ML14223A453

From kanterella
Jump to navigation Jump to search
Summary of Meeting with Tennessee Valley Authority Regarding the Watts Bar Nuclear Plant, Unit 2 Operating License Application
ML14223A453
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 08/28/2014
From: Justin Poole
Watts Bar Special Projects Branch
To:
Tennessee Valley Authority
Minarik A
Shared Package
ML14223A503 List:
References
Download: ML14223A453 (30)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August28, 2014 APPLICANT: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Power Plant, Unit 2

SUBJECT:

SUMMARY

OF JULY 22, 2014, MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING THE WATTS BAR NUCLEAR PLANT, UNIT 2 OPERATING LICENSE APPLICATION On July 22, 2014, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the Tennessee Valley Authority (TVA) at the NRC Headquarters 11555 Rockville Pike, Rockville, Maryland. The purpose of this meeting was for TVA to present the status of construction and licensing efforts for the Watts Bar Nuclear Plant (WBN), Unit 2 project. The meeting notice and agenda, dated July 16, 2014, is available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML14167A244. A list of attendees is enclosed.

TVA made a presentation to the NRC staff, which is included as an enclosure to this summary.

This presentation covered the following topics: WBN Unit 2 construction status; the overall project timeline; project risks; the status of licensing related documents; hydrology; TVA's Fukushima Response as it relates to WBN Unit 2; Fire Protection at WBN Unit 2; TVA's strategy to address questions on Title 10 of the Code of Federal Regulations Appendix A to Part 50 General Design Criterion 5; the substantially complete process and related notifications; as well as public outreach. Also during their presentation TVA stated that while the schedule identifies license issuance and fuel load in June of 2015, TVA's more aggressive schedule had originally planned for the license to be issued and fuel to be loaded in February of 2015. However due to various delays in construction and other licensing issues TVA now believes a date of March 29, 2015 is more appropriate for their internal schedule. TVA noted that a fuel load date of June 2015 would be needed to begin commercial operation by December 2015, which is the date that TVA has commited to the TVA board of directors.

Throughout TVA's presentation the staff asked clarifying questions, especially in regards to the issue of hydrology. The staff made it clear to TVA that at this point in the process of the project, timeliness in submittals, and completeness of submittals is of the utmost importance to ensure the NRC can make as efficient a review as possible. The NRC made it clear that their review will take as much time as necessary to ensure the safety of the public.

No regulatory decisions were made at this meeting.

A few members of the public were in attendance at this meeting and asked several questions of the NRC. A few of the questions were related to hydrology issues at the Watts Bar site.

Members of the public expressed concern at TVA identifying this issue as a moderate risk despite requiring substantial changes to be made by the end of August, TVA voluntarily

responded to these comments by stating that the schedule risks may change but they are doing their best to meet the current dates. Another question from the public related to how the issues related to Fukushima were resolved at the WBN Unit 2 site and a better understanding of the staff's priority list associated with seismic review that was released in May 2014 (ML14111A147). The staff explained that the current hydrology issues were for design basis type events, whereas Fukushima is recognized as a beyond design basis event, additionally the staff clarified that the priority list had to do with resource availability and staff availability, rather than with risks associated with seismic events. For these reasons WBN Unit 2 is following similar implementation milestones related to Fuksuhima as operating plants in accordance with the Orders that were issued. Additional questions were asked about how TVA planned on addressing any effects from the staff's rulemaking effort on Waste Confidence and fuel storage in general. TVA voluntarily responded that the rulemaking is out of their control, and as such they can only react to the final result. Finally, some additional concerns were raised by a member of the public on dam safety referencing the Kingston Coal Ash dam failure, which occurred even when the dam was constructed and inspected according to certain standards.

Justin C. Poole, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391

Enclosures:

1. List of Attendees
2. TVA Handouts cc w/encls: Distribution via Listserv

MEETING ATTENDANCE LIST Applicant: Tennessee Valley Authority Plant: Watts Bar Nuclear Plant, Unit 2

Subject:

Watts Bar Unit 2 Project Status Date: July 22, 2014 Location: U.S. Nuclear Regulatory Commission Time: 2:00 p.m. - 4:00 p.m.

