RC-15-0195, Notification of Compliance to NRC Security Order EA-13-228

From kanterella
(Redirected from ML15356A145)
Jump to navigation Jump to search
Notification of Compliance to NRC Security Order EA-13-228
ML15356A145
Person / Time
Site: Summer, 07201038  South Carolina Electric & Gas Company icon.png
Issue date: 12/16/2015
From: Gatlin T
South Carolina Electric & Gas Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
EA-13-228, RC-15-0195
Download: ML15356A145 (2)


Text

F" Thomas D. Gatlin Vice President, Nuclear Operations A sc-ANA-COMPAN December 16, 2015 A scAA COPANYRC-1 5-0195 U. S. Nuclear Regulatory Commission Document Control Desk Director, Division of Spent Fuei Storage and Transportation Office of Nuclear Material Safety and Safeguards Washington, DC 20555-0001

Dear Sir/Madam:

Subject:

VIRGIL C. SUMMER NUCLEAR STATION (VCSNS) UNIT 1 DOCKET NOs. 50-395 and 72-1 038 OPERATING LICENSE NO. NPF-12 NOTIFICATION OF COMPLAINCE TO NRC SECURITY ORDER EA- 13-228

Reference:

1. NRC Order Number EA-13-228, "Issuance of Order for Implementation of Additional Security Measures and Fingerprinting for Unescorted Access for Virgil C. Summer Nuclear Station Independent Spent Fuel Storage Installation," dated January 28, 2014 [ML 1329A541]
2. South Carolina Electric & Gas Company Response to Order for Implementation of Additional Security Measures and Fingerprinting for Unescorted Access for the Virgil C. Summer Nuclear Station Independent Spent Fuel Storage Installation, dated February 17, 2014 [ML14050A111]
3. South Carolina Electric & Gas Company Revised Implementation Schedule for Implementation of Additional Security Measures- NRC Order EA-13-228 dated January 27, 2015
4. South Carolina Electric & Gas Company Revised Implementation Schedule for Implementation of Additional Security Measures- NRC Order EA-13-228 dated April 1,2015 NRC issued Security Order EA-13-228 (Reference 1) which required South Carolina Electric &

Gas Company (SCE&G), the licensee for Virgil C. Summer Nuclear Station Unit 1 (VCSNS), to comply with Additional Security Measures (ASMs). SCE&G responded (Reference 2) with a schedule to achieve compliance with the ASMs. Subsequently, the implementation date was revised (Reference 3 and 4) based on current fuel load plans.

Box 88. Jenkinsville, SC. 29065. F(803) 941-9776 V.C.Summer Nuclear Station. P.O0.

'-4 Document Control Desk CR-14-0041 5 RC-1 5-0195 Page 2 of 2 This letter provides notification that VCSNS is in full compliance with the requirements of Security Order EA-1 3-228 as of December 10, 2015. VCSNS will store fuel in the Independent Spent Fuel Storage Installation on or after March 21, 2016.

This letter contains no new or modified regulatory commitments. Should you have any questions concerning the content of this letter, please contact Bruce L. Thompson at (803) 931-5042.

I certify under penalty of perjury that the information contained herein is true and correct.

Executed on Thomas D. Gatlin BJ D/TDG/wt c: K. B. Marsh S. A. Byrne J, B. Archie N. S. Cams J, H. Hamilton J. W. Williams W. M. Cherry L. D. Wert S. A. Williams M.D. Lombard NRC Resident Inspector K. M. Sutton NSRC NMSS RTS (CR-14-00415)

File (810.64, 815.07)

PRSF (RC-15-0195)

F" Thomas D. Gatlin Vice President, Nuclear Operations A sc-ANA-COMPAN December 16, 2015 A scAA COPANYRC-1 5-0195 U. S. Nuclear Regulatory Commission Document Control Desk Director, Division of Spent Fuei Storage and Transportation Office of Nuclear Material Safety and Safeguards Washington, DC 20555-0001

Dear Sir/Madam:

Subject:

VIRGIL C. SUMMER NUCLEAR STATION (VCSNS) UNIT 1 DOCKET NOs. 50-395 and 72-1 038 OPERATING LICENSE NO. NPF-12 NOTIFICATION OF COMPLAINCE TO NRC SECURITY ORDER EA- 13-228

Reference:

1. NRC Order Number EA-13-228, "Issuance of Order for Implementation of Additional Security Measures and Fingerprinting for Unescorted Access for Virgil C. Summer Nuclear Station Independent Spent Fuel Storage Installation," dated January 28, 2014 [ML 1329A541]
2. South Carolina Electric & Gas Company Response to Order for Implementation of Additional Security Measures and Fingerprinting for Unescorted Access for the Virgil C. Summer Nuclear Station Independent Spent Fuel Storage Installation, dated February 17, 2014 [ML14050A111]
3. South Carolina Electric & Gas Company Revised Implementation Schedule for Implementation of Additional Security Measures- NRC Order EA-13-228 dated January 27, 2015
4. South Carolina Electric & Gas Company Revised Implementation Schedule for Implementation of Additional Security Measures- NRC Order EA-13-228 dated April 1,2015 NRC issued Security Order EA-13-228 (Reference 1) which required South Carolina Electric &

Gas Company (SCE&G), the licensee for Virgil C. Summer Nuclear Station Unit 1 (VCSNS), to comply with Additional Security Measures (ASMs). SCE&G responded (Reference 2) with a schedule to achieve compliance with the ASMs. Subsequently, the implementation date was revised (Reference 3 and 4) based on current fuel load plans.

Box 88. Jenkinsville, SC. 29065. F(803) 941-9776 V.C.Summer Nuclear Station. P.O0.

'-4 Document Control Desk CR-14-0041 5 RC-1 5-0195 Page 2 of 2 This letter provides notification that VCSNS is in full compliance with the requirements of Security Order EA-1 3-228 as of December 10, 2015. VCSNS will store fuel in the Independent Spent Fuel Storage Installation on or after March 21, 2016.

This letter contains no new or modified regulatory commitments. Should you have any questions concerning the content of this letter, please contact Bruce L. Thompson at (803) 931-5042.

I certify under penalty of perjury that the information contained herein is true and correct.

Executed on Thomas D. Gatlin BJ D/TDG/wt c: K. B. Marsh S. A. Byrne J, B. Archie N. S. Cams J, H. Hamilton J. W. Williams W. M. Cherry L. D. Wert S. A. Williams M.D. Lombard NRC Resident Inspector K. M. Sutton NSRC NMSS RTS (CR-14-00415)

File (810.64, 815.07)

PRSF (RC-15-0195)