MONTHYEARML23362A0572023-12-28028 December 2023 NRR E-mail Capture - Callaway Plant, Unit 1 - SUNSI Review of the Final Safety Analysis Report (FSAR) Revision OL-26 ML23338A0392023-12-0101 December 2023 NRR E-mail Capture - LIC-109 Acceptance Review - Unacceptable with Opportunity to Supplement - Callaway - RR from Requirements of ASME BPV Code, Section Xl, Subsect IWL-Exam & Test-Unbonded Post Tensioning System - EPID L-2023-LLR-0061 ML23208A1052023-07-27027 July 2023 NRR E-mail Capture - Callaway Plant, Unit No. 1 - Regulatory Audit Questions - LAR to Clarify Support System Requirements for the Residual Heat Removal & Control Room Air Conditioning Systems ML23200A2982023-07-19019 July 2023 NRR E-mail Capture - Callaway Plant, Unit 1 - Final Request for Additional Information (RAI) - Request for Approval of Oqam, Revision 36a - EPID L-2023-LLQ-0000 ML23121A0112023-04-28028 April 2023 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of License Amendment Request to Revise TS to Adopt TSTF-501-A Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control - EPID L-2023-LLA-0046 ML23114A2302023-04-24024 April 2023 NRR E-mail Capture - Regulatory Audit Question - Callaway LAR and Exemption for Fuel Transition to Framatome Gaia Fuel - EPIDs - L-2022-LLA-0150 and L-2022-LLE-0030 ML23107A1812023-04-17017 April 2023 NRR E-mail Capture - Regulatory Audit Questions - Callaway LAR and Exemption for Fuel Transition to Framatome Gaia Fuel - EPIDs - L-2022-LLA-0150 and L-2022-LLE-0030 ML23096A0072023-04-0505 April 2023 NRR E-mail Capture - Final Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request to Revise TS 5.5.16 for Permanent Extension of Integrated Leak Rate Testing - EPID L-2022-LLA-0165 ML23073A0262023-03-13013 March 2023 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - SG Inspection Report Review - EPID L-2022-LRO-0143 ML23037A7092023-02-0606 February 2023 April 2023 Emergency Preparedness Exercise Inspection - Request for Information ML23037A0022023-02-0303 February 2023 NRR E-mail Capture - Callaway - LAR to Adopt AST - EPID L-2021-LLA-0177 - Revised Schedule for Completion of the Project ML23026A0212023-01-24024 January 2023 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - LAR for Proposed Changes to TS for SFP - ML23010A2902023-01-10010 January 2023 NRR E-mail Capture - LIC-109 Acceptance Review - Callaway Plant, Unit 1 - License Amendment Request to Clarify Support System Requirements for the RHR & Crac Systems - ML22346A0132022-12-0909 December 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of LAR to Revise TS 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies - EPID L-2022-LLA-0165 ML22322A0062022-11-17017 November 2022 NRR E-mail Capture - Final - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) Callaway - LAR for Proposed Changes to TS and Exemption Request Use of Framatome Gaia Fuel - L-2022-LLA-0150 & L-2022-LLE-0030 ML22287A0952022-10-14014 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22280A1322022-10-0707 October 2022 NRR E-mail Capture - Final - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) - Callaway - License Amendment Request for Proposed Changes to Tech Spec Changes for Spent Fuel Pool Storage - EPID L-2022-LLA-0 ML22278A0122022-10-0404 October 2022 NRR E-mail Capture - Draft - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) - Callaway License Amendment Request for Proposed Changes to Tech Spec Changes for Spent Fuel Pool Storage - EPID L-2022-LLA-013 ML22269A4312022-09-26026 September 2022 November 2022 Emergency Preparedness Program Inspection - Request for Information NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) ML22251A0122022-09-0707 September 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of License Amendment Request for Application to Revise TS to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections - EPID L-2022-LLA-0110 NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22216A0072022-07-0808 July 2022 NRR E-mail Capture - Callaway Plant, Unit No. 1 - Draft Acceptance Review (Unacceptable for Review with Opportunity to Supplement) for Framatome Fuel Transition LAR and Exemption - EPIDs L-2022-LLA-0083 and L-2022-LLE-0019) ML22167A0252022-06-15015 June 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - LAR for Proposed Revision