Headquarters. Room 0-4B6 NAME TITLE ORGANIZATION Acting Deputy Director of Michele Evans NRR and NRC/NRR Chairwoman of WRAG Acting Director of Division of Louise Lund NRC/NRRIDORL Operating Reactor Licensing Deputy Regional Fred Brown NRC/RII Administrator for Construction Director of Division of William Jones NRC/RII/DCP Construction Projects Robert Haag Branch Chief NRC/RII/DCP/CPB3 Jessie Quichocho Branch Chief NRC/NRRIDORLILPWB Senior Resident Inspector, Tomy Nazario NRC/RII/DCP/CPB3 Watts Bar Unit 2 Justin Poole Senior Project Manager NRC/NRR/DORLILPWB Senior Construction Project Christopher Even NRC/RII/DCP/CPB3 Inspector Enclosure 1

NAME TITLE ORGANIZATION Siva Lingam Project Manager NRC/NRRIDORL/LPWB Jeanne Dian Project Manager NRC/NRRIDORL/LPWB Anthony Minarik Project Manager NRC/NRRIDORL/LPWB Michael Miernicki Project Manager NRC/NRRIDORL/LPWB Andrew Han Project Manager NRC/NRR/DORL/LPII-2 Watts Bar, Tennessee Valley Gordon Arent Director of Licensing Authority (TVA)

Steven A. Hilmes I&C/Eiectrical Manager Watts Bar, TVA Ray Hruby General Manager Watts Bar 2, TVA WBN Fukushima Project Robert C. Williams Watts Bar, TVA Manager WBN 2 Mechanical/Nuclear Bill Crouch Watts Bar, TVA Manager Frank Koontz Engineering Specialist Watts Bar, TVA

NAME TITLE ORGANIZATION Mary-Jane Ross-Lee Deputy Director NRC/NRRIDE Yuan Chen Hydrologist NRC/NRRIDE/EMCB Yang Li Branch Chief NRC/NRRIDE/EMCB Stephanie Coffin Deputy Director NRO/DARR Southern Alliance for Clean Energy Sara Barczak Program Director (SACE)

Harmon, Curran, Spulberg and Diane Curan Counsel to SACE Eisenberg

  • William Freebairn Managing Editor Platts Nucleonics Week
  • Don Safer Member of Public Tennessee Environmental Council
  • Steven Sondheim Member of Public Sierra Club Bellefonte Efficiency and
  • Gary Morgan Member of Public Sustainability Team, MATRR
  • participated via teleconference

m

J

(")

0

(/)

c:

Cil N

£m Agenda

  • Introductions
  • Watts Bar Unit 2 Completion Status
  • Project Timeline
  • Project Risks
  • Licensing
  • Special ~opics

- Hydrology

- Fukushima

- Fire Protection

- GDC- 5

- Substantially Complete Process

- Outreach

  • Closing Remarks Hruby 2

[i!/J Watts Bar 2 Guiding Principles

  • Safe and High Quality
  • Design Basis Fidelity with Watts Bar 1
  • Systems, Structures, and Components -

Made Like New Hruby 3

1m Watts Bar 2 Construction Summary

  • Safety

- Over 28 million hours without lost-time incident

- Fiscal year-to-date Recordable Injury Rate at 0.33

  • QuaHty

- Project Quality Control (QC) Acceptance Rate >98%)

  • Cost & schedule

- Cost and schedule adherence meeting expectations Hruby 4

[m Project Ti eline Watts Bar 2 System Completion Status lU04,rUA ~ 8/U/14 ~~~ J/S/IS .,U/1'>

... ... ... 11/ll{lS 12/li/ll 5/,/14

_..A._

u.

  • Jn/14

...----*-~ -

~--~--~-------:~ll ttoc run C.re f<diT....,

7/1~j1S lam! PATIOlOO'!i, 1r;,,Ren.n,Sn (DIIUMrQol Start Opon Sbrt Opoa Cold VHSE:l y~""""

Hydro funclic>nlil CSI1 lead p,-_. Tort& c..-v O.y p,. Coon no Qo!oiool Opcr3t.....

COII'\FO*"'*tll Tsq:

lopcTstg Oec*U J<ln-14 Feb-14 lolbr* l4 l!pr- 14 P~*14 Jun*l~ .lo.J I*14 i!Uf* l4 Sep.-14 Ort*14 Nov-14 Dec-14 lall-15 Feb-15 BlJU< COtJSTRUCTION I

6: '  ! A

~~~~~~~~J I I I .

~~ru~~  :

~~~~~;m-Oim=o.s~~,-~ I I

<DM~m TESTING  ;

lf~J~~af-~~:;1 I I

. .- -- --. --=I ------

I

  • TAIIGET.~EROFSYSTEMS-U :

Pft-OP fESTiriG I

l~~~~!:_~~~-------- j Hruby 5

[i!lJ Project Risks Waste Confidence (Licensing)

Start-up Testing Delays Dual-Unit Operational Readiness Closure of Licensing Issues (Licensing) Moderate Hydrology (Licensing) Moderate Paper Closure Moderate Productivity Moderate Critical Equipment Failure During Start-up Moderate Employee Concerns Moderate Cyber Security (Licensing) Moderate Hruby 6

