MONTHYEARML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23304A0682023-11-0606 November 2023 Summary of October 24, 2023, Public Mtg W/Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, and Sequoyah Nuclear Plant, Units 1 and 2 to Revise Function 5, Turbine Trip and F ML23265A1512023-09-28028 September 2023 Summary of September 12, 2023, Partially Closed Meeting with Tennessee Valley Authority to Discuss Proposed License Amendment Request ML23198A3102023-07-20020 July 2023 July 10, 2023, Summary of Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML23068A1532023-03-16016 March 2023 Summary of February 22, 2023, Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request to Increase Allowable Number of Tritium Producing Burnable Absorber Rods at Watts Bar Nuclear Plant, Units 1 and 2 ML23055A4562023-03-0909 March 2023 Summary of February 15, 2023, Public Meeting with Tennessee Valley Authority Regarding Proposed Expedited License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML22329A1382022-12-0505 December 2022 Summary of Meeting with Tennessee Valley Authority Related to Planned Alternative Request WBN-2-ISI-01 for Watts Bar Nuclear Plant, Unit 2 ML22168A1642022-06-27027 June 2022 Summary of June 9, 2022, Meeting with TVA Regarding a Proposed License Amendment Request Related to Low Temperature Overpressure System and Cold Overpressure Mitigation System for Sequoyah and Watts Bar Nuclear Plants ML22109A0042022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Alternative Request Related to Testing of the Motor-Driven Auxiliary Feedwater Pumps at Sequoyah and Watts Bar Nuclear Plants ML22104A2252022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Exemption Request for Watts Bar Nuclear Plant, Unit 2 ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22042B3262022-02-14014 February 2022 Summary of February 8, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed License Amendment Request to Revise the Allowable Value for Trip of Turbine-Driven Main Feedwater Pump at Watts Bar Nuclear Plant, Unit 1 ML22025A3112022-02-0909 February 2022 Summary of January 19, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed Schedule for Development of a License Amendment Request for Increased Tritium Production ML21349A3642022-01-0404 January 2022 Summary of December 14, 2021, Teleconference with Tennessee Valley Authority Regarding a Proposed Change to the Capsule Withdrawal Schedule for Watts Bar Nuclear Plant, Unit 2 ML21279A0902021-11-0303 November 2021 Summary of Conference Calls Regarding the Fall 2021, Mid-Cycle Steam Generator Tube Inspections ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21245A4252021-09-15015 September 2021 Summary of August 19, 2021, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to the Watts Bar Nuclear Plant, Units 1 and 2 ML21253A0872021-09-15015 September 2021 Summary of August 19, 2021, Partially Closed Meeting with Tennessee Valley Authority to Discuss Mid-Cycle Outage Contingencies for Watts Bar Nuclear Plant, Unit 2 ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML21120A2192021-05-0404 May 2021 April 28,2021, Summary of Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, to Remove from Technical Specifications Redundant Units of Measurement for Control ML21099A2072021-04-13013 April 2021 Summary of April 7, 2021, Meeting with Tennessee Valley Authority Related to a Planned Relief Request from ASME Code Testing Requirements ML21060B0532021-03-0303 March 2021 Summary of February 11, 2021, Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2, to Apply a Temperature Adjusted Steam Generator Tube Flaw Growth Rate Methodology ML21033A5952021-02-23023 February 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar Nuclear Plant, Unit 2 Steam Generator Replacement ML20357A0092021-01-19019 January 2021 Summary of December 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to Use of Alternate Probability of Detection at Watts Bar Nuclear Plant, Unit 2 ML20351A4212021-01-19019 January 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar, Unit 2, Steam Generator Replacement ML20351A2192021-01-11011 January 2021 Summary of Conference Calls Regarding the Fall 2020 Steam Generator Tube Inspections ML20337A0402020-12-15015 December 2020 Summary of November 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification 5.9.9, Steam Generator Tube Inspection Report ML20323A0662020-11-27027 November 2020 Summary of October 28, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request for Technical Specification Surveillance Requirement 3.6.15.4, Shield Building ML20244A1892020-09-11011 September 2020 Summary of Teleconference Call with Tennessee Valley Authority Regarding a Proposed Change to the Containment Leakage Rate Testing Program ML20213C7112020-08-25025 August 2020 Summary of July 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned Alternative Request for Watts Bar Nuclear Plant, Unit 1 ML20233A8352020-08-25025 August 2020 Summary of August 11, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20175A8012020-08-11011 August 2020 Summary of June 23, 2020, Public Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20211L8222020-08-10010 August 2020 Summary of