to Radiological Emergency Response Plan Regarding Response & Notification Goals - EPID L-2022-LLA-0024 ML22157A0102022-06-0303 June 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood Ultimate Heat Sink Temporary Temperature Increase to 102.8 Degrees Fahrenheit ML22154A0122022-06-0202 June 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22151A0512022-05-27027 May 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22137A0292022-05-16016 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22096A0232022-04-0505 April 2022 NRR E-mail Capture - Callaway Plant - Final RAIs - License Amendment and Regulatory Exemptions for a Risk-Informed Approach to Address Generic Safety Issue - 191 and Respond to GL 2004-02 (EPIDs L-2021-LLA-0059 and L-2021-LLE-0021) ML22089A0222022-03-29029 March 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LAR to Adopt TSTF-505 and TSTF-439 - Follow Up Clarifications for the Audit Questions - EPID L-2021-LLA-0197 ML22087A4022022-03-28028 March 2022 NRR E-mail Capture - Callaway - Draft RAIs - License Amendment and Regulatory Exemptions for a Risk-Informed Approach to Address Generic Safety Issue - 191 and Respond to Generic Letter 2004-02 (EPIDs L-2021-LLA-0059 and L-2021-LLE-0021) ML22070A1362022-03-10010 March 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of License Amendment Request for Proposed Revision to Radiological Emergency Response Plan Regarding Response and Notification Goals - EPID L-2022-LLA-0024 ML22047A2312022-02-11011 February 2022 Email Between NRC NSIR and FEMA Regarding Callaway Sirens 021122 ML22003A0852022-01-0303 January 2022 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of License Amendment Request to Adopt TSTF-529, Clarify Use and Application Rules - EPID L-2021-LLA-0225 ML21334A5172021-11-30030 November 2021 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of Requested Licensing Action - Application to Adopt TSTF-439 and TSTF-505 - EPID L-2021-LLA-0197 ML21335A0172021-11-30030 November 2021 NRR E-mail Capture - Callaway Plant, Unit 1 - LIC-109 Acceptance of Requested Licensing Action - Application to Adopt TSTF-439 and TSTF-505 - EPID L-2021-LLA-0197 ML21308A0692021-11-0404 November 2021 NRR E-mail Capture - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) - Callaway Unit 1 - License Amendment Request - Adoption of Alternate Source Term and Revision of TSs - ML21258A0382021-09-14014 September 2021 NRR E-mail Capture - Final - Request for Additional Information - Callaway, Unit 1 - LAR to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors- EPID L-2020-LLA-023 ML21195A0252021-07-13013 July 2021 Email 7-13-21 Request for Information - Callaway EP Exercise Inspection - Sept 2021 ML21125A0452021-05-0404 May 2021 NRR E-mail Capture - LIC-109 Acceptance Review (Unacceptable for Review with Opportunity to Supplement) - Callaway Plant, Unit 1 - License Amendment Request - Final Resolution to Address Concerns of GSI-191 - EPID L-2021-LLA-0059 ML21007A1622021-01-0606 January 2021 NRR E-mail Capture - Final - Request for Additional Information - (COVID-19) Callaway Plant, Unit 1 - Additional Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs - EPID L-2021-LLE-0242 ML20342A1802020-12-0606 December 2020 NRR E-mail Capture - Callaway - LIC-109 Acceptance Requested Licensing Action - Application to Adopt 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors EPID L-2020-LLA-0235 ML20296A6332020-10-22022 October 2020 NRR E-mail Capture - Callaway Plant, Unit 1 - Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Section VI (EPID L 2020 Lle 0140 (Covid 19)) - Revised Completion Schedule ML20205L4252020-07-22022 July 2020 NRR E-mail Capture - Callaway Plant, Unit 1 - Acceptance of Requested Licensing Action Request for One-Time License Amendment to Defer Upcoming Steam Generator Inspection (EPID L-2020-LLA-0142)(COVID-19) ML20203M3682020-07-21021 July 2020 NRR E-mail Capture - Draft Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request - Revision to Technical Specification (TS) 5.3.1 and Deletion of TS 5.3.1.1 and 5.3.1.2 - EPID L-2020-LLA-0046 ML20162A1882020-06-10010 June 2020 Request for Supporting Information for the Callaway SPRA Audit Review - Draft Supplement ML20153A7902020-05-29029 May 2020 Emai: RFI for Callaway EP Program Inspection ML20133K6742020-05-11011 May 2020 05000483, Request for Information 2020-002 ML20099G2422020-04-0808 April 2020 NRR E-mail Capture - Acceptance Callaway Containment Tendon COVID-19 Relief Request ML20097C8362020-04-0606 April 2020 NRR E-mail Capture - Accepted: Callaway TS Change 5.3.1 LAR EPID: L-2020-LLA-0046 2023-07-27
