1) Ameren Missouri letter U LN RC-064 1 9, Owners Activity Reports (OAR-I Forms) for Cycle/Refuel 22. dated March 19. 2018 (Accession No. ML18078A788).

In the letter identified as Reference 1, Union Electric Company (Ameren Missouri) transmitted Owners Activity Reports (OAR-I forms) for Cycle 22 and Refuel 22 activities at Callaway Plant.

One OAR-I form was provided for Inservice Inspection (IS I) and Repair/Replacement activities during the first period of the fourth 151 Program interval. and another OAR- I form was provided for containment Inservice Inspection (pursuant to ASME Section IX, subsection IWE) for the third period of the second IWE Program interval.

In regard to the OAR-I form completed for ISI and Repair/Replacement activities, it was noted in the letter that the form was prepared and being submitted in accordance with ASME Code Case N-532-5, as requii-ed by the current Revision 0 of Callaways Fourth Interval 151 Program Plan. Although the Code Case reference was coirect, after submittal of the letter, it was determined that this OAR-i form had been inadvertently prepared in accordance with ASME Code Case N-532-4. A revised OAR form for ISI and Repair/Replacement activities is therefore being provided per this submittal (as enclosed),

which supersedes the previously submitted report. (The previousty submitted OAR-I form for containment Inservice Inspection activities is not affected.)

P.O. Box 620 Fulton, MO 65251 rnerenFljssOiLcørr,

ULNRC-06449 August 9.2018 Page 2 of 4 The error in regard to preparation and submittal of the noted OAR-I form has been identified and entered in the plants corrective action program. This letter does not contain new commitments.

If there are any questions, please contact Jim Kovar at 314-225-1478.

Sincerely, 4 Roger C. Wink Manager. Regulatory Affairs End osure

ULNRC-06449 August 9,2018 Page 3 of 4 cc: Mr. Kriss M. Kennedy Regional Administrator U. S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Caltaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. L. John Kios Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 09E3 Washington. DC 2t)555-000I

ULNRC-06449 August 9,2018 Pafle 4 of4 Index and send hardcopy to QA File A160.0761 Hardcopy:

Certrec Corporation 6100 Western Place. Suite 1050 Fort Worth, TX 761 07 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)

Electronic distribution for the following can be made via Othei- Situations ULNRC Distribution:

F. M. Diva T. E. Hemiann B. L. Cox S. P. Banker R. C. Wink T. B. Elwood Corporate Communications NSRB Secretary STARS Regulatory Affairs Mr. Jay Silberg (Pillsbury Winthrop Shaw Pittman LLP)

Missouri Public Service Commission

CALLAWAY NUCLEAR PLANT FORM OAR-I OWNERS ACTIVITY REPORT Report Number Plant Cltawav Eneroy Center P 0. Box /120. Fulton. MO 65151 Unit No 1 Commercial sepice date 121 RlOdt Refueling outage no 22 Current iimspectioi interval Current iri3pe:tion period 1° hO ii1 ih Eddien and Addenda of Section Xl applicable to the inspection plans 2007 Edition with 2008 AdOenda Dale atid revision of inspection plans 1/19:2016. Roe. 0 Edition and Addenda of Section Xl applicable to repair!replaceeisnt avlivitie. it iiiffmrerit than the inspection clans Samas inspection plan Code Cases used for inspection and evauation. N-532-5._N-661-2 and N-71B-l vtic nc.udisg camn, rrietf.e.1 by Case 532 viw te.. cn:

CERTIFICATE OF CONFORMANCE vilitj that (at the statements ntirln in this report are correct. (b) the examinations and lel meet the Inspection Plan as required by the ASME Code. Section Xl: and (c) the ropair!replacenient activities 3rd evaluations supporting the completion of 22 confomni to lii requirements of Sec;ticn Xl rt nlvjr n nit ri Sign d ( I C C D tte i,7/ tr I k.

CERTIFICATE OF INSERVICE INSPECTION I the undersigned. holding a valid cnmnirvviiin ivued by the National Board of Boiler and Pressure Vessel Inspec tors and empto,ed by Il +/-r45f 5of have inspected the items described in this Owners Acbeity Report, and state that to the best of my knowlodgo and belief th Owner has pertormed alt activities represe nted by this report in accordance with the requirenients of Section Xl By signing this certificate neither tti Inspector nor his employer makes any warranty. expressed or implied, concerning the repair/replacement activities and evaluation describer]

in thiy report Furthermore, neither the Inspector nor his employer shall be liable in any manner for anJ personal injury or property damaae or a loss of any kind arising from or connected with this nspection

__4z_____

hr .:r:v- i:

Commission ,v i733 tNhcpxi Beximi Nrrmyvr xxi Enrsxr,rxi.

Date 1-I t 06/il)

CALLAWAY NUCLEAR PLANT TABLE 1 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUiRED EVALUATION FOR CONTINUED SERVICE f Examinatton Category Item Description Eialuation Descriptton

TABLE 2 ABSTRACT OF REPAIR/REPLACEMENT ACTIVITIES REQUIRED FOR CONTINUED SERVICE Code Class Item Deschption Description of Work Date Completed Repar;RepIacement Plan I I Number 2 Heli-Coil Insert Install helical coil insert on atmospheric steam 10.22Cif 16001113,510 dump valve body-bonnet stud hole.

The traceability of the helical coil insert was not able to be venfied. CR 201801374 documents the ncn-conformina condition The non I contorming condition will be resolved by either validating the material traceabIity or by repcing with helical coil insert during the next I refueInq outace.