Teleconference Call with the Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20150A4162020-06-24024 June 2020 Summary of May 28, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 1 ML20153A3622020-06-22022 June 2020 Summary of May 27, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20143A1692020-05-28028 May 2020 Summary of May 14, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2 ML20135H2702020-05-28028 May 2020 Summary of May 5, 2020, Teleconference Call with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML20127H8412020-05-0606 May 2020 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plant, Meeting No. 20200384 ML20034F5232020-02-12012 February 2020 Summary of Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML19347D1592020-01-0707 January 2020 Summary of December 12, 2019, Meeting with Northern States Power Co., Doing Business as Xcel Energy, and Tennessee Valley Authority Planned License Amendment Requests for Prairie Island, Units 2 and 2, and Watts Bar, Units 1 and 2 ML19296B6642019-11-0707 November 2019 Summary of Pre-Application Meeting with TVA Regarding a Planned License Amendment Request to Revise Technical Specification 3.6.15 Condition B and Surveillance Requirement 3.6.15.1 at Watts Bar Nuclear Plant ML19301A4762019-11-0707 November 2019 Summary of Pre-Application Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request to Remove Technical Specification Requirement to Surveil Automatic Transfer (EPID L-2019-LRM-0038 ML19294A3082019-10-28028 October 2019 Summary of July 18, 2019, Pre-Application Meeting with Tennessee Valley Authority Planned License Amendment Request for Approval to Implement a Measurement Uncertainty Recapture Power Uprate ML19284A3532019-10-28028 October 2019 Summary of October 10, 2019, Meeting with Tennessee Valley Authority Regarding a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML19253A6732019-09-17017 September 2019 Summary of Closed Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment for Watts Bar Nuclear Plant, Units 1 and 2 ML19255H5522019-09-12012 September 2019 August 27, 2019, Summary of Public Meeting - Tennessee Valley Safety Conscious Work Environment Update at Watts Bar, Docket 50-390 and 50-391 ML19235A2862019-09-0303 September 2019 Summary of Meeting with Tennessee Valley Authority Regarding Request to Adopt Technical Specifications Task Force Traveler TSTF-500 at Watts Bar, Units 1 and 2 ML19218A2282019-08-15015 August 2019 Summary of July 1, 2019, Pre-Application Meeting with TVA Regarding Planned License Amendment Request to Implement Full Spectrum Loss-of-Coolant Accident Evaluation Methodology 2024-01-18
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 22, 2015 APPLICANT: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Plant, Unit 2
SUBJECT:
SUMMARY
OF MARCH 11, 2015, TELECONFERENCE WITH TENNESSEE VALLEY AUTHORITY REGARDING THE WATTS BAR NUCLEAR PLANT, UNIT 2 OPERATING LICENSE APPLICATION (EMERGENCY PREPAREDNESS AND ENVIRONMENTAL PROTECTION PLAN)
On March 11, 2015, a Category 1 public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of the Tennessee Valley Authority (TVA). There were two topics of discussion at this meeting. First, the representatives from TVA wanted to discuss additional changes that were going to be submitted concerning the Watts Bar Radiological Emergency Plan (REP). Second, the NRC staff wanted to ask some clarifying questions regarding the Environmental Protection Plan submitted for Watts Bar Nuclear Plant, Unit 2. The meeting notice and agenda, dated February 20, 2015, are available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML15058A741. A list of attendees is enclosed (Enclosure 1).
The NRC staff presented no information. TVA provided a handout for the discussion of the REP (Enclosure 2).
Representatives from TVA explained to the NRC that in the finalization of the REP they neglected to update the REP to match a recent change to plant equipment. Additional changes were made as part of this update for editorial or administrative purposes. TVA stated that they had submitted the changes for Unit 1 per Title 10 of the Code of Federal Regulations Part 50, Section 54(q), if the staff wanted to try to gain a better understanding of the changes prior to their submittal for Unit 2.
The NRC staff had no substantial questions beyond the timing of the submittal for Unit 2, but asked if these changes had already been implemented for Unit 1. TVA stated that the submittal for Unit 1 would be submitted to the NRC by mid-April and that the changes to the plant had been made.
Following this discussion, the NRC staff asked clarifying questions (ADAMS Accession No. ML15015A477) regarding the Environmental Protection Plan and why there are certain differences between the Unit 2 and Unit 1 plans. TVA explained that the differences were made mainly because the items removed from the Unit 2 Environmental Protection Plan referenced obsolete or redundant practices. The NRC staff requested that TVA submit its justification for the changes as part of its next revision to the Technical Specifications for Unit 2, at which time the NRC staff would determine the necessity of the items in the Unit 2 Environmental Protection Plan.