[Table view] |
Text
NRR-PMDAPEm Resource From: Klos, John Sent: Tuesday, August 11, 2015 1:28 PM To: 'Telwood@ameren.com' Cc: 'SMaglio@ameren.com'; Klos, John; Johnson, Don; Hoffman, Raymond
Subject:
Second round Requests for Additional Information: Callaway Amendment upgrade Emergency Action Level scheme adopt NRC-endorsed NEI 99-01, Revision 6 Importance: High Mr. Elwood, By letter dated October 2, 2014, Agencywide Documents and Access and Management System (ADAMS)
Accession Number ML14275A435 Ameren Missouri submitted a license amendment request for Callaway Unit 1 to upgrade the Emergency Action Level scheme by adopting NRC-endorsed Nuclear Energy Institute (NEI) 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors. Additional supplemental letters dated July 6, 2015 and July 16, 2015, ADAMS Accession No. ML15187A379 and ML15197A251, respectively, have also been submitted to support this license amendment The Nuclear Regulatory Commission (NRC) staff has been reviewing the submittals and has determined that requests for additional information (RAIs) are needed to complete its review. The draft questions were sent via electronic transmission on August 4, 2015 to Mr. Tom Elwood. A clarification teleconference was held on August 6, 2015 and determined that these questions are necessary for the NRC staff to complete its technical review and make a regulatory finding regarding this license amendment. Additionally, it was agreed that a response would be submitted within 21 calendar days from the date of this email which is Tuesday Sept 1, 2015.
If you have any questions, please contact John Klos per the contact information below.
The RAIs are as follows; SUPPLEMENTAL REQUESTS FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST EMERGENCY ACTION LEVEL SCHEME CHANGE CALLAWAY PLANT, UNIT 1 DOCKET NO. 50-483 By letter dated October 2, 2014, as supplemented by letters dated July 6, 2015 and July 16, 2015, Union Electric Company (dba Ameren Missouri) requested approval for an emergency action level (EAL) scheme change for the Callaway Plant (CP), Unit 1, Agencywide Documents Access and Management System (ADAMS) Package Accession No.s ML14275A435, ML15187A379, and ML15197A251, respectively. Ameren Missouri proposes to revise their current Emergency Action Level (EAL) scheme from one based upon Nuclear Energy Institute (NEI) 99-01, Revision 5, Methodology for Development of Emergency Action Levels, to one based upon NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors.
The following requests for additional information (RAIs), in reference to Attachment 3, Emergency Action Level Technical Bases (Draft D), of the submittal dated July 16, 2015 are needed for NRC staff to continue the review consistent with the regulatory basis of 10 CFR 50 Appendix E, Section IV.B.2.
1
Supplemental RAI-CP-14 NEI 99-01, Revision 6, EAL AA3 Initiating Condition (IC) states, in Section 6:
Radiation levels that impede access to equipment necessary for normal plant operations, cooldown or shutdown.
The basis for EAL AA3 further states that This IC addresses elevated radiation levels in certain plant rooms/areas sufficient to preclude or impede personnel from performing actions necessary to maintain normal plant operation, or to perform a normal plant cooldown and shutdown. As such, it represents an actual or potential substantial degradation of the level of safety of the plant.
NEI 99-01, Revision 6, EAL HA5 , in Section 10, states equivalent guidance for a gaseous release that impedes access to equipment necessary for normal plant operations, cooldown or shutdown.
The licensees previous response to RAI-CP-14 only addresses the actions needed to perform a plant shutdown, not the actions to initiate shutdown cooling.
The following questions are intended to address access to equipment needed to enter shutdown cooling:
- a. Please verify that all required manipulations to enter shutdown cooling can be performed from the Main Control Room or revise accordingly.