1m Licensing Status Supplemental Safety Evaluation Report

  • Final Environmental Statement- Compfete Open Item Status
  • Safety Evaluation - Nearing Completion
  • NIRC Closed
  • Pending ssm 27
  • NIRC Review

.iVA Open

  • Closure of Regulatory Commitments Accelerating Inspection Planning and Scheduling Item Status
  • No Watts Bar 2 Specific Contentions Remain Open
  • NRC Closed

. TVA Action

  • N RC Action Arent 7

[i!i! Watts B.a r 2 Licensing Fuel Load Schedule December 2014 October 2014 Fi1al AOR.S l..ettel" NRC Senior All Traditional!..iciDsing Actions Managemernt Complete Letter a.nd TVA Meeting April 2014 Hay

\'lRAG August 2 0 1 4 l Harch 2015 SiER f\Jktdlima 2015

,finaJ status Report IP 94300 2014 October 2014 April2015 NRC Commission l>e<lember 2014 February 2015 Issue Operating Briefng ACRS Full Gommitiee Final Supplemental License Safety Evaluation Report November 2014 February 2015 April2015 December 2014 Signed ACRS SUKommittee NRC l..el:ter tD Congress 30 Day status Report IndemMication NRC Actions IP 9'1300 Letter TVA Actions Januasy 2015 Hot Functional Test December 2014 January 2015 April Hay TVA letter Ready 2014 TVA Substantialll for Fuel load 2015 August2014 Complete Lerter Open Item Report Cok! Hydro 2014 January 2 !}15 TVAJNRC Slite Apri12015 Mafl3goemenl Meetmg FUEL LOAD Arent 8

CJ)

-c CD n

S>>

-1 0

-c nt/)

[i!n Tennessee River System Overview Brhtof Projn:trtlt tloUd>Ud<y Cfln~h Rill<>r Fr~nch 9too, River Little Te nnessee

'-.: TllOI'Jl~ (II )

Oo ~k ~ Creel< Q:- - Uontah.\1~ (II )

- santeetlah {T}

li,!llowee TeUico)l ~~ ~ ho1u ~

Hlill(lSH'I' River Watts Bor Plont

~~ ~*~ - ott ElkRi~~r

~"" .~

........,.....-.. . a( .

Ocoee1, 2. 3

.... -e Cumberland Ri**er S e.a1 Cleek P10j~'Cb ('I I T41inn~c:~Tnn'lhi~ W ~t ~ ;;,y flote:

OhlaRiw r (C) U.S Arm v Corp> of (ngin""'" Ooms (N ) llontahala Power & Ugflt Company (subsidiary of OukeEnergy) l'"!>OCO , Int. (>ub>idiory of ALCOA)

Arent 10

fim Hydrology

  • Assumption

- SOCH probable maximum flood (PMF) Level from 7/2012 submittal

  • Actions

- Evaluate 18 dams upstream of WBN/SQN against TVA Series 27 procedures (Federal Energy Regulatory Commission (FERC)

Implementation at TVA) acceptance criteria

- Determine dams with reduced margin

- For dams that do not meet criteria, perform additional evaluations by TVA River Operations (RO) to show dams with reduced margin are stable

- Confirm combination events are not affected (flood level , warning time)

- Perform 3rd party evaluation to confirm TVA results- recognized industry expert

- Revise FSAR Section 2.4.3 with new information Arent 11

~ Hydrology

  • Examples

- Changes in RO Operating Guides

- Additional site modifications that 1mprove marg1n

- Use HEC - RAS as sensitivity to support margin element

  • Provide License condition to address dams with reduced margin by analysis or physical modifications to TVA system 27 (FERC) criteria Arent 12

rnJ Fukushima Response

  • Spent Fuel Pool Level Instrumentation complete
  • Construction of Flexible Equipment Storage Building complete
  • Dominator, Triton &Transfer pumps, 480 volt diesel generators, and 6900 volt diesel generators delivered
  • Construction of FLEX modifications 90°/o complete Wil.liams 13

li!li] Fu kushi::m a Response

  • Interim Staff Eva luation for Mitigating Strategies - Received

- Two open items o Alternate Strategy for 3 megawatt DGs - submitted and accepted by NRC o Boron Injection to ensure shutdown margin (WCAP 17601 ) - resolved with NRC staff May 15, 2014 - revised calculation June 30, 2014

- 23 confirmatory items

  • Mitigating Strategies Audit - Complete
  • FLEX procedures - 90°/o complete
  • Programming changes to simulator - Complete
  • Drafting of training modules for updated procedures - Complete
  • Full compliance expected early fall 2014 Williams 14

