MONTHYEARRA-24-0015, Submittal of 2023 Sea Turtle Annual Report2024-01-10010 January 2024 Submittal of 2023 Sea Turtle Annual Report RA-23-0306, Procedures CSD-EP-BNP-0101-01, EAL Technical Basis Document, Revision 006 and CSD-EP-CNS-0101-01, EAL Technical Basis Document, Revision 005, Summary Of.2023-12-12012 December 2023 Procedures CSD-EP-BNP-0101-01, EAL Technical Basis Document, Revision 006 and CSD-EP-CNS-0101-01, EAL Technical Basis Document, Revision 005, Summary Of. RA-23-0318, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0404 December 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0284, RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0281, Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes2023-11-0101 November 2023 Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes RA-23-0225, Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes2023-09-20020 September 2023 Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes RA-23-0199, Response to Request for Additional Information (RAI) Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Inservice Inspection of the Torus Metallic Liner2023-08-18018 August 2023 Response to Request for Additional Information (RAI) Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Inservice Inspection of the Torus Metallic Liner RA-23-0122, License Amendment Request to Revise the 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors, Categorization Process to .2023-08-17017 August 2023 License Amendment Request to Revise the 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors, Categorization Process to . RA-23-0045, Inservice Inspection Program Owner'S Activity Report for Unit 2 Refueling Outage 262023-06-28028 June 2023 Inservice Inspection Program Owner'S Activity Report for Unit 2 Refueling Outage 26 RA-23-0145, Independent Spent Fuel Storage Installation (Isfsi), Registration for Use of General License Spent Fuel Casks2023-06-15015 June 2023 Independent Spent Fuel Storage Installation (Isfsi), Registration for Use of General License Spent Fuel Casks RA-23-0135, Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory2023-06-0707 June 2023 Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory RA-23-0139, Registration for Use of General License Spent Fuel Casks2023-06-0606 June 2023 Registration for Use of General License Spent Fuel Casks RA-23-0041, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-30030 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations RA-23-0044, Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.462023-04-26026 April 2023 Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.46 RA-23-0047, Duke Energy Annual Radiological Environmental Operating Report - 20222023-04-26026 April 2023 Duke Energy Annual Radiological Environmental Operating Report - 2022 RA-23-0046, Annual Radioactive Effluent Release Report - 20222023-04-24024 April 2023 Annual Radioactive Effluent Release Report - 2022 RA-23-0096, Post Accident Monitoring (PAM) Instrumentation Report2023-04-12012 April 2023 Post Accident Monitoring (PAM) Instrumentation Report RA-23-0063, Notification of Deviation from BWRVIP Guidelines2023-04-11011 April 2023 Notification of Deviation from BWRVIP Guidelines RA-23-0039, 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2023-03-30030 March 2023 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums RA-23-0040, Onsite Property Insurance Coverage2023-03-30030 March 2023 Onsite Property Insurance Coverage RA-23-0036, Biennial Decommissioning Financial Assurance Reports2023-03-30030 March 2023 Biennial Decommissioning Financial Assurance Reports RA-23-0021, Unit 2 Cycle 26 Core Operating Limits Report (COLR)2023-02-22022 February 2023 Unit 2 Cycle 26 Core Operating Limits Report (COLR) RA-22-0091, Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2023-02-16016 February 2023 Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RA-23-0001, Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI2023-02-0202 February 2023 Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI RA-23-0010, 2022 Sea Turtle Annual Report2023-01-0909 January 2023 2022 Sea Turtle Annual Report RA-22-0616, Revision to Brunswick Snubber Program Plan2023-01-0505 January 2023 Revision to Brunswick Snubber Program Plan RA-22-0308, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Inservice Inspection of the Torus Metallic Liner2022-12-16016 December 2022 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Inservice Inspection of the Torus Metallic Liner RA-22-0342, Revision to Emergency Plan On-Shift Staffing Analysis2022-12-0808 December 2022 Revision to Emergency Plan On-Shift Staffing Analysis RA-22-0335, Submittal of 30-Day Report Per 10CFR26.719(c)(1) - Unsatisfactory Performance of a Health & Human Services Certified Lab2022-12-0505 December 2022 Submittal of 30-Day Report Per 10CFR26.719(c)(1) - Unsatisfactory Performance of a Health & Human Services Certified Lab RA-22-0344, Notification of Deviation from BWRVIP Guidelines2022-11-30030 November 2022 Notification of Deviation from BWRVIP Guidelines RA-22-0261, Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License Spent Fuel Casks2022-09-15015 September 2022 Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License Spent Fuel Casks RA-22-0271, Accident Monitoring Instrumentation Special Report2022-09-13013 September 2022 Accident Monitoring Instrumentation Special Report RA-22-0252, Registration for Use of General License Spent Fuel Casks2022-08-25025 August 2022 Registration for Use of General License Spent Fuel Casks RA-22-0190, Submittal of Updated Final Safety Analysis Report (UFSAR) Revision 28, 10 CFR 54.37 Update, Technical Requirements Manuals, Quality Assurance Program Description, Technical Specification Bases, 10 CFR 50.59 and 10 CFR .2022-08-11011 August 2022 Submittal of Updated Final Safety Analysis Report (UFSAR) Revision 28, 10 CFR 54.37 Update, Technical Requirements Manuals, Quality Assurance Program Description, Technical Specification Bases, 10 CFR 50.59 and 10 CFR . RA-22-0165, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 242022-06-0909 June 2022 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 24 RA-22-0175, Post Accident Monitoring (PAM) Instrumentation Report2022-06-0101 June 2022 Post Accident Monitoring (PAM) Instrumentation Report RA-22-0155, Revision to Emergency Plan Annex and Implementing Procedure2022-05-26026 May 2022 Revision to Emergency Plan Annex and Implementing Procedure RA-22-0134, Unit 1 Cycle 23 Mellla+ Eigenvalue Tracking Data2022-05-25025 May 2022 Unit 1 Cycle 23 Mellla+ Eigenvalue Tracking Data RA-22-0151, Duke Energy Common Emergency Plan, Revision 2, Summary of Changes2022-05-24024 May 2022 Duke Energy Common Emergency Plan, Revision 2, Summary of Changes RA-22-0148, 10 CFR 26.719(c)(1) Report - Unsatisfactory Performance of a Health and Human Services Certified Laboratory2022-05-16016 May 2022 10 CFR 26.719(c)(1) Report - Unsatisfactory Performance of a Health and Human Services Certified Laboratory RA-22-0147, Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, Response to Request for Additional Information (RAI) Regarding License Amendment Request for Relocating the Duke Energy Emergency Operations Facility2022-05-13013 May 2022 Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, Response to Request for Additional Information (RAI) Regarding License Amendment Request for Relocating the Duke Energy Emergency Operations Facility RA-22-0029, Shearon Harris Power Plant, McGuire Nuclear Station, Oconee Nuclear Station, H. B. Robinson Steam Electric Plant - Annual Radioactive Effluent Release Report - 20212022-04-27027 April 2022 Shearon Harris Power Plant, McGuire Nuclear Station, Oconee Nuclear