Letter Sequence Request |
---|
EPID:L-2017-LRO-0068, Donald C. Cook Nuclear Plant Unit 2, Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program (Approved, Closed) |
|
MONTHYEARML17346A6832017-12-0808 December 2017 Donald C. Cook Nuclear Plant Unit 2, Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program Project stage: Request ML18043A0092018-02-0909 February 2018 NRR E-mail Capture - DC Cook, Unit 2 - Request for Additional Information Regarding Reactor Vessel Internals Again Management Program Project stage: RAI ML18092A0842018-03-28028 March 2018 Donald C. Cook Nuclear Plant Unit 2, Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program Project stage: Request ML18145A1862018-06-0505 June 2018 Review of Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program Project stage: Approval 2018-02-09
[Table View] |
Similar Documents at Cook |
---|
Category:Letter
MONTHYEARIR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 ML24004A1582024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0039 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report ML23159A0192023-06-13013 June 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report ML23131A3282023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 AEP-NRC-2023-19, Annual Radioactive Effluent Release Report2023-04-30030 April 2023 Annual Radioactive Effluent Release Report ML23117A0062023-04-27027 April 2023 Review of the Spring 2022 Steam Generator Tube Inspections Report ML23114A1142023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2023-23, Annual Report of Individual Monitoring for 20222023-04-24024 April 2023 Annual Report of Individual Monitoring for 2022 AEP-NRC-2023-24, Notification of Ph Non-Compliance for Turbine Room Sump2023-04-12012 April 2023 Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-20, Annual Report of Property Insurance2023-04-0303 April 2023 Annual Report of Property Insurance AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion AEP-NRC-2023-11, Form OAR-1, Owner'S Activity Report2023-01-31031 January 2023 Form OAR-1, Owner'S Activity Report IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 AEP-NRC-2023-02, Request for Approval of Change Regarding Neutron Flux Instrumentation2023-01-26026 January 2023 Request for Approval of Change Regarding Neutron Flux Instrumentation ML22363A5622023-01-0404 January 2023 Relief Request ISIR-5-06 Related to ASME Code Case N-729-6 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in ML22340A1392022-11-30030 November 2022 Submittal of Revision 31 to Updated Final Safety Analysis Report and 10CFR50.71(e) Updated and Related Site Change Reports IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2022-61, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-062022-10-24024 October 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-06 2024-01-08
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARAEP-NRC-2022-03, Final Supplemental Response to NRC Generic Letter 2004-022022-01-20020 January 2022 Final Supplemental Response to NRC Generic Letter 2004-02 AEP-NRC-2021-68, Response to Request for Additional Information on Requested Change Regarding Containment Water Level Instrumentation2021-12-16016 December 2021 Response to Request for Additional Information on Requested Change Regarding Containment Water Level Instrumentation AEP-NRC-2021-43, Response to Request for Additional Information Regarding Relief Request for Limited Coverage Examinations Performed in the Fourth 10-Year Inspection Interval2021-07-21021 July 2021 Response to Request for Additional Information Regarding Relief Request for Limited Coverage Examinations Performed in the Fourth 10-Year Inspection Interval AEP-NRC-2021-16, Unit 2 - Response to Request for Additional Information Regarding CFR 50.55a Request Associated with the Fifth Ten-Year Inservice Testing Interval2021-02-25025 February 2021 Unit 2 - Response to Request for Additional Information Regarding CFR 50.55a Request Associated with the Fifth Ten-Year Inservice Testing Interval AEP-NRC-2021-18, Response to Request for Additional Information Regarding License Amendment Request for One-Time Extension of the Containment Type a Leak Rate Testing Frequency2021-02-18018 February 2021 Response to Request for Additional Information Regarding License Amendment Request for One-Time Extension of the Containment Type a Leak Rate Testing Frequency AEP-NRC-2020-50, Response to Request for Additional Information Regarding License Amendment Request for One-Time Extension of the Containment Type a Leak Rate Testing Frequency2020-07-0909 July 2020 Response to Request for Additional Information Regarding License Amendment Request for One-Time Extension of the Containment Type a Leak Rate Testing Frequency AEP-NRC-2019-56, Seismic Probabilistic Risk Assessment in Response to Near Term Task Force Recommendation 2.1: Seismic2019-11-0404 November 2019 Seismic Probabilistic Risk Assessment in Response to Near Term Task Force Recommendation 2.1: Seismic AEP-NRC-2019-32, Unit 2 - Response to Request for Additional Information Regarding Unit 2 Leak-Before-Break Analysis and Deletion of Containment Humidity Monitors for Unit 1 and Unit 22019-08-22022 August 2019 Unit 2 - Response to Request for Additional Information Regarding Unit 2 Leak-Before-Break Analysis and Deletion of Containment Humidity Monitors for Unit 1 and Unit 2 AEP-NRC-2019-40, Response to Request for Additional Information Regarding License