Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the Environmental Qualification Program; Inspection Report 05000331/2017010 (DRS-N.Feliz-Adorno)
ML17326A691
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 11/21/2017
From: Nestor Feliz-Adorno
Engineering Branch 3
To: Dean Curtland
NextEra Energy Duane Arnold
References
IR 2018010
Download: ML17326A691 (6)


See also: IR 05000331/2017010

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, ILLINOIS 60532-4352

November 21, 2017

Mr. Dean Curtland

Director of Site Operations

NextEra Energy Duane Arnold, LLC

3277 DAEC Road

Palo, IA 52324-9785

SUBJECT: DUANE ARNOLD ENERGY CENTERREQUEST FOR INFORMATION

FOR AN NRC DESIGN BASES ASSURANCE INSPECTION (PROGRAM):

IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM;

INSPECTION REPORT 05000331/2018010

Dear Mr. Curtland:

On April 23, 2018, the U. S. Nuclear Regulatory Commission (NRC) will begin a triennial

baseline Design Bases Assurance Inspection (Program) at the Duane Arnold Energy

Center. This inspection will be performed in accordance with NRC Baseline Inspection

Procedure 71111.21N, Attachment 1.

The Design Bases Assurance Inspection will focus on the implementation of the electrical

equipment Environmental Qualification (EQ) Program to verify you are maintaining the qualified

status of equipment during the life of the plant. The EQ components to be reviewed during this

baseline inspection will be identified during the in-office preparation week that occurs prior to the

onsite inspection week.

The inspection will include a bagman trip to support selection of components and 2 weeks of

onsite inspection. The inspection team will consist of 3 NRC inspectors. The current inspection

schedule is as follows:

Bagman trip onsite week: February 19, 2018

Team preparation week: April 16-20, 2018

Onsite inspection weeks: April 23-27, 2018, and May 7-11, 2018.

Experience with previous baseline design inspections of similar depth and length has shown

that this type of inspection is extremely resource intensive, both for the NRC inspectors and the

licensee staff. In order to minimize the inspection impact on the site and to ensure a productive

inspection for both parties, we have enclosed a request for information needed for the

inspection.

It is important that all of these documents are up-to-date and complete in order to minimize the

number of additional documents requested during the preparation and/or the onsite portions of

the inspection. Insofar as possible, this information should be provided electronically to the lead

inspector. The information request has been divided into four groups:

D. Curtland -2-

The first group lists information necessary for our initial inspection scoping activities.

This information should be provided to the lead inspector no later than January 5, 2018.

Prior to the bagman trip on January 19, 2018, the lead inspector will communicate the

initial selected set of approximately 12 EQ components.

The second group of documents requested is those items needed to support the

bagman trip. This set of documents should be available to the lead inspector onsite

on February 19, 2018.

The third group of documents requested is those items needed to support our

in-office preparation activities for the selected set of 6-9 EQ components. This set of

documents should be provided to the lead inspector at the Regional Office no later than

April 5, 2018. During the in-office preparation activities, the team may identify additional

information needed to support the inspection.

The last group includes the additional information above as well as plant specific

reference material. This information should be available to the team onsite on

April 23, 2018. It is also requested that corrective action documents and/or questions

developed during the inspection be provided to the lead inspector as the documents

are generated.

The lead inspector for this inspection is Mr. Néstor J. Féliz Adorno. We understand that our

licensing contact for this inspection is Mr. B. Murrell of your organization. If there are any

questions about the inspection or the material requested in the enclosure, please contact the

lead inspector at (630) 829-9739 or via e-mail at Nestor.Feliz-Adorno@nrc.gov.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget Control

Number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA Michael Jones Acting for/

Néstor J. Féliz Adorno, Senior Reactor Inspector

Engineering Branch 3

Division of Reactor Safety

Docket No. 50-331

License No. DPR-49

Enclosure:

Document Request for Design Bases

Assurance Inspection EQ Program

cc: Distribution via LISTSERV

D. Curtland -3-

Letter to Dean Curtland from Néstor J. Féliz Adorno dated November 21, 2017

SUBJECT: DUANE ARNOLD ENERGY CENTERREQUEST FOR INFORMATION

FOR AN NRC DESIGN BASES ASSURANCE INSPECTION (PROGRAM):

IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM;

INSPECTION REPORT 05000331/2018010

DISTRIBUTION:

Jeremy Bowen

RidsNrrDorlLpl3

RidsNrrPMDuaneArnold Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Kenneth OBrien

