Withdrawal of Proposed Alternatives FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-05-02 Instrument Lines on the Pressurizer (Epids L-2017-LLR-0115,L-2017-LLR-0116)
ML18115A267
Person / Time
Site: Vogtle, Farley  Southern Nuclear icon.png
Issue date: 05/01/2018
From: Michael Orenak
Plant Licensing Branch II
To: Gayheart C
Southern Nuclear Operating Co
Orenak M
References
EPID L-2017-LLR-0115, EPID L-2017-LLR-0116
Download: ML18115A267 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 1, 2018 Ms. Cheryl A. Gayheart Regulatory Affairs Director Southern Nuclear Operating Co., Inc.

BIN 038 40 Inverness Center Parkway Birmingham, AL 35201-1295

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2, AND VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 -WITHDRAWAL OF PROPOSED ALTERNATIVES FNP-ISI-ALT-05-02 AND VEGP-ISI-ALT-04-02 REGARDING INSTRUMENT LINES ON THE PRESSURIZER (EPIDS L-2017-LLR-0115 AND L-2017-LLR-0116)

Dear Ms. Gayheart:

By letter dated October 6, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML172858088), Southern Nuclear Operating Company, Inc., (SNC) submitted proposed alternative FNP-ISI-ALT-05-02 for the Joseph M. Farley Nuclear Plant, Units 1 and 2, (Farley) and proposed alternative VEGP-ISI-ALT-04-02 for the Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle). SNC proposed the use of alternative requirements for American Society of Mechanical Engineers (ASME) Class 1 upper level instrumentation lines on the pressurizers for Farley and Vogtle.

By letter dated April 23, 2018 (ADAMS Accession No. ML18113A447), SNC requested to withdraw FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-04-02 because the proposed alternatives are not required due to previous U.S. Nuclear Regulatory Commission (NRC) approval during plant construction. This letter acknowledges the withdrawal of FNP-ISI-ALT-05-02 and VEGP-ISI-ALT-04-02. No further NRC staff review will be performed under EPIDs L-2017-LLR-0115 and L-2017-LLR-0116.

C. Gayheart If you have any questions, please contact me at (301) 415-3229 or via email at Michael.Orenak@nrc.gov.

Sincerely,

,Mvl oJ__

Michael Orenak, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348, 50-364, 50-424, and 50-425 cc: Listserv