Amendment Request to Address NSAL-15-1, Rev. 02019-07-30030 July 2019 Response to Request for Additional Information Regarding License Amendment Request to Address NSAL-15-1, Rev. 0 AEP-NRC-2018-81, Supplement to Response to Request for Additional Information Regarding License Amendment Request for Approval of Application of Proprietary Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping2018-11-27027 November 2018 Supplement to Response to Request for Additional Information Regarding License Amendment Request for Approval of Application of Proprietary Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping AEP-NRC-2018-82, Response to Request for Additional Information Regarding the Alternative Request for Elimination of the Reactor Pressure Vessel Threads in Flange Examination2018-11-20020 November 2018 Response to Request for Additional Information Regarding the Alternative Request for Elimination of the Reactor Pressure Vessel Threads in Flange Examination AEP-NRC-2018-64, Response to Request for Additional Information Regarding License Amendment Request for Approval of Application of Proprietary Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping2018-09-27027 September 2018 Response to Request for Additional Information Regarding License Amendment Request for Approval of Application of Proprietary Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping ML18334A2722018-09-18018 September 2018 LTR-SDA-II-18-41-NP, Revision 1, Responses to NRC Questions on the Expanded Scope Leak-Before-Break Evaluations for D.C. Cook, Units 1 and 2. AEP-NRC-2018-45, Response to Request for Additional Information Concerning 2017 Decommissioning Funding Status Report2018-08-0909 August 2018 Response to Request for Additional Information Concerning 2017 Decommissioning Funding Status Report AEP-NRC-2018-01, Response to Request for Additional Information Regarding Generic Letter 2016-012018-05-25025 May 2018 Response to Request for Additional Information Regarding Generic Letter 2016-01 AEP-NRC-2018-23, Response to Request for Additional Information Regarding Independent Spent Fuel Storage Installation Decommissioning Funding Plan2018-04-11011 April 2018 Response to Request for Additional Information Regarding Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML18092A0842018-03-28028 March 2018 Donald C. Cook Nuclear Plant Unit 2, Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program ML17346A7662017-12-0808 December 2017 Enclosures 2 & 3 to AEP-NRC-2017-56 - Response to Request for Additional Information Regarding the License Amendment Request to Revise Emergency Action Levels and EAL Technical Basis Manual AEP-NRC-2017-56, Response to Request for Additional Information Regarding the License Amendment Request to Revise Emergency Action Levels2017-12-0808 December 2017 Response to Request for Additional Information Regarding the License Amendment Request to Revise Emergency Action Levels AEP-NRC-2017-30, Response to Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 3.9.3, Containment Penetrations2017-05-26026 May 2017 Response to Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 3.9.3, Containment Penetrations AEP-NRC-2017-16, Submittal of Focused Evaluation in Response to March 12, 2012, Request for Information Regarding Near- Term Task Force Recommendation 2.1: Flooding2017-05-11011 May 2017 Submittal of Focused Evaluation in Response to March 12, 2012, Request for Information Regarding Near- Term Task Force Recommendation 2.1: Flooding AEP-NRC-2017-09, Response to Request for Additional Information Regarding the License Amendment Request for the Containment Leakage Rate Testing Program2017-02-27027 February 2017 Response to Request for Additional Information Regarding the License Amendment Request for the Containment Leakage Rate Testing Program AEP-NRC-2016-81, Unit 2 - Supplemental Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTP-425, Relocate Surveillance Frequencies Program to Licensee Control-Risk Informed ...2016-11-0303 November 2016 Unit 2 - Supplemental Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTP-425, Relocate Surveillance Frequencies Program to Licensee Control-Risk Informed ... AEP-NRC-2016-80, Response to NRC Generic Letter 2016-01: Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools2016-10-31031 October 2016 Response to NRC Generic Letter 2016-01: Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools AEP-NRC-2016-79, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2016-10-12012 October 2016 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident AEP-NRC-2016-69, Follow-up Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies Program to License Control-Risk Informed Technical Specification Task Force.2016-09-0909 September 2016 Follow-up Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies Program to License Control-Risk Informed Technical Specification Task Force. AEP-NRC-2016-56, Response to Seventh Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2016-07-12012 July 2016 Response to Seventh Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2016-48, Unit 2 - Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies Program to Licensee-Control...2016-06-16016 June 2016 Unit 2 - Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies Program to Licensee-Control... AEP-NRC-2016-54, Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force Initiative 582016-06-16016 June 2016 Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force