There were no public comments at this meeting, and no feedback forms were received.
Docket No. 50-391
Enclosures:
1: List of Attendees 2: Discussion of Radiological Emergency Plan Updates cc w/enclosures: Distribution via Listserv
LIST OF ATTENDEES MARCH 11. 2015. TELECONFERENCE WITH TENNESSEE VALLEY AUTHORITY REGARDING THE WATTS BAR NUCLEAR PLANT. UNIT 2 OPERATING LICENSE APPLICATION (EMERGENCY PREPAREDNESS AND ENVIRONMENTAL PROTECTION PLAN)
Applicant: Tennessee Valley Authority Plant: Watts Bar Nuclear Plant. Unit 2
Subject:
Emergency Preparedness and Date: March 11. 2015 Environmental Protection Plan Location: Teleconference Time: 9:00 a.m. -12:00 p.m.
NAME TITLE ORGANIZATION U.S. Nuclear Regulatory Commission (NRC)/Office of Nuclear Reactor Senior Project Manager Watts Regulation (NRR)/Division of Justin Poole Bar Unit 2 Operating Reactor Licensing (DORL)/Watts Bar Special Projects Branch (LPWB)
Anthony Minarik Project Manager NRC/NRR/DORL/LPWB NRG/Nuclear Security and Incident Response (NSIR)/Division of Senior Emergency Steve LaVie Preparedness and Response (DPR)/
Preparedness Specialist Inspection and Regional Improvement Branch NRC/NSIR/DPR/New Reactor Alison Rivera Branch Chief Licensing Branch (NRLB)
Dan Barss Team Leader NRC/NSIR/DPR/NRLB NRC/NRR/Division of License Elaine Keegan Senior Project Manager Renewal/Reactor Projects Branch 2 Bob Bryan Licensing Engineer Tennessee Valley Authority Enclosure 1
Teleconference with NRC Discussion of Radiological Emergency Plan Updates
- TVA REP Appendix C Revision 105 issued and submitted to NRC 2/27/2015 -this change addresses the replacement of the failed condenser vacuum exhaust monitor on WBN Unit 1 with a monitor that is essentially the same as WBN Unit 2. The change is to reflect a new monitor tag numbers and revised EAL values for this monitor for NOUE, Alert, Site Area, and General Emergency. The threshold did not change. Conforming changes are made to a number of other pages to reflect the associated revision to the setpoint calculation.
- The change to Appendix C also requires conforming changes to EPIP-1, CECC EPIP-8, and EPIP-13 for setpoints for the Unit 1 monitor.
REP Appendix C Revision 105X
- This update will be issued shortly. The changes consist of the following:
o Inclusion of changes associated with Revision 105 o A number of items were found during recent review that represents an oversight by TVA;
- On various pages of Appendix C, buildings and components are identified as potentially affected by certain events. The current Appendix C does not state that there will be multiple RWSTs or CSTs. This is judged an editorial clarification.
- Under Fuel Handling accident, several area radiation monitors for WBN2 were not included (their Unit 1 counterparts are present in the REP).
Summary Are there any outstanding concerns or questions on our prior submittals?
Enclosure 2
There were no public comments at this meeting, and no feedback forms were received.
Please direct any inquiries to me at 301-415-2048 or justin.poole@nrc.gov.
IRA/
Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
Enclosures:
1: List of Attendees 2: Discussion of Radiological Emergency Plan Updates cc w/enclosures: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrPMWattsBar2 Resource LRonewicz, NRR LPWB R/F RidsNrrLABClayton Resource MWaters, OEDO RidsACRS_MailCTR Resource RidsRgn2MailCenter Resource TWertz, NRR RidsNrrDorllp_WB Resource EKeegan, NRR AMinarik, NRR SLaVie, NRR RidsNrrPMWattsBar1 Resource ARivera, NSIR DBarss, NSIR AWilson, Rll ADAMS A ccess1on Nos.: p ac kage: ML15097A432 M eef mg S ummary: ML15097A422 OFFICE DORL/LPWB/PM DORL/LPWB/PM DORL/LPWB/LAiT DORL/LPWB/LA NAME AMinarik JPoole (AMinarik for) LRonewicz BClayton DATE 4/15/15 4/15/15 4/10/15 4/10/15 OFFICE DORL/LPWB/BC DORL/LPWB/PM NAME JQuichocho JPoole DATE 4/17/15 4/22/15 OFFICIAL RECORD COPY