1m Fire Protection

  • As-Designed Ftre Protection Report (FPR) Submitted March 13, 2013
  • Partial Submittal of As-Constructed FPR Submitted June 30, 2014
  • Remaining portion of As-Constructed FPR to be Submitted August 15, 2014

- Dual Unit Fire Safe Shutdown Analysis

- Unit 2 and Common Feasibility and Reliability Evaluations

- Unit 2 Multiple Spurious Operation Evaluation Report

- Resolution of NRC Comments on June 30, 2014 Submittal

  • Conducting Integrated Demonstration of two Appendix R Response Procedures on August 11 , 2014
  • Final confirmation of construction completion via Substantially Complete letter Crouch 15

fi!1 GDC-5

  • Sharing of Structures, systems, and components (SSC). SSCs important to safety shall not be shared among nuclear power units unless it can be shown that such sharing will not significantly impair their ability to perform their safety functions, including, in the event of an accident in one unit, an orderly shutdown and cooldown of the remaining units.
  • Component Cooling System (CCS) is shared between two WBN units
  • WBN 1/2 is hot standby design plant (mode 3). Considered safe to remain in Mode 3 until decay heat allows further cooldown.
  • Limiting event is LOCA in one unrt and reactor shutdown in other unit with loss of train A power. One 8 train heat exchanger remains to cooldown both units. Flow shared between units.
  • Within system capacity to handle accident unit and cooldown non-accident unit, provided non-accident unit cooldown can be delayed_

Koontz 16

iJ!] GDC-5

  • If non-accident unit is in Mode 1-3, remain in Mode -3 for 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> with cooling by steam generators. (Safe Shutdown)
  • If non-accident unit is in mode 5, prior to venting of RCS (48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />), allow RCS to return to mode 4 or 3 and steam from steam generators.
  • Technical Specification prohibition TS 3.0.4
  • Potential solutions being examined:

- Technical Specification revrsion

- Credit 3 out of 4 diesels (loss of both A or 8 train diesels not possible by active single failure)

Koontz 17

rnJ SubstantiaUy Compl~ ete Process

  • Readiness Program Assessment Methodology
  • Project Approach for Watts Bar 2
  • Plant Completion Verification (examples)

- Original Design and Construction Documentation

- Refurbishment

- N-Stamp

- New Design Change Alterations

- Preoperational Test Program

- NRC Open Items/commitments

- Appendix B Program audits

- Design Basis Verification Procedures

-Appendix R Arent 18

mJ Substantial:ly Complete Process

    • Readiness Program Assessment Results

- Licensing

- QA/QC

- Engineering

- Construction and start-up

- Organizational readiness

  • Plant Completion (summary tevel conclusions)
  • Transition to operating organization
  • CAP and Special Program Closure Arent 19

II) Substantially Complete Process

  • Schedule

- Substantially Complete Letter with open items- December 2014

- Readiness for Fuel Load with open ite*ms - January 2015

- Open item closure update - February 2015

- Final update - March 2015 Arent 20

1m Outreach Key Objectives

  • Visits/tours by key stakeholders

- Commissioners with the NRC

- Clean and Safe Energy Coalition

- Nuclear Energy Institute's Washington International. Representative Committee ~' E w _. 1 - ,- -..,.-,-= .,-

- Elected officials

- National Nuclear Security Administration

-Customers

  • Community Action Panel in place
  • Speeches
  • Public meetings
  • Proactive media strategy
  • Updated website and increased social media presence
  • Family & friends and community events Hruby 21

0 0

en

  • 1m Conclusion
  • Work to complete Watts Bar 2 is being done safely, in a quality manner, and in accordance with stringent standards.
  • The combination of construction , refurbishment, improvements, and ongoing pre-startup testing will demonstrate systems, structures, and components have achieved "like new" condition .
  • Startup testing and system turnovers support a March 2015 fuel load date.
  • Project challenges are being identified and addressed.
  • Regulatory and l'icensing issues including waste confidence remain a risk to receipt of the operating license.
  • Fukushima response , hydrology, and cyber security actions continue to progress in support of the operating license schedule.
  • A comprehensive outreach plan is being implemented.

Hrub~r 23

0 C1)

(/)

0

1

(/)

PKG ML14223A503 Meeting Notice: ML14167A244 Meeting Summary: ML14223A453 OFFICE DORL/LPWB/PMiT DORLILPWB/PM DORL/LPWB/LA DORL/LPWB/BC DORL/LPWB/PM NAME AMinarik JPoole BCiayton JQuichocho JPoole DATE 8/26/14 8/22/14 8/19/14 8/26/14 8/28/14