Initiative 58 ML16169A1152016-05-0606 May 2016 Donald C. Cook Nuclear Plant Units 1 and 2 - Response to Sixth Request for Additional Information the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2016-24, Response to Fifth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2016-02-19019 February 2016 Response to Fifth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2016-14, Response to Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2016-01-21021 January 2016 Response to Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation AEP-NRC-2015-11, Response (Part 2) to Fourth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-12-17017 December 2015 Response (Part 2) to Fourth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term ML15323A4332015-11-16016 November 2015 Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions. ML15323A4342015-11-16016 November 2015 Response (Part 1) to Fourth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2015-98, Supplemental Response to Follow-Up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program2015-10-30030 October 2015 Supplemental Response to Follow-Up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program AEP-NRC-2015-99, Response to Request for Additional Information Re License Amendment Request to Revise Technical Specification Section 3.8.1, AC Sources - Operating, Surveillance Requirements 3.8.1.10, 3.8.1.11 and 3.8.1.152015-10-30030 October 2015 Response to Request for Additional Information Re License Amendment Request to Revise Technical Specification Section 3.8.1, AC Sources - Operating, Surveillance Requirements 3.8.1.10, 3.8.1.11 and 3.8.1.15 ML15308A0932015-10-15015 October 2015 Pressurized Water Reactor Owners Group (Pwrog), 15066-NP, Revision 1, Responses to Follow-Up NRC RAI 2 on the D.C. Cook, Units 1 and 2, Reactor Internals Aging Management Program. AEP-NRC-2015-86, Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent With. Previously Licensed Conditions.2015-09-18018 September 2015 Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent With. Previously Licensed Conditions. AEP-NRC-2015-80, Response to Third Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-08-28028 August 2015 Response to Third Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2015-88, Response to Request for Additional Information Regarding Proposed Alternative to the American Society of Mechanical Engineers Code, Section XI Repair Requirements2015-08-24024 August 2015 Response to Request for Additional Information Regarding Proposed Alternative to the American Society of Mechanical Engineers Code, Section XI Repair Requirements AEP-NRC-2015-75, Response to Second Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-08-24024 August 2015 Response to Second Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2015-69, Response to Follow-Up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program2015-08-0606 August 2015 Response to Follow-Up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program ML15223A4362015-07-28028 July 2015 PWROG-15066-NP, Revision 0, Responses to Follow-Up NRC RAI 2 on the DC Cook Units 1 and 2 Reactor Internals Aging Management Program. AEP-NRC-2015-64, Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-07-17017 July 2015 Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2015-63, Response to Request for Additional Information Regarding 2014 Unit 1 Steam Generator Tube Inspection2015-07-17017 July 2015 Response to Request for Additional Information Regarding 2014 Unit 1 Steam Generator Tube Inspection AEP-NRC-2015-60, Response to a Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification Section 3.8.1, AC Sources - Operating, Surveillance Requirements 3.8.1.10, 3.8.1.11, and 3.8.1.152015-07-0909 July 2015 Response to a Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification Section 3.8.1, AC Sources - Operating, Surveillance Requirements 3.8.1.10, 3.8.1.11, and 3.8.1.15 AEP-NRC-2015-66, Response to Request for Additional Information Regarding Exigent License Amendment Request Regarding Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2015-07-0202 July 2015 Response to Request for Additional Information Regarding Exigent License Amendment Request Regarding Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation ML18219D0951978-09-29029 September 1978 D.C Cook - Acknowledges 07/12/1978 Letter Advising of Additional Information to Complete NRC Staff'S Review of D.C Cook Nuclear Plant'S Ice - Basket Stress Analysis ML18219D7991978-09-29029 September 1978 Response to Request for Additional Information on Ice Basket Stress Analysis, Prepared by Westinghouse Electric Corporation 2022-01-20
[Table view] |
Text
= INDIANJ,I MICHIGA1N POWER. A unit of American Electric Power March 28, 2018 Docket No.: 50-316 U.S. Nuclear Regulatory Commission ATTN: DocumentControl Desk -Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Unit 2 Indiana Michigan Power Cook Nuclear Plant One Cook Place Bridgman, Ml 49106 lndianaMichiganPower.com
--AEP-NRC-2/018-22 10 CFR 50.4 Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program
References:
- 1. Letter from_ J. P. Gebbie, Indiana Michigan Power Company (l&M), to U. S. Nuclear Regulatory Commission (NRC), "Donald C. Cook Nuclear Plant Units 1 and 2, Transmittal of Reactor Vessel Internals Aging Management Program," dated October 1, 2012, Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12284A320.
- 2. Letter from K. Hsueh, NRC, to A Demma, Electric Power Research Institute, "Final Safety Evaluation.
of WCAP-17096-NP, Revision 2, 'Reactor Internals Acceptance Criteria Methodology and Data Requirements' (TAC No. ME4200)," dated May 3, 2016, ADAMS Accession No'. ML 16061A187.
- 3. Letter from D. J. Wrona, NRC, to J. P. Gebbie, l&M, "Donald C. Cook Nuclear Plant, Units 1 and :2 -Staff Assessment Regarding Prograry, Plan for Aging Management for Reactor Vessel Internals (CAC Nos. MF0050 and MF0051)," dated September 8, 2016, ADAMS Accession No. II/IL 16063A434.
- 4. Letter from Q. S. Lies, l&M, to NRC, "Donald C. Cook Nuclear Plant Unit 2, Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program," dated DecE~mber 8, 2017, ADAMS Accession No. ML 17346A683.
- 5. Electronic Mail from J. K. Rankin, NRC,* to H. L. Levendosky, l&M, "DC Cook, Unit 2 -Request for Additional Information Regarding Reactor Vessel Internals Again Management Program (EPID L-2017-LR0-0068)," dated February 9, 2018, ADAMS Accession No. ML 18043A009.
- -"-* This letter provides the Response to a Request for Additional Information Regarding Supplemental Information for the Donald C. Cook Nuclear Plant (CNP) Uriit 2, pertaining to the CNP Reactor Vessel Internals Aging Management Program.
U.S. Nuclear Regulatory Commission Page 2 AEP-NRC-2018-22 By Referer1ce 1, Indiana Michigan Power Company (l&M) transmitted the CNP Reactor Vessel Internals Aging Management Program which implemented guidance from the Electric Power Research institute provided in MRP-227-A, "Materials Reliability Program:
- Press*urized Water Reactor Internals Inspection and Evaluation Guidelines," (MRP-227-A).
By Reference 2, the U. S. Nuclear Regulatory Commission (NRC) transmitted a Final Safety Evaluation of WCAP-17096-NP, Revision 2, "Reactor Internals Acceptance Criteria Methodology and Data Requiremer,ts." Section 4 of Reference 2 requires licensees to submit plant-specific and/or generic analyses to the NRC within one (1) year after any inspection that detects relevant conditions as defined in MRP-227-A.
By Reference 3, the NRC transmitted a Final Safety Evaluation of the CNP Reactor Vessel Internals Aging Management Program which approved the program. By Reference 4, l&M provided supplemental information regarding the Reactor Vessel Internals Aging Management Program pursuant to Section 4 of Reference
- 2. By Reference 5, the NRC requested additional ir,1formation in order to complete its review of Reference
- 4. Enclosure
- 1 to this letter is an Affirmation Statement.
Enclosure 2 to this letter provides l&M's response to the follow-up RAI contained in Reference
- 5. Enclosure 3 to this letter provides . WCAP-18133-NP, a Non-Proprietary version of Section 3.6 of WCAP-18131-P, which was submitted by Reference
- 4. There are no* new reguiatory commitments made in this letter. Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.
DB/mll
Enclosures:
- 1. Affirmation
- 2. Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program 3. Westinghouse WCAP-18133-NP, Revision 0, "Inspection Flaw Acceptance Criteria for D.C. Cool< Unit 2 Reactor Vessel Internals MRP-227-A Primary and Expansion Components," Section 3.6
- c:-R .. J. Ancona -MPSC MDEQ-RMD/RPS NRC Resident Inspector J-. K. Rankin, NRC Washington, D.C. K. S .. West, NRG Region 111 A J. Williamson -AEP Ft. Wayne,w/o enclosures
- *.*
- '._:) ....
Enclosure 1 to AEP-NRC-2018-22 AFFIRMATION I, Q. Shane Lies, being duly sworn, state that I am the Site Vice President of Indiana Michigan Power Company (l&M}, that I am authorized to sign and file this request with the U. S. Nuclear Regulatory Commission on behalf of l&M, and that the statements made and the matters set forth herein pert~1ining to t*&M are true and correct to the best of my knowledge, information, and belief. Indiana Michigan Power Company Q[,~lLl. Site Vice Priesident SWORN TO AND SUBSCRIBED BEFORE ME THIS~_DAYOF
\\:o.._.c~ , 2018 ~....,:£)0.
~-~~~f'"ll Nota he . My Commis.sion Expires C)':\,-c:-,q-d~~
DANIELLE BURGOYNE Notary Publlo, State of Mlohlaan
- countV of Berrien MY Commission Expires 04~2;J~ Acting In the CounW of .. . . '* . ,,,_ 1.:*1*, .. : \" ,'-.
Enclosure 2 to AEP-NRC-2018-22 Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program By letter elated December 8, 2017, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 17346A683), Indiana Michigan Power Company (l&M), the licensee for Donald C. Cook Nuclear Plant (CNP), Units 1 and 2, submitted supplemental information regarding the Reactor Vessel Internals Aging Management Program for CNP Unit 2. The U. S. r.\Juclear Regulatory Commission (NRG) staff is currently reviewing the submittal, and has determined that additional information is needed in order to complete the review. The request for additional information (RAI) and l&M's response is provided below. RAl-1 Condition 3 of the NRG staff's *final safety evaluation (SE) of WCAP-17096-NP-A, Revision 2, "Reactor Internals Acceptance Criteria, Methodology and Data Requirements" (ADAMS Accession No. ML16061A187) requires licensees to submit to the NRG the plant specific failure modes and
- effects ana,lysis (FMEA) within one year after the inspection that detects relevant conditions.
In Enclosure 2 of the December 8, 2017, submittal, the licensee provided a proprietary FMEA of the baffle-edge bolts for CNP, Unit 2. Specifically, the licensee provided sections relevant to baffle-edge bolts from WCAP-18131-P, Revision 1, "Background and Technical Basis Supporting Engineering Flaw Acceptance Criteria for D. C. Cook Unit 2 Reactor Vessel Internals MRP-227-A Primary and Expansion Components." The methodology arid analysis section for baffle-edge bolts as described in WCAP-17096-NP-A (ADAMS Accession No. ML 16279A320) states, in part, "[o]bservation of relevant conditions in the baffle edge bolts or locking bars would require a FMEA on the observed condition." The NRG staff notes that the information provided in the December 8, 2017, submittal describes the process for baffle-edge bolt FMEA and the generic results of the FMEA, but does not take into account the specific "observed condition" of the baffle-edge
{Jolts at CNP, Unit No. 2 as described in WCAP-170!~6-NP-A.
Please provide the results of the baffle-edge bolt FMEA considering the found condition at CNP, Unit No. 2. l&M Response to RAl-1 The plant-specific failure modes and effects analysis (FMEA) documented in WCAP-18131-P, Revision 1, "Background and TechniGal Basis Supporting Engineering Flaw Acceptance Criteria for D.C. Cook Unit 2 Reactor Vessel Internals MRP-227-A Primary and Expansion Components," was prepared prior to the baffle-edge bolt inspection and included a full range of potential conditions that could be 0~1served.
The observed condition of baffle-edge bolts at CNP Unit 2 was considered patterned/clustered which was an analyzed condition in the plant-specific FMEA documented
The condition was considered patterned/clustered since the five (5) baffle-edge bolts with relevant indications were located on the same column (Column 7 -see Figure 1) and . were all between Former Level D *and Former Level F (See Figure 2). Column 7 baffle-edge bolts "fasten Plate 7 to Plate 6 as shown in Figure 1. The five baffle-edge bolts are locations Y; AB, AD, AE, and AF shown on Figure 2.
.. , Enclosure to AEP-NRC-2018-22 (l' .MOW$ nd i cate , nt~ edge 1ion ~ons Baff l e P l ate 7 Figure 1 -Baffle-Former Assembly with Columns Labeled (looking down from above) Page 2 Enclosure to AEP-NRC-2018-22 F ormer L evel H Former L e v e l G Former L e v e l F Former Level E F orme r L eve l C
- F orni e r L~v eJ A C*fJ L lJMN. 1, (L .15, aa . COLUMN 7, l4:, ~1, *2t3 OPPOSITE H AND Figure 2 -Column 7 with Baffle-Edge Bolts and Former Levels Labeled Page 3 Enclosure to AEP-NRC-2018-22 Page4 Baffle-edg.e bolts are not considered structural components that need to meet requirements for safe shutdown.
Based on the decision to leave the baffle edge bolts as-is, informed by replacement feasibility and potential consequence of localized fuel damage due to jetting through vacant baffle-.. edge bolt counter bores, a loose parts assessment was prepared by Westinghouse.
The loose parts assessment concluded that if the lockbars or pieces of edge bolts become loose parts during future operating cycles, safe operation of the unit would not be affected.
However, to mitigate the risk of fuel defects due to flow induced vibration, debris (from potentially broken bolts) and baffle jetting, the fuel assemblies at core locations R11 and P12 were armored with stainless steel pins in the areas adjacent to the baffle-edge bolt heads and the seam between the baffle plates to which the baffle-edge bolts were fastened.
The appamnt cause of the baffle-edge bolt degradation was that the large clustered region of failed baffle-former bolts surrounding Column 7 most likely led to increased stress on the baffle-edge bolts on Column 7 where the five baffle-edge bolts were found with cracked heads. Since the apparent cause of the edge bolt cracking was due to clustered baffle-former bolt failures, the baffle-edge bolts in thE3 area of the baffle assembly that experienced significant baffle-former bolt clustering were inspected again during the current Unit 2 Cycle 24 refueling outage which began on March 1, 2018. The inspection included Columns 1 through 14 (shown in Figure 1). The inspection performed was a visual (VT-3) examination.
The examination concluded that the previously recorded indications on the five baffle-edge bolts are non-relevant indications that were likely shadowing
.. The discrepancy between the two examinations can be explained due to factors such as the 2018 examination being performed using the Ahlberg Mega Rad camera which is a higher resolution camera. The Ahlberg camera provides greater latitude in camera angles and lighting as well as a higher resolution image which can be qualified for a VT-1 examination.
In conclusion, the five baffle-edge bolts previously identified as containing relevant indications do not contain indications of cracking or any other age-related degradation.
During the Unit 2 Cycle 23 refueling outage, the NRC evaluated CNP's baffle-edge bolt inspection in accordance with Inspection Procedure 71111.08.
The baffle-edge bolt inspections were included in the scope of this NRC review. After identification of the degraded baffle-edge bolts, an operability evaluation was prepared to determine if CNP Unit 2 was operable considering the identified degradation.
The operability evaluation determined that the affected support structure was operable but degraded pending completion of additional inspections and corrective actions during the subsequent refueling outage. The operability evaluation was reviewed by the NRC inspection team. There were no findings or observations associated with the actions taken in response to the baffle-edge bolt inspection.
The results of the inspection are summarized in "Donald C. Cook Nuclear Power Plant, Units 1 and 2-NRC Integrated Inspection Report 05000315/2016004; 05000316/2016004; 05000315/2016501
- 05000316/2016501.
II Enclosure 2 to AEP-NRC-2018-22 Westinghouse WCAP-18133-NP, Revision 0, "Inspection Flaw Acceptance Criteria for D.C. Cook Unit 2 Reactor Vessel Internals MRP-227-A Primary and Expansion Components," Section 3.6