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

ADAMS Accession Number ML17326A691

OFFICE RIII RIII RIII RIII

NAME MJones for NFeliz-

Adorno:cl

DATE 11/21/17

OFFICIAL RECORD COPY

DOCUMENT REQUEST FOR DESIGN BASES ASSURANCE INSPECTION EQ PROGRAM

Inspection Report: 05000331/2018010

Bagman Dates: February 19, 2018

Inspection Dates: April 23-27, 2018, and May 7-11, 2018

Inspection Procedure: IP 71111.21N, Design Bases Assurance Inspection (Program),

Attachment 1, Environmental Qualification (EQ) under 10 CFR

50.49 Programs, Processes, and Procedures

Lead Inspector: Néstor J. Féliz Adorno, Senior Reactor Inspector, DRS

630-829-9810

Nestor.Feliz-Adorno@nrc.gov

I. Information Requested Prior to the Onsite Information Gathering/Bagman Week

The following information is requested by January 5, 2018, or sooner, to facilitate

inspection preparation. If you have any questions regarding this information, please call

the team leader as soon as possible. Please provide the information electronically in

pdf files, Excel, or other searchable formats, preferably on some portable electronic

media (e.g., CD-ROM, DVD, etc.). The portable electronic media should contain

descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information

in lists should contain enough information to be easily understood by someone who

has knowledge of light water reactor technology.

1. Risk-ranking of top 250 components required to meet environmental

qualifications (EQ) from your site specific probabilistic safety analysis

sorted by Fussell Vesely Importance.

2. Probabilistic Safety Analysis listing of top ten risk significant systems.

3. U.S. Nuclear Regulatory Commission Safety Evaluation Report(s) associated

with EQ.

4. Electronic copies of Updated Final Safety Analysis Report, Technical

Specifications, and Technical Specifications Bases. Specifically identify which

Updated Final Safety Analysis Report sections address EQ (including seismic).

5. Identify the various EQ standards (including year, edition, or revision) that the

station is committed to.

6. Site (and corporate, if applicable) procedures associated with the Title 10 of the

Code of Federal Regulations, Part 50.49, EQ Program for electrical components.

Include procedures for procurement of qualified equipment, maintenance of

qualified equipment, modification to qualified equipment (including Equivalency

or Commercial Grade Dedication (CGD) Programs), and material storage and

shelf life controls.

Enclosure

DOCUMENT REQUEST FOR DESIGN BASES ASSURANCE INSPECTION EQ PROGRAM

7. Copy of EQ Design Basis Document, if applicable.

8. Copy of any open licensing commitments related to EQ, if applicable.

9. Equipment Qualification Master List. Specific issues to be identified include:

safety classification (safety-related or nonsafety-related), Regulatory Guide 1.97

instrumentation, EQ qualification (e.g., DOR, NUREG 588, 50.49), original or

replaced after implementation of 50.49, and plant location.

10. List of any installed equipment removed from the Equipment Qualification Master

List and basis for removal.

11. List of EQ solenoid valves that are normally continuously energized.

12. List or drawings of plant areas that are subjected to EQ, identifying design

(limiting) temperature, both normal and accident, high energy line break,

radiation levels, etc. that the associated equipment will have to be qualified to

meet EQ. If unit has obtained a power uprate (greater than 5 percent) provide

same information pre-update (earliest available if multiple uprates).

13. List of CGD evaluations performed, for which the dedicated parts have been

issued for installation (parts issued for the last 10 years) on EQ applications in

the plant. Include CGD evaluation number, name of part, component ID or

description of the component the part was issued to repair, work order, and date

issued or installed.

14. List of Corrective Action Documents related to the EQ program or EQ of specific

components for the last 5 years.

15. Current management and engineering organizational chart.

II. Information Requested (for the approximate 9-12 selected components) to be

Available by the Bagman Trip on February 19, 2018.

1. EQ summary report for each component/subcomponent.

2. Qualification Maintenance Requirement Sheet or equivalent.

3. List of corrective action documents associated with each of the selected

components for the last 5 years.

4. Photos of any component in containment or high radiation areas, if available.

III. Information Requested (for the approximate 6-9 selected components) to be

Available by April 5, 2018.

This information should be separated for each selected component, especially if

provided electronically (e.g., folder with component name that includes EQ files,

Qualification Test Reports, calculations, corrective action documents, maintenance

history, etc.).

1. EQ file, including associated Qualification Test Reports.

2

DOCUMENT REQUEST FOR DESIGN BASES ASSURANCE INSPECTION EQ PROGRAM

2. Vendor manual (electronic copy or availability of hard copy during inspection).

3. Preventive maintenance template.

4. Last performed work order (WO) for each associated EQ preventive

maintenance.

5. List of corrective maintenance WOs for the last 10 years. Include WO number,

date performed, and brief one line description.

6. If repair work (e.g., a motor rewind) was performed under a purchase order,

provide copy of the purchase order.

7. Thermal life calculation.

8. Any self-assessments of the EQ program in the last 3 years.

IV. Additional Information to be Provided on April 23, 2018, Onsite

1. During the in-office preparation activities, the team may identify additional

information needed to support the inspection. The lead inspector will provide a

list of the additional information needed during the week of April 16, 2018.

V. Information Requested to be Provided Throughout the Inspection

1. Copies of any corrective action documents generated as a result of the teams

questions or queries during this inspection.

2. Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily by 2:30 p.m.

during the inspection to each team member).

If you have questions regarding the information requested, please contact the lead inspector.