- b. Please verify that no local breaker operations (e.g., accumulator isolation valves or shutdown cooling valves) are required for initiation of shutdown cooling or revise accordingly.
Supplemental RAI-CP-18 The licensee states the following EAL wording to address EAL CA1.1:
Loss of RCS inventory as indicated by Reactor Vessel level < bottom of RCS hot leg ID (RVLIS Pumps Off < 73% or BBLI-53 A/B at 0 inches)
The EAL wording indicates that the EAL condition is based on a level that is < the bottom of the hot leg ID; whereas the Callaway Basis provides that BBLI-53A/B cannot sense level changes in the Reactor Vessel below the elevation of the RCS loop hot leg penetration. Therefore, it is unclear to staff how the RVLIS and BBLI-53A/B can be used to determine a level that is less than the bottom of the RCS hot leg ID.
Please provide the following:
- a. If the proposed EAL is intended to use a setpoint that is different than that provided by approved guidance, then please provide justification for that change and modify the EAL wording to reflect that change.
- b. If the proposed EAL is intended to use different levels based on instrumentation availability, then please clearly indicate when each level indication should be used and modify the EAL wording to clearly reflect when the specific instrumentation would be used. (Note: BBLI-53 A/B usage would also require EAL wording changes to clearly identify that the condition is not < the bottom of RCS hot leg ID.)
Supplemental RAI-CP-23 The NEI 99-01, Revision 6, developer notes states that:
The EAL and/or Basis section may specify use of a non-safety-related power source provided that operation of this source is recognized in AOPs and EOPs, or beyond design basis accident response 2
guidelines (e.g., FLEX support guidelines). Such power sources should generally meet the Alternate ac source definition provided in 10 CFR 50.2.
However, EAL schemes must also support timely and consistent assessments. As such, the staffs review verifies that the licensee provided basis section does not introduce wording that could potentially delay or potentially alter EAL assessments. For EALs CU2.1, CA2.1, SU1.1, SA1.1, SS1.1, SG1.1, and SG1.2, AC power sources are specifically provided by Table C-3/S-1. The Callaway Basis provides that credit can be taken for additional sources of power if they are capable of carrying an emergency bus. These additional sources of power are not clearly indicated on Table C-3. Additionally, the Basis discusses future actions that the licensee anticipates to take in accordance with the FLEX requirements.
- a. Please revise Table C-3 / S-1 and/or modify the basis discussion to ensure the EAL wording associated with EALs CU2.1, CA2.1, SU1.1, and SA1.1 is consistent with the applicable Basis document discussions and the current plant configuration (reflects current AC power capabilities).
- b. Please consider removing Table S-1, AC Power Sources, from EALs SS1.1, SG1.1, and SG1.2. If Table S-1 is not removed, please revise Table S-1 to ensure that an inappropriate classification would not be made when a bus is capable of supplying the required electric power within the designated time.
John Klos DORL Callaway Project Manager U.S. NRC, Office of Nuclear Reactor Regulation, Division of Operating Reactor Licensing NRC/NRR/DORL/LPL4-1, O7G1, Washington, DC 20555-0001 301.415.5136, 301.415.3313 (fax)
MS O8B1, John.Klos@NRC.gov 3
Hearing Identifier: NRR_PMDA Email Number: 2290 Mail Envelope Properties (6cbda0889fd2408b97e08c336e0430f0)
Subject:
Second round Requests for Additional Information: Callaway Amendment upgrade Emergency Action Level scheme adopt NRC-endorsed NEI 99-01, Revision 6 Sent Date: 8/11/2015 1:28:06 PM Received Date: 8/11/2015 1:28:07 PM From: Klos, John Created By: John.Klos@nrc.gov Recipients:
"'SMaglio@ameren.com'" <SMaglio@ameren.com>
Tracking Status: None "Klos, John" <John.Klos@nrc.gov>
Tracking Status: None "Johnson, Don" <Don.Johnson@nrc.gov>
Tracking Status: None "Hoffman, Raymond" <Raymond.Hoffman@nrc.gov>
Tracking Status: None
"'Telwood@ameren.com'" <Telwood@ameren.com>
Tracking Status: None Post Office: HQPWMSMRS05.nrc.gov Files Size Date & Time MESSAGE 7377 8/11/2015 1:28:07 PM Options Priority: High Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: