MONTHYEARDCL-15-007, Response to NRC Request for Additional Information Regarding License Amendment Request 13-02, Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision, 1...2015-02-0505 February 2015 Response to NRC Request for Additional Information Regarding License Amendment Request 13-02, Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision, 1... Project stage: Response to RAI DCL-15-065, Response to NRC Request for Additional Information Regarding License Amendment Request 13-02. Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505. Revision 1. 'Provide Risk-Informed..2015-05-28028 May 2015 Response to NRC Request for Additional Information Regarding License Amendment Request 13-02. Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505. Revision 1. 'Provide Risk-Informed.. Project stage: Response to RAI ML15279A4222015-10-0909 October 2015 Summary of 8/25/15 Meeting with Pacific Gas and Electric to Discuss Diablo Canyon Units 1 and 2 Amendment Request to Adopt Risk-Informed Completion Times, TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times-RITSTF Initiati Project stage: Meeting DCL-18-016, Withdrawal of License Amendment Request 13-02 Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505. Revision 1. Provide Risk-Informed Extended Completion Times - Times RITSTF Initiative 482018-03-0707 March 2018 Withdrawal of License Amendment Request 13-02 Revision to Technical Specifications to Adopt Risk Informed Completion Times TSTF-505. Revision 1. Provide Risk-Informed Extended Completion Times - Times RITSTF Initiative 48 Project stage: Withdrawal ML18082A0552018-03-29029 March 2018 Letter - Withdrawal of an Amendment Request to Adopt TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times -RITSTF Initiative 4b (CAC Nos. MF3240 and MF3241; EPID L-2013-LLA-0001) Project stage: Withdrawal 2015-05-28
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 29, 2018 Mr. James M. Welsch Vice President, Nuclear Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - WITHDRAWAL OF AN AMENDMENT REQUEST (CAC NOS. MF3240 AND MF3241; EPID L-2013-LLA-0001)
Dear Mr. Welsch:
By letter dated November 25, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13330A557), as supplemented by letters dated February 5 and May 28, 2015, and July 7 and October 27, 2016 (ADAMS Accession Nos. ML15036A592, ML15148A480, ML16189A282, and ML16301A425, respectively), Pacific Gas and Electric Company (PG&E, the licensee) submitted a license amendment request for the Diablo Canyon Power Plant, Units 1 and 2, Facility Operating License Nos. DPR-80 and DPR-82, respectively.
The proposed changes would have modified the DCPP technical specifications (TSs) to permit the use of Risk-Informed Completion Times (RICTs) in accordance with Technical Specifications Task Force (TSTF) traveler TSTF-505, Revision 1, "Provide Risk-Informed Extended Completion Times - RITSTF [Risk-Informed TSTF] Initiative 4b," (ADAMS Accession No. ML111650552). The proposed amendments would have, in part, modified selected Required Actions to permit excluding the Completion Times in accordance with a new TS-required RICT program.
Subsequently, by letter dated March 7, 2018 (ADAMS Accession No. ML18066A938), PG&E withdrew the amendment request. The U.S. Nuclear Regulatory Commission (NRC) acknowledges this request to withdraw the application. NRC staff activities for the review of this amendment request have ceased and the associated Enterprise Project Identifier (EPID) number has been closed.
If you choose to resubmit this amendment request, the NRC staff would recommend the licensee address the following:
- All necessary peer reviews have been completed and Facts and Observations resolved, as appropriate;
J. Welsch
- Any TS loss of function conditions meet design basis analysis requirements for parameters; and
- Ensure that a RICT is not proposed for actions not listed in TSTF-505, Revision 1.
The NRC has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.
Sincerely,
~ ~* ~ cf-ey Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosure:
Notice of Withdrawal cc: Listserv
ENCLOSURE FEDERAL REGISTER NOTICE
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-275 and 50-323; NRC-2014-0260]
Pacific Gas and Electric Company; Diablo Canyon Power Plant, Units 1 and 2 AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment application; withdrawal by applicant.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) has granted the request of Pacific Gas and Electric Company to withdraw its application dated November 25, 2013, as supplemented by letters dated February 5 and May 28, 2015, and July 7 and October 27, 2016, for proposed amendments to Facility Operating License Nos. DPR-80 and DPR-82. The proposed amendments would have modified the facility technical specifications (TSs) to permit the use of Risk-Informed Completion Times (RICTs) in accordance with Technical Specifications Task Force (TSTF) Traveler TSTF-505, Revision 1, "Provide Risk-Informed Extended Completion Times - RITSTF [Risk-Informed TSTF] Initiative 4b."
DATES: [INSERT DATE OF PUBLICATION IN THE FEDERAL REGISTER].
ADDRESSES: Please refer to Docket ID NRC-2014-0260 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
2
- Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID NRC-2014-0260. Address questions about NRC dockets to Jennifer Borges; telephone: 301-287-9127; e-mail: Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRC's Agencywide Documents Access and Management System (ADAMS):
You may obtain publicly-available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select "ADAMS Public Documents" and then select "Begin Web-based ADAMS Search." For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov.
The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document.
- NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room 01-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Balwant K. Singal, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; telephone: 301-415-3016, e-mail: Balwant.Singal@nrc.gov.
3 SUPPLEMENTARY INFORMATION:
The NRC has granted the request of Pacific Gas and Electric Company (the licensee) to withdraw its November 25, 2013, application (ADAMS Accession No. ML13330A557) for proposed amendments to Facility Operating License Nos. DPR-80 and DPR-82 for the Diablo Canyon Power Plant, Units 1 and 2, located in San Luis Obispo County, California.
The proposed amendments would have modified the Diablo Canyon Power Plant TSs to permit the use of RICTs in accordance with TSTF-505, Revision 1 (ADAMS Accession No. ML111650552). The proposed amendments would have, in part, modified selected required actions to permit excluding the completion times in accordance with a new TS-required RICT program.
4 The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration, published in the Federal Register on December 9, 2014 (79 FR 73111 ). The licensee provided supplemental information by letters dated February 5 and May 28, 2015, and July 7 and October 27, 2016 (ADAMS Accession Nos. ML15036A592, ML15148A480, ML16189A282, and ML16301A425, respectively). However, the licensee requested to withdraw the application on March 7, 2018 (ADAMS Accession No. ML18066A938).
Dated at Rockville, Maryland, this 29th day of March, 2018.
For the Nuclear Regulatory Commission.
IRA/
Siva P. Lingam, Project Manager, Plant Licensing Branch IV, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
J. Welsch
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2-WITHDRAWAL OF AN AMENDMENT REQUEST (CAC NOS. MF3240 AND MF3241; EPID L-2013-LLA-0001) DATED MARCH 29, 2018 DISTRIBUTION:
PUBLIC PM File Copy RidsACRS_MailCTR Resource RidsNrrDorlLpl4 Resource RidsNrrLAPBlechman Resource RidsNrrPMDiabloCanyon Resource RidsRgn4MailCenter Resource RidsNrrDraApla Resource ADAMS Accession Nos.: L TR (NRR-106) ML18082A055 FRN (ADM-012) ML18082A025 OFFICE NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA NRR/DRA/APLA/BC NAME BSingal (Slingam for) PBlechman $Rosenberg DATE 03/27/18 03/27/18 03/27/18 OFFICE NRR/DORL/LPL4/BC NRR/DORL/LPL4/PM NAME BPascarelli BSingal (Slingam for)
DATE 03/28/18 03/29/18 OFFICIAL AGENCY RECORD