Station, H. B. Robinson Steam Electric Plant - Annual Radioactive Effluent Release Report - 2021 RA-22-0028, Annual Report of Changes Pursuant to 10 CFR 50.462022-04-27027 April 2022 Annual Report of Changes Pursuant to 10 CFR 50.46 RA-22-0114, Duke Energy Carolinas, LLC and Duke Energy Progress, LLC Submittal of 10CFR26.719(c)(1) Report of Unsatisfactory Performance of Health and Human Services Certified Laboratory2022-04-0101 April 2022 Duke Energy Carolinas, LLC and Duke Energy Progress, LLC Submittal of 10CFR26.719(c)(1) Report of Unsatisfactory Performance of Health and Human Services Certified Laboratory RA-22-0095, Unit 1 Cycle 24 Core Operating Limits Report (COLR)2022-03-29029 March 2022 Unit 1 Cycle 24 Core Operating Limits Report (COLR) RA-22-0110, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf.2022-03-25025 March 2022 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. RA-22-0014, Duke Energy Response to NRC Regulatory Issue Summary 2022-01 Preparation and Scheduling of Operator Licensing Examinations2022-03-21021 March 2022 Duke Energy Response to NRC Regulatory Issue Summary 2022-01 Preparation and Scheduling of Operator Licensing Examinations RA-22-0003, Response to Requests for Additional Information for Reactor Vessel Closure Stud Exam Extension Alternative2022-01-31031 January 2022 Response to Requests for Additional Information for Reactor Vessel Closure Stud Exam Extension Alternative RA-22-0046, Withdrawal of One-Time Exemption from 10 CFR 50, Appendix E, Section IV.F.2.d2022-01-31031 January 2022 Withdrawal of One-Time Exemption from 10 CFR 50, Appendix E, Section IV.F.2.d RA-20-0107, Duke Energy Progress, LLC, and Duke Energy Carolinas, LLC, Application to Revise Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2022-01-18018 January 2022 Duke Energy Progress, LLC, and Duke Energy Carolinas, LLC, Application to Revise Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position 2024-01-10
[Table view] |
Text
Brunswick Nuclear Plant P.O. Box 10429 Southport, NC 28461 August 06, 2018 Serial: RA-18-0110 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Renewed Facility Operating License Nos. DPR-71 and DPR-62 Docket Nos. 50-325 and 50-324 Request for One-Time Allowance to Submit License Amendment Request Referencing Topical Report Draft Safety Evaluation
References:
- 1. Letter from Andrew Hon (U.S. Nuclear Regulatory Commission) to Duke Energy, Summary of October 26, 2017, Second Pre-Submittal Meeting with Duke Energy Regarding Brunswick Advanced AREVA Methods License Amendment Request (CAC NOS. MF9965 and MF9966; EPID L-2017-LRM-0033), dated December 22, 2017, ADAMS Accession Number ML17317A330.
- 2. Letter from Kevin Hsueh (U.S. Nuclear Regulatory Commission) to Gary Peters (AREVA Inc.), Acceptance for Review of AREVA Inc. Topical Report ANP-10332P, Revision 0, "AURORA-B: An Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident Scenarios" (CAC NO. MF3829), dated October 27, 2016, ADAMS Accession Number ML16288A837.
Ladies and Gentlemen:
As described in the October 26, 2017, pre-submittal meeting summary (i.e., Reference 1), Duke Energy Progress, LLC (Duke Energy) plans to submit a license amendment request (LAR) in September 2018 for the Brunswick Steam Electric Plant (BSEP), Unit Nos. 1 and 2, regarding adoption of advanced Framatome (i.e., formerly AREVA Inc.) methodologies to support transition to the Framatome ATRIUM 11 fuel design. Duke Energy is pursuing the ATRIUM 11 fuel type to improve fuel cycle economics and safety margins.
The September 2018 submittal date for the BSEP advanced Framatome methodology LAR is necessary to support a critical milestone in December 2018 for the ATRIUM 11 fuel transition.
Approval of the BSEP advanced Framatome methodology LAR will be required by February 20, 2020, to support reactor startup following the Unit 1 refueling outage.
