Letter to M. E. Tursa Request for Additional Information Regarding Portland General Electric Company'S Decommissioning Funding Plan Update for Trojan Independent Spent Fuel Storage Installation
ML18094A489
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 04/03/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Tursa M
Portland General Electric Co
Longmire P
Shared Package
ML18094A486 List:
References
CAC 001028, EPID No.: L-2017-FPR-0069
Download: ML18094A489 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 3, 2018 Mr. Mark E. Tursa Trojan ISFSI Manager Portland General Electric Company 71760 Columbia River Hwy Rainier, Oregon 97048

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING PORTLAND GENERAL ELECTRIC COMPANYS DECOMMISSIONING FUNDING PLAN UPDATE FOR TROJAN INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Mr. Tursa:

By letter dated December 10, 2015, Portland General Electric Company (PGE) submitted for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at Trojan Nuclear Generating Station (Agencywide Documents Access and Management System Accession No. ML15349A939). The NRC staff reviewed PGEs DFP update for the ISFSI and believes PGEs submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.

The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred March 7, 2018.

M. Tursa The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov.

Sincerely,

/RA John McKirgan Acting for/

Pamela Longmire, Ph.D.

Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-17 CAC No.: 001028 EPID No.: L-2017-FPR-0069

Enclosure:

Request for Additional Information

M. Tursa 3 REQUEST FOR ADDITIONAL INFORMATION REGARDING PORTLAND GENERAL ELECTRIC COMPANYS DECOMMISSIONING FUNDING PLAN UPDATE FOR TROJAN INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: April 3, 2018 DISTRIBUTION:

SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson CMarkley Letter: G:\SFST\72.30 Decommissioning Funding Plans\RAIs\Trojan\Trojan-RAI.docx

Enclosure:

G:\SFST\72.30 Decommissioning Funding Plans\RAIs\Trojan\Trojan-Enclosure.docx ADAMS Package No.: ML18094A486 Letter: ML18094A489 Encl.: ML18094A487 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley JMcKirgan DATE 3/27/18 3/ 28 /18 4/03/18 OFFICIAL RECORD COPY