The BSEP advanced Framatome methodology LAR will propose to incorporate eight new Topical Reports (TRs) into the BSEP Technical Specifications (TSs), one of which is TR ANP-10332P, Revision 0, AURORA-B: An Evaluation Model for Boiling Water Reactors; Application to Loss of Coolant Accident (LOCA) Scenarios (AURORA-B LOCA TR) which was accepted for NRC review on October 27, 2016 (i.e., Reference 2). As documented in Reference 2, the NRC originally projected to have the draft safety evaluation (SE) issued by March 30, 2018. However, due to the advanced nature of the methodology, additional review
U.S. Nuclear Regulatory Commission Page 2 of 3 time was required and the latest projection for issuance of the draft SE is by August 31, 2018.
Therefore, by the September 2018 submittal date for the BSEP advanced Framatome methodology LAR, the review of the AURORA-8 LOCA TR will be near completion and there will be a solid understanding of the potential limitations and conditions (L&Cs).
Apart from the AURORA-8 LOCA TR, all other elements of the LAR will use NRG-approved or detailed plant specific methodology. The AURORA-8 LOCA TR is only one piece of the BSEP advanced Framatome methodology LAR; the majority of the technical content does not directly involve the AURORA-8 LOCA TR.
As a result of the needed approval timeline for the BSEP advanced Framatome methodology LAR, the complexity of the LAR, and the status of the AURORA-8 LOCA TR review, Duke Energy is requesting an allowance to submit the BSEP advanced Framatome methodology LAR referencing the draft SE for the AURORA-8 LOCA TR. The generally accepted practices to reference the NRG-approved TR or to include the entire TR with a plant-specific justification would significantly delay submittal and would not add value to the review process in this circumstance. If this strategy is acceptable to the NRC, Duke Energy will address each of the L&Cs from the AURORA-8 LOCA TR draft SE with submittal of the BSEP advanced Framatome methodology LAR. Following issuance of the approved AURORA-8 LOCA TR (i.e.,
ANP-10332P-A), Duke Energy will supplement the BSEP advanced Framatome methodology LAR referencing the approved AURORA-8 LOCA TR and addressing any differences between the draft and final SEs.
Duke Energy acknowledges that this strategy will introduce additional uncertainty into the NRC's initial projection of LAR review hours and duration. In addition, Duke Energy understands that there are remaining regulatory processes that need to be completed before the AURORA-8 LOCA TR final SE can be issued; Duke Energy acknowledges that there is uncertainty in the outcome of these processes which may impact the LAR review schedule. Notwithstanding these schedule risks, Duke Energy has confidence that submitting the LAR referencing the AURORA-8 LOCA TR draft SE remains the best strategy at this juncture and that sufficient, reliable information regarding the LAR review duration will be available in December 2018 to support the critical ATRIUM 11 fuel transition milestone.
To facilitate submittal of the BSEP advanced Framatome methodology LAR in September 2018, Duke Energy requests that the NRC grant this allowance by September 6, 2018.
No new regulatory commitments are contained in this letter.
Please refer any questions regarding this submittal to Mr. Lee Grzeck, Manager - Regulatory Affairs, at (910) 832-2487.
Bryan 8. Wooten Director - Organizational Effectiveness Brunswick Steam Electric Plant SBY/sby
U.S. Nuclear Regulatory Commission Page 3 of 3 cc:
U.S. Nuclear Regulatory Commission, Region II ATTN: Ms. Catherine Haney, Regional Administrator 245 Peachtree Center Ave, NE, Suite 1200 Atlanta, GA 30303-1257 U.S. Nuclear Regulatory Commission ATTN: Mr. Andrew Hon (Mail Stop OWFN 8G9A) 11555 Rockville Pike Rockville, MD 20852-2738 U.S. Nuclear Regulatory Commission ATTN: Mr. Dennis J. Galvin (Mail Stop OWFN 8B1A) 11555 Rockville Pike Rockville, MD 20852-2738 U.S. Nuclear Regulatory Commission ATTN: Mr. Gale Smith, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 Chair - North Carolina Utilities Commission (Electronic Copy Only) 4325 Mail Service Center Raleigh, NC 27699-4300 swatson@ncuc.net